KIRBY Erection Manual
KIRBY Erection Manual
KIRBY Erection Manual
BUILD1NGSYSTEMS-
1 5 O 9 0 0 1 : 2000 C E R T I F I E D
1-4
RECOMMENDED TOOLS & EQUIPMENT FOR ERECTION
5-8
7-22
23
24
25
26
27-30
31
32-34
35-36
37
ROOF PANELING
38
39
40
41
42-43
44
45
46
47
48
SKYLIGHT INSTALLATION
49
50-52
A.
All erection work will be treated as outlined in the American Institute of Stee!
Construction Code of Standard Practices for Steel Buildings and Bridges,
Section 7, which deals with the correction of errors in situations where the
material is not being erected by the fabricator and which reads in substance
as follows: The correction of minor misfits by moderate amounts of reaming,
grinding, welding or cutting, and the drawing of elements into line with drift
pins, shall be considered to be normal erection operations. Errors that cannot
be corrected using the foregoing means, or that require major changes
in member or Connection configuration, shall be promptly reported to the
Owner's Designated Representatives for Design and Construction and the
Fabricator by the Erector, to enable the responsible entity to either correct
the error or approve the most efficient and economical method of correction
to be used by others.
B.
INSPECTION BY KIRBY
Kirby shall have the right to inspect from time to time all erection work being
carried on by the Builder or by others. It shall be the responsibility of the Builder/
Erector to finish permits, if required, for entry to the job site for the inspection and
Builder/Erector shall provide equipment (ladders level etc.) for such inspection,
if requested, Builder/Erector will receive a copy of the Inspection Report. In the
event erection errors are detected at the time of the inspection, the Builder/Erector
will be notified of the errors in writing with a suggested method of correction.
In the event the errors are not corrected by the Builder/Erector, the owner will
be notified in writing by Kirby with a copy of the original report included with
the owner notification. A copy of the notification to the owner will be forwarded
to the Builder/Erector. Kirby shall have no liability to the Builder/Erector or to
any customer for defective workmanship in the erection of buildings including
by way of description, but not by way of limitations, defects arising from loose
connections, missing parts, roof leaks, damaged sheets, omission of sealer, of
closure, scratched surfaces, poor alignment, inadequate drainage or defects
arising out of materials furnished and or installed by Builder/Erector or others. The
Builder/Erector agrees to indemnify and hold harmless from any and all claims
which may or might be made against Kirby by any customer or owner arising from
or growing out defects in the erection of any Kirby Building erected by or under
the direction of, or for the account of the builder and or erector.
ERECTION
A.
A.
Before starting Erection, make sure that you have a complete set of
Erection drawings marked "For Construction", The cover sheet of Kirby
Erection drawings lists all the drawings in the set along with the latest
revision number and date.
B.
B.
C.
C.
D.
When commencing erection of the building, the first braced bay must be
erected with all wind bracing, eave struts, purlins, girts and -flange braces
completely installed and all bolts properly tightened to make certain that
3
the building is properly braced. (See appropriate pages that follow in this
manual).
D.
Ali joints should be made up and all bolts in place before releasing raising
equipment.
E.
Until the first run of roof sheets is secured, temporary scaffold should
be used to start sheeting so that sheeters will have something to stand
on. See proper method of walking on the roof described in the sheeting
section of this Manual.
F.
G.
Workers should never slide down columns and other structural members.
Ladders should be used to get on and off the building. Wail girts and
diagonal braces should not used as ladders.
The following list of tools and equipment is considered adequate for erection of
most Kirby Buildings. Actual Equipment Required may vary due to differences
in building type and size, job site conditions, and erection personnel. This list
is intended to serve as a recommendation only and should not be used as a
limitation to your inventory of erection equipment should be in accordance with
the general guidelines set forth in this manual.
Screw Guns
2
2
1
1
1
1
Socket Wrenches
Spud Wrenches
Box End Wrenches
Open End Wrenches
Vice Grip Pliers
Pop Rivet Too!
Pop Rivet Tool
Staple Guns
Hammers
Sheet Metal Gutters
Wrecking bars
Drift Pins
Hack Saws
5
2
2
10
2
2
4
2Ea
2Ea
2
4
4
Electric
With Staples
Shop, sledge, rubber
Left, right, straight
Heavy Duty
Heavy Duty
With Assorted Blades
5
Chokers
Chokers
Cable Clamps
Slings
Spreader Bar
Steel Cable
Work Platform
Extension Ladders
Safety Belts with
Tool Pouches
Hard Hats
Goggles
Goggles
Welding Hood
Steel Measuring Tapes
Steel Measuring Tapes
Level
Framing & Try squares
Transit 7 level Rod
Plumb bob & Chaulk
String
Nylon Line 3/8
Manila Rope
Caulking Guns
Brooms
Dust Pans
Water can with cup holder
4
^
/"
'8
4
V2"
Assorted sizes
4
With Clevices
1Ea 3m, 5m
100m With 8Turnbuckles
2
6m, Steel or Plywood reinforced
6m
2
2
2
2
1
4Ea
2Ea
2Ea
1Ea
1Ea
2Ea
100m
100m Ea 3 / 8 ". V
4
Cartridge Type
2
2
1
A light gauge cold formed channel which replaces the base angle when liner or
double sheeted partitions are required.
The Distance between the centerline to the first interior frame to the inside of the
endwal! panel.
Frame composed of corner columns, wind columns, flush girts and rafter
sections, which is designed to carry one-half bay loading, also referred to as
Tight Endwall".
Cantilever
Angles or rods primarily on Roof and sidewalls or RF (Rigid Frame) or BC (Beam &
Column) buildings for transferring wind force to foundation and aiding in plumbing
the structure.
A roof composed of layered felt or jute, saturated with tar, with each layer set by
mopping a hot tar or asphalt.
A free standing, single or double column roof structure having a valley gutter at the
centerline of the building having the outer edge of the roof projecting upwards.
The pre-punched end plate of a structural member which usually rests against a
matching plate of another member in forming a bolted connection.
Clip Angle
An angle used for fastening various members together.
Closure Strip
Sealant material formed to match either inside or outside wall or roof panel
configuration used at base, eave, rake or accessory locations to provide closure
against the elements,
Cold-Formed
Various shapes such as angies, channels, girts and purlins, formed from steel at
room temperature.
Column
A vertical structural member
Continuous Gift or Purlin
Gift or purlin that overlaps at columns or frames to form a continuous member.
"C"
A member cold-formed from steel coil in the shape of "C" used primarily in bearing
frame endwalls and framed openings.
Corner Column
A predetermined curvature designed into a structural member to offset the
anticipated deflection when load is applied.
Corner column (usually a "C" shape) located at the corner of a bearing frame
endwall.
Corner Trim
Preformed sheet meta! trim used to close the junction of side and endwall
sheets.
Eave
The line along the top of the sidewail, formed by the intersection of roof and wall
panels.
Crane Rail
Track upon which a top running crane moves (usually hot-roiled A.S.C.E. Rails).
Eave Canopy
A roof extension beyond the sidewail of a building. May also be cantilevered
below the eave.
Eave Height
The vertical dimension from finished floor to top of eave strut.
Curb
Raised flashing around a roof accessory to provide water tightness at the roof
opening
Curtain Wall
Perimeter wall panels which carry only their own weight.
Damper
A baffle used to open or close the throat of ventilators.
Dead Load
The weight of the structure itself plus any permanent stationary loads.
Deflection
The transverse displacement of a structural member in the direction of load and
measured from its no-load position.
Diaphragm Action
The action of Kirby Wall panels on flush-framed walls to act as one unit to resist
longintudinal wind force.
Downspout
A hollow rectangular, square or round tubular section used to carry water from a
gutter to the ground.
Driftpin
A tapered pin used to align holes in steel members to be connected. Also called
"Spud Wrench"
10
Eave Strut
Structural member at the eave to support roof and wall paneis; also transmits
forces due to wind on endwall from roof brace rods to wail brace rods.
Eave Strut Gusset
A small gusset shop-welded to main frame on RF and BC buildings to support
eave struts and afford alignment with by-framed girts.
Eave Trim
Trim used to close off top of sidewail panels in lieu of eave gutter.
Erection
The on-site assembly of pre-engineered components to form complete
structure.
Erection Drawings
Drawings prepared specifically for each building, showing piece mark, and
location of all components.
Expansion Joint
A break of space in construction to allow for thermal expansion and contraction.
Fascia
Decorative trim or panel projecting from the face of a wall.
Fixed Base
A vertical structural member, bolted to and positioned at 90 to a sidewail column
to provide additional base fastening and to prevent column rotation.
11
ISO*
Flange
The projecting edge of a structural member.
Flange Brace
A brace from flange of column or rafter to git or purlin to provide lateral support
and stability.
Flashing
A sheet metal closure to insure weather-tightness.
Footing
A pad or mat, usually concrete, located under a column, wall, or other structural
member, used to distribute loads from the member into supporting soil.
Foundation
The substructure on which a building rests.
Frame
Primary structural members, made up of columns and rafters, which support the
secondary framing.
Girt
A secondary horizontal structural member attached to sidewall or endwall
columns to which wall covering is attached and supported horizontally : usually a
cold-formed "Z" shape.
Glaze or Glazing
The process of installing glass in window and door openings.
Grout
A mixture of cement, sand and water used to fill cracks and cavities. Often used
under base plates or leveling plates to obtain uniform bearing surfaces.
Gusset Plate
A steel plate used to connect two or more structural members in the same
plane.
Gutter
The member used to collect and carry rain water off the roof.
Framed Opening
Opening in a wall, roof or floor that is framed with secondary members.
Hasr-Pso
Reinforcing bar used to help transfer anchor bolt shear (due to column thrust) to
concrete floor mass. The "U" shaped hair pin wraps around the anchor bolts in
side the slab.
Gable
A triangular portion of the endwall of building, directly under the sloping roof and
at the bottom of the eave strut line.
Haunch
Also knee. The deepened portion of a column or rafter, designed to accommodate
the high stress where column and rafter intersect and connect.
Gauge
Thickness range of steel (24,26 etc). Distance between holes punched in flanges,
base or splice plates.
Haunch Brace
A diagonal brace between eave strut and haunch.
Header
A horizontal member over a wall opening.
Galvanized
Zinc-coated steel.
Girder
A main horizontal or near horizontal structural member that supports vertical
loads.
12
Header Trim
Trim used above a wall opening.
High Strength Bolts
Any bolt made from steel having a tensile strength in excess of 100,00 pounds
per square inch (PSI). Some examples are ASTM A-325, JiS 11.86.
13
Structural steel having a yield stress in excess of 36,000 pounds per square
inch.
Kilo-Pound (1000 #)
A roof which rises by inclined planes from all four sides.
Steel sections (angles, channels, l-Beams, etc.) which are formed by rolling mills
while the steel is in a semi-molten state.
A diagonal brace designed to resist horizontal loads usually from wind or moving
material handling equipment. This brace member normally has the lower end
connected to a column and the upper end connected to a rafter or eave strut.
Lean-To
A structure having only one slope or pitch and depending on another structure for
partial support.
Jamb
Aside column of a doorway or opening.
Live Load
Any moving or variable load which the structure must support which is not
permanently attached to the structure.
Acantilevered boom or horizontal beam with hoist and trolley. This lifting machine
may pick up loads in all or part of a circle around the column to which it is
attached.
14
Louver
An opening provided with fixed or adjustable blades to allow air flow.
15
Mansard
A tilted fascia system mounted to the roof, outside the steel line, and above the
roof line to form a decorative fascia appearance and hide the roof line.
Main or Primary Framing
Steel Frames which support secondary framing members such as girts, purlins
or eave struts.
Mastic
Caulking or sealant furnished in Rolls, Normally used in sealing roof panel laps.
Partition
An interior dividing wall
Peak Box
A pre-fabricated trim piece that trims rake trim connection at the apex of gable,
and bears a metal plate with the Kirby Trade Mark.
Peak Panel
Kirby Rib panel located along building ridge, conforms to roof slope and
configuration.
Pier
A concrete structure designed to transfer vertical load from the base of a column
to a footing.
Mezzanine Beam
Primary framing for mezzanines.
Mezzanine Joist
Secondary framing for mezzanines
Pilaster
A masonry column built into a wall and projecting from it.
Moment
Force times distance (torque)
Moment Connection
A joint capable of transmitting moment to another member of the system.
Monitors
Superstructure located above the ridge of the building used for ventilation or
additional light.
IV] ullions
Vertical member connecting two windows located side by side.
MS-Multi-Span
More than one building tied together: Multiple gable buildings.
Nibbier
Al electric hand tool used to cut steel roof or wall sheet openings.
Parapet
That portion of the wail which extends vertically above the roof line to form a
fascia-type appearance to hide roof slope.
16
Pop Rivet
A small headed pin with expandable shank for joining light gauge metal. Typically
used for flashing trim etc.
Portal Frame Brace
Columns and horizontal beam substituted for standard bracing in areas where
rod bracing is not allowed because of access requirements.
Primer Paint
Initial coat of paint applied at factory to structural framing for protection against
elements during shipping and erection only.
Purlin
A secondary member, usually cold-formed horizontal structural member located
in the roof to support roof panels, that is itself supported by the primary structural
framing. Generally, purlins in Kirby Buildings overlap at frames to form a
continuous design.
Purlin Extension Canopy
Cantilevered continuation of Roof at rake line.
17
. Purlin Strut
Additional purlin added at or near intersection of wind bracing members at the
rigid frame where a series of wind bracing is required in the roof plane. This strut
may or may not be a continuous member through out the length of the building.
Rafter
A fabricated primary structural member with parallel flanges that extends from
haunch to apex. Any beam used in a primary frame to support purlins.
Rake
The intersection of roof and endwall,
A fastener which combines the functions of drilling and tapping. Used for attaching
Rake Angle
Angle attached to purlins at rake for attachment of endwail sheets.
A Fastener which taps its own threads in a pre-drilled hole. Used for attaching
panels to purlins and girts. For panel laps, and for trim and flashing.
Reactions
Forces required to resist loads from a structure.
Reinforcing SteeS
Steel rods placed in concrete to take tension. Compression and shear stresses.
(RF)-Rigid Frame
Aclearspan structure. Characterized by tapered columns, tapered haunches and
rafter beams.
Translucent fiberglass panel formed like Kirby Rib used on roof or like Kirby Wall
used on walls in place of pre-determined panels to supply natural light to interior
of building.
Soil Pressure
Allowable load per unit area a substructure slab may exert on a given soil.
Space Saver
Kirby's straight column, slope beam rafter building. Girts are flush framed within
the column,
Span
Width of building inside to inside of wall panels (sidewall to sidewall).
Torque Wrench
A wrench containing an adjustable mechanism for measuring and controlling the
amount of torque of turning force to be exerted - used to tighten nuts on high
strength bolts.
Trim
Light gauge sheet metal used around building openings and at intersections of
roofs, walls, etc., often referred to as flashing.
Truss
A structure composed of three or more members so designed and connected
that the structure as a whole acts as a beam and the individual members are
subjected primarily to longitudinal stress.
Splice
A connection in a structural member.
Splice Plate
Plate used to connect two steel members.
Spud Wrench
See "Drift Pin"
Steel Line
The outside perimeter of structural steel or inside of wall panels.
Stiffener
A member used to strengthen a plate against lateral or local buckling. Usually a bar
welded perpendicular to the longitudinal Axis of the member. Large concentrated
loads such as crane loads usually require stiffeners at the point of connection.
Stitch Screw
Screw used to fasten pane! to panel at side laps.
Threshold
An aluminium extrusion kick plate that spans between jambs beneath a personnel
walk door leaf.
Thrust
Horizontal force developed as a result of a load being applied to a rigid frame.
Tie
A structural member that tends to lengthen under stress, (i.e. wind brace rod)
20
21
"Wainscot
A liner starting at floor but less than ceiling height.
As the building material is unloaded, it should be placed in and around the building
site near the place where it will be used. While each job will vary according to
size or site conditions, the layout below is a typical arrangement which offers
convenience and accessibility during assembly and erection.
Rigid frame columns are laid in position for raising :
The part of a channel, purlin, girt, column or rafter between the flanges.
A wind bracing system used in sidewalls when brace rods cannot be used.
Wind Column
A column located in endwalls of building designed to carry required wind loads.
The stress at which the strain ceases to be directly proportional to the stress.
Rafters are stacked for sub-assembly and easily accessible for setting.
"Z" S@ctson
A girt or purlin : a member cold-formed from steel sheet coil in the shape of a
block "Z" with stiffener lips.
Girts, purlins, eave struts and bracing are devided according to the requirements
of each bay.
Nestgd_Barts.(purlins. gjrte etc.) should be separated and blocked to allow drainage
Qlcoliected moisture.to^revejTLrijsjingjDrior to erection.
Endwail material is laid out for each end.
Small components (nuts, bolts, clips, fasteners etc.) are stored in a given area
convenient to all parts of the building.
Wall and roof paneling and other components which will not be used in the initial
stage of erecting the steel, are placed to the outside of the work area and properly
stored and protected from the weather.
Insulation should not be stored on the edge of the roll as this will damage the
edges.
22
23
Step 1
3 ) Spacers
Air
Circulation
1.
1.
2.
3.
4.
5.
Tie down cover ends away from stack to permit air circulation. Do not wrap
2.
3.
Notes :
1.
Plain to erect a braced bay first. Usually this is the first interior bay from
either end of the building,
2.
Refer to the glossary section of this manual for "Turn-of-Nut" method for
tightening bolts.
3.
24
25
Flange Brace
Roof Rafter
Splice Connection
Column
Haunch Connection
(Column to Roof Rafter)
Notes :
1.
2.
3.
4.
5.
Column
Base Plate
Adjustable
Roof Rafter
Roof Rafter
Column at Base
26
27
Step 3
Step 2
Notes :
Notes :
1.
2.
Make sure roof rafter is level and straight before structural bolts are fully
tightened.
3.
Bolt in place as many clips and flange braces as possible before raising
roof rafters to reduce erection time as it is easier to assemble these pieces
on the ground than it is to do it in the air.
4.
For suggested method of hoisting roof rafters, see page 18 of this manual.
28
If the roof rafter consists of more than two segments, additional purlins are to
be installed while roof rafter is held in place so that there are at least two purlins
spanning between roof rafter segments.
29
Step 4
Rigid Frame
Brace rod/cable
with hillside
washer
and nut
/
/
Wall
Brace
Rod
/
/
/
/
/
/
\
\
Temporary
Bracing
Roof
Rafter
/
/
Sequence
1.
2.
3.
Notes :
Brace Rod/Cable
with hillside
washer flat
washer & nut
Rigid Frame
1.
See pages 32-34 for methods of plumbing and squaring the braced bay.
2.
Base Rod/Cable
Cable Flange
Base
Plate
The protruding lug on the hill side
washer is always located in the
slotted hole to restrain its movement
when brace rod is tightened.
30
31
Step 5
Step 5 contd.
Sequence contd.
The plumbing and squaring operation is one of the most important functions of the erection
sequence. Spend sufficient time on this sequence to insure the braced bay is level, plumb and
square to avoid id problems when continuing the erection sequence.
^sg^T
Caution:
This method is not recommended
under conditions that would be
affected by wind.
-^*
Ridge Point
Roof Rafter
Center Line
of Column
Fig. 2.
Detail B
32
33
Step 6
Step 5 contd.
Transit
Location
Note:
!n all cases the transit
method of plumbing and
squaring the building is
preferred.
Sequence
Sequence
1. Locate transit as shown above, (in this
example it is located slightly to the left of IN
first rigid frame.)
2. Make sure transit is perfectly level.
3. Rotate transit until you get the same exact
tape reading at points A&B. (Base of coluifl
Outside flange-see detail).
Lock horizontal rotation of Transit.
Adjust rod bracing until the tape reading ai
point a&b is obtained at all points indicated
on above sketch - take all readings from**"
same surface as "A" & "B".
Proceed with the erection of the remaining frames and bearing end frames.
In each braced bay shown on the erection drawings, repeat step 4 before
proceeding with the erection of additional bays.
Eave struts and peak purlins may be installed in intermediate bays between
braced bays to stabilise frames, however, do not start more work than can be
completed in a work day to ensure all structural framing is completed in those
bays before leaving the site at the end of the day.
IMPORTANT NOTE:
As erection progresses, each braced bay must be fully completed as outlined in
step 4 before proceeding with the erection of additional bays.
35
Step 7
Base Angle
xpansion Bolt
Sheet
Notch
Reinforced
Concrete
Expansion Bolt
Sequence
1. Complete erection of main and secondary framing
2. Upon Completion of all secondary framing in the braced bay, plumbing and
squaring the braced bay, installing secondary framing in the end bay, paneling
may commence and be worked in conjunction with the completion of the
balance of the secondary framing. This could save time on larger buildings if
separate sheeting crews are used.
Note:
When the building reaches this stage of erection, sheeting should proceed
immediately. The structure without sheeting should not be left standing for
prolonged periods of time without taking proper precautions (temporary bracing,
blocking etc.) to prevent wind damage especially to purlins and girts due to
excessive vibration they are exposed to in the unsheeted condition.
36
Base Channel
Sheet
Notch
Finished Floor Line
Reinforced
Concrete
Base channel is substituted for base angle when liner is furnished with a
building
37
Kirby Rib roof panels may be damaged by erection traffic. Traffic damage can be
avoided by the use of walk boards.
Two sets are suggested; one for the workman laying or fastening panels, the
Panel to panel
panel to framing without
insulation with 50 mm
insulation with 75 mm
insulation
^>
SDS
Stiching Screw
SDS
#14SDS
25 mm long
#17STS
20 mm long
#12 SDS
Stiching Screw
Walkboard placement on
Kirby Rib roof panel
CAUTION
Before starting to panel,
recheck the building
structure to be sure it is
still plum and square.
38
39
lI Direction of panel
' ' Kirby Rib Roof
Endwa
rtBirt
Sidewa
Girt
Girt
^>
Kirby wa
sidewa
pane
c
LU
Finished
Floor
Sidewall
Girt
"a
c
ID
See Note 1
Base Angle
Kirby Wall
Sidewall
Panel
Kirby wall
endwall panel
1.
2.
Start or finish
"sheeting endwaS!
3.
4.
5.
from base angle and secured to each structural girt toward the eave.
Foundation must be square, level and correct to the out to out of steel
dimensions.
Erection crew is to clean ail wall panels before leaving job site,
40
ROOF PLAN
"Steel "|
Line
1.
2.
Start or
Finish' sheeting
Sidewall
Corner
Trim
Building Length
(A) & (C) denote Kirby RIB roof sheet. (B) denotes Kirby Rib peak panel.
Locate the center of the first major rib exactly over steel line or as indicated
on the Erection drawing - attach panels (A) and (C) and then attach peak
panel (B)
3. Each side of Kirby Rib pane! and the Kirby Rib peak panel must be run in
conjunction with each other to ensure correct alignment.
Refer to other sections of this manual for details relating to eave alignment
of roof panels, sealer application and fastener types.
5. All damaged paint finishes are to be retouched to prevent rusting.
6. In the event a screw is installed in the wrong location or should a screw
break during the driving process, remove the screw and install one of the
larger diameter to prevent leaking.
7 Concentrated heavy loads (personnel or material) occurring on the roof during
construction shall be distributed uniformly over a large area in such a
manner as to prevent damage to building components.
8 All metal shavings occurring as a result of drilling operations on the roof are to
be remove in such a manner as to prevent damage or staining of roof finish.
(The roof should be swept clean at the end of each day)
Note:
For buildings having roof extension, canopies, lean-to's etc. Wall paneling
must be installed before roof sheets to allow for working clearances.
41
\
Mastic to be applied
to pane! edges only
Mastic to panel
edge only
Existing Mastic
11
13
15 \
10
12
14 V
Step 'B'
Step 'A'
Provide +25 mm
mastic overlap to tie
into existing horizontal
mastic on pane! 2
Corner of
pane! 2
must be
under panel
3
Provide +25 mm
mastic overlap to tie
into existing horizontal
mastic on panel 2
Existing
Mastic
Step 'D'
Step 'C
Provide +25 mm
mastic overlap to tie
into existing horizontal
mastic on panel 4
Step 'E*
42
1.
2.
3.
4.
Check location of center line of center line of high Rib 5m from steel line at
end of building so adjustment on gain or loss can be made if necessary.
5.
Erection crew is to sweep roof panels clear of all metal shavings daily until
roofing is completed,
43
important: remove
release paper by
pulling back at
approximately 150G
1.
Wall insulation "A" is shipped in maximum length rolis and are to be field cut
to exact length before installing refer to erection drawings for specific details
for your building.
2.
Wall insuiation should extend from top of eave strut to 40 mm below finished
floor. Clamp insulation to eave strut as shown in fig.1 page 46, pull facing
tight an hold in place until wall pane! is attached.
3.
Roof insulation 'B' depending on building width, may be shipped in one roll
or a series of rolls (refer to your erection drawings for specific details)
#12SDS
Stich'mg Screw
Mastic
Pull insuiation simultaneously from each side of building until facing is tight
(see fig. 2 page 47 for method of holding insulation tight). Secure to top of
eave strut, fold down and secure to outside face of eave strut.
Removing release paper
Roof fastener ^
Mastic
~\ \J
f Roof Panel
This step is necessary to
complete the vapour barrier seal
Base Angle
Typica
through v
Floor Line
MASTIC
Attach tab
to rank
angle
Vinyl Face
Base Angle
Standard Lap
Peak Panel
Insulation
Roof Fastener
&
Purlin
5- Rafter
(Shapes Vary)
'Sheet Notch
Detail at Endwall
Roof Panel
Eave Strut
Fig. 1.
,-Eave
j4r
Insulation
Corner
Angle
s w
Roil out the second insulation strip overlapping the first (see your erection drawings
for splice location) and temporarily hold in place by applying a vice grip tool to the
two tabs at the purlin.
nsulation
Girts -
46
47
Kirby Wall
Kirby Wall
Kirby Rib
Kirby Rib
Inside Closures
Outside Closures
Roof Pane
/
Rake
Trim
Purlin
Kirby Rib
Inside
Closure
Eave
Trim
Eave
Strut
Kirby Wail
Outside Closure
Kirby Wa!
Panei
Eave With
Eave Trim
Kirby Rib
nside Closure
Roof Panle
Kirby wai
panei
Kirby wall Inside
closure girt
Eave
Gutter
Flashing
.Roof
Panel
Note:
Skylights shall be installed as roof is sheeted,
Protective measures are to be taken to prevent
personnel damaging the skylight. Do not walk
on skylights.
Kirby Rib
Outside
Closure
Kirby Wa
Panel
Eave with
Gutter
Lean to below
roof line
Ventilator
Roof Panle
Kirby Rib
Outside
Closure
Soffit
/Panel
/
ii
Kirby Wai
Panel
Ridge Vent
Eave Soffit
48
Appendix'1'
the site (not via Kuwait) without issuing a shipper covering this item
from Kuwait.
The claim could be any of the previous four categories.
Type of Claim
The majority of claims fall within the following categories :
Category 1 - Items not received
A.
B. Any items ordered but not included in the shipper and accordingly
not received on site.
Category 2 - Damaged Items
50
51
(3)
(4)
(5)
(6)
(7)
(8)
52
'"-"""^WMBiiJBSSSSia^S^S^S^^iaga^Pi^^^^^^^g