Introduction To Cost Control - Conceptual Stage
Introduction To Cost Control - Conceptual Stage
Lecture 6-1
OUTLINE
Lecture 6-2
Quality Control
Adhering to the owners quality standards.
constructed facility should work safely for specified years.
Schedule Control
Complete in specified time.
Cost Control
Completed within budget.
Owner can realize his expected profits.
and Keep financial requirements within anticipated limits.
Safety
Construct Safely.
Good safety record can yield cost benefits (reduced insurance, improved
productivity).
Minimize Disruptions to Existing Operations
In case of addition or modification of existing facility, special arrangements required
for minimizing disruptions.
Can impact cost and schedule.
Lecture 6-3
Reporting
Control
Lecture 6-5
Lecture 6-8
Objectives:
To establish clear-cut cost responsibilities
To establish proper/formal lines of communication
Types of Contracts
Lump Sum
Guaranteed Maximum Price
Unit Price
Cost Plus
Cost-Reimbursable Alternative
Fully reimbursable with fixed fee.
Fully reimbursable with a fixed target cost and mutual
sharing of any under run to the target cost.
cost-reimbursable plus performance-based incentives
direct cost-reimbursable plus fixed construction
management costs.
Lecture 6-10
Contractor
One of prime responsibility.
doing the spending.
Owner
Direct responsibility for basic design specifications.
Changes made during execution.
Monitor and appraise contractors cost control efforts.
Lecture 6-11
Provides information.
Points out areas of cost overruns.
Investigate and recommend corrective action.
Forecast and prepare complete project monthly cost
outlook.
Monitors costs between outlooks.
Keeps complete record.
Quick cost estimates for alternatives.
Sends information back to main office for record keeping
for future.
Lecture 6-12
Role of Owners CE
Lecture 6-13
Role of Contractors CE
Lecture 6-14
Lecture 6-15
Lecture 6-16
Lecture 6-17
Lecture 6-18
Definition
Well-defined project.
Definition must be reflected in control estimate and schedule.
Documentation
Decisions, change orders, commitments, contracts, procedures.
Discipline
Explicit project procedures must be followed.
Project must not fall in Tomorrow Syndrome
Eg.: Change drawings now, we will work out costs tomorrow.
Lecture 6-19
Summary
Focal point of cost control program: CE
Main tool: control estimate
Main approach: analyze existing trends and
forecast total cost.
Pay attention to 3 Ds.
All costs are controllable.
Lecture 6-20
Outline
Introduction
Types of Cost Estimates
Blackout Periods
Cost Monitoring
Changes to Estimate Basis
Yardsticks
Cost Monitoring during Conceptual Phase
Cost-Monitoring Committee
Flow of Information
Committee Reports Outline
Lecture 6-22
Introduction
Screening Studies
Early estimates to compare competitive processes/alternatives
Preliminary Estimates
Used as preliminary economics
Semi-detailed Estimates
Prepared near end of conceptual engineering
Owners use to allocate funds for projects
Definitive Estimates
Prepared as early as possible during detailed engineering
Used as basis for cost control.
Lecture 6-24
Blackout Periods
Lecture 6-25
Cost Monitoring
Eliminate
Lecture 6-26
Many changes to the basis of the preliminary estimate are made during
conceptual engineering.
Operational
Safety
Intangible Benefits
All changes that are absolutely necessary for the operation of end product.
Changes necessary from safety aspect (structural design changes, user related safety etc.)
Changes that are desirable but have intangible benefits only (elaborate landscaping,
impressive entrance gate.)
Uncontrollable Changes
Economic
Lecture 6-27
Lecture 6-28
Responsibility
identifies changes w.r.t. basis of original
estimates and advises CE.
Lecture 6-29
Cost-Monitoring Committee
Members
The Lead Planner/Designer
Technical Specialists
Project Manager
Project CE
Duties
Review Plans
Question any client requirements that appear to cost an
exorbitant amount.
Define economic yardsticks.
Put out periodic reports.
Lecture 6-30
Cost-Monitoring Committee
Flow of information
Lecture 6-31
Cost-Monitoring Committee
Lecture 6-32
Lecture 6-33
Approved Changes
Lecture 6-34
Lecture 6-35
Lecture 6-36
Summary
Keep
Lecture 6-37