1433429565-PIN Mongolia (2013) Energy Audits of Chosen Typical Buildings in Mongolia
1433429565-PIN Mongolia (2013) Energy Audits of Chosen Typical Buildings in Mongolia
1433429565-PIN Mongolia (2013) Energy Audits of Chosen Typical Buildings in Mongolia
BUILDINGS IN MONGOLIA
Ulaanbaatar city
November 2013
Within the project Turning Sheep Wool into Environmentally Friendly Building Material
SEVEn team:
Bohuslav Malek,
Engineer, PhD.
Petr Zahradnok
Engineer
KlkraTauschova Engineer
This document covers humanitarian aid activities implemented with the financial assistance of the
European Union. The views expressed herein should not be taken, in any way, to reflect the official
opinion of the European Union, and the European Commission is not responsible for any use that
may be made of the information it contains.
2 Page
CONTENT:
Foreword ............................................................................................5
GENERAL BACKGROUND OF ENERGY AUDITING ..................................7
2.1. Selection of typical buildings in Mongolia ..............................................................7
2.2. Background and motivation for energy auditing in Mongolia ...........................7
2.3. Outline of the energy audit report ...........................................................................8
2.4. Recommended measures setting ...............................................................................9
2.5. Assessment of the energy performance of the building ....................................10
3.
Description of surrounding conditions ................................................11
3.1. Climatic conditions and overall environment .......................................................11
3.2. Standards requirements ............................................................................................12
3.3. Energy availability and renewable sources potential...........................................13
3.4. Economic features ......................................................................................................14
4. Overview of building parameters and Conclusions and recommendations...15
4.1. Description of the sample buildings ........................................................................15
4.1.1. Brick apartment building ..............................................................................15
Building constructions......................................................................................15
Technical systems.............................................................................................16
4.1.2. Pre-cast concrete (panel) apartment building ..........................................17
Building constructions ....................................................................................18
Technical systems ..........................................................................................18
4.1.3. School - brick building ....................................................................................18
Building constructions ...................................................................................19
Technical systems ...........................................................................................20
4.1.4. Single family house - combined timber and brick structure..................20
Building constructions.....................................................................................21
Technical systems..............................................................................................21
4.1.5. Single family house - timber structure .........................................................22
Building constructions......................................................................................23
Technical systems..............................................................................................23
4.2. Evaluation of current state ........................................................................................24
4.2.1. Thermal characteristics of a building..........................................................24
4.2.2. Energy sources and energy price................................................................25
4.2.3. Other technical equipment and lighting use ............................................26
4.2.4. Basic energy balance ...................................................................................26
4.3. Energy saving measures and their combination ..................................................26
4.3.1. Measures description ...................................................................................26
4.4. Environmental evaluation...........................................................................................28
4.5. Economic evaluation ..................................................................................................28
4.6. Auditors conclusions and recommendations .......................................................29
4.6.1. Brick apartment building...............................................................................29
Walls....................................................................................................30
Roof....................................................................................................................31
Windows..........................................................................................................31
Floor (ceiling) ..................................................................................................31
Others ..............................................................................................................31
Conclusion........................................................................................................32
Page 3
1.
2.
5.
6.
7.
8.
4 Page
Foreword
Within the scope of the project Turning Sheep Wool into Environmentally Friendly
Building Material Integrated Approach for Supply Chain Development, People in Need
with its partner NGO SEVen have successfully completed energy audits of typical Mongolian
buildings. A summary is presented to the reader in this publication.
Although foreseeable, the results are stunning. Enormous energy savings could be
achieved by adopting simple and reasonably cheap efficiency measures.
We sincerely hope this will be a source of inspiration for the multi-sectoral stakeholders.
Policy makers should find here the relevant figures related to energy savings (directly linked to
the needs of energy production), rehabilitation costs as well as payback period of investment.
The construction sector could use this document to calculate additional initial cost of insulation
and eventually use this analysis as a marketing leverage intended for end consumers. Finally
the end consumer should be able to figure out his own financial interest in taking energy
efficient measures for his habitation.
I would like to thank very much Mr Petr Zahradnik from SEVEn, the Energy Efficiency
Center NGO, who led energy audits on the field and authored present publication. Special
thanks also go to the owners of the audited buildings, apartments and houses and last but
not least to all People in Need NGO team in Mongolia.
Quentin Moreau
Head of Mission
People in Need, Mongolia
Page 5
In rather narrower perspective, which is the one of our projects, the author has
suggested to use Sheep wool building insulation as an energy saving measure. Though the
product is new and recently emerging on domestic market, we hope that the construction
sector stakeholders will take advantage of this new product by introducing it as green and
sustainable practice in the construction sector, conducive to economic growth of the country.
We also believe the policy maker will take the new product not only as an insulation material,
but as one of the very few environmentally friendly products made in Mongolia and hence
consider it in their effort to greening of the construction sector.
Energy audits of five defined buildings are carried out as separate documents that can be
understood as separate reports on energy audits. Following chapters serve as a summary of
these separate energy audits.
6 Page
In this chapter, basic background of carrying out energy audits is being described to
make clear its goals, procedures, methodology and overall features.
For following energy auditing, four residential and one school buildings (as defined
above) have been selected with the objective to demonstrate that the implementation
of energy savings measures could significantlyreduce energy consumption of
the apartments or school and increase quality of living there. Further, stress on heat
distribution systems of buildings is being laid in terms of heat losses reduction potential
searching for.
Energy auditing of chosen typical buildings in Mongolia is focused especially on:
Improving quality (i.e. thermally-technical parameters and durability) of envelope
constructions;
Reduction of heat consumption in a form of heat from district heating system, coal
or other energy carrier;
Improving quality of indoor environment in buildings including higher internal
temperature in winter time and avoiding of vapour condensation and moulds risk;
Increasing awareness on energy saving potential and its impacts among nonprofessionals;
Avoid overloading of existing electricity grids and heat pipelines;
Further, if energy related measures are applied hand in hand with relevant rehabilitation
of a building and/or its technical systems (e.g. heat distribution system), its lifetime
(durability) can be noticeably extended.
Following common featuresof Mongolian surroundings were identified as the crucial
arguments for supporting energy savings in Mongolia:
8 months long heating season with more than 6200 heating degree days in
average (central public heating season runs from 15 September till 15 May);
Most widespread existing residential buildings are pre-cast panel buildings (over
400 buildings in Ulaanbaatar) with huge heat losses as the heat energy consumption
Page 7
This report and the energy audits contain detailed description of sample buildings,
surrounding conditions, and conclusions and recommendations that were identified during
auditing process. The energy auditor presents conclusions on a basis of both experience and
calculations that are crucial part of the report.
Energy auditor always must bring or accept several approximations and expert
estimations as precise data or necessary documents are not available. In this case of five
energy audits, project design documentation or drawings were not available as well as data
on real (i.e. measured) energy consumption. Very often, heat consumption was not measured
anyway.
Energy prices that are necessary to be taken into account for economic evaluation
of the proposed measures were estimated on a basis of auditors investigation and verbal
discussion with tenants during the auditing visits. Further, specific costs for measures
(mostly in EUR/m2) were gathered in the same way.
In energy auditing, the energy performance (delivered energy) is the most important
result as it is directly related to costs savings and economy of energy savings related project.
Further, the primary energy as well as the CO2 emissions savings are very important global
indicators that say how big is an impact of building operation on environment.
10 Page
Description of surrounding
conditions
Most important surrounding conditions for energy auditing relate to climatic conditions in
the country, economic features of market, energy sources availability and technical accessibility
of materials and technologies.
(Source: http://weatherspark.com/)
For further calculations of energy consumption of chosen buildings, following values defining
surrounding climatic conditions in Mongolia were taken into account.
Page 11
Following figure shows average temperatures for Ulaanbaatar that were approximated for
Darkhan.
Table 3.11 - Monthly values of external temperature and relative air humidity used for
calculations
Month
10
11
12
Temperature
[C]
-24,6
-21,1
-8,2
2,4
10,7
16,4
18,2
16,3
9,1
0,5
-11,0
-20,8
Humidity
[%]
71
69
60
46
45
52
60
60
59
64
72
73
Especially in single family houses areas (and ger areas too), the buildings are heated
with highly inefficient stoves (burning coal or firewood) that cause huge air pollution during
wintertime in these urban areas. The family houses are usually generally under-heated during
wintertime as well.
For further comparison, basic models of the same existing state of buildings were
calculated using surrounding conditions related to average conditions in the Czech Republic.
Obviously, such an approach has theoretical value only and its results serve for comparison
of influence of these buildings on surrounding environment in two different locations with
different type of use of the buildings and climatic conditions.
Table 3.12 - Typical monthly values of Czech external temperature and relative air humidity
used for comparison
Month
10
11
12
Temperature
[C]
-1,3
-0,1
3,7
8,1
13,3
16,1
18,0
17,9
13,5
8,3
3,2
0,5
Humidity
[%]
83
80
73
66
67
68
67
67
74
79
85
85
12 Page
Required
UN (RN) [W/(m2K)]
in Mongolia
External wall
0,30
(3,16)
0,26
(3,70)
Roof
0,24
(4,03)
0,20
(5,00)
0,60
(1,33)
Floor
0,45
(2,05)
Windows
1,50
(0,50)
1,30
(0,60)
Doors
1,70
(0,42)
Construction
(Source: Mongolian standard BCNS 23-02-2009 Buildings Thermal Performance and Czech national
standard SN 730 0540-2 Thermal protection of buildings)
It can be stated that the requirements on thermal protection of buildings in these two
countries are quite similar, but usual winter conditions differ significantly. After a transition
to market energy prices and consumption-oriented billing, further strengthening of these
requirements can be expected as it becomes cost-effective.
It can be said, that energy (electricity and heat) are available in urban areas of Mongolia,
but the grids capacity and their technical state are getting to the maximum with sharply
growing economy. This is one of the reasons to focus on energy savings in buildings in
general.
Mongolia has large reserves of accessible coal which is the main heating fuel in urban
areas both for coal burning stoves and heat power plants. Especially the stoves without any
regulation, filtration and with inefficient burning process are huge sources of air pollution
during wintertime. Mongolia does not have own gas or oil reserves. Further, in the countryside,
the main sources for heating are dung and firewood.
Mongolia as a country has quite significant potential for production of electricity using
renewable sources based on water, ground heat, wind and solar energy. Directly for
separate buildings, some of these renewable are not possible to be used (hydro power
or wind power) as these huge producing plants cannot be installed directly on/nearby the
buildings, but must be connected to a grid. From this point of view, biggest potential can be
identified in solar power.
One of the crucial facts related to solar energy production is that Mongolia has 270 to
300 sunny days a year in average. Thanks this abundant sunshine (between 2500-3000 hours
per year) about 5-6kWh/m2 per day can be gained for free from this renewable source, that
equals to about 1200-1600kWh/m2 per year.
Page 13
Figure 3.42 - Initial investments of construction by type of a property built in billions MNT
14 Page
Five buildings that underwent energy auditing procedure evince similar features in
terms of energy efficiency and energy performance. Deep description and analysis
including model-based calculation see in separate energy audits of defined sample buildings.
South facade
Technical systems
District heating system is a source of heat for heating of the building. Main pipe system
brings hot water to the basement, where main closing valves are installed. Pipes are insulated
with glass or mineral wool and covered partly with gypsum layer or aluminium foil.
Then, heat is directly distributed by central water heating system to all flats. These pipes
are insulated partly only (about 50% of these basement pipes) with felt or synthetic rubber.
Heat exchanger is missing. Measurement of heat for heating system is missing as well.
Monthly costs for heating are calculated adequately per each flat per square meter of floor
area.
Metering of electricity is provided by separate meters per each flat.
Hot water consumption is being measured by metering of hot water volume that is being
used in the building as a whole (with about 60 families occupying the flats).
Standard light bulbs or energy saving compact fluorescent lamps (if changed recently) are
usually being installed for lighting in common spaces and staircases. Additionally, insufficient
daylight will cause an increase of electricity consumption for lighting in these spaces.
The apartments are always ventilated naturally using usual air-change around the windows
frames. Additionally, opening of windows helps to rise air exchange if needed. Often in commercial
units, and especially in restaurants, artificial ventilation is necessary to ensure good quality air
change in a kitchen as high relative air humidity and odour are typical for these premises.
16 Page
Air conditioning (and especially cooling) split-type units (e.g. with the compressor and
heat exchanger placed outside on the wall) are being installed usually in commercial premises
as individual cooling units.
The building part itself is rectangular shaped, its basic dimensions are 102 x 13
meters, total height is 15,4 meters. Total height of each floor is 3,0meters. All the envelope
Page 17
Chosen type of a pre-cast concrete (panel) apartment building is the most typical one used
for apartment housing in Mongolia.
Data on this sample building were collected mostly from personal visit of an energy
auditor and from discussion / investigation with inhabitants. Simplified measurements and photo
documentation were done. Data on real energy consumption of a building were not available.
As an example for further investigation of typical pre-cast concrete (panel) apartment
building, multi-family building at Darkhans New Districthas been chosen.
Model building is a 5-above-ground and one underground storied apartment building.
These buildings were typically built in larger composition as can be seen in Figure 4.12. As
these compositions (that are being created from similar rectangular separate buildings) differ
a lot, for further calculations only one typical rectangular part has been taken into account.
This typical part of a building has 5separate entrances on Western side and 94 flats
in total with average useful floor area about 55m2 each. There are 320 people living in
this part of a building. Further, there are several commercial units (typically small shops) on
ground floor (first above-ground level, i.e. floor above basement floor). Usually very low
basement cannot be used for any commercial purposes or for living. It is being used for heat
pipeline distribution purpose. Its height is about 1,5meters.
constructions have been measured and current state of constructions composition has been
checked on site because design documentation/drawings were not available.
Building constructions
Outer walls are made of heavy pre-cast concrete blocks with total thickness about
20cm (sometimes a bit more due to different plaster thicknesses). As the thickness is this low,
it is impossible to contain any functioning thermal insulation in it. Plaster made of common
cement/lime-cement mortar is applied on interior surface only.
Mostly old wooden doubled windows (with single glazing each) are installed. Due to lack
of quality maintenance, painting, sealing and due to water leakage, these wooden windows
are usually very bad shaped and their lifetime is over. Sometimes, huge holes between a
frame and a window wing can be found. Low percent of all the windows has already been
exchanged.
Main entrance doors of the building are wooden with small single-glazed part. Entrance
doors of flats (i.e. doors between a common staircase and flats) are mostly wooden as well
without glazing. Some of them are additionally insulated from their interior side.
The roof is flat simply composed without any thermal insulation. Load bearing part of the
roof is made of pre-cast concrete reinforced slab about 20cm thick.
Floor under the lowest flats has very simple composition of a reinforced concrete slab
without any additional layer. On the upper side of it, tiles, carpets or similar layers are used,
obviously.
Technical systems
District heating system is a source of heat for heating of the building. Main pipe system
brings hot water to the basement, where main closing valves are installed. Pipes are insulated
with glass or mineral wool and covered partly with gypsum layer or aluminium foil.
Metering of electricity is provided by separate meters per each flat. On its basis, costs
for electricity are calculated. The electricity in the building is being used for typical electrical
appliances and lighting.
Hot water consumption is being measured by metering of hot water volume that is being
used in the building as a whole (with about 20 families occupying the flats).
The apartments are always ventilated naturally using usual air-change around the
windows frames. Additionally, opening of windows helps to rise air-exchange if needed. Any
artificial ventilation has not been indentified even in commercial units.
Any artificial ventilation has not been indentified even in commercial units.
18 Page
Ortophoto map
Model building is a 2-story brick school building with total useful floor area m2 each. The building
has not any basement. The school is connected to district heating pipeline distribution. The building
is complicated shaped, composed of several rectangles. Its overall basic dimensions are 76,3x
100meters, total height is 7,5meters. Total height of each floor is about 3,5meters. All the envelope
constructions have been measured and current state of constructions composition has been checked
on site because design documentation/drawings were not available.
Building constructions
Outer walls are made of bricks with total thickness about 65cm (sometimes a bit more due
to different plaster thicknesses). Supposedly, outer part of the wall is made of white full lime-sand
bricks that are almost soak-proof compared to common red/orange bricks made of burnt clay. High
resistance to soaking water or air humidity is crucial in localities with higher number of freezing days
as the probability of soaked water or condensed vapour freezing is very high.
Old wooden windows were already exchanged and new plastic windows with double-glazing
unit with vacuum are installed in all the building except a gym. In the gym, there are still original glass
bricks instead of common windows.
There is only one main entrance to a building. Main entrance doors of the building are wooden
with small single-glazed part.
The roof is flat simply composed without any thermal insulation. Load bearing part of the roof
is made of pre-cast concrete reinforced slab about 20cm thick. A waterproof layer, sometimes
significantly damaged and patched is laid over the slab. Thickness of this layer is about 4mm.
The lowest floor on a ground has very simple composition of a concrete slab without any
additional thermally insulating layer. On the upper side of it, ceramic tiles or vinyl layers are used,
obviously.
Page 19
Technical systems
District heating system is a source of heat for heating of the building. Main pipe system
brings hot water to the building, where main closing valves are installed. Pipes are insulated
with glass or mineral wool and covered partly with gypsum layer or aluminium foil,allegedly.
Then, heat is directly distributed by central water heating system to all classrooms. These
pipes are not insulated.As they lead through heated parts of the building, heat losses are not
crucial.
Metering of electricity is provided by separate meter. The electricity in the building is being
used for typical electrical office appliances, computers and lighting. Lighting is provided mostly
by (saving) fluorescent lamps.
Hot water consumption is being measured by metering of hot water volume that is being
used in the building as a whole. Hot water is directly connected to the district heating distribution
grid.
All the building is ventilated naturally using usual air-change around the windows frames.
Additionally, opening of windows helps to rise air exchange if needed. A common hall is
ventilated by additional ventilator that helps to increase the air-change occasionally.
Any air conditioning units are not installed.
The chosen wooden/brick single family house is quite typical one used for single family
housing in Mongolia. It is a house that was / is being built by the owner himself with a help of
several craftsmen for some special works like plumbing, electrical network and installations. The
owner started with the building two years ago and the works still continue. As a majority of the
house was built by the owner who is not a professional, it can be expected that some mistakes
have been done or inappropriate procedures made. The house was not completed at time of
the visit. A balcony structure, a terrace above the entrance/kitchen room and masonry of a
gable wall were not finished.
As an example for further investigation,combined wooden and brick single family house in
Darkhanhas been chosen.
20 Page
Building constructions
Outer walls are made of very lightweight materials so, the owner decided to add a layer
of masonry that helps to increase thermal resistance of a wall and its weight that helps to
balance quick changes of internal temperatures due its heat accumulation function. The final
composition of the wall is: load bearing timber frame structure (about 150mm thick) covered
by wooden boards on both sides. Additionally there is about 40mm of soft mineral wool on
outer side of this wooden construction. Further, covering masonry made of 150mm thick wall
has been built on exterior side (not around the whole house at time of the visit, as mentioned
above).
Combination of new single-framed plastic / wooden windows with double-glazing unit
with vacuum inside are being installed. The wooden frames were, allegedly, produced by
a domestic joiner. The plastic frames are usually being imported from China and then
assembled in Mongolia by local enterprises.
The entrance doorto the house is simple wooden without glazed parts.
The roof is sloped with an attic floor below it. The roof composition is fixed to a loadbearing structure that is being made of wooden beams rafters. There is 10cm of polystyrene
(styrofoam) insulation and additional 4cm of mineral wool (the same material as used in walls
composition)between the rafters. The roof is waterproofed by metal sheets fixed to wooden
planks that help to make a very thin cavity between the sheets and insulation material.
Floor on a ground of a house is simply made of concrete, covered by vinyl or carpets.
Technical systems
For the heating of this house, coal and wood burning stoves are installed. Further, the
stoves can be used for cooking too. The stoves are connected to a hot water pipe system that
distributes produced heat to other rooms. As the owner mentioned, there is a huge problem
Page 21
This model building is a 2-stories(one full story on a ground plus one attic floor) single
family house without any basement. An entrance to the house is on its south-eastern side.
Windows are oriented on all sides of the house except the north-eastern one, where a shelter
for a car is located and directly connected to the facade. Useful floor area of the entire house
(its heated area) is 258m2. Entire house is heated except the shelter for a car as mentioned.
The building is T-shaped, its overall dimensions are 14 x 13meters anda total height is 5,4
meters from a ground to a top of the roof. Calculated volume of the house is 603m3. All the
envelope constructions have been measured and a current state of constructions composition
has been checked on site because design documentation/drawings were not available.
with heating during the severe winter as it is impossible to reach comfortable temperature in
the rooms.
Electricity is being used for lighting, partly cooking and for hot water preparation. Meals
are partly being cooked with the coal/wood stoves that serve mainly for heating. For lighting
mainly (saving) fluorescent lamps are being used.
Hot water is being prepared simply by using electrical boiler. At present, the owner does
not plan to install any renewable technology (e.g. solar thermal collectors).
At present, there is very low number of lighting sources in the house. As usual in the
country, quite efficient lighting sources (compact fluorescent lamps) are being used in the
house but as quite cheap, the quality of the sources may be low. Additionally, sufficient
daylight causesdecrease of electricity consumption for lighting.
Any artificial ventilation is not installed.
Any air conditioning units are not installed.
Chosen type of a wooden single family house is probably not the most typical one used
for single family housing in Mongolia but it is an example of active approach of Mongolian
citizens to find a way to own energy efficient housing.
As an example for further investigation,wooden single family house in Darkhanhas been
chosen.
This model building is a 2-stories(one full story on a ground plus one attic floor) single family
house. Entrance to the house is on western side. Windows are oriented on all sides except
the east, where an unheated shelter for a car is directly connected to the facade. Useful
floor area of the entire house (its heated area) is 213m2. Entire house is heated except
22 Page
the shelter for a car as mentioned. The building is almost rectangular shaped, its basic
dimensions are 14 x 8 meters anda total height is about 6 meters from a ground to a top
of the roof. Calculated volume of the house is 504m3. All the envelope constructions have
been measured and a current state of constructions composition has been checked on site
because design documentation/drawings were not available.
Technical systems
Electricity is being used for all the energy consumers in the house including hot water
preparation and the house itself for covering heat losses. Based on information by the owner,
it was not allowed to have a three-phase connection to existing electricity grid so, only a
simple one-phase connection was installed there.
Simple electric floor heating is being installed in all the floors of the house. The temperature
of heating source was set to 38C.
At present, hot water can not be prepared in the house as it is still under construction.
It is planned to install electricity consuming hot water boiler and, in future, solar thermal
collectors.
At present, as the house is still under construction, only a part of the lighting is being
installed. Efficient lighting sources (compact fluorescent lamps) are being used in the main
living space.
Any artificial ventilation is not installed.
Any air conditioning units are not installed.
Page 23
Building constructions
Outer walls are made of lightweight materials, composed of timber frame structure
(100mm thick) filled with 50mm of soft mineral insulation. On outer side, half-round wooden
timber is being used as a natural wooden facade. On interior side, wooden boards cover the
wall so, there is a 50mm thick non-ventilated cavity between the wooden boards and thermal
insulation in the framed structure. Any water vapour barrier has not been used.
wsingle-framed plastic windows with double-glazing unit with vacuum inside are being
installed. These plastic frames are usually imported from China and then assembled in
Mongolia by local enterprises. Fixing of the windows to walls is done using additional
wooden frame covering the PUR (polyurethane) foam joint filling.
The entrance doorto the house is simple wooden without glazed parts.
The roof is sloped with an attic floor below it. The roof above a heated bathroom is
significantly less sloped but has the same composition. The composition of the main part of
the roof (above the attic floor), thatis fixed to a load-bearing structure, is made of wooden
beams rafters. There is about 10cm of mixed thermal insulation between the rafters. The
thermal insulation is uneven and crooked with huge holes.
Floor on a ground of a house is simply made of concrete, covered by a base layer of
floor heating (to create even and flat surface, floor heating film with electric cables and a
laminate floating floor.
24 Page
Reinforced concrete
Wooden board
Timber
Wooden board
Insulation - mineral wool
Wooden board
Bricks
25
10
200
5
40
10
200
12,5
50
10
200
25
200
50
80
25
150
25
40
25
150
3,281
(0,13)
0,30
(0,16)
0,26
(3,70)
insufficient /
insufficient
0,932
(0,90)
0,30
(3,16)
0,26
(3,70)
insufficient /
insufficient
0,974
(0,86)
0,30
(3,16)
0,26
(3,70)
insufficient /
insufficient
0,756
(1,15)
0,30
(3,16)
0,26
(3,70)
insufficient /
insufficient
0,673
(1,32)
0,30
(3,16)
0,26
(3,70)
insufficient /
insufficient
Flat roof
Sloped roof
Sloped roof
(wooden house)
Ceiling above
the non-heated
space
Floor (wooden
house)
25
50
50
120
20
200
4
12,5
100
40
x
x
12,5
100
x
x
200
50
25
120
20
40
20
Window
wooden
Window plastic
Doors wooden
Doors metal
Full
0,628
(1,42)
0,30
(3,16)
0,26
(3,70)
insufficient /
insufficient
3,315
(0,16)
0,24
(4,03)
0,20
(5,00)
insufficient /
insufficient
0,497
(1,87)
0,24
(4,03)
0,20
(5,00)
insufficient /
insufficient
0,726
(1,24)
0,24
(4,03)
0,20
(5,00)
insufficient /
insufficient
1,880
(0,19)
0,60
(1,33)
insufficient
/x
1,285
(0,61)
0,45
(2,05)
insufficient
/x
2,800
(0,19)
2,000
(0,33)
3,500
(0,12)
5,600
(0,009)
1,50
(0,50)
1,50
(0,50)
1,70
(0,42)
1,70
(0,42)
1,30
(0,60)
1,30
(0,60)
x
x
insufficient /
insufficient
insufficient /
insufficient
insufficient
/x
insufficient
/x
External wall
(wooden house)
Wooden board
Air space
Mineral wool
Half-round timber
Plaster interior
Reinforced concrete
Waterproof layer
Gypsum board
Insulation - styrofoam
Insulation - mineral wool
Ventilated air space
Metal sheets
Gypsum board
Insulation - styrofoam
Ventilated air space
Metal sheets
Reinforced concrete
Concrete
Ceramic tiles
Reinforced concrete
Thermal insulation
Concrete
Laminate flooring
As the heat consumption is not being measured very often and energy price (either
price per square meter of a building or price per kilowatthour, gigajoule or other unit) is
significantly low, awareness to meaningful energy saving motivated by costs savings is low
too. Much more important is indoor comfort for the building users.
Coal
In family houses (and gers), inhabitants use coal boilers or stoves. Extremely low efficiency
is typical for the stoves as any system of regulation or useless heat accumulation is missing
in this case. Efficiency of boiler system is about 60% and 50% in case of boiler.Price of coal
for households is about 96000MNT/ton or about 44EUR/ton with a calorific value
about 19,9 GJ/ton. Final considered price of heat energy produced from coal is 7,96 EUR/
MWh.
Electricity
Electricity consumption is being measured using usual electricity meters per each flat or
family house.Price of electricity for households is about 90MNT/kWh (about 40,91EUR/
MWh) with a potential to grow significantly in coming years. At present the low electricity
price is not well motivating to consumers to be saved enough.
Electricity is being produced in coal power plants with low efficiency of burning process
and still high emissions. At present, electricity supply seems to be stable but present economic
growth brings potential risk of blackouts due to future overload of existing grid.
In apartment buildings (including grocery stores, shops and restaurants in ground floor),
family houses and school, part of electricity is being consumed by common domestic / office
appliances that are generally taken into account in calculations.
Lighting systems in buildings usually combine common inefficient light bulbs, energy
saving compact fluorescent lamps or commonfluorescent lamps.
External
wall - panel
with interior
insulation
External
wall - panel
with interior
insulation
140
10
200
Sheep wool
Plaster interior
Insulation - styrofoam
Plaster
Reinforced concrete
Gypsum board
Insulation - mineral wool
Plaster
Reinforced concrete
Plaster interior
Reinforced concrete
Insulation - styrofoam
Reinforced concrete
150
5
40
10
200
12,5
50
10
200
25
200
50
80
Wooden board
Vapour barrier
Sheep wool / timber
External wall Wooden board
wooden/bricks
Insulation - mineral wool
Wooden board
Bricks
Wooden board
Vapour barrier
External wall
Wooden board
(wooden
Sheep wool
house)
Sheep wool
Half-round timber
Plaster interior
Reinforced concrete
Flat roof
Waterproof layer
Sheep wool
sufficient /
sufficient
0,258 (3,71)
0,30
(0,16)
0,26
(3,70)
sufficient /
sufficient
0,932 (0,90)
0,30
(3,16)
0,26
(3,70)
insufficient /
insufficient
0,974 (0,86)
0,30
(3,16)
0,26
(3,70)
insufficient /
insufficient
0,756 (1,15)
0,30
(3,16)
0,26
(3,70)
insufficient /
insufficient
0,25
(3,83)
0,30
(3,16)
0,26
(3,70)
sufficient /
sufficient
0,258 (3,70)
0,30
(3,16)
0,26
(3,70)
sufficient /
sufficient
0,186 (5,23)
0,24
(4,03)
0,20
(5,00)
sufficient /
sufficient
25
x
150
25
40
25
150
25
x
25
40
100
120
20
200
4
240
Page 27
Sheep wool
Plaster interior
Reinforced concrete
Evaluation
MN/CZ
Sloped roof
Sloped roof
(wooden
house)
Gypsum board
Insulation - styrofoam
Insulation - mineral wool
Ventilated air space
Metal sheets
Gypsum board
Vapour barrier
Sheep wool between
rafters
Sheep wool under rafters
Ventilated air space
Metal sheets
12,5
100
40
x
x
12,5
x
160
Doors plastic
0,24
(4,03)
0,20
(5,00)
insufficient /
insufficient
0,196 (4,97)
0,24
(4,03)
0,20
(5,00)
sufficient /
sufficient
0,410
(2,10)
0,60
(1,33)
sufficient / x
1,300
(0,60)
1,300
(0,60)
1,300
(0,60)
1,50
(0,50)
1,70
(0,42)
1,70
(0,42)
1,30
(0,60)
insufficient /
insufficient
insufficient
/x
insufficient
/x
100
x
x
Sheep wool
80
Ceiling above Reinforced concrete
200
the non-heated
Concrete
50
space
Ceramic tiles
25
Single frame with high quality thermoWindow plastic
insulating double glazing unit
Doors wooden Full or partly glazed
0,497 (1,87)
x
x
Sensitivity analysis
The economic value of the project will depend, among other parameters, on the future
development of energy prices (in this case both electricity and heat) and on actual installation
costs of the insulation and other energy efficiency measures. The impact of these two factors
on the projects economic results was analysed in the sensitivity analysis.
Tocompare, present economic environment in Mongolia is partly similar to the situation
in the Czech Republic several years ago. The Czech Republic has already passed through
the transition period connected to energy prices. The Czech Republic may be regarded as
a typical representative with the Energy Performance of Buildings Directive fully implemented
into its legislature and with liberalized prices of energy linked to prices in other regional
countries.
Current Mongolian electricity and heat prices are still significantly below market prices
(subsidized by state). A deregulation of energy prices most probably comes in near future.
From the technical point of view, the only right solution of problems defined above
and in separate reports on energy audits, is the complex solutionthat consists of whole
building envelope improvement (if possible) and heating system regulation installation. It has
been stated earlier that the thermally technical parameters of the building constructions are
poor so, complex building insulation is the most important basic measure that needs to be
applied. As the energy prices are low at present, economic feasibility calculation does not
bring good results using present prices. In real, taking into account economic predictions, the
energy prices will most probably rise and the payback periods get shorter.
Following chapters summarize the conclusions and recommendations related to concrete
sample buildings.
Page 29
Walls
The ventilated facade is recommended to be applied as it is more secure type of composition
and it avoids risk of vapour condensation in the construction. Further, sustainable domestic soft sheep
wool insulation can be simply used.
Figure 4.61 - Scheme of ventilated facade composition on a brick wall with wooden bearing
structure
All facades will be provided with an insulation system based on 140mm of sheep wool
(=0,042 W/mK). Calculation of vapour condensation risk and temperatures inside the
construction is done for the same climatic conditions as for other existing constructions.
Roof
Definitely, the ventilated (double case) roof is recommended to be applied as
it is more secure type of composition, it avoids risk of vapour condensation in the roof and
damage-prone water vapour barrier layer is not necessary to be used.
Figure 4.63 - Sketch of added waterproof bearing structure with ventilated cavity underneath
An insulation layer will be made of 240mm sheep wool (=0,042W/mK). The waterproof
insulation must be secured against direct UV-rays to provide long-lasting protection so,
crushed stone (often a part of the waterproofing) or other similar covering must be applied
on it.
For this calculation purposes it is expected that all windows and doors are original in
the building. It means that exchange of all these windows and doors is contained in
this measure.
Floor (ceiling)
Expected thermal insulation of pipes in basement will cause further decrease of basement
temperature. Then, the thermal insulation of ceiling of this basement comes to be more efficient.
It is suggested to thermally insulate whole the ceiling of the building basement
using 80mm of sheep wool (=0,042W/mK).
Others
Page 31
Windows
Value
MWh/a
567
Energy savings
MWh/a
1 448
EUR/a
13 549
EUR/a
226
simple payback
years
6,9
EUR
115 030
Conclusion
From the technical point of view, the right solution of problems, caused by the poor
thermal resistance of the building, would be solved by installation of necessary
thermal insulation measures for all building envelope constructions and
improving heating system. Concretely, very poor thermally-technical parameters of
envelope constructions, missing regulation of heating system, insufficient thermal insulation of
common pipes in the building basement are the main findings of the audit.
These conclusions lead to following recommendations:
thermal insulation of walls
thermal insulation of roof
thermal insulation of ceiling of a basement
windows exchange
doors exchange (or at least improvement of main entrance doors)
thermal insulation of heat pipes and hot water pipes in the common spaces of the
building
quality regulation of heat radiatorsinstallation.
In later stage, before transition to consumption-oriented payment for heat and hot water,
the metering equipment must be installed measurement of heat and hot water consumption
in the building and introduction of a system that allows to divide total consumption to
separate flats.
These measures lead to significantly high energy consumption reduction.
Concretely in this case, consumption of heat from district heating system decreases from
1995 MWh/a to 547 MWh/a, that means 73% reduction!In absolute numbers, about
13,5thousand EUR per year can be saved on energy costs. Further, emissions can
be reduced by about 554tons per year.
The recommended combination of measures is cumulated in suggested project solution
that underwent economic and environmental evaluation. Based on assumed measures costs
and energy costs development (see the Sensitivity analysis), following results were received:
estimated installation costs are about 93 thousand EUR
real payback is about 8,6 years which is usually well acceptable in case of
building improvement investments, the payback period is shorter than measures
lifetime.
32 Page
Figure 4.64 - Scheme of ventilated facade composition including water vapour transfer
Page 33
All facades will be provided with an insulation system based on 150mm of sheep wool
(=0,042 W/mK). Calculation of vapour condensation risk and temperatures inside the
construction is done for the same climatic conditions as for other existing constructions.
Roof
Definitely, the ventilated (double case) roof is recommended to be applied as
it is more secure type of composition, it avoids risk of vapour condensation in the roof and
damage-prone water vapour barrier layer is not necessary to be used.
34 Page
Figure 4.66 - Sketch of added waterproof bearing structure with ventilated cavity underneath
An insulation layer will be made of 240mm sheep wool (=0,042W/mK). The waterproof
insulation must be secured against direct UV-rays to provide long-lasting protection so,
crushed stone (often a part of the waterproofing) or other similar covering must be applied
on it.
Windows and doors
For this calculation purposes it is expected that all windows and doors are original in
the building. It means that exchange of all these windows and doors is contained in
this measure.
Ceiling (floor)
Expected thermal insulation of pipes in basement will cause further decrease of basement
temperature. Then, the thermal insulation of ceiling of this basement comes to be more efficient.
It is suggested to thermally insulate whole the ceiling of the building basement
using 80mm of sheep wool (=0,042W/mK).
Others
Thermal insulation of common heat pipelines
Regulation of a heating system
Measurement of heat consumption
Repairing the lighting in common areas
Awareness increasing
Table 4.62Economic evaluation of measures combination
Unit
Calculated energy performance of suggested state of a building
MWh/a
Energy savings
Value
885
MWh/a
3 320
EUR/a
31 078
EUR/a
331
simple payback
years
EUR
4,7
331 151
Conclusion
From the technical point of view, the right solution of problems, caused by the poor thermal
resistance of the building, would be solved by installation of necessary thermal
insulation measures for all building envelope constructions and improving
heating system.Concretely, very poor thermally-technical parameters of envelope
constructions, missing regulation of heating system, insufficient thermal insulation of common
pipes in the building basement are the main findings of the audit.
These conclusions lead to following recommendations:
thermal insulation of walls
thermal insulation of roof
Page 35
All facades will be provided with an insulation system based on 140mm of sheep wool
(=0,042 W/mK). Calculation of vapour condensation risk and temperatures inside the
construction is done for the same climatic conditions as for other existing constructions.
Page 37
Figure 4.67 - Scheme of ventilated facade composition on a brick wall with wooden bearing
structure
Roof
Definitely, the ventilated (double case) roof is recommended to be applied as
it is more secure type of composition, it avoids risk of vapour condensation in the roof and
damage-prone water vapour barrier layer is not necessary to be used.
Figure 4.69 - Sketch of added waterproof bearing structure with ventilated cavity underneath
An insulation layer will be made of 240mm sheep wool (=0,042W/mK). The waterproof
insulation must be secured against direct UV-rays to provide long-lasting protection so, crushed
stone (often a part of the waterproofing) or other similar covering must be applied on it.
Windows and doors
In this case, windows and entrance doors were already exchanged. It means that all
thesenew windows and doors are already contained in existing state calculation.
Floor
Thermal insulation of any floor that is not above any accessible space (unheated basement)
is a measure that can be provided from heated interior. It is connected with demolishing of
existing floor and building operation restriction. This measure is reasonable only in case of
total building refurbishment with reduction/stop of building operation during site works. For
this sample building audit, this measure is not taken into account as the aim is to show widely
possible solution for energy efficiency improvement of buildings.
Others
Regulation of a heating system
Measurement of heat consumption
Awareness increasing
Table 4.63Economic evaluation of measures combination
Value
MWh/a
1 044
Energy savings
MWh/a
2 774
EUR/a
25 964
EUR/a
--
simple payback
years
5,2
EUR
265 330
Conclusion
From the technical point of view, the right solution of problems, caused by the poor
thermal resistance of the building except windows, would be solved by installation
of necessary thermal insulation measures for all building envelope constructions
and improving heating system regulation. Concretely, very poor thermally-technical
parameters of envelope constructions and missing regulation of heating system in the building
are the main findings of the audit.
These conclusions lead to following recommendations:
thermal insulation of walls
regulation of heat radiatorsinstallation.
In this case, windows and entrance doors were already exchanged. It means that all
thesenew windows and doors are already contained in existing state calculation.
Thermal insulation of the floor is a measure that is connected with demolishing of existing
floor and building operation restriction. This measure is reasonable only in case of total
building refurbishment with reduction/stop of building operation during site works. For this
sample building audit, this measure is not taken into account as the aim is to show widely
possible solution for energy efficiency improvement of buildings.
Above mentioned measures, even reduced by floor thermal insulation,still
lead to significantly high energy consumption reduction. Concretely in this
case, consumption of heat from district heating system decreases from 3793MWh/a to
1019MWh/a, that means 73% reduction. Separate roof insulation theoretically brings
58% heat consumption reduction.
In absolute numbers, about 26thousand EUR per year can be saved on energy
costs. Further, emissions can be reduced by about 1063tons per year.
The recommended combination of measures is cumulated in suggested project solution
that underwent economic and environmental evaluation. Based on assumed measures costs
and energy costs development (see the Sensitivity analysis), following results were received:
estimated installation costs are about 134 thousand EUR
real payback is about 6,1years which is usually well acceptable in case of
building improvement investments, the payback period is shorter than measures
lifetime.
not meet standard requirements as well, but it is technically and logically unsuitable to
recommend them to be parts of proposed energy saving project.
Walls
Thermal insulation on internal surface of the walls. This solution always must be well
designed and perfectly installed to avoid vapour condensation in the construction.
Further, the cavity between the masonry and the existing structure must be ventilated (naturally)
and a vapour barrier must be on internal side of the walls (beyond the wooden
boards). To install the thermal insulation to lightweight construction (from interior side) is
usually doable with good possibility to eliminate risk of future vapour condensation risk. It
differs from internal insulation of heavy brick or concrete constructions.
Obviously, this insulation on internal surface means a reduction of floor area
in the house as an increase of thermal insulation thickness influences the construction on its
internal side. This proposed solution of safe and well functioning thermal insulation application
is based on sensitive implementation of physical principals related to partial pressure of
vapour in constructions. It means that it is necessary to install well working vapour-proof layer
on internal surface (beyond the wooden or gypsum boards).
Another complication is in thermal bridges that are always created in a place of
connection of external wall with internal wall and between wall and ceiling.
In this case, when the construction does not have any extremely tight vapour barrier
inside or on outside surface, it is usually sufficient to use tightened (with well sealed joints)
wooden boards on internal surface. (Possibility and adequacy of such solution should always
be confirmed by an energy expert or calculation). Soft sheep wool insulation is suitable for
this composition.
All walls will be provided with a sheep wool thermal insulation with thicknessof 150mm
of sheep wool (=0,042W/mK). Calculation of vapour condensation risk and temperatures
inside the construction is done for the same climatic conditions as for other existing constructions.
Roof
After inspection of the sloped roof construction it was stated that its composition is critical at
present. Thermally technical parameters are not very poor but still, the construction does not meet
standard requirements. The worse problem is that the vapour condensation risk in this construction is
almost certain.
An insulation layer will be made of 260mm sheep wool (=0,042W/mK). The wool will be
partly put between the wooden rafters and partly to additional (e.g. wooden) bearing structure. Then,
airtight (sealed joints) vapour barrier must be well installed. The layer must be securelyfixed against
additional holes in it.
Value
MWh/a
93,3
Energy savings
MWh/a
73,4
EUR/a
584
EUR/a
584
simple payback
years
12,9
EUR
1 428
Conclusion
From the technical point of view, the right solution of problems, caused by the insufficient
thermal resistance of the building, would be solved by installation of necessary
thermal insulation measures for those building envelope constructions, where it
is technically and logically still relevant.
These conclusions lead to following recommendations:
thermal insulation of walls
thermal insulation of roof
The thermal insulation of both wall and roof need to be well installed including necessary
vapour barrier that ensures avoiding vapour condensation risk. Further, wall insulation is
understood as an internal thermal insulation that significantly affects floor area inside the
building. Obviously, such measure can not be installed widely.
Any external thermal insulation of the facade is not possible as it is uneven. Further, the
facade has its aesthetical value that should not be destroyed by this technical measure (at
least the owner would not agree on such measure).
To install the thermal insulation to lightweight construction (from interior side) is usually
doable with good possibility to eliminate risk of future vapour condensation risk. It differs
from internal insulation of heavy brick or concrete constructions.
This solution means reduction of floor area in the house as an increase of thermal
insulation thickness influences the construction on its internal side. This proposed solution of
safe and well functioning thermal insulation application is based on sensitive implementation
of physical principals related to partial pressure of vapour in constructions. It means that
it is necessary to install well working vapour-proof layer on internal surface. In this case,
when the construction does not have any extremely tight vapour barrier inside or on outside
surface, it is usually sufficient to use tightened (with well sealed joints) wooden boards on
internal surface. (Possibility and adequacy of such solution should always be confirmed by
an energy expert or calculation). Soft sheep wool insulation is suitable for this composition
as the covering layers creating aesthetical and waterproofing part of the facade are held by
separately fixed wooden frame structure.
All walls will be provided with a sheep wool thermal insulation with thickness of 140mm
of sheep wool (=0,042 W/mK). Calculation of vapour condensation risk and temperatures
inside the construction is done for the same climatic conditions as for other existing constructions.
Roof
Thermally technical parameters are not very poor but still, the construction does not
meet standard requirements. The worse problem is that the vapour condensation risk in this
construction is almost certain. This fact is given especially by these two reasons:
Water vapour barrier close to internal surface (beyond the wooden boards) of the roof is
missing;
There are metal sheets on external surface of the roof covering it and functioning as a
waterproofing.
An insulation layer will be made of 260mm sheep wool (=0,042W/mK). The wool will be
partly put between the wooden rafters and partly to additional (e.g. wooden) bearing structure. Then,
airtight (sealed joints) vapour barrier must be well installed. The layer must be securelyfixed against
additional holes in it.
Floor
No measures were suggested.
42 Page
Others
Awareness increasing
Table 4.65Economic evaluation of measures combination
Basic economic evaluation of suggested measures package
Unit
Value
MWh/a
39,1
Energy savings
MWh/a
33,4
EUR/a
1 367
EUR/a
1 367
simple payback
years
7,6
EUR
10 649
Conclusion
These measures lead to significantly high energy consumption reduction. Concretely in this
case, consumption of electricity for heating and hot water preparation decreases from 71,5MWh/a
to 38,1MWh/a, that means 47% reduction! In absolute numbers, about 1,3thousand EUR per
year can be saved on energy costs. Further, emissions can be reduced by about 39tons
per year.
Page 43
The recommended combination of measures is cumulated in suggested project solution that underwent
economic and environmental evaluation. Based on assumed measures costs and energy costs
development (see the Sensitivity analysis), following results were received:
Relevant definitions
Delivered energy (Energy use): Delivered energy refers to energy carrier (coal, heat
from district heating, electricity, gas etc.), supplied to the technical building system through the
system boundary, to satisfy the uses taken into account (heating, cooling, ventilation, domestic
hot water, lighting, appliances etc.) or to produce electricity in the building. This amount of
energy contains energy needed for covering lost in heat source, pipes, energy for running
ventilators and pumps. See following figure.
U-value: U-value (or Heat-transmittance coefficient) is the measure of the rate of heat
loss through a material. Lower U-Values are always better because the lower the U-value
the less heat that is being lost. The U-value is measured as the amount of heat lost through
a one square meter of the material for every degree difference in temperature either side of
the material. It is indicated in units of Watts per meter squared per degree Kelvin i.e. W/m2K.
Useful energy(Energy demand): Useful energy equals to demanded amount of
energy that is needed to keep planned/expected internal conditions in a building (i.e.
expected internal temperature, hot water temperature and amount, sufficient lighting etc.).
See figure above.
Water vapour condensation risk: The risk calculation helps to predict possible water
vapour condensation in construction. Result depends on diffusion resistance of materials used,
their thicknesses, relative humidity of air (especially in interior) and on air temperatures both
inside and outside. Simply said, the lower is temperature on interior side, the higher risk of
condensation on interior surface of construction or in it. Results of vapour condensation are
obvious: wet (even freezing) patches especially in colder corners of rooms and further, dark
patches of moulds that can be a source of allergy.
Page 45
Calculation tool Teplo 2010, Svoboda software , used for calculations of U-values
and water vapour condensation risk
Calculation tool Energie 2013, Svoboda software , used for calculations of
delivered energy, primary energy, energy savings and emissions parameters
http://www.beep.mn/,information from the UNDP project BEEP Energy Efficiency in
New Construction in the Residential and Commercial Buildings Sector in Mongolia,
project MON/09/301
http://weatherspark.com/, meteorological data
46 Page
List of tables
Page 47
List of figures
48 Page