Effective Qualification of Critical Utilities PDF
Effective Qualification of Critical Utilities PDF
Effects on Equipment/Systems
Qualifications Quality Systems
Approach
Design Qualification/Review
Purchasing Controls
During Construction
Start-Up and Commissioning
Structured Design
Review
QA Change Control
Design
Development
Enhanced Design
Review
commissioning
PQ
Process
Validation
IQ & OQ
Scope of Guide
GEP Contribution
Of Interest to the Regulatory
April 23, 2013
Qualification
Design
Discontinuation
Plan
Do
Act
Verify
Life-Cycle Phases
Design
User Requirements
Functional
Requirements
Detailed Design
Qualification
Continued System
Verification
Monitoring
Change Control
Deviations/OOS
Maintenance
12
13
Project Phases
Indirect Impactno
product contact but may
have indirect effect on
product quality
Vessel jacket heating/
cooling
Potable water for
washing/cleaning
not final rinse
Vacuum for drying/
coating
IQ and OQ required
15
Approval of Suppliers/Vendors
Quality Agreements/Contracts
Quality Agreements/
Contracts
18
Design
Specs
Performance
Qualification
Verifies
Operational
Qualification
Verifies
Verifies
Installation Qualification
Design Review
System Build
19
Specifications Purpose
20
21
22
23
24
Design Qualification/Review
Application
25
27
28
EDR Rationale
To be included in Plan:
What will be reviewed
What method will be used supporting data
Who will be involved
When?
How will be documented?
Could be in a standard procedure
29
30
31
32
33
Construction
34
Factory Acceptance
Testing (FATs)
35
36
Project Phases
Design
Purchasing
Construction
Installation
Start-up
Validation
V $
April 23, 2013
37
Commissioning Leads
to IQ/OQ for Indirect and
Direct Impact Systems
38
Key Question:
Is Commissioning going to be
considered part of Validation
Effort?
Yes!
Define Commissioning
process and documentation
in Project/Quality Plan and
in Master Validation Plan
and how they will relate to
further qualification of
systems
No
Complete
Commissioning
Will need to repeat
some tests for
Qualification
Still need to describe
Commissioning
requirements in
Plans
39
Commissioning as part of
Master Validation Plan
Advantages:
Requirements:
40
Historical:
Installation
Qualification
Operational
Qualification
Performance
Qualification
41
Questions to be Answered
42
43
44
45
46
47
48
Process Parameters vs. Equipment Design Verify that the equipment is capable of
operating at the desired process parameters
independently of the equipment design
Flexibility, Reliability, Future Growth
49
50
Protocol Requirements
General Outline
Approvals
Objective/Purpose
Scope/Boundaries
System Description
Overview
Basis of Design
Flow Diagrams
Qualification Approach:
policies, procedures,
references
Responsibilities
Pre-Requisites
Definitions
Test requirements
Record of Signatures
Test Instruments
Calibrations
Qual. Tests
Acceptance Criteria
Documentation/ Handling
of deviations or exceptions
Attachments
51
52
PLC IQ/OQ
53
54
55
56
Legacy Systems - IQ
Documentation Available:
57
Legacy Systems - OQ
58
Performance Qualification
(PQ) Direct Impact Systems
59
Qualification Summary
Reports - Outline
Approvals
Objective
Data Summary
Analysis of Deviations or
Exceptions
Cause
Effect on Study
Conclusion
Approval By Quality
Function
Conclusions
60
Facilities
Requirements New
61
User Requirements
Functional Requirements
62
63
Design Specifications
64
Utilities installations no
recesses, unsealed openings and
difficult to clean surfaces
Pressure differential warning
system
Changing rooms with physical
barrier between class levels
Air locks with interlocks
Layout of equipment consider
ergonomics and personnel
comfort and ease of movement
Flow of personnel limit entries
and exits and the amount of
personnel
Limit the activities/interventions
into the aseptic processing area
April 23, 2013
65
Decisions on Parameters
Parameter
Industry Suggestions
(PDA, Others)
Air Velocity
HEPA Filters
Air Exchange
Rates
Pressure
Differentials
Temperature and
RH%
requirements
66
67
Qualification Requirements
for an HVAC System
68
69
Controls/Alarms Verification
Sequence of Operation
Interlocks testing
Reports
System Security/Data Retrieval
Temperature/Humidity Control Verification minimum of
five days for continuous monitoring. Longer for frequent
checks during the day.
Power Loss and Recovery Testing
Sterile Operations Air velocity, Pressure Differentials, Air
Flow/Laminar Flow Verification as per design. Pressure
Differentials for five days if continuous or longer for
frequent checks during the day.
April 23, 2013
70
Performance Qualification
72
System Design
Biofilm
Process Water
Inspection Strategy
Maintenance records
System Drawing
System Validation
74
Variety of Pharmaceutical
Products
Industry References
77
Pre-Treatment Options
Final Treatment Options
Instrumentation
Storage/Distribution
Qualification/Validation
Appendix
78
Feed Characterization
Ground Water vs
Surface Water
Chemical and
Microbiological
Loads
Seasonal Variations
Volume and effects
of peak usage
Multi-Disciplinary
Team Approach
Define User Needs:
Water Quality
Use Points
Requirements
System Criteria
Filtration requirements
Safety Considerations
Water Systems
Pre-Treatment
Multimedia Filter
Softener
Carbon Filter
Cartridge Filters
DI Columns
RO Units
UV Lamps
Storage and Distribution
Instrumentation
TOC On-Line
Resistivity/Conductivity Meters
pH
Pre-Treatment
Specifications
Scaling
hardness and
minerals
Corrosion chlorides
Degradation chlorines
Large
Large
None
Large - Membrane
dependent
Other Membrane
Process
Large - Moderate
Large - Moderate
None
Large - Membrane
dependent
Moderate
Moderate
Moderate-Large
Large
Large - Moderate
Large - Moderate
Moderate-Large
Large
Moderate
Moderate
Small
Large
RO
Multi-Effect Still
Vapor
Compression Still
88
Micro Control in
Pre-Treatment
Final Treatment
90
P-8
Carbon
Multi-Media
P-7
RO
Softener
CDI/EDI
Storage Tank
Heat Exchanger
Pump
System C
93
Carbon
Softener
RO
Nitrogen Blanket
Storage Tank
Pump
TOC
UV
Final filter
95
Still Design
Multi-Effect
VC
Capacity Range
(GPH)
1-100
25-3000
100-6000
WFI Temperature
Range (C)
80-100
37-100
- Ambient
-80-100
-Combination (hot/
cold loops)
Designed to
maintain water
quality and
deliver to use
points at
temperature and
flow required
Capacity
Continuous flow/
movement
Minimize Cost
98
Materials of Construction
Non compendial:
Polyvinyl Chloride (PVC)
Polypropylene (PP)
Polyvinyldene flouride (PVDF)
Compendial water
316 stainless is preferred but PVDF is an option
Sanitary Fitting
Other Considerations
Microbial Controls
101
Qualification Pre-Requisites
Qualification Documents
System specifications
Performance criteria
Design parameters
System boundaries
Qualification Documents
Installation Qualification
Documents
Qualification Documents
Operational Qualification
Operational Verification
Sequences System/components cleaning/
sanitization/flushing/regeneration procedures
and frequency
Critical parameters data collection
Procedures may be in draft or operational
Qualification Documents
Operational Qualification
Sampling points
Source water
After each critical step in the purification process
Storage tank (temperature profile and water quality)
Circulation loop (temperature profile only)
At each POU (temperature profile and water quality)
Sampling procedures
Testing requirements
Testing methods
Acceptance criteria
Qualification Documents
Operational Qualification
Documentation
Summary report and conclusion
Qualification Documents
Performance Qualification
Qualification Documents
Performance Qualification
Sampling procedures
Testing requirements
Testing methods
Acceptance criteria
Documentation
Summary report and conclusions
Sampling Plan
Phase 1 (OQ):
During the initial phase the operational parameters and cleaning/
sanitation procedures and frequencies will be developed.
Sampling should be daily after each step in the purification
process and at each point of use for two to four weeks. The
sampling procedures for point of use should reflect how they are
taken, e.g. use of hose, and time for flushing. At the end of the
two (2) to four (4) weeks of sampling, the firm should have
developed its SOPs for operation and maintenance of the water
system.
Develop operating ranges
Develop and finalize operating, cleaning, and maintenance
procedures
Demonstrate production and delivery of in-spec water
Sampling Program
Sampling Program
Sampling Program
FDA Requirements:
The validation of the water system is completed
when the firm has collected data for a full year.
The FDA states that while the above validation
scheme is not the only way a system can be
validated, it contains the necessary elements for
validation of a water system.
Microbiological/
Chemical Limits
USP Limits
Tests
Potable
Water
Purified
Water
pH
TOC
Conductivity
N/A
N/A
N/A
Bacteria
Endotoxins
500 cfu/mL
N/A
5.0 - 7.0
500 ppb C/liter
1.3 S/cm @ 25C
1.1 S/cm @ 20C
100 cfu/mL
Not Specified
5.0 - 7.0
500 ppb C/liter
1.3 S/cm @ 25C
1.1 S/cm @ 20C
10 cfu/100mL
0.25 EU/mL
TOC
Conductivity
Temperature
Flow
Pressure
Specific Requirements
Clean Steam
Design Aspects:
118
Specific Requirements
Clean Steam
(contd)
Clean steam:
IQ:
Control valves and
steam traps checked
Flushing, cleaning,
passivation logs/
records reviewed
OQ:
Temperature/pressure
PQ:
Pure steam condensate
= USP WFI
119
CLEAN STEAM
SPECIFICATIONS
Table: Microbiological/Chemical Limits
Tests
pH
TOC
Conductivity
Bacteria
Endotoxins
Clean Steam
5.0 - 7.0
500 ppb
USP 2? Specifications/
method
10 cfu/100mL
0.25 EU/mL
120
Specific Requirements
Compressed Gases
121
Specific Requirements
Compressed Gases
(contd)
122
Specific Requirements
Compressed Gases
(contd)
OQ:
SOPs for operation and maintenance
Proper operation of controls and indicators
(compressor start or tankbank switching)
Alarms and interlocks
Line pressure (throughout distribution piping)
Air temperature
123
Dew point
Hydrocarbons
Viable/non-viable
particulates
124
125
CLEAN AIR
SPECIFICATIONS
Table: Microbiological/Chemical Limits
Tests
Compress Gas
Dew Point
Hydrocarbon as Oil
Mist
Gas Content
< -10 oC
< 1 ppm
Bacteria
Non-Viable Particulate:
USP 23 Specifications/
method for Purity
< 0.1 CFU/ft3
Room Classification
126
127
Monitoring Program
Laboratory testing:
Data handling
Analysis of Trends (Quarterly?)
Alert Limits and Action Limits
Outside Limit Conditions/Failure Investigations
Alarms
Critical parameters
temperature, RH%, Pressure
Differential, Velocities/Filter
Pressure Drop
Critical to Program
Adequate Alarm Limits and
Delays
Procedural Action Plan for
Alarm Conditions
129
130
Process Deviations/Failure
Investigations
131
Data Handling/Review/
Approval
132
Training of Laboratory
Personnel
Sampling Techniques
Sample handling and testing
Incubation Controls
Media selection:
Incubation conditions
Growth promotion tests
133
Analysis of Trends
134
Not specifications
Alert potential drift from normal operational conditions
135
Training enforcement
Additional testing/frequencies
Additional Sanitization
Additional product testing
ID of Microbial Contamination and possible source
Re-assess current procedures
Revalidation
136
Maintenance Requirements
Preventive Maintenance
procedures are being
followed:
Pumps, Filters,
Equipment
Frequency for
repassivation
Repairs equivalent
replacement parts
Changes following
Change Control procedure
cGMPs
Documentation
Practices
Test Comprehension
Calibration of
Instrumentation
NIST Traceability
Calibration procedures per
type of instrument
Control software/hardware
maintained as per procedures
Change Control
Impact of Change
determined
Documentation of
results and modified
documents and
drawings included in
package
Quality review
Operational Procedures
Sanitization/Cleaning
Procedures
Sampling/Testing
Procedures
Revalidation
Is it required?
141
Internal Audits
142
Carbon tank, 2 mixed bed resin tank, single effect still. System
requirement is for Purified Water. Action limit is TOC does not
exceed 300 ppb. POU measurement is 1X/week. Successive weeks
look like this:
Week 1
100
Week 2
155
Week 3
95
Week 4
200
Week 5
290
Week 6
250
Week 7
275
Week 8
280
Week 9
270
Is it time to investigate?
Interactive Exercise:
Based on a critical utility system description
to be provided, the participants will list the
key protocol requirements and tests for the
OQ and PQ of these systems.
Conclusions
Questions?
147
THANK YOU!!!
Contact Info.:
Miguel Montalvo
Expert Validation Consulting, Inc.
Mobile Phone +1(407) 587-6540
Email: [email protected]
www.expertvalcon.com
148