Adhunik Metaliks Limited Project Report
Adhunik Metaliks Limited Project Report
Adhunik Metaliks Limited Project Report
CONTENTS:
Seria Topic
l No.
1.
2.
3.
-3.1.
-3.2.
-3.3.
-3.4.
-3.5.
-3.6.
-3.7.
-3.8.
-3.9.
4.
-4.1.
-4.2.
5.
-5.1
ACKNOWLEDGEMENT
INTRODUCTION
ABOUT ADHUNIK METALIKS LTD.
CAPTIVE POWER PLANT
COAL WASHERY
DRI DIVISION
MINI BLAST FURNACE
OXYGEN PLANT
ROLLING MILL
SINTER PLANT
STEEL MELTING SHOPS
QUALITY CONTROL
WHAT IS TOTAL PRODUCTIVE MANAGEMENT?
8 PILLARS OF TPM
IMPLEMENTATION OF TPM
WHY STEP-4 TRAINING IS PROVIDED?
NO. OF PARTICIPANTS FOR STEP-4 TRAINING
Page
No.
1. ACKNOWLEDGEMENT
I extend my deep gratitude and sincere thanks to our
principal Dr. K. K. Patra, RIMS for giving me an
opportunity to carrying my summer project at Adhunik
Metaliks Limited. It is my privilege to thank our head of
department Dr. S. K. Sarangi. I express my sincere thanks
to my guide Mr. Sandip Bhadra, (Sr. Engineer, AML) for his
valuable suggestions and guidance for doing the summer
project.
I express my sincere gratitude to Mr. Ratan J. Ray
(General Manager & Head, Training and Development) for
providing me this wonderful opportunity to do my
summer project work on this topic.
2. INTRODUCTION:
First of all, we fulfilled the formalities regarding gate pass and bus
pass. Then we were told to visit the Training and Development
department, where we were introduced to the company, Adhunik
Metaliks Limited.
We were told to go through the Plant Study Guide book to get a brief
overview of the plant.
Then we came to know about different dos and donts for our safety
and protection inside the plant premises.
Then we received a five-day orientation program schedule.
The orientation program was held so that we can gain knowledge
about the different departments of the plant.
When the orientation program got over, we were send to our
respective department under the guidance of well-known person for
our project.
Under his valuable guidance we collected all required data and
prepared our project.
Then finally, we had submitted the project two days before the last
day of our training so as to rectify the errors if any.
3. ABOUT AML:
Adhunik Metaliks Limited was incorporated as Neepaz Metaliks Private
Limited on 20th November 2001 under the Companies Act, 1956. The
company subsequently became a public limited company and received a
fresh certificate of incorporation in the name of Neepaz Metaliks Limited
with effect from March 25, 2004. The name of the company has been
further changed to Adhunik Metaliks Limited with effect from 9th August
2005.
Adhunik Metaliks Limited (AML), the flagship of the Group, has emerged
as one of the fastest growing alloy, special and construction steel
manufacturing companies in the country with significant presence in the
mining and power sectors through its subsidiaries. It has completed almost
all major capital expenditure for both backward and forward integration and
emerged as an integrated manufacturer of special steel with downstream
utilization of products.
It has set up an integrated steel plant of 0.45 million ton at Sundergarh,
Orissa, with state-of-the-art technology. It has been allotted a captive iron
ore mine at Keonjhar and captive coal mines at Talcher and Angul in
Orissa. The company has also started operations and dispatches from it
captive iron ore mines. Complete integration of facilities and ownership of
captive resources will help the Company insulate itself from any fluctuation
in prices of raw materials along with maintenance of healthy profitability
even in the worst of times.
Over the years, the Company has shown robust financial growth with
consistent profit making. Within a very short span of time, the products of
the Company have been recognized by major automobile component
manufacturing and automobile companies. The Company caters to
diversified sectors including automobiles, telecom, power, railways,
engineering, oil & gas and construction.
Its core business can be classified into three categories: Integrated Steel business through Adhunik Metaliks Limited(AML)
Merchant mining of iron ore and manganese ore through its
subsidiary, Orissa Manganese & Minerals Limited(OM&ML)
Power generation business through its subsidiary, Adhunik Power
and Natural Resources Limited(APNRL)
AML strongly focuses on the reduction of production costs and zero waste
management to make it one of the lowest cost producers of quality steel.
Adhunik Metaliks Limited has different plants for their specific work
34
24
365
269.28
The 700,000 TPA Coal Washery has been set up for washing of
RoM coal. The washed coal is being utilized in the DRI plant. Coal and
coal products are mainly used in the production of sponge iron, pig
iron and In captive power plant.
Coal is India's most abundant, safe and secure fossil fuel for use in
Steel Plants, Cement plants and Sponge Iron Plants. However, the only
problem is the limited availability of good quality coal. The ingress of
extraneous dirt further deteriorates the quality. As a result coal of
recommended grade is not available. A dedicated coal washery can only
help the supply of washed clean coal of recommended quality to the user
plants so as to avoid the disadvantages associated with inferior quality of
available coal. Therefore a coal washer having beneficiated beneficiation
capacity is 700,000TPA. The installed capacity has been estimated at 18
hours of working per day and 312 days of working per annum. The coal
washery capacity is being expanded by 700,000 TPA to meet the increased
requirement of proposed DRI and power plants .
well as non- magnetic char are stored in separate designated bins. From
bins the sponge iron passes through an automatic packing machine. The
bagged DRI is dispatched either to the customer or released for internal
use in steel melting shop. Thus, there are seven 100 TPD and two 150
TPD modules of DRI plants along with all required auxiliary and balancing
facilities for the production of 300,000 tons of sponge iron per annum. The
plant currently operates on three shifts per day and 300 working days per
annum have been considered for calculating the installed capacity.
Further, a 350 TPD DRI plant is also under implementation which will add a
105,000 TPA capacity from FY 2013.
Modern steel making relies heavily on the use of oxygen to enrich air
and increase combustion temperatures in blast furnaces and open
hearth furnaces as well as to replace coke with other combustible
materials. During the steel making process, unwanted carbon combines
with oxygen to form carbon oxides, which leave as gases.
Oxygen is fed into the steel bath through a special lance. Oxygen is used
to allow greater use of scrap metal in electric arc furnaces. The
Company has also set up 3 units of 400 SM 3 per hour for production
of oxygen for the above purposes. The plant will operate 24 hours in
a day and 330 days in year. The installed capacity of the plant works
out at 97,92,000 NM3 per year.
Apart from the above, Company has set up captive oxygen plant of 3500
NM3/ hr. to meet its enhanced requirement of oxygen and nitrogen with
BOC India.
heating (to
avoid
decarburisation) and
thorough
soaking to
achieve trouble free rolling, a Top & Bottom Fired Walking Beam Type
Reheating Furnace has been set up.
In the Rolling Mill. The installed capacity of the rolling mill (with 45 TPH reheating furnace) is 220,000 TPA.
brought
down and
simultaneously
improvements
in
productivity and hot metal quality can be achieved. Apart from the
above advantages, almost all the waste materials, flue dust and
sludge can be utilised in the sintering process. It will minimize the waste
disposal problem. Considering the above advantages, one circular sinter
plant having an area of 25 square meters and productivity of 1.5 ton
per square meters has been set up for the conversion of iron ore
fines into sinter. The sinter plant operates 24 hours per day and
considering working of 330 days per annum, the installed capacity of the
plant has been estimated at 267,300 TPA. The Company's
designed and supplied by SSIT, Beijing.
sinter plant is
Particulars
SMS I
SMS -
II
No. of furnace
35
20
26
10
340
340
309,000
136,000
Honda and Tata Motors, drive shaft for Spicer India and Meritor
Applications, front wheel hub for Ford, etc.
A comprehensive continuous improvement philosophy has been
deployed throughout the organisation to continuously improve the
quality, service and price for all customers by means of perfection of
process methods to ensure that the requirements / needs are always
met.
Customer service representatives have been placed at various
locations to act as the link between the customer and the Quality
Assurance department to ensure that customers are satisfied with the
product or service and so maintain profitable customer relationship.
Benchmark quality standards are set up at steelmaking stage through
ELVAC process with special attention paid to use of raw materials of
highest standards. Manufacturing processes are strongly supported
by VD &AMLC, EMS in continuous casters.
Adhunik Metaliks has been recently certified for ISO 14001
(Environment) and OSHAS 18001 (Health & Safety), besides having
ISO/TS 16949, IBR, RDSO, RITES and BIS (IS-2830 & 2831)
certificates.
Quality of final delivered products is ensured through a number of
important and relevant tests in line with the customers' requirements.
4. WHAT IS TPM?
OBJECTIVES: At the end of the lesson, you will be able to define Total
Productive Maintenance. You will also become familiar with the importance
and necessity of Total Productive Maintenance.
An organization always works towards increasing production, reducing
losses, and ultimately improving the satisfaction level of the customers. In
order to achieve this, the organization needs to focus on the identification
of losses, and gradually reduce or eliminate them. Total Productive
Maintenance (TPM) is a process of continuous improvement and
innovation which enables the organization to identify and eliminate losses.
The origin of TPM can be traced back to the early 1950s when Preventive
Maintenance was introduced in Japan. Nippondenso was the first company
to introduce plant wide preventive maintenance in 1960. However, with the
introduction of more and more factory automation, maintenance became a
problem as more maintenance personnel were required. Thus, the
management of Nippondenso, added Autonomous maintenance wherein
the routine maintenance was performed by its
production operators. The maintenance group began identifying
modification to improve overall equipment reliability. The modification were
shop floor employees and strives to achieve zero losses through small
group activities.
The basic measure associated with TPM is Overall Equipment
Effectiveness (OEE). It offers a simple and powerful measurement tool to
measure the efficiency and effectiveness in terms of availability or uptime,
performance rate and quality rate.
There are certain major losses that are incurred in the production system.
They are:
. Equipment failure
. Production adjustment
. Process failure
. Normal production loss
. Abnormal production loss
. Shutdown
. Quality defect
. Reprocessing
. Production stoppage
. Line organization
. Measuring and adjustment
. Poor management
. Poor operating conditions
STEP-2
The second step of this stage is to launch an educational campaign
through training programs. The training programs should be designed to
explain TPM, eliminate resistance to TPM and raise morale.
STEP-3
Once the introductory education of the employees is completed, the
building of TPM promotional system can begin. Special committees are
formed at every level of the organization to promote TPM.
STEP-4
The fourth step is to establish basic TPM policies and goals by analysing
existing conditions and predicting results.
Goals should be quantifiable precise, specifying the target, quantity and
time frame. Once the goals have been set, they must be developed further
in each department and at each level.
STEP-5
The last step of this step is to formulate a master plan for TPM
development. The master plan should include a detailed implementation
plan for eight core TPM activities which are:
1. Focused improvement
2. Autonomous maintenance
3. Planned maintenance
4. Education and training
5. Development management
6. Quality maintenance
7. Office TPM
8. Safety, health and environment
STEP-6
The TPM kick off is the first step of implementation, the beginning of battle
against the major losses. The kick-off should be designed to cultivate an
atmosphere that raises morale and inspire dedication. During the kick-off,
employees are informed of the plans developed so far and the work
accomplished during the preparation stage.
STEP-7
In this step, TPM is implemented through the four core activities to improve
the effectiveness of the equipment experiencing the loss. Four core
activities are focused improvement, autonomous maintenance, planned
maintenance and training.
STEP-8
Development management is implemented in this step. The objective is to
minimize future maintenance costs and deterioration losses of new
equipment.
STEP-9
Quality maintenance method are implemented in this step. The idea is to
build in quality, during the process of production and prevent quality
defects.
STEP-10
STEP-11
The quality and timeliness of the information supplied by the administrative
and support departments has a major impact on production activities.
Therefore office TPM is introduced in this step to support TPM in the
workplace and strengthen the functions of the various departments.
STEP-12
The final step in TPM development program is to perfect TPM
implementation and set even higher goals for the future. Simultaneously,
the TPM implementation is evaluated for the PM Prize.
5.
The work areas are divided into circles as per the capability of the
personnels. The circle is called as JH Circles or Jishu Hozen circles. Two
types of personnels are included in the Jishu Hozen circle- Operation,
Maintainance (Electrical, Mechanical)
Their Responsibility is to maintain and restore cleanliness of the area. The
operators should be capable of doing the basic maintenance on the
machine on which they operate. If major breakdowns (more than 30
minutes) occur then it is sorted out by the maintenance personnel. If any
anomaly occurs and it is handled by the operation personnel, it is tagged as
White Fuguai. If it is restored by maintenance personnel, it is tagged as
Red Fuguai.
In order to do the jobs of the operation in the circle area assigned the
operators should possess basic maintenance skill and the competency
level of the operators needs to be enhanced. So trainings to the operators
are imparted to bridge the gap between the actual level and the desired
level.
Training sessions are conducted in every circle which comes under the
jurisdiction of the education and training pillar. To make the operators
competent so that they can eliminate White Fuguais, trainings are given to
the operators by trained maintenance personnel. Only the circles which are
in Step-3 are given trainings. A summary report on the number of operators
trained is provided department-wise which concludes my project.