Plumbing Installation

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 38

SECTION 19

PLUMBING INSTALLATION

SL NO.

TITLE OF SPECIFICATIONS

BARWA VILLAGE EXPANSION DEVELOPMENT


ELECTRICAL AND MECHANICAL SPECIFICATIONS
VOLUME 03

19.1.00

SECTION 19

GENERAL SPECIFICATIONS

19.1.01
GENERAL CONDITIONS OF CONTRACT
19.1.02
WORK BY OTHERS
19.1.03
MAJOR EQUIPMENT AND LOCAL REPRESENTATION
19.1.04
CODES AND STANDARDS FOR WORKS
19.1.05
DATA TO BE SUPPLIED WITH TENDER
19.1.06
DRAWINGS, SUBMITTALS, INSTRUCTION MANUALS, ETC
19.1.07
PRODUCTS
19.1.08
EXECUTION
19.1.09
GENERAL REQUIREMENTS
19.1.10
TESTS AT SITE
19.1.11COMMISSIONING BY SPECIALISTS
19.1.12
PRACTICAL COMPLETION CERTIFICATE
19.1.13
GUARANTEE AND MAINTENANCE PERIOD
19.2.00 TECHNICAL SPECIFICATION PLUMBING .......................................................13
19.2.01

GENERAL..........................................................................................................13

19.2.02

INSTALLATION, STORAGE AND PROTECTION...............................................14

19.2.03

PIPE SUPPORTS, BRACKETS AND HANGERS...............................................14

19.2.04

PIPE SLEEVES..................................................................................................16

19.2.05

VALVES AND STOPCOCKS...............................................................................16

19.2.06

STRAINERS AND DRAIN COCKS.....................................................................17

19.2.07

FLOAT BALL VALVES........................................................................................17

19.2.08

AUTOMATIC AIR VENTS & TAPS......................................................................18

19.2.09

TRENCH EXCAVATION.....................................................................................18

19.2.10

UNDERGROUND COLD WATER SERVICES....................................................19

19.2.11

PIPEWORK INSULATIONS................................................................................19

19.2.12

COLD WATER STORAGE TANKS.....................................................................20

19.2.13

HOT WATER SERVICE HEATERS....................................................................22

19.2.14

PUMP SETS.......................................................................................................22

19.2.15

WATER FILTERS................................................................................................23

19.2.16

STERILIZATION OF WATER SERVICES...........................................................24

19.2.17

INCOMING WATER SUPPLY AND METER.......................................................24

19.2.19

SNG System.......................................................................................................26

19.2.20
19.2.21

NOTES
31
SCHEDULE OF APPROVED MANUFACTURER...............................................32

AEB-1086-14-REV.00

S-19-1/31
PLUMBING INSTALLATION

BARWA VILLAGE EXPANSION DEVELOPMENT


ELECTRICAL AND MECHANICAL SPECIFICATIONS
VOLUME 03

SECTION 19

19.1.00

GENERAL SPECIFICATIONS

19.1.01

GENERAL CONDITIONS OF CONTRACT

The work under this section of the specification shall include the supply, delivery on
site, installation, testing and commissioning and setting to work the Plumbing system
for the BARWA VILLAGE BUILDINGS.
The contractor shall provide all the materials, labour, cartage, plant and appliances
necessary for the supply, installation, testing and commissioning of the work and all
other minor and incidental works necessary for the system.
The specification and the drawings are intended to indicate the nature and over all
scope of the project. Any discrepancies, omissions, ambiguities or conflicts in or
among contract documents, or any doubts as to their meaning should be called to
the attention of the Consultants by the works contractor at the time of submitting his
tender.
The contractor shall visit the site and ascertain by himself the nature and scope of
the works, prior to tendering. It is important that the contractor fully familiarizes
himself about dismantling work if any - in connection with carrying out his work.
The Contractor is responsible for the installation of a complete system of correct
capacity and shall guarantee the efficient and optimum performance of the system as
a whole. Contractor shall guarantee for the efficient performance of various
equipment which shall not be less than the specified ratings when working under the
operating conditions for the respective items as given in the specifications.
It is mandatory to have performance testing under simulated conditions at the factory
of prospective suppliers of all the equipment prior to shipment. Anything, not
specifically mentioned, but necessary for the fulfillment of the guarantee and
requirements called for in the contract or necessary for the proper operation of the
installations is to be provided by the works contractor without any additional cost.
The works contractor shall guarantee holding a full set of spare-parts for all of the
equipment he intends to supply and install, for a minimum period of two years.
Entire works shall be carried out as a single contract. All items of works even if not
listed in the Bill of Quantities but covered in the specifications or in the drawings are
deemed to be included in Contractors price. The contractor shall submit the lump
sum price for the whole works with a breakdown for individual headings as per the
Bill of Quantities. No variation claims shall be entertained.
The contractor shall not without the consent in writing of the Engineer assign or
sublet his contract or any substantial part thereof other than for raw materials or
minor details. Consent for subletting shall not relieve the contractor from any
obligation, duty or responsibility under the contract.

AEB-1086-14-REV.00

S-19-2/31
PLUMBING INSTALLATION

BARWA VILLAGE EXPANSION DEVELOPMENT


ELECTRICAL AND MECHANICAL SPECIFICATIONS
VOLUME 03

SECTION 19

The contractor shall comply with all bye-laws and regulations of local and other
statutory authorities having jurisdiction over the works and shall be responsible for
the payment of all fees and other charges and the giving and receiving of all
necessary notices. Works shall be carried out in conformity with the specifications
and in coordination with the architectural/structural/other services requirements
/constraints.
The contractor shall submit within seven days from the date of acceptance of the
tender, detailed schedules showing the programme and order in which the contractor
proposes to carry out the works with dates and estimated completion time for various
parts of the work in the form of bar-chart based on the critical path method. Such
schedules shall be approved by the Consultant before starting of the work and shall
be binding on the contractor.
Routine tests for various items of equipment shall be performed at the contractors
works, prior to shipment and test certificates shall be furnished. Contractor shall
inform and permit Engineer to be present during these tests. Contractor shall bear all
the expenses thereof.
The contractor shall operate, test and adjust all plumbing system provided in
connection with this installation and shall make all necessary adjustments and
corrections thereof including the adjustment of all drainage system for the purpose
achieving the design foul flow through all pipes.
If the completed drainage system or any portion thereof before it is taken over or
during the guarantee and defects liability period be found defective or fails to fulfill
the intent of this specification, the contractor shall on receipt of notice from the
Consultant forthwith make the defective drainage system good.
If he fail to do so within a time considered reasonable by the Consultant, the owner
may reject and replace at the risk and expense of the contractor the whole or any
portion of the system which is defective or fails to fulfill the requirements of the
contract.
The contractor appointed for plumbing works shall have the valid Grade A license
from KAHRAMAA (formerly QGEWC) or Ministry of Municipality and Urban
Planning(formally MMUPDA) or Credentials to that equal up to the discernment of
Consultant. A copy of the license shall be submitted to the Consultant. The contractor
shall also submit the qualifications and experience particulars of the Public health
Engineer, Foreman and Technicians to be employed on the project along with their
ASHGHAL license copies, and obtain approval from the Consultant.
Inclusion in the list of approved manufacturers does not absolve the
supplier/contractor of his obligations to fulfill the detailed specifications in accordance
with contract documents.
Canvassing in connection with tenders is strictly prohibited and the tender submitted
by the contractor who resorts to canvassing is liable to be rejected.
The Contractor is responsible for the safe storage, protection and safety of his
equipment and materials at site. All materials and equipment must be stored and

AEB-1086-14-REV.00

S-19-3/31
PLUMBING INSTALLATION

BARWA VILLAGE EXPANSION DEVELOPMENT


ELECTRICAL AND MECHANICAL SPECIFICATIONS
VOLUME 03

SECTION 19

protected properly so as to prevent damage, corrosion, deterioration or dirt


penetration. Manufacturers recommendations shall be strictly followed regarding
storage. All pipes and pipe outlets must be adequately closed to prevent dust and dirt
penetration during the course of erection.
The following terms and abbreviations used in these specifications shall mean:
Contractor

The tenderer whose tender has been accepted


by the Owner and shall include the tenderers
heirs, successors and assigns approved by the
owner

Subcontractor

The firm or persons named in the contract for


any part of the work or any person to whom any
part of the work has been sublet with the
consent in writing of the Owner/Consultants and
shall include his heirs, successors and assigns
approved by the owner

Specification

The specification annexed to or issued with


these Conditions of Contract

Contract

The agreement between the Contractor


and
Owner to be entered into
under
these
conditions and shall include these conditions
of contract,
specifications,
schedules,
correspondence, letter of intent of the owner
and any subsequent amendment
mutually
agreed upon.

Site

The place or places at which the plant is to be


delivered or work to be done by the Contractor
and shall include where applicable the lands
and buildings upon or in which the works are to
be executed and shall also include the place or
places at which fabrication and other work will
be carried out by the contractor.

Plant, Equipment, Stores

The plant and materials to be provided and


Work or Works to be done by the contractor
under the contract

Test on Completion

Tests as are prescribed by the Specification or


as per International standards as applicable, to
be carried out before the plant is taken over by
the owner. In case, tests are not possible due to
climatic conditions at the time of completion, the
contractor
shall be bound to carry out tests
at any time subsequent to the date of
completion, but before the end of defects
liability period.

AEB-1086-14-REV.00

S-19-4/31
PLUMBING INSTALLATION

BARWA VILLAGE EXPANSION DEVELOPMENT


ELECTRICAL AND MECHANICAL SPECIFICATIONS
VOLUME 03

19.1.02

SECTION 19

WORK BY OTHERS

All builders works related to equipment foundations, pits, pumps, wall openings for
plumbing piping, final flashing and water proofing of roof openings, Access panels in
plumbing shaft for operation/maintenance, Door undercuts, grading shall be
provided by the main Civil contractor.
Plumbing contractor shall liaise and co-ordinate with other Contractors as necessary.
Particular attention is drawn to the following:
a. Coordination with civil for the underground piping
b. Coordination with architect for water supply point in wall.
c. Coordination with interior for the selection of sanitary wares and brass
wares.
The division of work between the Drainage contractor and the Electrical contractor
shall be as specified elsewhere under clause ELECTRICAL WORKS AND
CONTROL SYSTEM .
19.1.03

REGULATIONS, CODES AND STANDARDS FOR WORKS

Meet the requirements of the General Conditions of Contract


Meet the requirements and recommendations of all authorities having jurisdiction.
All work shall be carried out in accordance with the relevant Safety Regulations
applicable to the Site.
Unless otherwise specified, all equipments are to comply with the relevant British
and American codes of practice as listed below. However, the ASHGHAL latest
regulations and requirements of Qatar Construction Specification shall take
prominence over all other regulations.
1. KAHRAMAA :

Qatar General electricity and water authority

2. ASME

American Society of Mechanical Engineers, USA

3. ASTM

American Society of Testing Materials, USA

4. ASPE

American Society of Plumbing Engineers, USA

5. HI

Hydraulic Institute, USA

6. ANSI

American National Standards Institute, USA

7. CIBSE

Chartered Institute of Building Services Engineers, UK

The workmen employed must be accustomed to the highest class of plumbing


installation.
A competent Engineer must be in regular attendance throughout the whole contract.

AEB-1086-14-REV.00

S-19-5/31
PLUMBING INSTALLATION

BARWA VILLAGE EXPANSION DEVELOPMENT


ELECTRICAL AND MECHANICAL SPECIFICATIONS
VOLUME 03

SECTION 19

The whole of the installation shall be executed in conformity with the specification,
internationally accepted codes of practice and the current KAHRAMMA/QCS
regulations.
19.1.04

MAJOR EQUIPMENT AND LOCAL REPRESENTATION

The make, model and type of all equipment, materials and accessories proposed to
be used in the Project are subject to prior approval of the Engineer.
All these equipment and other materials must have an established Local Qatari
Agent who shall have complete after-sales service & maintenance facility and also
holds adequate spare parts as recommended by the manufacturer.

19.1.05

DATA TO BE SUPPLIED WITH TENDER


a.
b.
c.
d.
e.
f.

19.1.06

Technical data of all equipment proposed, performance curves.


Selection data sheet etc. as applicable.
Exclusions and deviations from specification.
Guarantee particulars.
List of spare parts required for 2 years maintenance and special tools
Engineering catalogues in Originals.
DRAWINGS, SUBMITTALS, INSTRUCTION MANUALS, ETC

General
All drawings and material submittals, other information and samples must be
supplied to the Consultant as laid in the specifications or as instructed by the
Consultant.
Drawings show general design and arrangement of M+E system installation, and
diagrammatic. Obtain further clarification of Drawings or Specifications from
Consultant/Engineer prior to installation.
Drawings do not indicate exact Architectural or Structural features. Examine drawings
prior to laying out.
Do not scale drawings to order materials. Take field measurements where possible to
obtain confirmation from Consultant/ Engineer of all dimensions required before
ordering major plant items in advance of construction.
Clarify roughing-in requirements of equipment, which is not part of this specification
before proceeding.
Leave areas clear where space is indicated as reserved for future equipment and
where space is required to maintain equipment. Maintenance clearance, in addition
to providing for servicing of equipment, shall allow for removal and reinstallation of
replaceable items such as pumps, drains.

AEB-1086-14-REV.00

S-19-6/31
PLUMBING INSTALLATION

BARWA VILLAGE EXPANSION DEVELOPMENT


ELECTRICAL AND MECHANICAL SPECIFICATIONS
VOLUME 03

SECTION 19

Shop Drawings to be prepared by the Contractor


The Contractor shall prepare and submit for approval, detailed shop drawings for all
equipment or distribution services described herein. Such drawings shall indicate:
a.
b.
c.
d.
e.
f.
g.
h.

All civil works, openings, bases, position of sleeves etc.


The physical dimensions of the equipment.
The sizes of foundation base wherever required.
Location of pits, pumps, tanks
Position of pumps, controls, etc.
Detailed piping profile of all the plumbing system
Piping isometric diagram
Any other drawing found necessary or requested by the Consultant for
coordination of works.

The work described on any shop drawing submitted shall be properly checked by the
Contractor for all clearance, field conditions, maintenance space and proper
coordination.
Equipment layout is to be detailed on drawings showing the exact method of
installing and clearly illustrating components to be used in making all connections.
All drawings prepared by the Contractor shall be submitted in the form of three sets
of prints to the Consultant for approval, who in turn, after making his comments will
return two sets of the same to the Contractor for necessary revisions if any.
Thereafter the Contractor shall submit five sets of prints for the Consultant's final
approval. Once the drawings are finally approved, the contractor shall submit in
reproducible copy negative for Consultant's signature and the same shall be kept on
site for execution.
Electrical diagrams shall show the following:
a. Composite circuit layout diagrams for electrical services shall detail circuity within
main control panels
b. If abbreviations are employed for the designation of components these should be
in accordance with the standard symbols drawings provided.
Co-ordination
The Contractor shall work from the drawings and specifications provided for Tender
purposes by the Engineer. These drawings show the design intent having taken into
account the building and all services so that ppumps, drain connection and water
tanks are adequate for the accommodation with in the civil requirements.
Examine the site and all Contract Documents prior to bid submission. No allowance
will be made for any difficulties encountered due to any features of the building,
methods of construction, site or surrounding public and private property which
existed up to the bid close.

AEB-1086-14-REV.00

S-19-7/31
PLUMBING INSTALLATION

BARWA VILLAGE EXPANSION DEVELOPMENT


ELECTRICAL AND MECHANICAL SPECIFICATIONS
VOLUME 03

SECTION 19

The Contractor shall be responsible for co-ordinating the works and shall produce
such drawings as are necessary for co-ordination and for the proper installation of
plant and services. These drawings shall take into account.
a. The final choice of equipment
b. The inter-relationship of all engineering systems servicing the buildings and their
relationship to the buildings.
c. Accepted good practice for the installation of Mechanical and Electrical systems.
d. In order to achieve detailed co-ordination the Contractor may depart from the
Engineers drawings subject to the approval of the Engineer.
Identify and resolve interference problems prior to prefabrication and installation of
equipment. Submit interference drawings for review upon Consultant/Engineers
request.
As-Built Drawings
Two weeks prior to the Practical Completion date, the Contractor shall hand over to
the Engineer, three complete sets of all As-Built record drawings plus one set of the
reproducible negatives, and the Operation and Maintenance Manuals.
The drawings shall be folded and contained in approved-labelled boxes.
Record drawings shall comply with the following:
a. The contractor shall provide the record drawings on the date detailed above and
as a condition precedent to the certification by the Engineer that the work is
complete.
b. Each drawing shall be in accordance with BS 308, Part 1 (to ensure suitability for
microfilming) and of a standard A1 to A4 size to BS 3429.
c. During the course of the works the Contractor shall maintain a fully detailed
records of all changes from the shop drawings to facilitate easy and accurate
preparation of the as installed drawings and to ensure that these drawings are in
all respects a true records of the installation.
The as installed drawings shall show:
a.
b.
c.
d.
e.

The complete installation, including the sizes and routes of all services
The precise location of all services which are buried within the structure.
The location of all isolation and regulating devices
The location of all pumps, water tanks , pits
The manufacturers name, models and type number and full details of duty and
rating for all items off pumps including control equipment.
f. Electrical circuit references.
g. The contract number, the name of the contractor and the date of installation.
Material Submittals
On award of the contract, the Contractor shall provide a list of the items for which
they propose to furnish submittals. All submissions shall be made within 15 days of

AEB-1086-14-REV.00

S-19-8/31
PLUMBING INSTALLATION

BARWA VILLAGE EXPANSION DEVELOPMENT


ELECTRICAL AND MECHANICAL SPECIFICATIONS
VOLUME 03

SECTION 19

the award of the contract or earlier as directed by the Consultants.


The Contractor shall furnish submittals in triplicate or as required for all the
equipments and materials to the Consultant.
Wherever recommended/approved makes have been specified, the contractor shall
comply with the requirements of the specification. If it is necessary to offer any
alternate or substitute material, the contractor may do so, but clearly substantiating
the necessity for the change, cost comparisons, technical equivalence or superiority
of the proposed substitute for the scrutiny of the Consultant.
The following information should at least be covered while furnishing the submittals:
a. Reference number of the specification clause and BOQ.
b. A comparison of the salient points of the equipment/material offered vis-a-vis
specified like capacity, size, model no. etc.
c. A confirmation that the item offered complies fully to the specifications,
drawings and the application in question. Deviations, if any, shall be clearly
spelt out and reasons shall be given for the changes proposed.
d. Complete technical literature for the particular item. In case only general
catalogues are available, the particular item/features offered should be stated
clearly on a separate sheet and also marked on the catalogues. Points not
applicable should be struck-off.
e. Confirmation that equipment/material proposed can be housed within the
space available.
f. General requirement drawings.
g. Samples, wherever required by the Consultant.
The approval of a submittal shall not absolve the Contractor of their responsibility to
provide equipment's/materials/services conforming to the Specifications, Bill of
Quantities and the application in question.
The Contractor shall be responsible for the supply, installation, testing,
commissioning and proper performance of a complete functional system,
Even though some items may not have been specifically stated in the contract
documents.
Waivers for deletion/deviation from the Specification, Tender drawings, Bill of
Quantities etc., must be requested by the Contractor in writing, stating categorically
the change compared to the contract (specified vis-a-vis proposed). The same shall
be considered 'waived' only if written specific approval is obtained from the
Consultant.
The approval of a submittal, any implicit reference or verbal instructions shall not be
treated as a waiver. Waivers shall also be subject to reduction in cost and/or time,
conditional or unconditional as decided by the Consultant.
Material Status Report
A material status report shall be prepared by the Contractor and submitted every two

AEB-1086-14-REV.00

S-19-9/31
PLUMBING INSTALLATION

BARWA VILLAGE EXPANSION DEVELOPMENT


ELECTRICAL AND MECHANICAL SPECIFICATIONS
VOLUME 03

SECTION 19

weeks or earlier as directed by the Consultant. The report shall indicate the following:
a.
b.
c.
d.
e.
f.
g.
h.
i.

Description of the material/equipment


Name of the manufacturer/supplier
Submittals Number
Date submitted
Date of approval
Order number/date and L.C reference, if any
Delivery period and expected time of arrival on site
Actual required-at-site date
Remarks, if any

Samples of Materials
The Contractor shall submit at no extra cost or charge and with no recourse to any
claim for extra time, samples of materials as required by the Consultant for his
approval.
Time required for arranging the sample shall be considered by the Contractor.
Engineer shall and approve the sample and the submittal with reasonable
promptness.
Samples shall remain at site till the final Handing over.
OPERATION AND INSTRUCTION MANUALS
The Contractor shall make provision for the supply of Three (3) copies of the
Instruction Manuals before issue of Practical Completion Certificate. This manual
shall include the following items:
a. Complete list of all items of equipment, controls and accessories as actually
supplied, including serial nos. & all name plate details.
b. A set of 'As-Built' drawings showing equipment layout, pump details, drain pipe layout
and details, electrical wiring & pumped drain piping.
c. The drawings shall show plans and sections necessary to show all required
information correctly.
d. A set of manufacturer's catalogues, wiring diagram and installation drawings relevant
only to the particular item of drainage system equipment concerned. General
catalogues will not be acceptable.
e. Manufacturer's printed spare parts list for all items of equipment.
f.

Operational description of the plumbing system including starting point of start , and
final dropping point

g. Preventive maintenance routine at monthly, quarterly, semi-annually and yearly


intervals and maintenance procedures for all sanitary wares

AEB-1086-14-REV.00

S-19-10/31
PLUMBING INSTALLATION

BARWA VILLAGE EXPANSION DEVELOPMENT


ELECTRICAL AND MECHANICAL SPECIFICATIONS
VOLUME 03

SECTION 19

The O & M instructions shall be in English.


CD-Rom containing all above information shall also be submitted.
19.1.07

PRODUCTS

A. General
Product shall:
1. Meet the requirements of this specification, the general contract
requirements and all contract documentation.
2. Meet the requirements of best international standards and codes of
practice.
3. Meet the requirements of the Consultant and their representatives.
4. Meet the requirements of all local authorities including KAHRAMMA (Qatar
General Electricity and Water Authority)
5. Meet the general requirements of BS or other approved standards as
applicable.
6. Meet the requirements of building fire and safety policies.
Whenever practical, source products from authorized agencies or
representatives with state of Qatar Make and quality of products shall be
subject to the approval of the Consultant/Engineer.
B. Hangers
1. Provide supports for other piping types, such as plastic, mechanically
fused, or packed joined pipe according to the pipe manufacturers published
recommendations. Support continuously where required to prevent
sagging.
2. Provide spring hangers similar to Grinnel Pre-Engineered Spring hangers
on piping where there is vertical travel due to expansion. Limit transfer of
hot load to 20%.
3. Provide constant supports where vertical travel exceeds 40mm (1 ) and
where designated.
4. Provide the arrester support at the end of the pipe turning and end of the
pipe connection from the shaft
5. Provide the arrester support inside the plumbing and drainage shaft
6. Provide the L and T angle support at the pump rooms
C. Sleeves, Floor and Wall Plates
1. Use machine cut and reamed standard weight steel piping. Pipe sleeves
200mm (8) and larger shall have minimum 6mm (1/4) wall thickness.
2. Concealed perimeter risers and runouts may have sleeves of 1.31mm(18
gauge) galvanized steel set around section of insulation to provide freedom
of movement of piping. Extend 50mm(2) above finished floor level.

AEB-1086-14-REV.00

S-19-11/31
PLUMBING INSTALLATION

BARWA VILLAGE EXPANSION DEVELOPMENT


ELECTRICAL AND MECHANICAL SPECIFICATIONS
VOLUME 03

SECTION 19

3. For piping through exterior walls, co-operate with the waterproofing trade at
all times, and do not break any water proofing seal without consent of the
water proofing trade. Provide water proof link seals.
4. Cover pipe sleeves in walls and ceilings of finished areas, other than
equipment rooms, with satin finish stainless tell, or stain finish chrome or
nickel plated brass escutcheons, with non-ferrous set screws. Do not use
stamped steel split plates. Split cast plates with setscrew locks, however,
may be used.
D. Curbs
1. Curbs required for the work and shown on the Structural drawings will be
carried out under other contractors.
2. Detail all required curbs and reinforcing steel on the working drawings for
installation by other contractors.
3. Pre-manufactured curbs for mechanical equipment mounted on roof shall
be supplied by the equipment manufacturer.
E. Concrete
1. Provide 250mm (10) concrete housekeeping pads under all floor mounted
mechanical equipment and supports. Extend pads over the full equipment
base and isolator area.
2. Where floating acoustic reinforced concrete floors are provided in plant
rooms, all concrete works including housekeeping pads, will be undertaken
by a separate division and shown on the structural or Architectural
drawings.
3. Provide reinforced floating concrete bases and inertia plinths that are
specified under sound and vibration control.
F. Covers
1.
2.
3.
4.

Supply frames for installation by others.


Provide covers for pits
Provide gas tight gaskets for water tanks
Provide trench gratings near the water tank

G. Steel
1. Provide steel required for the work including supports, framing of openings
and lintels over openings that are not shown on Structural or Architectural
drawings
2. Provide steel or adequate strength to support equipment and materials
during all operating and test conditions.
3. Support suspended points. Support tanks and similar equipment with
adequate beam strength by saddles with curvature to match the
equipment. Continuously support other equipment.
4. Provide base supports for all pipe risers. Design to distribute operating and
static loads to meet Consultants requirements

AEB-1086-14-REV.00

S-19-12/31
PLUMBING INSTALLATION

BARWA VILLAGE EXPANSION DEVELOPMENT


ELECTRICAL AND MECHANICAL SPECIFICATIONS
VOLUME 03

SECTION 19

5. Fabricate steel supports and hot-dip galvanise after fabrication.


H. Fire-stopping
1. Provide fire-stopping material for all openings around services that pass
through floors or fire rated walls. Provide material for each application as
recommend by the manufacturer, Nullifire Ltd. 3M Gulf Ltd or approved
equivalent. The fire stopping installation shall be in accordance with
manufacturers recommended procedures for each application. A detailed
method statement shall be submitted for Consultants or Engineers
approval prior to commencing the work.
19.1.08

EXECUTION

A. General
Execution shall:
1. Meet the requirements of this specification, the general contract
requirements and all contract documentation.
2. Meet the requirements of best international standards and codes of
practice.
3. Meet the requirements of the Consultant and their representatives.
4. Meet the requirements of all local authorities including Civil Defense and
KAHRAMMA (Qatar General Electricity and Water Authority)
5. Include skilled and trained management and labor team, experienced and
competent to carry out the works herein described.
6. Include full detailed working drawings, coordinated site installation works
and harmonization with all other trades and contractors throughout the
construction programme.
7. Include safety clothing, training and working procedures for all operatives.
8. Include safety equipment, tools and accessories to minimize exposure to
risks.
9. Provide project safety plan to Consultant/Engineer for approval.
10. Execute the works diligently in accordance with programme. Obtain all
approvals and test the works prior to concealment.
11. Comply with Consultant/Engineer supervision and site reports whenever
corrective action is necessary.
B. Inspection, Testing and Certificates
1. Periodic inspection of the work in progress will be made to check general
conformity of the work to the Contract Conditions. Observed deficiencies
will be reported.
2. Correct deficiencies immediately. Meet the requirements of all laws,
bylaws, codes, regulations and authorities having jurisdiction.
3. Give sufficient notices of readiness for inspection and schedule the date
and tome of such inspection and testing.
4. Uncover any work that is covered without consent, upon
Consultant/Engineers request, for examination and restore at no extra cost
to the Owner.

AEB-1086-14-REV.00

S-19-13/31
PLUMBING INSTALLATION

BARWA VILLAGE EXPANSION DEVELOPMENT


ELECTRICAL AND MECHANICAL SPECIFICATIONS
VOLUME 03

SECTION 19

5. Furnish certificates and evidence that the works meets the requirements of
authorities having jurisdiction.
6. Correct deficiencies immediately upon notification.
C. Cutting and Patching
1. Give notification in item to other contractors of openings required for
services works. Supply accurate details of location and size. When these
requirements are not met, bear the cost of cutting and patching.
2. In existing work. All cutting, patching and restoration of finished work to
original condition, will be carried out by other contractors at the expense of
services contractor.
3. Obtain written approval from Consultant/Engineer before cutting openings
through structure.
D. Protection of works
1. Protect all works in this volume of specifications from damage. Keep all
equipment dry and clean at all times.
2. Cover openings in equipment, pipes and valves, pumps, with caps or
heavy gauge plastic sheeting until final connections are made.
3. Repair any damage caused by improper storage, handling or installation of
equipment and materials.
4. Protect equipment, pipes and temporary services installed from weather
damage.
E. Completion
1. Meet the requirements of the General Conditions of Contract
2. Remove all debris from inside systems and equipment
3. Rectify deficiencies and complete work before submitting request for
substantial completion inspection.
4. Protect equipment, pipes and temporary services installed from weather
damage.
F. Completion
1. Meet the requirements of the General Conditions of Contract
2. Remove all debris from inside systems and equipment
3. Rectify deficiencies and complete work before submitting request for
substantial completion inspection.
4. Follow manufacturers written instruction regarding bearing lubrication,
remove grease from pillow-block type bearings and install new grease
before equipment is put into operation.
5. Check and align all drives to manufacturers acceptable tolerances.
6. Adjust belts for proper tension.
7. Check and align all pumps to manufacturers acceptable tolerances.
8. Remove all temporary protection and covers.
9. Remove oil and grease from equipment and base.
10. Clean all fixtures and equipment. Polish all plates surfaces.
11. Vacuum clean the inside of all clean outs, drains. Including pumps coils
and terminal units to ensure that they are free from debris.

AEB-1086-14-REV.00

S-19-14/31
PLUMBING INSTALLATION

BARWA VILLAGE EXPANSION DEVELOPMENT


ELECTRICAL AND MECHANICAL SPECIFICATIONS
VOLUME 03

19.1.09

SECTION 19

GENERAL REQUIREMENTS

Quality of Equipment and Materials


All equipment and materials shall be brand new, of a quality accepted by the
Consultant and presenting no dent, damage or breakage during transportation or
installation.
All equipment and materials shall be from the latest product range of the
manufacturer and shall be approved by the Engineer.
Protection during Storage and Installation
All metal parts shall be protected on site from rust, corrosion and dirt by properly
storing, packing and covering. All rusted parts of metal, subject to the Consultant's
approval, shall be cleaned of corrosion products and given two coats of anti-rust
paint before installation.
All moving/rotating/live parts of any equipment shall be suitably protected for
personnel safety and to avoid injuries.
Paint, Tags and Nameplates
All steel works in connection with supports for drain pipe etc., exposed to the
elements are to be painted with two coats of an approved rust preventive paint,
preferably zinc rich primer and two coats of enamel paint of grey or as approved by
the Consultant. And underground pipe / running through wall must be covered by 2
coat of denso tape for the protection for the concrete partials
Scaffoldings / Lifting facilities
Scaffoldings as necessary for the installation of plumbing system etc shall be
provided by the plumbing system contractor. All such scaffoldings shall be approved
by the Consultant.
Hoisting/lifting facilities to mount the equipments at their final position shall be the
responsibility of the plumbing system contractor in co-ordination with the Main
Contractor.
19.1.10

TESTS AT SITE

General
The Contractor shall submit to the Consultant, one month prior to the date of
commencement of the tests, three (3) copies of the complete test procedures to be
used. The procedures, method of calculation etc., shall be approved by the
Consultant before any test is carried out. Three (3) copies of the test results shall be

AEB-1086-14-REV.00

S-19-15/31
PLUMBING INSTALLATION

BARWA VILLAGE EXPANSION DEVELOPMENT


ELECTRICAL AND MECHANICAL SPECIFICATIONS
VOLUME 03

SECTION 19

furnished to the Consultant for his approval.


The Contractor shall supply skilled staff and all necessary instruments and
carryout tests of any kind on a piece of equipment, apparatus, part of system or a
complete system if the Consultant requests such a test, for determining specified or
guaranteed data as given in the specifications or in the schedule of equipment filled in
by the Contractor.
Any damage resulting from the test shall be repaired and/or damaged material
replaced, all to the satisfaction of the Consultant. In the event of any repair or
adjustment required to be made, other than the normal running adjustment, the tests
shall be void and shall be recommended after the adjustments or repairs have been
completed. The test shall not be void due to circumstances beyond the Contractor's
control.
Pipe work
All main, branches and outlets shall be tested for pressure test 1.5 times of system
pressure.
Equipment
All plumbing system equipment shall be tested in accordance with manufatures
recommendation
Other tests as specified under the specific equipment headings are to be completed
to the satisfaction of the Consultant.
Test on Completion
After finishing the above tests and adjustments, the Contractor shall be responsible
for running a full operational test i.e. leak and gravity, and column test for the whole
drain pipe installed. The test shall operate continuously without readjustments or
repair to the satisfaction of the Consultant.
The complete performance test shall then be repeated. The date of commencement
of the above said tests shall be subject to agreement with the Consultant.
As soon as all tests prescribed in this clause are carried out satisfactorily in the
opinion of the Consultant, a formal Letter of Completion shall be drawn up in three
(3) copies and signed by the Consultant.
19.1.11

COMMISSIONING BY SPECIALISTS

Where ever necessary, it is the responsibility of the contractor to arrange and provide
for visit (s) of specialists to assist him in the pre-commissioning activities, start up
and commissioning activities for the system and/or any other equipment.
Commissioning shall include but not limited to:
a. Preliminary checks to ensure that all systems and system components are in

AEB-1086-14-REV.00

S-19-16/31
PLUMBING INSTALLATION

BARWA VILLAGE EXPANSION DEVELOPMENT


ELECTRICAL AND MECHANICAL SPECIFICATIONS
VOLUME 03

SECTION 19

satisfactory and safe condition before start up.


b. Preliminary adjustments and setting of all equipment consistent with eventual
design performance.
c. Energizing and setting to work all plant.
d. Final regulation and demonstration that the installation delivers the correct rate of
flow of fluids at the conditions specified in the Contract Documents.
The contractor shall employ the services of an approved independent commissioning
Engineer to commission all the system including pressure, leak test for the plumbing
system.The results of the commissioning shall be recorded by the Contractor
endorsed by the Engineer and included in the Operation and Maintenance manual.
The items on the certificate shall be read in conjunction with the appropriate Clauses
of this Specification and the design requirements of the drawings and the certified
results and statements pertaining to the commissioning procedure shall be
interpreted accordingly.
19.1.12

PRACTICAL COMPLETION CERTIFICATE

On satisfactory acceptance of Completion tests, the Contractor shall deliver the


Operation and Maintenance Manuals along with 'As built' drawings to the Client. The
Practical Completion certificate will be issued by the Consultant only after obtaining
the Operation and Maintenance Manuals and As Built Drawings.
Recommendation for release or the release of practical completion certificate would
not absolve the contractor of his responsibility to provide an installation complete in
all respects and in satisfactory working order. If, at any time of the contract, any item
is discovered to be short supplied or not in working order, the contractor shall be
liable to make good the same to the satisfaction of the Consultant.
19.1.13

GUARANTEE AND MAINTENANCE PERIOD

All equipment, accessories and the complete pipe work for the drainage system and
works shall be guaranteed for 400 days of un-interrupted operation, against all
manufacturing defects and installation defects.
The guarantee shall start from the date the Letter of Practical Completion is issued.
.
In addition, regular visits of specialist maintenance personnel as required by the
equipment supplier shall be provided.
During the maintenance period, the Contractor shall demonstrate that all plumbing
work in comply with test procedures.
Maintenance and Final Handing Over Test
During the last month of the 400 days Maintenance period, the Contractor shall
demonstrate to the Consultant that all equipment and systems are operating

AEB-1086-14-REV.00

S-19-17/31
PLUMBING INSTALLATION

BARWA VILLAGE EXPANSION DEVELOPMENT


ELECTRICAL AND MECHANICAL SPECIFICATIONS
VOLUME 03

SECTION 19

according to the capacities and the manner set down in the specifications.
The Maintenance Certificate will not be issued to the Contractor until all sanitary ware & pipe
works has been tested to the complete satisfaction of the Consultant
19.2.00 TECHNICAL SPECIFICATION PLUMBING SERVICES
19.2.01

GENERAL

Hot and Cold water services within the building shall comply with British Standard
code of practice BS 6700: 1987 CP 342 : Part 2 : 1974.
All hot water pipes shall be insulated at site with manufacturer sleeves and sized to
O.D. of pipes.
All pipe work fittings, valves and other components forming the piping installation
shall be erected such that they can be dismantled and are accessible for repair and
replacement. Where valves and equipment are fitted, unions and flanges shall be
provided as appropriate for the diameter pipe work in order to allow valves and
equipment removal.
All pipe work shall be erected such that it may be vented and drained satisfactorily. All
low points in the system shall have drain cocks fitted and high points shall have air
bottles or automatic air vents.
A.

All cold and hot water pipes exposed to the sun at roof shall be insulated with rigid
fibreglass 25 mm thick with density 64 Kg/m3 or Flexible Elastomeric Insulation:
Closed-cell, sponge- or expanded-rubber materials. Comply with ASTM C 534,
Type I for tubular materials and Foam insulation materials shall not use CFC or
HCFC blowing agents in the manufacturing process and Flexible Elastomeric
Adhesive shall Comply with MIL-A-24179A, Type II, Class I. this shall be lagged
with glass cloth and applied with three coats of anti fungus vapour barrier as its
weather proof/sun proof protective material. All the pipes must be claded with light
weight Aluminim sheet to protect against mechanical damages.
b) Polypropylene PP-R Pipes and Fittings
All hot and cold water pipes for underground / buried , inside the building or inside
shafts shall be in polypropylene plastic PP-R pipes to DIN 8078. Fittings shall be both
welding fittings and metal insert fittings. All metal inserts shall be in dezincification
resistant brass. Jointing between pipes and fittings shall be made by melting the
parts. Locations where pipe is to be connected to equipment, PP-R fittings with metal
insert shall be used.
Polypropylene valves shall be used where available with manufacturers in their
product range. All the components inside the valve in contact with water shall be
dezincification resistant brass. For those valves (type and sizes) which are not

AEB-1086-14-REV.00

S-19-18/31
PLUMBING INSTALLATION

BARWA VILLAGE EXPANSION DEVELOPMENT


ELECTRICAL AND MECHANICAL SPECIFICATIONS
VOLUME 03

SECTION 19

available in the PP-R pipe manufacturer range, shall be made dezincification


resistant brass as described in clause below.
All components of polypropylene pipe systems shall be suitable for a working
pressure of 6 bars at 70 0C for 50 years life expectancy. The whole polypropylene
piping installation including supports shall be carried out strictly in accordance with
manufacturers recommendations.
The contractor shall make allowance for
expansion in the pipework. The whole PP-R installation shall be guaranteed for a
period of 5 years.
19.2.02

INSTALLATION, STORAGE AND PROTECTION

All pipework, fittings and accessories shall be installed strictly in accordance with the
manufacturer's recommendations and due allowance made for thermal movement.
All pipework, fittings and accessories shall be obtained from one manufacturer only,
who shall be nominated by the contractor in writing and approved by the Consultant
prior to ordering any materials. Materials from different manufacturers shall not be
incorporated into the system. All pipework, fittings and accessories shall be stored in
properly ventilated well-supported racked storage sheds.
All pipework shall be erected to present a neat and orderly appearance arranged to
or at right angles to the structural member of the building, giving maximum headroom
and not obstructing window or doorways. Pipes shall bend round piers, projections
and into recesses forming part of the structural works whether so indicated on the
drawings or not. Pipework shall be erected such that there is a minimum of 50 mm
clear below to the finished floor level and at least 25 mm clear to the finished wall
face.
The pipeworks, which are to be insulated, contractor shall allow space for each pipe
around its whole circumference. Adequate clearance shall be provided between
insulated pipework running together and adjacent to walls and floors. Clearances
between insulation and floor and insulation and wall shall be as for bare pipework.
No joints shall be formed in the thickness of walls, floor slabs or roof slabs. The pipe
droppes connecting the sanitarywares shall be dropped in wall by chasing the wall in
proper manner with 2 coat of 3mm foam wrapping tape. The final wrapping with PVC
Tape White vapor-retarder tape matching field-applied PVC jacket with acrylic
adhesive; suitable for indoor and outdoor applications During the installation period
open ends of pipework shall be capped off using purpose-made plugs or blank
counter flanges. Pipework shall be kept free of dirt and other foreign debris at all
times.
All pipework fittings, valves and other components forming the piping installation shall
be erected such that they can be dismantled and are accessible for repair and
replacement. Where valves and equipment are fitted, unions and flanges shall be
provided as appropriate for the diameter pipework in order to allow valves and
equipment removal.

AEB-1086-14-REV.00

S-19-19/31
PLUMBING INSTALLATION

BARWA VILLAGE EXPANSION DEVELOPMENT


ELECTRICAL AND MECHANICAL SPECIFICATIONS
VOLUME 03

SECTION 19

All pipework shall be erected such that it may be vented and drained satisfactorily. All
low points in the system shall have drain cocks fitted and high points shall have air
bottles or automatic air vents.
19.2.03

PIPE SUPPORTS, BRACKETS AND HANGERS

All pipework shall be adequately supported in such a manner as to permit free


movement due to expansion, contractions, vibration or other changes in the system.
Supports shall be arranged as near as possible to joints and changes of direction.
Spacing of supports shall comply with Table 13 contained in British Standard BS
5572: 1978. Vertical rising pipes particularly in shafts shall be adequately supported
at the base to withstand the total weight of the riser. Under no circumstances shall
branches from vertical rising pipes be the means of support for the vertical pipework.
Pipework up to and including 65 mm diameter shall be supported clear of the
structure with cast brass brackets. Where exposed to view, bright finish brass
hospital brackets shall be used with rawl plugs and brass screws.
All multi runs of pipework within false ceilings or service shafts shall be supported on
purpose designed proprietary brackets suitable for carrying more than one pipe run,
and shall be secured using expanding plugs or other purpose designed fixing
devices. Softwood plugs shall not be allowed. All purpose designed proprietary
brackets shall be submitted to the Consultant for approval prior to ordering.
All Steel hangers and supporting brackets shall be electrogalvanized steel.The
spacing of supports where not specified must not exceed the spacing given in the
following schedules. Where one-support carries more than one pipe diameter the
spacing shall be that specified for the smallest diameter.
Maximum Spacing of Supports for copper pipes
Nominal Size
of Pipes

Support Spacing
Vertical Pipes

108 mm
67 mm
67 mm
54 mm
42 mm
35 mm
28 mm
22 mm
15 mm

3.6 m
3.6 m
3.0m
3.0 m
3.0 m
3.0 m
2.4 m
2.4 m
1.8 m

Horizontal Pipes
3.0 m
3.0 m
2.7 m
2.7 m
2.4 m
2.4 m
1.8 m
1.8 m
1.2 m

Maximum Spacing of Supports for PPR pipes


Maximum Spacing of Supports
Nominal Size

AEB-1086-14-REV.00

Support Spacing

S-19-20/31
PLUMBING INSTALLATION

BARWA VILLAGE EXPANSION DEVELOPMENT


ELECTRICAL AND MECHANICAL SPECIFICATIONS
VOLUME 03

SECTION 19

of Pipes

Vertical Pipes

100 mm
80 mm
63 mm
54 mm
42mm
35 mm
28 mm
22 mm
15mm

1.50 m
1.50 m
1.25 m
1.10 m
0.90 m
0.90 m
0.86 m
0.80 m
0.80 m

Horizontal Pipes
1.0 m
0.75 m
0.65 m
0.55 m
0.55 m
0.45 m
0.45 m
0.4 m
0.4 m

All vertical drops shall be supported so as to prevent sagging or swinging. Unless


otherwise indicated, pipe hangers shall be spaced as follows.
a.
b.
c.

20 to 32mm
40 to 100mm
Over 100mm

Not over 2.4m apart Not over 3.0m apart Not over 3.6m apart -

10mm rods
15mm rods
22mm rods

Horizontal steel pipes on the roof shall be supported to prevent sagging or swinging.
The pipes supports spacing shall be as follows.
a.
b.
c.

19.2.04

20 to 32mm
40 to 65 mm
80 to 100mm

1.8 m
2.4 m
3.0 m

PIPE SLEEVES

Pipe sleeves shall be supplied where pipework passes through walls, floors, footings
and waterproofed membranes. Sleeves shall be built in the correct locations at the
time required by the main contractor. The inside diameter of all sleeves shall not be
less than 15 mm larger than the outside diameter of the pipe passing through. Where
pipes pass through buried walls or footings, sleeves shall be 25 mm larger than the
outside diameter of the pipe passing through. The space between the pipe sleeve
shall be neatly packed using asbestos string or rope to prevent the passage of noise,
vermin or smoke. Sleeves shall not protrude beyond the finished surface. Where
pipework is exposed to view and passes through wall or floor, chromium plated
copper pipe flanges of the correct pipe diameter shall be fitted.
19.2.05

VALVES AND STOPCOCKS

All valves and stopcocks shall comply with the regulations of the KAHRAMAA and
shall be made from gunmetal or bronze. Valves shall be provided as shown on the
drawings and detailed below or similar and approved. All valves shall be submitted to
the Engineer for approval and approval obtained in writing prior to ordering.
All valves shall be fitted in readily accessible positions. They shall be of even
thickness throughout, clean and smooth from scale. All stuffing boxes shall be packed

AEB-1086-14-REV.00

S-19-21/31
PLUMBING INSTALLATION

BARWA VILLAGE EXPANSION DEVELOPMENT


ELECTRICAL AND MECHANICAL SPECIFICATIONS
VOLUME 03

SECTION 19

with material specially selected and recommended by the manufacturer for the
particular service in which each valve is used.
Non-return valves shall be in accordance with the valve schedule in this specification.
All non-return valves shall be suitable for both vertical and horizontal mounting and
shall be fitted in readily accessible positions. Shall be installed in discharge line of
pumps and other locations directed by the Engineer to prevent reversal of flow.
1. Gate Valves/Servicing valves shall be used for isolation purpose in the service
pipelines. Valves shall be of the same nominal bore as the pipeline in which they
are installed. Gate valve/Servicing valves shall be of bronze construction with
threaded/flanged ends. The bronze valves shall conform to BS5154. Gate valves
shall have screwed ends & bonnet pattern. The valves shall be pressure rated for
16bar & have a BSI kite mark for quality assurance.
2. Check/Non return valves shall be used wherever required to stop the back flow
i.e as a back flow preventer. Check valves up to 50mm dia.shall be threaded
bronze pattern, spring loaded type with bronze body and PTFE seats and
positive leak tight seals and can be installed in any mounting position (vertically &
horizontally. 65mm dia and above shall be with flanged end connections. The
bronze NRVs shall conform to BS5154. The valve shall be pressure rated for
16bar & have a BSI kite mark for quality assurance. All valves shall be located
so as to provide easy access for operation and servicing.
3. House connection Back flow preventors shall comply the following
House connection back flow preventor shall be double check valve
assemblies capable of preventing the back flow of condaminated water into
portable water supply. It shall consist of bronze (1/2 to 2 in) body
construction that is easy to maintance and service
Maximum working pressure shall be 175 psi.

4. HOSE BIBBS
Hose Bibbs shall be of following
Standard: ASME A112.18.1 for sediment faucets.
Body Material: Bronze.
Seat: Bronze, replaceable.
Supply Connections: NPS 1/2 or NPS 3/4 (DN 15 or DN 20) threaded or
solder-joint inlet.
Outlet Connection: Garden-hose thread complying with ASME B1.20.7.
Pressure Rating: 125 psig (860 kPa).
Vacuum Breaker: Integral or field-installation, nonremovable, drainable,
hose-connection vacuum breaker complying with ASSE 1011.
Finish for Equipment Rooms: Rough bronze, or chrome or nickel plated.
Finish for Service Areas: [Rough bronze or Chrome or nickel plated.
Finish for Finished Rooms: Chrome or nickel plated.

AEB-1086-14-REV.00

S-19-22/31
PLUMBING INSTALLATION

BARWA VILLAGE EXPANSION DEVELOPMENT


ELECTRICAL AND MECHANICAL SPECIFICATIONS
VOLUME 03

SECTION 19

Operation for Equipment Rooms: Wheel handle or operating key.


Operation for Service Areas: Wheel handle
Operation for Finished Rooms: Wheel handle
Include operating key with each operating-key hose bibb.

VALVE CONSTRUCTION/APPLICATION SCHEDULE


Valve Type

Pipe Size

Gate

Check (Silent)

50 mm (2 ) &
Smaller
76 mm (3")
& Larger
65 mm (2-1/2") &
76 mm (3")
All

Check

All

Gate
Ball

AB
IBBM
RS
NRS
UB
ISB
SOB
OS&Y
IPS
FL
SE
19.2.06

Press. Rate
Steam/WOG
/Style
125#/200#

Bonnet/Stem
Assembly

Material/ Body
(Class)

UB/RS
UB/NRS
FL/NRS

AB/IPS or SE293
AB/IPS or SE291
IBBM/FL 415
AB/IPS or SE

150#/300#

Chrome Ball
Rings 3-piece
Spring

150#/500#

Spring

125#/200#
150#/600#

IBBM/BOLT
LOCK
IBBM/BOLT
LOCK

= All Bronze
= Iron Body Bronze Mount
= Rising Stem
= Non-Rising Stem
= Union Bonnet
= Inside Screw
= Screw Over Bonnet
= Outside Screw and Yoke
= Iron Pipe Size
= Flanged
= Soldered Ends
STRAINERS AND DRAIN COCKS

All strainers shall be fitted in a readily accessible position and adequate access shall
be allowed for maintenance and cleaning of strainer basket. Strainers shall be
installed in pipeline before the pump.
Strainers (Y type) up to 80mm dia shall be of gunmetal body & stainless steel screen
material with threaded ends connection.100mm & above shall be of same material
construction with flanged end connection. The body shall be as per BS1400 LG2
standard.

AEB-1086-14-REV.00

S-19-23/31
PLUMBING INSTALLATION

BARWA VILLAGE EXPANSION DEVELOPMENT


ELECTRICAL AND MECHANICAL SPECIFICATIONS
VOLUME 03

SECTION 19

All draincocks shall be of gunmetal and be in accordance with BS 2879:Part 2.


Generally draincocks shall be provided at all low points in the system and other
points where necessary and as directed by the Engineer.
19.2.07

FLOAT BALL VALVES

Float ball valves on the mains shall be of equilibrium type, full bore, 14 bar
medium/high pressure of gunmetal body to BS 1212 Part 1.

19.2.08

AUTOMATIC AIR VENTS & TAPS

The automatic air vents automatically allow accumulated/blocked air in the pipeline
networks to breather out of the system thus removing air pockets and eventually
eliminating related problems such as noise and erratic water supply etc
Automatic air vents shall be fitted at all high points in the system and other points
where necessary. Shall be of high pressure type made of DZR brass body and cap to
BS 2872, fixing components shall of stainless steel. AAV shall be designed for a max
test pressure of 15 bars.
Taps shall be manufactured from chrome plated, DZR brass, and shall be suited
specifically to work on low water supply pressure. Taps operating mechanism shall
be of the traditional spindle design or ceramic disc taps. Taps shall meet the
requirements to BS 5412 the specification for low resistance single taps and
combination tap assemblies.

19.2.09

PIPEWORK INSULATIONS

All thermal insulation shall comply with British Standard BS 5970: 1981 and BS 5442:
1987.
Thermal insulation to pipework shall be carried out by specialists and strictly in
accordance with this specification. No thermal insulation shall be applied to pipework
prior to pressure testing and inspection by the Consultant giving clear instructions for
further insulation applied. In order that tests may be made of the thickness of
insulation to be applied to each pipe size, plant and equipment, the contractor shall
allow for the cost of cutting away one section for each size of pipe, plant and
equipment for inspection by the consultant. If the insulation proves to be of the
thickness specified, then the cut section shall be made good and the whole
installation completed. Should any cut section show a deficiency of thickness, further
sections shall be cut at the direction of the consultant for inspection.
If a deficiency of thickness or any other defects are found, the contractor shall
remove the whole of the insulation installed or as the consultant directs and then
shall supply, deliver and apply new insulation complying with the specification and
restore it to the satisfaction of the consultant. This work shall be carried out at the
contractor's own expense.

AEB-1086-14-REV.00

S-19-24/31
PLUMBING INSTALLATION

BARWA VILLAGE EXPANSION DEVELOPMENT


ELECTRICAL AND MECHANICAL SPECIFICATIONS
VOLUME 03

SECTION 19

Thermal insulation shall be applied to all valves, strainers, non-return valves,


draincocks, automatic air vents, and bosses for gauges/test points. Insulation of
these components in the pipework system up to and including 65-mm diameter
pipework shall be carried out using sectional insulation cut to suit and of the same
size as the line pipework.
No insulation shall be concealed within false ceilings or vertical and horizontal
builders work shafts prior to inspection and approval by the engineer.
Thermal insulation shall be 25 mm thick with a density of 64 kg/m3 rigid fiberglass
sections as set down in British Standard Specification BS 5422: 1977. Or Flexible
Elastomeric Insulation: Closed-cell, sponge- or expanded-rubber materials. Comply
with ASTM C 534, Type I for tubular materials and Foam insulation materials shall not
use CFC or HCFC blowing agents in the manufacturing process and Flexible
Elastomeric Adhesive shall Comply with MIL-A-24179A, Type II, Class I. The sections shall
be lagged with glass cloth and applied with three coats of anti fungus vapour barrier.
All piping, branching off to fixtures chased in the floors or walls shall be protected
according to Table Y of BS 2871:
a. Two (2) coats of clear synthetic lacquer.
b. One (1) layer of asphalt impregnated felt wrap with 25 mm (1 inch) overlaps.
Where exposed to view, the insulation shall be painted with two coats primer and one
finishing coat rubberized paint to an approved color prior to the fixing of aluminum
bands at 1.2 m centers. The finishing color shall be to British Standard BS 1710:
1975, identification of pipelines complete with direction arrows. All the pipes must be
claded with light weight Aluminim sheet to protect against mechanical damages
19.2.12

COLD WATER STORAGE TANKS

Cold water storage tanks shall be manufactured to British Standards and comply
strictly with the Water Department's Regulations of the State of Qatar. The following
tank may be used:
a. Roof Tanks
GRP sectional water tank complete with bolted inspection cover and with
gunmetal pipe connections pre-molded in position. The tanks shall be suitable for
ultra violet light and comply with the National Water Council of the United
Kingdom and /or Water department of the State of Qatar, shall be located at roof
level.
The tanks shall be provided to the capacities, dimensions and locations shown on
the drawing. Each tank is to be fixed on a base, which supports the whole of the
tank. The details of the tank base are to be approved by the engineer before any
installation work begins.

AEB-1086-14-REV.00

S-19-25/31
PLUMBING INSTALLATION

BARWA VILLAGE EXPANSION DEVELOPMENT


ELECTRICAL AND MECHANICAL SPECIFICATIONS
VOLUME 03

SECTION 19

All tanks shall be assembled on the supporting bases in accordance with the
Manufacturer's instructions, using torque wrenches to prevent damage to the
sections due to over-tightening of nuts and bolts
The tank shall have the following additional components in addition to the listed
above:
a. Low level electric float switches interlocked to their pressure pumps.
b. External ladder of GRP or aluminium, supplied by the Tank
manufacturer.
c. Internal ladder of Fibre Glass or Stainless steel comply with grade 316 L
supplied by the Tank manufacturer.
d. Vent with wire mesh
e. External graduated water level indicator
f. Channel base, of galvanized steel
g. Interconnecting pipes with valves
h. Overflow and drain connection
i. Access cover
The Contractor shall supply and assemble at Site sectional water tank of hot
pressed moulded.
GRP insulated panels (Glass Reinforced Plastic) of ivory or grey colour provide
with lockable Manhole covers air vent with overflow and all piping connections.
The panels shall comply with BS 7491: part 3: 1994 and shall have convex shape
to assist a complete draining of water of the following characteristics:
a.
Specific gravity of 1.8
b.
Tensile strength of not less than 850 kg/cm
c.Flexural strength of 1600 kg/cm
d.
Impact strength of 50 kg-cm/cm
e.
Thermal expansion of 2.1 x 10-5 C
f. Thermal conductivity of 0.02 kcal/m hr C (insulated panels)
g.
Water absorption less than 0.2%
h.
Glass content more than 30%
i. No light transmission
j. Gasket of synthetic rubber
k.Bolts and nuts of stainless steel
l. Frame angles and frame plates of hot dipped galvanized steel
m.
External ladder shall be GRP or Aluminium
n.
Internal ladder of rigid UPVC or SS according to Manufacturer's
Standards
o.
Tie rods of stainless steel
p.
GRP panel thick not less than 8 mm
q.
Resin cover of 2 mm
r. Glass tube level indicator for all compartments
19.2.13

HOT WATER SERVICE HEATERS

Individual Water Heater

AEB-1086-14-REV.00

S-19-26/31
PLUMBING INSTALLATION

BARWA VILLAGE EXPANSION DEVELOPMENT


ELECTRICAL AND MECHANICAL SPECIFICATIONS
VOLUME 03

SECTION 19

Water heater shall be thermal - electric, individual constructed from heavy gauge high
carbon steel tank with allaying at 2cm CFC free compact foam insulation and to be
glass-lined. Insulation between inner and outer container shall be of CFC free,
flame retardant pure-foam of minimum 30 mm thickness, according to ISO standard
3582. Internal surface to be glass lined.
The water heater shall be of pressurized type, horizontal or vertical type above false
ceiling, suitable for a working pressure of 8 bar and tested for 16 bar.
The heating element constructed to BS 3456 shall be from zinc-plated, copper
sheathed resistance wire, embedded conifer rod type immersion type protected
against stress cracking and pitting corrosion complete with thermostat of 20 Amps.
minimum rating and an additional safety temperature limiter for protecting the water
heater against overheating with 2 years warranty. The heating element shall be
brazed on to a screw - on immersion type apparatus plate.
The loading of water heaters shall be 1.0 kW for capacities of 30 litres, 1.5 kW each
for capacities of 50 litres and 2 kW for capacities for 80 litres and 100 litters - 240v, 50
Hz. single-phase supply, the respective loading shall be at heat recovery of 50 degree
C at one (1) hour. The Water heater shall be complete with pressure relief valve
(preset according to allowed working pressure), non-return valve and temperature
gauge.
Combination Temperature-and-Pressure Relief Valves: ASME rated and stamped.
Include relieving capacity at least as great as heat input, and include pressure setting
less than domestic-water heater working-pressure rating. Select relief valves with
sensing element that extends into storage tank. Anode Rod shall be Replaceable
magnesium
Glass lined heaters of approval make can be accepted as alternative.
19.2.14

PUMP SETS
COLD WATER BOOSTER PUMP SETS

Supply and install pressure booster sets where shown on drawings and in accordance
with the schedule of equipment furnished. The booster shall generally comprise of vertical
multi-stage pumps driven operating on variable frequency drives to achieve varying pump
speed to give uniform water pressure in the ring mains of the system
Quality Assurance
Manufacturer shall assume "Unit Responsibility" to ensure that all components effectively
interface to properly execute the sequence of operation specified herein.
The manufacturer shall have a minimum of 30 years of experience in the design and
construction of domestic water presser booster systems. Pumps shall be rated for a
minimum of 1190kPa working pressure.
The package pressure booster shall be hydraulically tested to 1100kPa for a minimum of
one hour.
The manufacturer shall be fully certified by the International Standards Organisation per
ISO 9001. Proof of this certification shall be furnished at time of submittal

AEB-1086-14-REV.00

S-19-27/31
PLUMBING INSTALLATION

BARWA VILLAGE EXPANSION DEVELOPMENT


ELECTRICAL AND MECHANICAL SPECIFICATIONS
VOLUME 03

SECTION 19

Manufactured Units
The packaged domestic water pressure booster system shall consist of a structural base,
pumps, motors, suction & discharge headers, pressure vessel, control panel, variable
frequency drive and necessary interconnecting piping.
System shall require a single point power connection and suction & discharge piping
connections.
Each pump in the system shall be of equal size to minimise spare parts requirements.
Pumps shall have the duty points as scheduled in the drawings.Packaged pump sets shall
be self-contained fully automatic packaged units using vertical multi stage, high efficiency
pumps, of stainless construction, unless otherwise indicated. The pumps shall be
interconnected using copper pipe work to BS.2871 Table X and shall incorporate isolating
valves and non-return valves. The units shall be complete with duty/ standby pumps, a
hydraulic accumulator with replaceable diaphragm and an IP65 automatic control panel all
mounted on a common heavy gauge galvanised steel base plate.
The selection of pumps shall be made considering the NPSH in the event of the water
Reservoir is located below the pump suction level. The speed of pumps shall not exceed
2900 rpm. The pressure sizing shall be made in order to provide minimum run time on the
lead pump.
Components
Water pressure booster pump set package shall comprise of 1 x duty, 1 x stand-by, and 1
x diaphragm pressure vessel unless otherwise noted. Duty and stand-by pump sets shall
be of identical performance characteristics. All the pumps shall be vertical multistage
design having all wetted parts in stainless steel usable for potable water applications. The
packaged pumping system shall be constructed with Type L copper headers. Unit shall be
rated for 1.5 times the working pressure. Headers shall be easily removable to allow for
service access and moving the package through doorways.
Each pump shall be fitted with isolating valves, non-return valve, interconnected with
copper piping to copper suction and delivery manifolds with pressure gauges fitted at the
common suction and delivery points. The operation of the pumps shall be controlled by
PLC based control panel on fall and rise in water pressure. Low water level in tanks shall
be sensed and controls arranged to prevent dry running of pump sets at any time. The
diaphragm pressure vessel shall be fabricated steel construction to housing a removable
bag. The internal surface of the vessel shall be coated with epoxy polyester resin, ideally
suitable for potable water application. Vessels shall be pre-charged with nitrogen to the
correct pressure at the factory test stage. The integral control panel shall be rated to IP 65
and shall contain the following minimum items.
a. Starter with overloads for each motor.
b. Variable frequency drives.
c. Door interlocked TP&N isolating switch.
d. System pressure gauge.
e. Residual current circuit breaker of 100ma rating.
f. Set timing relays.
g. Hand/off/auto switch for each pump.
h. Duty pump selector switch.
i. Run and trip indicators for each pump.
j. Indicators for power on & low water level.

AEB-1086-14-REV.00

S-19-28/31
PLUMBING INSTALLATION

BARWA VILLAGE EXPANSION DEVELOPMENT


ELECTRICAL AND MECHANICAL SPECIFICATIONS
VOLUME 03

k.
l.
m.
n.

SECTION 19

Main neutral link.


PLC controller with adequate digital/analogue input/output data points.
Ground fault alarm.
Volt free contacts for monitoring signals to BAS as per data point schedule furnished.

The pump logic controller shall provide the following standard user-selectable features:
a.
b.
c.
d.
e.
f.
g.

Low Suction Pressure Alarm and Cut Out


High System Pressure Alarm and Cut Out
Low level Alarm and Cut Out
No - Flow Shut Down
Audio Visual alarm with push button silence feature
Overload Failure Alarm
Pump Failure Alarm

Motors shall meet EC specifications and shall be of the size, voltage and enclosure as
specified.
The pump logic controller shall be microcomputer based and hold its software in EPROM.
On-line field modified data entries, such as stage point, or method of staging, shall be
stored in EEPROM. EPROM memory storage shall prevent accidental loss of data due to
voltage surge or spike. In the event of a complete power outage, all factory pre-set data
values remain stored and available for recall by the operator.
The pump logic controller shall operate if the microcomputer should fail and it shall revert
to HAND operation. The HAND operation shall absolutely mimic standard selector
switches. The number of pumps that will operate in HAND is predetermined from prior
HAND operation, and shall be held in memory with CPU fail and power off.
The pump logic controller shall be powered by 120V/240V AC power from a multi-tap
control power transformer (suitable for voltages of 208V, 240V, 415V, 460V, 575V) within
the control enclosure. The controller shall be equipped with an integral, regulated 24V DC
power-supply to power analogue input signals. The Pump Logic Controller shall be
capable of receiving four 4-20mA analogue input signals and RTD signals.
The staging of pumps shall be user-selectable based on pressure.Pressure shall be
derived from a transducer with a 4-20mA analogue input.The control enclosure shall
conform to NEMA 1 requirements and it shall include motor starters, overloads, inputoutput board and NEMA 4 rated operator interface.The 70E controller shall have off line
and on line diagnostic software. Off line diagnostics shall consist of CPU, EPROM and
RAM memory test. The controller shall have digital input diagnostics, display test, program
test and all analogue and digital I/O user-tests. Fault information may be accessed by
interrogating the pump logic controller through its HELP key.
The pump logic controller shall be powered by 220/1ph./50Hz power. The incoming power
and I/O circuitry shall reject electromagnetic (EMI) and radio frequency interference (RFI).
All digital outputs shall be externally isolated.The pump controller shall be capable of
operation in ambient conditions of 0deg C to 60deg C and a humidity range of 5% to 95%,
non-condensing.All external sensors/transmitters and switches shall be powered by the
pump logic controller through its integral 24V DC power-supply. Over voltage and short
circuit protection shall be on-board. All analogue circuits shall be protected with a fast-

AEB-1086-14-REV.00

S-19-29/31
PLUMBING INSTALLATION

BARWA VILLAGE EXPANSION DEVELOPMENT


ELECTRICAL AND MECHANICAL SPECIFICATIONS
VOLUME 03

SECTION 19

acting fuse and sacrificial input resistors.The controller's user interface shall contain a 2
line x 20-character liquid crystal display with 1/4" characters.
The pump logic controller shall be capable of operating in automatic, manual or off-line
diagnostic modes. One level of password and software security shall be provided for
protection of field programs and user-accessible features.
Hardwire communication shall be provided to the Energy Management System. This shall
include remote start/stop, system alarm output and pump status indication.
19.2.15

WATER FILTERS

A packaged multimedia filtration system shall be supplied for turbidity odor and smell
removal.
Tanks shall be of fibre glass construction rated for 100 psig, working pressure and
hydrostatically tested at 50% in excess of the working pressure.
Access opening for tank shall be provided. Support for tanks shall be structural steel
strap legs welded to lower tank head or adjustable jacklegs.
Tank shall be sandblasted internally to white metal, and then coated with 8-10 mils
DFT epoxy polyamide. The exterior surface shall be cleaned and coated with 2-3 mils
DFT rust resistant primer.
Upper distribution system shall be of the baffle type to evenly distribute the water
over the entire tank area.
Lower distribution system shall be of a proven design constructed with individual fine
slotted non-clogging polyethylene strainers arranged for even flow distribution
through the resin bed.
The main operating valve shall be an industrial Automatic Multiport diaphragm type,
slow opening and closing, free of water hammer. The diaphragm assembly shall be
fully guided on its perimeter when pressure actuated from one position to another to
assure a smooth reliable shut-off without sticking. There shall be no contract of
dissimilar metals within the valve and no special tools shall be required to service the
valve.
The manufacturer of the equipment shall manufacture the main operating valve.
Single units shall have an internal automatic by-pass of untreated water during
regeneration. Valve shall have a treated water sampling cock.
An automatic flow controller shall be provided to maintain proper backwash and flush
rates over wide variations in operating pressures and require not field adjustment.
A factory-mounted and wired cycle controller shall incorporate an adjustable time
switch with multiport pilot valve to control all steps of automatic regeneration.
Provision for push-button initiated regeneration shall be included.
An electrical signaling device shall initiate regeration with 240V / 1 ph / 50 Hz power
supply.

AEB-1086-14-REV.00

S-19-30/31
PLUMBING INSTALLATION

BARWA VILLAGE EXPANSION DEVELOPMENT


ELECTRICAL AND MECHANICAL SPECIFICATIONS
VOLUME 03

SECTION 19

All filter media shall be of good quality possessing characteristics of durability, long
life and resistance to attribution and shall not impart taste, odor or color to the water
being treated. Filter media shall be selected for removing particulates down to 10micron size.
The filtration unit shall be supplied to remove suspended matters, dechlorination and
organic removal and odor removal.
The granular media (multilayered) shall consist of three distinct filter layers in addition
to a support layer. Each layer shall be of selected density and particle size to stratify
in the same order following a backwash. The filters layers shall be stratified with the
coarsest layer at the top and the finest layer at the bottom. Particle retention shall be
10 micron or larger.
19.2.16

STERILIZATION OF WATER SERVICES

All pipework, fittings and storage tanks shall be sterilized starting with the external
water supplies, storage tanks and finally the water distribution system.
Sterilization may be done by a specialist company and a water sample to be tested
from any government approved laboratory and a Certificate to be submitted to the
Engineer concerned.
Chlorine Disinfection
The system shall be filled with Chlorinated water at an initial concentration of 50 mg/l
(50p.p.m) for a contact period of 1 hr. If the free residual chlorine measured at the
end of the contact period is less than 30 mg/l (30p.p.m), the disinfection process shall
be repeated.
After successful chlorination, the system shall be immediately drained and thoroughly
flushed with clean water. Flushing shall continue until the free residual chlorine is at
the level present in the drinking water supplied.

The following procedure shall be adopted for sterilization of the water distribution
systems:
a. Flush out all tanks, pipework, etc.
b. Recharge all water systems adding sufficient sterilization chemical at
the roof tank to a concentration of 1-2 parts per million. The
concentration shall be confirmed by using a measuring instrument
approved by the water department.
c. Starting with the draw-off point nearest the cold water storage tank,
each draw-off point shall be opened until chlorine odor is present at
each draw-off.
d. When all draw-off points have discharged chlorinated water, the cold
water storage tanks shall be recharged adding sufficient sterilization
chemical to give the correct concentration of 1-2 parts per million of

AEB-1086-14-REV.00

S-19-31/31
PLUMBING INSTALLATION

BARWA VILLAGE EXPANSION DEVELOPMENT


ELECTRICAL AND MECHANICAL SPECIFICATIONS
VOLUME 03

SECTION 19

chlorine. The system shall then remain charged for a minimum period
of one hour.
e. The water shall then be chemically analyzed. Should no residual
chlorine be found, the test shall be repeated until satisfactory results
are obtained.
f.

Drain down all storage tanks and pipework, flushing out tank and
pipework, and run the system clean prior to retesting of the water to
ensure no residual chlorine is present.

g. Finally a sample of tank water shall be taken to the Water Department


for testing. The results of these tests shall be forwarded to the
Consultant for his approval.
Cisterns with Internal Coatings

Because high chlorine concentrations and other disinfectants can adversely


affect new coatings in cisterns, copper pipes, etc., and release chlorinated or
other compounds into the water, the coating shall be thoroughly cured before
disinfection takes place and care shall be taken not to exceed 50 m/l chlorine
concentration or, in the case of an alternative approved disinfectant, the
manufacturers recommendation.
Localised Repairs
Junctions or fittings for a localised repair, inserted into an existing external
pipeline shall be disinfected by immersion in a solution hypochlorite containing
200 mg/l of available chlorine. Where other disinfectants are used, the
concentration shall be in accordance with the manufacturers
recommendations
Safety
Systems, or parts of systems, shall not be used during the disinfection
procedure and all outlets shall be marked with DISINFECTION IN PROGRESS, DO
NOT USE.
To avoid the generation of toxic fumes, no other chemicals, like toilet cleaners
shall be added to the water until disinfection is complete.
All building users shall be informed of the disinfection before it takes place.
This includes those users not normally in attendance during working hours i.e.
cleaners and security guards.

19.2.17

INCOMING WATER SUPPLY AND METER

The plumbing contractor shall take connections from the proposed main water supply
to the main electronic water meter cabinet, which shall be located at boundary line of
the project, as per the tender drawings. The water meter and cabinets shall be

AEB-1086-14-REV.00

S-19-32/31
PLUMBING INSTALLATION

BARWA VILLAGE EXPANSION DEVELOPMENT


ELECTRICAL AND MECHANICAL SPECIFICATIONS
VOLUME 03

SECTION 19

supplied and installed by the contractor and all meters and cabinets to be as per
KAHRAMAA (Water Division) approved meter.

19.2.19

SNG SYSTEM

General
This specification is to be read in conjunction with the drawings. The complete
installation shall be carried out by a Specialist Contractor and shall comply with the
current waqood, QCDD, B.S. codes and codes of practice. The Contractor shall
ensure that the materials and installation are suitable for local conditions and comply
with local regulations.
The Contractor shall be responsible for the supply, installation and execution of the
works described in these specifications for the SNG system to produce a complete,
tested, commissioned and fully operational installation including all necessary labor
and materials whether or not specified in details.
SCOPE OF SUPPLY AND WORK
A. SNG supply
The SNG connection shall be supplied to the building from the external SNG
connection according to the layout.
B. Pressure Regulator
Shall have general shut off valves for source of gas supply, pressure to be
determined by the SNG specialist contractor. The system pressure, pressure
restricting stations are per the tender issued drawing.
C. Internal Piping Works
Piping should be includes manual shut off valve with locking in closed, emergency
shut off valve (solenoid valve 220V AC, NPT), safety automatic shut off, cooker
automatic cut off valve and cooker flexible hose. Kitchen shall have gas leak
detection system.
D. Gas Detection System
The Contractor shall provide a fully functional system comprising of all components
whether or not mentioned in the design drawings. The complete SNG gas detection
system installation shall be carried out by approved supplier cum installer.All the
shaft for the SNG is fitted with gas detection system at the bottom of shaft and these
shafts are vented above at roof.

AEB-1086-14-REV.00

S-19-33/31
PLUMBING INSTALLATION

BARWA VILLAGE EXPANSION DEVELOPMENT


ELECTRICAL AND MECHANICAL SPECIFICATIONS
VOLUME 03

SECTION 19

F. Pipes and Fittings


All pipework shall be in under ground comply with HDPE or seamless Carbon steel.
pipe sch 40 conforming to ASTM A53 welded pipe. The high level piping up to gas
meter shall be seamless C.I. pipe sch 40 conforming to ASTM A53 with welding
joints. From the meter to internal kitchen piping up to isolating valve shall be copper
pipe confirming with copper tube BS EN 1057 R250 (equivalent to BS 2871 table X).
from isolating valve to burner point shall be rubber hose pipe.The All the changes in
direction of pipes shall be achieved by using proper fittings. No gas pipe shall be
bent. All branch connections shall be taken from the top or sides of horizontal main
lines and not from the bottom. Compression fittings will not be allowed on gas
pipework.
G. Isolating Valves
Valves shall be of lever operated ball type with an indication of ON and OFF
positions. Valves shall be of the non-lubricated type and constructed of non-ferrous
materials. The valves shall be designed for capillary joint connections to the pipe
lines. Where screwed connections are provided for pipe line connection, they should
have I.S.O. metric thread in accordance with BS 3643. The valves shall be of
wrought copper or bronze. Details of the valves shall be submitted to the Engineer for
approval.
H. Identification of Gas Installation
All pipes shall be identified with the appropriate color near stop valves, at any change
of direction and at 1.8m intervals along the line by means of self-adhesive 2 ply vinyl
tapes. Self adhesive vinyl tapes shall be wrapped to overlap so that the tape adheres
to itself as well as to the pipe. Each junction point shall be clearly marked by a color
band. Self adhesive vinyl banding shall not be less than 50mm wide and shall include
lettering to indicate the SNG.
I. Testing and Commissioning
Testing and commissioning of the whole installation shall be carried out in
accordance with relevant BS, NFPA Standards. It shall be the responsibility of the
Specialist Contractor to provide all labor, materials, instruments and equipment
required to test and commission the installation to the satisfaction of the Engineer.
The tests shall be conducted and all defects rectified before any part of the
installation is concealed or buried.
The pressure tests on the pipework shall be carried out by the Specialist Contractor
as described below.
Plug all open ends of the pipework and put the pipework on pressure test (7 bars)
with the air. Disconnect the air supply and keep the pipework on test for 24 hours. No
leak shall be observed during this period. If the above pressure is not maintained, the
Specialist Contractor shall detect any leaks by the use of soap solution applied

AEB-1086-14-REV.00

S-19-34/31
PLUMBING INSTALLATION

BARWA VILLAGE EXPANSION DEVELOPMENT


ELECTRICAL AND MECHANICAL SPECIFICATIONS
VOLUME 03

SECTION 19

externally to joints and connections. The soap solution shall be carefully washed off
and dried after testing.
Care shall be taken to ensure that all valves on main and sub-main branches of the
pipework are properly subjected to this test.
19.2.21

NOTES

1. Equipments warrantees shall come into effect only from the date of
commissioning and handing over of the equipment / system to the end user.
2. Contractor to submit minimum three nos. of hard copies of the As Built drawings,
O & M Manuals, etc. along with the soft copy.
3. Contractor to submit the list of all calibrated equipments with the calibration
expiry date.
4. Catwalk and platform to be provided wherever the void area above false ceiling is
high.

AEB-1086-14-REV.00

S-19-35/31
PLUMBING INSTALLATION

BARWA VILLAGE EXPANSION DEVELOPMENT


ELECTRICAL AND MECHANICAL SPECIFICATIONS
VOLUME 03

19.2.22

SECTION 19

SCHEDULE OF APPROVED MANUFACTURER


ITEM

MANUFACTURER

COUNTRY OF ORIGIN

1. Pressure PVC pipes and Fittings George Fischer


Pullen
ABS
2. Copper Pipes and Fittings

3. Valves

4. Water Heater

5. Water Pumps

SWITZERLAND
UK
SWEDAN

YORKSHIRE
WEDNESBURY
MUELLER BRASS
CONEX

UK

PEGLER
CRANE
HATTERSLY

UK

SANTON
A.O.SMITH
IGNIS

UK

WILO

GERMANY
UK
DENMARK
UK

SPP
GRUNDFOS
ARMSTRONG

UK
UK
UK
UK
UK
USA
ITALY

6. Thermal Insulation

KIMMCO
KUWAIT
ARABIAN FIBERGLASS
KSA
EXEED
UAE
ARMAFLEX
KSA

7. Water Filters

CULLIGAN
USA
AQUASANA
NETHERLANDS
INNOVA
ITALY
BETZ DEARBORN
USA
DREW MARINE CHEMICALS USA

8. Pressure Reducing Valves

GRINNEL
HONEYWELL
ZURN
NIBCO
ARMSTRONG

9. PPR Pipes and Fittings

AEB-1086-14-REV.00

AQUATHERM
COPRAX
WEFATHERM
HEPWORTH
GF+
HAKAN PLASTICS

UK
GERMANY
USA
USA
USA
GERMANY
ITALY
GERMANY
UK
SWITZERLAND
TURKEY

S-19-36/31
PLUMBING INSTALLATION

BARWA VILLAGE EXPANSION DEVELOPMENT


ELECTRICAL AND MECHANICAL SPECIFICATIONS
VOLUME 03

10. Pipes Hangers & Supplies

SECTION 19

HILTI
FISCHER
GRINNEL
TOLCO
COOPER B-LINE
FLAMCO

11. Water Tanks

EXTRACO
FTC
AL MUFTAH
BK PLATECH
SAMSUNG-MCP

GERMANY
GERMANY
USA
USA
USA
NETHERLANDS
UAE
UAE
QATAR
KOREA
KOREA

12. SNG EQUIPMENTS SUPPLIER


QATAR GAS
UNIGAZ
AL JABER

QATAR
QATAR
QATAR

NOTES:
1) The Country of Origin does not limit the respective manufacturers from having
Similar manufacturing facility at other countries. Most of the manufacturers have
manufacturing facilities globally (USA /Europe /GCC/ Asia) and these listed
manufacturers assure that the products manufactured in any of their facility
comply with the assured Quality. The end user may source the materials from
any of the facility to suit their requirements.
2) The description of each system or equipment detailed in the specification has to
be read with respect to the project requirement and compliance to
expected performance, efficiency, quality, life expectancy and operational
safety. It may be noted that any of the listed material/ equipment is
acceptable based on the Consultants acceptance.
3) All the Valid / Updated Authority Approvals for the products shall be reviewed
before approving the product.

AEB-1086-14-REV.00

S-19-37/31
PLUMBING INSTALLATION

You might also like