March 4 Digests
March 4 Digests
Davao Corrugated
Carton Corp.
GR No. 176868, 26 July 2010.
FACTS:
Solar Harvest, Inc., entered into an
agreement
with
respondent,
Davao
Corrugated Carton Corporation, for the
purchase of corrugated carton boxes,
specifically designed for petitioners business
of exporting fresh bananas. The agreement
was not reduced into writing. To get the
production underway, petitioner deposited,
on March 31, 1998, US$40,150.00 in
respondents US Dollar Savings Account with
Westmont Bank, as full payment for the
ordered boxes.
Despite such payment, petitioner did not
receive any boxes from respondent. On
January 3, 2001, petitioner wrote a demand
letter for reimbursement of the amount paid.
On February 19, 2001, respondent replied
that the boxes had been completed as early
as April 3, 1998 and that petitioner failed to
pick them up from the formers warehouse
30 days from completion, as agreed upon.
Respondent mentioned that petitioner even
placed an additional order of 24,000 boxes,
out of which, 14,000 had been manufactured
without any advanced payment from
petitioner. Respondent then demanded
petitioner to remove the boxes from the
factory and to pay the balance of
US$15,400.00 for the additional boxes and
P132,000.00 as storage fee.
On August 17, 2001, petitioner filed a
Complaint for sum of money and damages
against respondent. The Complaint averred
that the parties agreed that the boxes will be
delivered within 30 days from payment but
respondent failed to manufacture and deliver
the boxes within such time.
In its Answer with Counterclaim, respondent
insisted that, as early as April 3, 1998, it had
already completed production of the 36,500
boxes, contrary to petitioners allegation.
According to respondent, petitioner, in fact,
made an additional order of 24,000 boxes,
out of which, 14,000 had been completed
without waiting for petitioners payment.
Respondent stated that petitioner was to
pick up the boxes at the factory as agreed
upon, but petitioner failed to do so.
RATIO:
The right to rescind a contract arises once
the other party defaults in the performance
of his obligation. In determining when default
occurs, Art. 1191 should be taken in
conjunction with Art. 1169 of the same law.
In reciprocal obligations, as in a contract of
sale, the general rule is that the fulfillment of
the parties respective obligations should be
simultaneous. Hence, no demand is
generally necessary because, once a party
fulfills his obligation and the other party does
not fulfill his, the latter automatically incurs in
delay. But when different dates for
performance of the obligations are fixed, the
default for each obligation must be
determined by the rules given in the first
paragraph of the present article, that is, the
other party would incur in delay only from
the moment the other party demands
fulfillment of the formers obligation. Thus,
even in reciprocal obligations, if the period
for the fulfillment of the obligation is fixed,
demand upon the obligee is still necessary
before the obligor can be considered in
default and before a cause of action for
rescission will accrue.
Evident from the records and even from the
allegations in the complaint was the lack of
demand by petitioner upon respondent to
fulfill its obligation to manufacture and
deliver the boxes. The Complaint only
alleged that petitioner made a follow-up
upon respondent, which, however, would not
qualify as a demand for the fulfillment of the
obligation. Petitioners witness also testified
that they made a follow-up of the boxes, but
not a demand. Note is taken of the fact that,
with
respect
to
their
claim
for
reimbursement, the Complaint alleged and
the witness testified that a demand letter
was sent to respondent. Without a previous
demand for the fulfillment of the obligation,
petitioner would not have a cause of action
for rescission against respondent as the
latter would not yet be considered in breach
of its contractual obligation.
Notwithstanding
the
said
remittances, APIC does not own a
single share of APC. On the other
hand, defendant could not even
satisfactorily substantiate its claim
that at least it had the intention to
cause the transfer of APC shares to
APIC. Defendant obviously did not
enter into the stipulated SPA
because it did not have the shares
of APC transferred to APIC despite
its representations. Under the
circumstances, it is clear that
defendant fraudulently violated
the provisions of the MOA.
ISSUE:
FACTS:
HELD:
YES
RATIO:
We affirm the hospitals liability not on the
basis of Article 2180 of the Civil Code, but
on the basis of the doctrine of apparent
authority or agency by estoppel.
Despite the absence of employer-employee
relationship between SJDH and the
petitioning doctors, SJDH is not free from
liability.
As a rule, hospitals are not liable for the
negligence of its independent contractors.
However, it may be found liable if the
physician or independent contractor acts as
an ostensible agent of the hospital. This
exception is also known as the doctrine of
apparent authority.
Therefore, we hold that, under the doctrine
of apparent authority, a hospital can be held
vicariously liable for the negligent acts of a
physician providing care at the hospital,
regardless of whether the physician is an
independent contractor, unless the patient
knows, or should have known, that the
physician is an independent contractor.
SJDH impliedly held out and clothed Dr.
Casumpang with apparent authority leading
the respondent to believe that he is an
employee or agent of the hospital.
Whether or not
consignation.
there
was
valid
HELD:
NO
RATIO:
In the cases of Del Rosario v. Sandico, 85
Phil. 170 (1949) and Salvante v. Cruz, 88
Phil. 236 (1951), likewise cited as authority
by petitioner, this Court held that, for a
consignation or deposit with the court of an
amount due on a judgment to be considered
as payment, there must be prior tender to
the judgment creditor who refuses to accept
it. The same principle was reiterated in the
later case of Pabugais v. Sahijwani, 423
SCRA 596 (2004). As stated above, tender
of payment involves a positive and
unconditional act by the obligor of offering
legal tender currency as payment to the
obligee for the formers obligation and
demanding that the latter accept the same.
In the instant case, the Court finds no
cogent reason to depart from the findings of
the CA and the RTC that petitioner and her
coheirs failed to make a prior valid tender of
payment to respondents.
Furthermore, the fact that the subject lots
are in danger of being foreclosed does not
excuse petitioner and her coheirs from
tendering payment to respondents, as
directed by the court.
BPI v. Domingo
GR No. 169407, 25 March 2015
FACTS:
Spouses Domingo executed a promissory
note in favour of Makati Auto Centre payable
in 48 successive instalments. They
simultaneously executed a Deed of Chattel
Mortgage over a 1993 Mazda vehicle to
secure payment of the promissory note.
Makati Auto Center, Inc. then assigned,
ceded, and transferred all its rights and
interests over the said Promissory Note and
chattel mortgage to Far East Bank and Trust
Company (FEBTC), which the SEC
approved and issued the Certificate of Filing
of the Articles of Merger and Plan of Merger
and between BPI, the surviving corporation,
and FEBTC, the absorbed corporation. By
virtue of said merger, all the assets and
liabilities of FEBTC were transferred to and
absorbed by BPI.
Consequently, Spouses Domingo defaulted
in their installments. BPI, being the surviving
corporation after the merger, demanded that
the spouses Domingo pay the balance of the
Promissory Note including other charges or
to return the subject vehicle for purposes of
foreclosure. When the Spouses Domingo
still failed to comply with its demands, BPI
filed a complaint with the MTC. Spouses
Domingo argued that BPI had no cause of
action against them and that Maryden
Domingo once obtained a car loan from
FEBTC but sold it to Carmelita Gonzales
with the banks conformity and the buyer
subsequently assumed payment of the
balance of the mortgaged loan.
MTC rendered a decision in favor of BPI as
the bank was able to establish by
preponderance of evidence a valid cause of
action against the spouses. They held that
novation is never presumed and must be
clearly shown by express agreement or by
acts of equal import. The MeTC found
Amadors bare testimony as insufficient
evidence to prove that he and his wife Mercy
had been expressly released from their
obligations and that Carmelita Gonzales
(Carmelita) assumed their place as the new
debtor within the context of subjective
novation. Upon appeal to the RTC, the RTC
Hence,
a
lessor-lessee
relationship
indubitably existed between them and BSP.
On this score, Article 1654 of the Civil Code
provides that [t]he lessor (BSP) is obliged:
(1) to deliver the thing which is the object of
the contract in such a condition as to render
it fit for the use intended; (2) to make on the
same during the lease all the necessary
repairs in order to keep it suitable for the use
to which it has been devoted, unless there is
a stipulation to the contrary; and (3) to
maintain the lessee in the peaceful and
adequate enjoyment of the lease for the
entire duration of the contract. In relation
thereto, Article 1664 of the same Code
states that [t]he lessor is not obliged to
answer for a mere act of trespass which a
third person may cause on the use of the
thing leased; but the lessee shall have a
direct action against the intruder. Here, BSP
was not remiss in its obligation to provide
Sps. Mamaril a suitable parking space for
their jeepneys as it even hired security
guards to secure the premises; hence, it
should not be held liable for the loss suffered
by Sps. Mamaril.
ISSUE:
Whether or not BSP should be liable for
the loss to the Spouses Mamaril.
HELD:
NO
RATIO:
Article 20 of the Civil Code provides that
every person, who, contrary to law, willfully
or negligently causes damage to another,
shall indemnify the latter for the same.
Similarly, Article 2176 of the Civil Code
states: Art. 2176. Whoever by act or
omission causes damage to another, there
being fault or negligence, is obliged to pay
for the damage done. Such fault or
negligence, if there is no preexisting
contractual relation between the parties, is
called a quasi-delict and is governed by the
provisions of this Chapter. In this case, it is
undisputed that the proximate cause of the
loss of Sps. Mamarils vehicle was the
negligent act of security guards Pea and
Gaddi in allowing an unidentified person to
drive out the subject vehicle. Proximate
cause has been defined as that cause,
which, in natural and continuous sequence,
unbroken by any efficient intervening cause,
produces the injury or loss, and without
which the result would not have occurred.
Moreover, Pea and Gaddi failed to refute
Sps. Mamarils contention that they readily
admitted being at fault during the
investigation that ensued.
In the instant case, the owners parked their
six (6) passenger jeepneys inside the BSP
Lorenzo
Shipping
v. BJ
Marthel
Intenational, Inc.
GR No. 145483, 19 November 2004
FACTS:
Petitioner Lorenzo Shipping Corporation is a
domestic corporation engaged in coastwise
shipping. It used to own the cargo vessel
M/V Dadiangas Express.
On the other hand, respondent BJ Marthel
International, Inc. is a business entity
engaged in trading, marketing, and selling of
various industrial commodities. It is also an
importer and distributor of different brands of
engines and spare parts.
From 1987 up to the institution of this case,
respondent supplied petitioner with spare
parts for the latters marine engines.
Sometime in 1989, petitioner asked
respondent for a quotation for various
machine parts. Acceding to this request,
respondent furnished petitioner with a formal
quotation
1.
2.
NO
NO
RATIO:
1. In determining whether time is of the
essence in a contract, the ultimate
criterion is the actual or apparent
intention of the parties and before
time may be so regarded by a court,
there
must
be
a
sufficient
manifestation, either in the contract
itself
or
the
surrounding
circumstances of that intention.
Petitioner insists that although its
purchase orders did not specify the
dates when the cylinder liners were
supposed
to
be
delivered,
nevertheless, respondent should
abide by the term of delivery
appearing on the quotation it
submitted to petitioner. Petitioner
theorizes
that
the
quotation
embodied the offer from respondent
while
the
purchase
order
represented
its
(petitioners)
acceptance of the proposed terms of
the contract of sale. Thus, petitioner
is of the view that these two
documents cannot be taken
separately as if there were two
distinct contracts. We do not agree.
It is a cardinal rule in interpretation
of contracts that if the terms thereof
are clear and leave no doubt as to
the intention of the contracting
parties, the literal meaning shall
control. However, in order to
ascertain the intention of the parties,
their
contemporaneous
and
subsequent
acts
should
be
considered.
While
this
Court
recognizes
the
principle
that
contracts are respected as the law
between the contracting parties, this
principle is tempered by the rule that
the intention of the parties is
primordial and once the intention of
the parties has been ascertained,
that element is deemed as an
integral part of the contract as
though it has been originally
expressed in unequivocal terms.
As an aside, let it be underscored
that [e]ven where time is of the
essence, a breach of the contract in
that respect by one of the parties
may be waived by the other partys
wifes name.
Testifying for Land Bank, Atty. Hingco
claimed during trial that as branch manager
she had no authority to approve loans and
could not assure anybody that their
assumption of mortgage would be approved.
According to Atty. Hingco, the bank
processes an assumption of mortgage as a
new loan, since the new borrower is
considered a new client. They used
character, capacity, capital, collateral, and
conditions in determining who can qualify to
assume a loan. Alfredos proposal to
assume the loan, she explained, was
referred to a separate office, the Lending
Center.
The RTC held that the contract approving
the assumption of mortgage was not
perfected as a result of the credit
investigation conducted on Alfredo. It noted
that Alfredo was not even informed of the
disapproval of the assumption of mortgage
but was just told that the accounts of the
spouses Sy had matured and gone unpaid.
The CA affirmed the RTC Decision. It held
that Alfredos recourse is not against the Sy
spouses. According to the appellate court,
the payment of PhP 750,000 was for the
approval of his assumption of mortgage and
not for payment of arrears incurred by the
Sy spouses. As such, it ruled that it would be
incorrect to consider Alfredo a third person
with no interest in the fulfillment of the
obligation under Article 1236 of the Civil
Code. Although Land Bank was not bound
by the Deed between Alfredo and the
Spouses Sy, the appellate court found that
Alfredo and Land Banks active preparations
for Alfredos assumption of mortgage
essentially novated the agreement.
ISSUE:
Whether or not the assumption
mortgage novated the agreement.
HELD:
NO
RATIO:
of