Method Statement For The Flushing of Chilled Water Pipes: Document Number: REE-MS-MOQH-HVAC-014 REV 00
Method Statement For The Flushing of Chilled Water Pipes: Document Number: REE-MS-MOQH-HVAC-014 REV 00
Method Statement For The Flushing of Chilled Water Pipes: Document Number: REE-MS-MOQH-HVAC-014 REV 00
Project
The Consultant
The Project
Manager
K-63-281-14-HSR
MALL OF QATAR
HOTEL
Rev
Date
Reason
for
Revision
00
26-12-2015
Issued for
Approval
Compiled
By QA/QC
Engineer
Reviewed
by HSE
Methodology
and Checked
By Engineer
Reviewed
By Technical
Manager
Approved
By Sr.
Projects
Manager
John
Stephin
Bibin Raj
Sanjith
Gopakumar
Hyder Ali
Adel Kontar
Page: 1 of 33
REE
P.O. Box
17540
Date: 26th Dec 2015
Doha
Qatar
MEP Contractor
Project
The Consultant
The Project
Manager
K-63-281-14-HSR
MALL OF QATAR
HOTEL
Table of Contents
1.
INTRODUCTION........................................................................................... 4
2.
REFERENCE DOCUMENTS.............................................................................4
2.1
2.2
2.3
DOCUMENTATION..................................................................................................... 4
DRAWINGS................................................................................................................ 5
MATERIAL SUBMITTALS............................................................................................. 5
3.
4.
ACCESS/EGRESS..........................................................................................7
4.1
5.
ACCESSIBILITY.............................................................................................................. 7
LOGISTICS................................................................................................... 8
5.1
6.
TRAFFIC
MANAGEMENT................................................................................................... 8
7.
RISK ASSESSMENT......................................................................................................... 8
REE HSE REQUIREMENTS............................................................................................... 8
PERSONAL PROTECTIVE EQUIPMENT..................................................................................8
CONTRACTUAL REQUIREMENT.......................................................................................... 9
INFORMATION TO PERSONNEL........................................................................................10
PERMIT REQUIREMENTS.................................................................................................10
ENVIRONMENT..........................................................................................10
7.1
7.2
8.
RESPONSIBILITIES.....................................................................................11
9.
RESOURCES...............................................................................................12
9.1
9.2
MANPOWER............................................................................................................ 12
TOOLS AND EQUIPMENT......................................................................................... 12
10.
TRAINING...............................................................................................12
11.
WORKING HOURS....................................................................................12
12.
HOUSE KEEPING.....................................................................................13
13.
13.1
13.2
13.3
14.
14.1
14.2
15.
HANDLING................................................................................................................. 13
STORAGE................................................................................................................... 13
STORAGE IN HOT CLIMATE......................................................................................14
APPLICATION OF CHEMICALS..................................................................................15
PASSIVATION........................................................................................................... 16
SCHEMATIC DIAGRAM..............................................................................18
17.
Page: 2 of 33
REE
P.O. Box
17540
Date: 26th Dec 2015
Doha
Qatar
MEP Contractor
Project
The Consultant
The Project
Manager
K-63-281-14-HSR
MALL OF QATAR
HOTEL
18.
DISTRIBUTION........................................................................................20
19.
20.
APPENDICES........................................................................................... 21
APPENDIX-1....................................................................................................22
RISK ASSESSMENT........................................................................................... 22
APPENDIX-2....................................................................................................23
METHOD STATEMENT & RISK............................................................................23
ASSESSMENT BRIEFING FORM..........................................................................23
APPENDIX-3....................................................................................................25
INSPECTION AND TEST PLAN (ITP)....................................................................25
1. INTRODUCTION
The purpose of this method statement is to establish the necessary guidelines for the
Flushing of Chilled water Pipes and Fittings for HVAC system in accordance with the
specifications. This Method Statement shall ensure that the Flushing of Chilled water
Pipes and Fittings is executed safely and in accordance with the contract requirements.
Page: 3 of 33
REE
P.O. Box
17540
Date: 26th Dec 2015
Doha
Qatar
MEP Contractor
Project
The Consultant
The Project
Manager
K-63-281-14-HSR
MALL OF QATAR
HOTEL
This method statement aims to ensure that quality assurance and quality control
activities are conducted in a systematic manner, works are inspected and conformance
is verified and documented.
2. REFERENCE DOCUMENTS
2.1 DOCUMENTATION
2.2 DRAWINGS
KCT281-REE-M-SD-MP-MZAB-036
KCT281-REE-M-SD-MP-MZAB-036
KCT281-REE-M-SD-MP-MZAB-036
KCT281-REE-M-SD-MP-MZAB-036
KCT281-REE-M-SD-MP-01AB-121
KCT281-REE-M-SD-MP-MZAB-036
Page: 4 of 33
REE
P.O. Box
17540
Date: 26th Dec 2015
Doha
Qatar
MEP Contractor
Project
The Consultant
The Project
Manager
K-63-281-14-HSR
MALL OF QATAR
HOTEL
KCT281-REE-M-SD-MP-04AB-154
KCT281-REE-M-SD-MP-05AB-165
KCT281-REE-M-SD-MP-ALAB-054
KCT281-REE-M-SD-MP-ALAB-054
KCT281-REE-M-SD-MP-ALAB-054
KCT281-REE-M-SD-MP-06AB-539
Only approved materials shall be used, see the bellow listed material submittal
reference numbers for the reference and record.
KCT281-REE-MAT-0031 - Hangers & Support
KCT281-REE-MAT-0062 - CHW Grooved Fittings
KCT281-REE-MAT-0063 - CHW Threaded Fittings
KCT281-REE-MAT-0064 - CHW Welded Fittings
KCT281-REE-MAT-0111 - CHW Welded Fittings (Alt)
KCT281-REE-MAT-0030 - HVAC Valve
KCT281-REE-MAT-0093 - Pressurization Unit
KCT281-REE-MAT-0099 - Air Valve for CHW - Pump room & Chiller Yard
KCT281-REE-MAT-0095 - Pressure Relief Dampers
KCT281-REE-MAT-0034 - Thermo Insulation
KCT281-REE-MAT-0013 - Acoustic Insulator
KCT281-REE-MAT-0059 - Adhesive, Sealant & Self Adhesive Hanger
KCT281-REE-MAT-0041 - Aluminum Tape
KCT281-REE-MAT-0011 - Sound Attenuator
KCT281-REE-MAT-0151 - Flexible Connectors for FCU & AHU
Page: 5 of 33
REE
P.O. Box
17540
Date: 26th Dec 2015
Doha
Qatar
MEP Contractor
Project
The Consultant
The Project
Manager
K-63-281-14-HSR
MALL OF QATAR
HOTEL
I
ISO
ITP
KCT
ERGA
REE
MEP
MS
MSDS
PPE
PQP
Project
QA/QC
QCS 2010
R
S
SE
T
Third Party
W
WIR
1
2
Inspection
International Organization for Standardization
Inspection and Test Plan
Al Khayyat Contracting & Trading (The Design & Build Contractor)
The Consultant.
Radiant Engineering Enterprises. ( MEP Contractor)
Mechanical Electrical Plumbing
Method Statement
Material Safety Data Sheet
Personal Protective Equipment
Project Quality Plan
This shall refer to HOTEL AND SIGNATURE RESTAURANT
Quality Assurance/Quality Control
Qatar Construction Specifications 2010
Review
Surveillance
Site Engineer
Testing
An External Independent Agency
Witness
Work Inspection Request
= 100%
= 10%
Radiant Engineering Enterprises (REE) is the appointed MEP contractor for the project,
responsible for all aspects of MEP of the project.
Al Khayyat Contracting & Trading (KCT) is the appointed contractor for the project,
responsible for all aspects of construction of the project.
KCT is also responsible for procuring the Designer, Subcontractors, Project Management Team
and Facilities Management Company to operate the project.
Hill International Project Manager appointed by the Client to manage the successful delivery
of the Project.
ERGA Consultants have been appointed as:
1. Design Consultants
2. Supervision Consultants
Witness Point (WP):
Witness Points are Non Mandatory inspections which mean that if the required personnel do
not attend for the inspection at the stipulated time and location, work may proceed.
Hold Point (HP):
A mandatory stop to the works beyond which work may not proceed without the inspection
and/or test being completed and being found satisfactory by the specified party.
Review (R):
Document No.: REE-MS-MOQH-HVA-014 Rev. 00
Page: 6 of 33
REE
P.O. Box
17540
Date: 26th Dec 2015
Doha
Qatar
MEP Contractor
Project
The Consultant
The Project
Manager
K-63-281-14-HSR
MALL OF QATAR
HOTEL
Review of the inspection and testing records by the specified party for compliance and
accuracy.
Surveillance (S):
In process monitoring of the activities to the degree necessary to ensure that the work
proceeds in compliance with the established criteria.
4. ACCESS/EGRESS
4.1 ACCESSIBILITY
This section shows the accessibility of employees, material and machineries and the
appointments of Rigger/Banks man where needed.
5. LOGISTICS
5.1 TRAFFIC MANAGEMENT
Page: 7 of 33
REE
P.O. Box
17540
Date: 26th Dec 2015
Doha
Qatar
MEP Contractor
Project
The Consultant
The Project
Manager
K-63-281-14-HSR
MALL OF QATAR
HOTEL
Contractor shall be responsible for complying with the Exhibit-2 HSE Requirements for
Subcontractors and Suppliers in Contract. In addition, Contractor shall fully comply with the
following HS&E requirements:
HS&E Orientation & Training, HSE Pre-Task Briefing, HS&E Assessments, HS&E Incident
Notification and Investigation, HS&E Emergency Response.
Safety Helmet
Safety Shoes / Rubber Boots
Safety Glasses
High Visibility Vest
Over all (Only Labour)
Also there will be additional special PPE to be used in case of necessary as
follow;
Goggle
Dust Mask
Gloves
Face Shield
Necessary PPEs which are mentioned in Material Safety Data Sheet (MSDS)
Page: 8 of 33
REE
P.O. Box
17540
Date: 26th Dec 2015
Doha
Qatar
MEP Contractor
Project
The Consultant
The Project
Manager
K-63-281-14-HSR
MALL OF QATAR
HOTEL
Through management and monitoring, ensure the HSE Plan is implemented and
kept update as the project progresses.
Ensure the site rules are displayed at conspicuous locations in the project and
effectively communicated to all personnel in the Project.
Ensure risk assessments are carried out for all critical activities and it is
communicated to all those involved in the activity and risk mitigating measures are
adopted on the job.
Ensure site operatives are given daily task briefing by supervisors prior to
commencement of shift.
Ensure materials are not stacked outside the plot limit and dispensation obtained
from KCT/UCC for any storage outside.
Ensure coordination between Client, REE Project Manager, REE safety team and
consultants are maintained so as to update information on site general changes and
restrictions due to H&S reasons.
Ensure that accidents and significant incidents are properly investigated and
reported to the REE Management.
Ensure workers welfare committee for the project is formulated and meeting
conducted monthly to attend / resolve operatives issues.
Ensure hazardous substances are not stored outside the plot limit without
dispensation from the Site Manager.
Ensure appointments are made for lifting operation, temporary works and
housekeeping etc.
Information, instruction and awareness training about this Manual and KCT/UCC
norms shall be ensured for guidance and compliance.
Page: 9 of 33
REE
P.O. Box
17540
Date: 26th Dec 2015
Doha
Qatar
MEP Contractor
Project
The Consultant
The Project
Manager
K-63-281-14-HSR
MALL OF QATAR
HOTEL
All Workers shall be inducted and issued with site identification badge prior to
commencement of work.
Where application, the following passes / Permit shall be applied.
Vehicle Entry Pass
Defensive Drive Permission (Training is required)
Excavation permit
Hot work Permit
Construction Equipment Entrance Permit
Confined Space Permit (Training is required)
7. ENVIRONMENT
7.1 ENVIRONMENTAL IMPACT ASSESSMENT
In case of spilling of diesel, lubricants or hazardous chemical necessary spill
kits will be available on site.
An area for allocation of concrete waste and for concrete pumps washing shall
be arranged. This area should be properly bounded and labelled. The concrete
waste should be removed from site later on. To discharge onto the ground
contaminated water and remained concrete from concrete pumps or mixer is
prohibited.
The Chemical mixed water that is used for the flushing shall not be drained to
the public drainage system
The chemical mixed water that is used for the flushing shall be drained and
collected in containers.
8. RESPONSIBILITIES
Document No.: REE-MS-MOQH-HVA-014 Rev. 00
Page: 10 of 33
REE
P.O. Box
17540
Date: 26th Dec 2015
Doha
Qatar
MEP Contractor
Project
The Consultant
The Project
Manager
K-63-281-14-HSR
MALL OF QATAR
HOTEL
QA/QC Engineer is responsible to ensure work has been done as per the
specifications, method statement and drawings; inspections are done as per
Quality Control Procedure and Inspection and Test plan and offer works for
ERGA inspection.
The Safety Engineer is responsible to ensure that all Safety precautions are in
place, and that all personal on site are using the required Personal Protective
Equipments like Helmet, Gloves, Shoes, and Coveralls. We will also ensure
all relevant permissions are available for the works.
9. RESOURCES
9.1 MANPOWER
Page: 11 of 33
REE
P.O. Box
17540
Date: 26th Dec 2015
Doha
Qatar
MEP Contractor
Project
The Consultant
The Project
Manager
K-63-281-14-HSR
MALL OF QATAR
HOTEL
Insulation cutter
Sheet cutter
Screw driver
Pressure Gauge
Air Flow testing Machine
The tools and equipment utilized in carrying out the works shall be in good condition. All
tools/equipment will be inspected prior to use to ensure their fitness for purpose. Power tools
will be inspected on a regular basis/colour coded as per safety plan. Approved fit
transformers shall be provided/ used on site.
10. TRAINING
Pre start Task Safety Briefing by supervisor for executing the work is mandatory.
Training on method statement and risk assessment should be given to all the
employees involved in the mentioned activity by Site Engineer / Supervisor.
Any material delivered to the site that not confirming to the approved material
submittal shall be returned to the point of supply and to be replaced with approved
Page: 12 of 33
REE
P.O. Box
17540
Date: 26th Dec 2015
Doha
Qatar
MEP Contractor
Project
The Consultant
The Project
Manager
K-63-281-14-HSR
MALL OF QATAR
HOTEL
material.
Prevent end damage and dirt and moisture from entering into the chemicals for
Flushing.
Take all reasonable care when handling the chemicals, pumps and accessories
particularly in extreme climate conditions which will affect the physical properties
adversely.
13.2 STORAGE
If stored in the open for long periods, or exposed to strong sunlight, cover the stack
with opaque sheeting
Where possible store the material inside and protect from weather. Where necessary
to store outdoors, store above grade and enclose with waterproofing wrapping.
Store the materials under cover. Do not remove from cartons or packaging until
required
Ultra-violet light can affect the chemical property and shall be protected accordingly
- Store all materials in well-ventilated, shady conditions
- Do not expose to direct sunlight
- Keep the material in original packaging until required for use
Page: 13 of 33
REE
P.O. Box
17540
Date: 26th Dec 2015
Doha
Qatar
MEP Contractor
Project
The Consultant
The Project
Manager
K-63-281-14-HSR
MALL OF QATAR
HOTEL
sufficient quantity, these Contaminants will make the system prone to blockage at strainer,
control valves and small bore heat Exchanger. The micro-organisms may also initiate further
corrosion and may encourage the growth of micro-organisms.
The first stage towards removal of these contaminants is to thoroughly flush the system with
clean water. However, system flushing by itself will not remove these contaminants mainly
metal oxide, which adhere to the internal surfaces of the pipes. When the system is set to
work, movement of the pipe work due to the thermal expansion or contraction will cause
these contaminants to be released back into the fluid stream. Therefore the objective of
chemical cleaning are to loosen the surface deposits so that they can be flushed away and to
create a stable surface layer inside the pipe which if maintained by a proper water treatment
regime, will resist further corrosion. There is potential for a chemical clean to do more harm
than good if it is not carried out properly. The chemical used for cleaning must be compatible
with the system materials.
In particular the success of the chemical cleaning is dependent on the ability to undertake
through system flushing, before and afterwards, to ensure removal of the loose material and
the waste chemicals. The clean must be carried out as continues operation to avoid allowing
time for further corrosion to develop. Further only forward flushing alone will not remove as
much dirt from the system as a two stage, forward flush/ backward flush operation. This is
because it is extremely difficult to move particles through upsweep bends or prevent them
setting in unintentional traps such as valve bodies. By flushing the systems in both directions,
particles, which fail to move in one direction, will move in the other direction.
Bends from horizontal to vertical down & from down to horizontal or bends in the same plane
do not retard debris movement. The need to flush from horizontal to vertically upward can be
avoided in the first instance and should be carried out by back flushing of the system.
Page: 14 of 33
REE
P.O. Box
17540
Date: 26th Dec 2015
Doha
Qatar
MEP Contractor
Project
The Consultant
The Project
Manager
K-63-281-14-HSR
MALL OF QATAR
HOTEL
14.2 PASSIVATION
Once the system is thoroughly cleaned it should be properly passivated using passivation
chemicals. Clean Guard 70F03 (Passivation chemical) is a gentle passivator of the metal
surface.
System to be dosed with Clean Guard 70F03 at the rate of 1 kg per m and the system is to
Document No.: REE-MS-MOQH-HVA-014 Rev. 00
Page: 15 of 33
REE
P.O. Box
17540
Date: 26th Dec 2015
Doha
Qatar
MEP Contractor
Project
The Consultant
The Project
Manager
K-63-281-14-HSR
MALL OF QATAR
HOTEL
be circulated for the 8 hours. All the drain and flushing points of the system should be closed
during passivation of chilled water circuit.
Chilled Water System is having automatic dosing system and the operation of the system is
as follows.
15.3
Page: 16 of 33
REE
P.O. Box
17540
Date: 26th Dec 2015
Doha
Qatar
MEP Contractor
Project
The Consultant
The Project
Manager
K-63-281-14-HSR
MALL OF QATAR
HOTEL
The corrosion inhibitor Corroguard 33L01 dosing pump works based on the signal produced
by circulating chilled water conductivity. The conductivity set point is 2000 uS/cm (+/- 100
uS/cm band) and if it goes below set point the pump gets signal from controller to feed the
chemical till the desired result is achieved. Once the desired level of conductivity is achieved
the pump will stop feeding the chemical Corroguard 33L01.
The initial dosing of the Corro guard 33L01 is 3.0 Kg/m of chilled water.
c. Biocide Dosing Pump Settings:
Biocide dosing, Bio-guard 40H06 is based on the monthly timers. The pump starts for regular
interval once a month and is operating for the set time through controller. Dosing rates of the
biocide is 50 ppm per month and is based on system volume.
d. System Interlocks:
The Water treatment controller is supplied with the flow switch. In case of NO FLOW
condition none of the equipment will operate. This is to avoid any malfunctioning of the any
equipment if the plant is not in operation. In addition to this each tank is equipped with float
level switch. In the case of the low level of chemical in storage tank the pump will not be
operated.
List of BMS point is as follows;
1. Low Conductivity
2. Pump 1 Run Status
3. Pump 2 Run Status
4. Tank Low Level Status
Page: 17 of 33
REE
P.O. Box
17540
Date: 26th Dec 2015
Doha
Qatar
MEP Contractor
Project
The Consultant
The Project
Manager
K-63-281-14-HSR
MALL OF QATAR
HOTEL
16.
SCHEMATIC DIAGRAM
Page: 18 of 33
REE
P.O. Box
17540
Date: 26th Dec 2015
Doha
Qatar
MEP Contractor
Project
The Consultant
The Project
Manager
K-63-281-14-HSR
MALL OF QATAR
HOTEL
Internal inspections and client inspections will comply with the approved inspection
test plan.
The QA/QC Engineer shall inspect after the completion of all work for compliance
with project specification, approved drawing, method statement and quality of
workmanship prior to raise the inspection.
Approved installation check sheets shall be used for the Installed duct work
inspection.
All Step by step inspection shall be conducted in daily basis to monitor and analyse
the quality of job.
After the completion of installation activity duct test shall be conducted as stated
above.
Raise WIR for inspection of installations /testing of ducting as per approved Shop
drawings, to obtain the approval from the CONSULTANT as per approved ITP.
18. DISTRIBUTION
Approved copies of this method statement will be issued to the following for information and
necessary action:
Project Manager
Technical Manager
MEP Manager
QA/QC Manager
Construction Manager
Site Engineer
Site Supervisor
Safety Engineer
QA/QC Engineer
Page: 19 of 33
REE
P.O. Box
17540
Date: 26th Dec 2015
Doha
Qatar
MEP Contractor
Project
The Consultant
The Project
Manager
K-63-281-14-HSR
MALL OF QATAR
HOTEL
Signed: ____________________
Dated: ________________
20. APPENDICES
Page: 20 of 33
REE
P.O. Box
17540
Date: 26th Dec 2015
Doha
Qatar
MEP Contractor
Project
The Consultant
The Project
Manager
K-63-281-14-HSR
MALL OF QATAR
HOTEL
APPENDIX-1
RISK ASSESSMENT
Page: 21 of 33
REE
P.O. Box
17540
Date: 26th Dec 2015
Doha
Qatar
MEP Contractor
Project
The Consultant
The Project
Manager
K-63-281-14-HSR
MALL OF QATAR
HOTEL
APPENDIX-2
METHOD STATEMENT & RISK
ASSESSMENT BRIEFING FORM
Page: 22 of 33
REE
P.O. Box
17540
Date: 26th Dec 2015
Doha
Qatar
MEP Contractor
Project
The Consultant
The Project
Manager
K-63-281-14-HSR
MALL OF QATAR
HOTEL
Page: 23 of 33
REE
P.O. Box
17540
Date: 26th Dec 2015
Doha
Qatar
MEP Contractor
Project
The Consultant
The Project
Manager
K-63-281-14-HSR
MALL OF QATAR
HOTEL
APPENDIX-3
INSPECTION AND TEST PLAN (ITP)
Page: 24 of 33
REE
P.O. Box
17540
Date: 26th Dec 2015
Doha
Qatar
Document Reference
KCT-IMS-CM-3303B
Rev. No.
00
26/12/2015
Page Number
25 of 33
ITP LOCATION:
ITP MANAGED BY:
Rev. Date
SCOPE OF WORKS:
QA/QC MANAGER
REV. 00
ITP NO.:
ITP REV. DATE:
REE-MS-MOQH-HVA014
26/12/2015
Approval
T=
Testing
I =
Inspection
Inspection conducted at site level by the supervisory personnel and / or Project Manager.
S=
Supervision
V=
Verification
H1
A1
Random Actual
Witness Point
Review
ERGA QATAR
Requires IR submission. Hold Point require the person to sign the IRF and relevant Checklist (if applicable), for
the release prior to proceeding to the next activity.
IR submission is not required. To be Notified in the Contractors Daily Inspection Programme / Schedule of
Works; Required Checklist to be signed off by Project Managers representative.
IR not required. To be Notified in the Contractors Daily Inspection Programme / Schedule of Works;
No sign-off required.
Notification and proceed. Signing of relevant Checklist by the Project Managers Representative is optional.
Review documents only.
QME
CME
QME REE
LAB / 3RD PARTY
Laboratory / 3
SC
Subcontractor
Rd
Party
Page: 25 of 33
REE
P.O. Box 17540
Doha
Qatar
Document Reference
KCT-IMS-CM-3303B
Rev. No.
Rev. Date
00
26/12/2015
Page Number
26 of 33
FREQUENCY
I=
Initially
R=
Randomly
C=
Continually
F=
Final at End
S=
As Per Specification
This is with ref. to the client specification, Project Material & Workmanship Specification , QCS 2010
PREPARED BY:
QA/QC MANAGER
REVIEWED BY:
CORPORATE QA/QC MANAGER
APPROVED BY:
PROJECT DIRECTOR/MANAGER
26/12/15
26/12/15
26/12/15
NAME:
SIGNATURE:
DATE:
Page: 26 of 33
REE
P.O. Box 17540
Doha
Qatar
Document Reference
KCT-IMS-CM-3303B
Rev. No.
00
26/12/2015
Page Number
27 of 33
PROJECT:
MANAGED BY:
PROCESS
CONTROL
TYPE
SCOPE OF WORKS:
QA/QC MANAGER
REV. 00
ACTIVITY
NO
DESCRIPTION
CME
QME
REE
REE
3RD
PARTY
/ LAB
QME
KCT
ERGA
FREQUENCY
DOCUMENTATION
H/W
I/A
HSE
Rev. Date
ITP NO.:
ITP REV. DATE:
REFERENCE TO SPECIFIED
REQUIREMENTS FOR
INSPECTION TEST APPROVAL
SPECIFIED
REQUIREMENTS &
TOLERANCE
Project Specifications
15801
Project Specifications
15801
Material Receiving
Inspection Report
Project Specifications
15801
Project Specifications
15801
REE-MS-MOQH-HVA014
26/12/2015
DOCUMENTS
Page: 27 of 33
REE
P.O. Box 17540
Doha
Qatar
Document Reference
KCT-IMS-CM-3303B
Rev. No.
00
26/12/2015
Page Number
28 of 33
PROJECT:
MANAGED BY:
A1/R
A1/R
A1/R
A1/R
SCOPE OF WORKS:
QA/QC MANAGER
REV. 00
ACTIVITY
NO
DESCRIPTION
REE
REE
3RD
PARTY
/ LAB
SC
CME
QME
QME
KCT
ERGA
PRE INSTALLATION
I
INSTALLATION
TESTING:
Smoke test
Pressure reading
QCS 2010
PROCES
S
CONTRO
L TYPE
A1/R
INSULATION:
Installation of all joint insulation
Installation of Test points
Rev. Date
Project Specifications
OHAS 180012007.
ITP NO.:
ITP REV. DATE :
REFERENCE TO SPECIFIED
REQUIREMENTS FOR
INSPECTION TEST APPROVAL
N/A
REE-MS-MOQH-HVA-014
26/12/2015
SPECIFIED
REQUIREMENTS &
TOLERANCE
DOCUMENTS
Project Specifications
15801
Project Specifications
15801
Page: 28 of 33
Project Specifications
15051-Section 3
REE
P.O. Box 17540
Doha
Qatar
Document Reference
KCT-IMS-CM-3303B
Rev. No.
00
26/12/2015
Page Number
29 of 33
CONTROL TYPES
A = Approval
NOTES
QA/QC Manager
QME
CME
REE
Radiant Engineering
Enterprises / official
LAB / 3RD
PARTY
SC
Subcontractor
T = Testing
I = Inspection
S = Supervision
V = Verification
Page: 29 of 33
FREQUENCY
Rev. Date
PREPARED
REVIEWED
APPROVED
APPROVED (ERGA)
QA/QC MANAGER
CORPORATE
QA/QC MANAGER
PROJECT
MANAGER
ERGA QA/QC
MANAGER / REP.
I = Initially
R = Randomly
C = Continually
F = Final at End
S =As Per Specification
RESP. PERSON:
DATE:
REE
P.O. Box 17540
Doha
Qatar
MEP Contractor
Project
The Consultant
The Project
Manager
K-63-281-14-HSR
MALL OF QATAR
HOTEL
INSTALLTION CHECKLIST
DUCTING
REV:
WIR NO.
DRAWING REF:
SPEC. REF:
LOCATION/
AREA:
ITP NO.
SR
NO.
Check for the Bolt and Nut are Properly Fixed and
approved material is used.
8
9
10
11
12
13
14
REE
KCT
ERGA
SIGNATURE
NAME
DATE
Page: 30 of 33
REE
P.O. Box 17540
Doha
MEP Contractor
Project
The Consultant
The Project
Manager
K-63-281-14-HSR
MALL OF QATAR
HOTEL
DRAWING REF:
SPEC. REF:
LOCATION/
AREA:
MIR REF.:
ITP NO:
Material Specification:
Static Pressure:
Type of leakage test
Type of Jointing:
Date of test:
Duration of Test:
Testing Media:
Comments/ Discrepancies if any:
REE
KCT
ERGA
SIGNATURE
NAME
DATE
Page: 31 of 33
REE
P.O. Box 17540
Doha
MEP Contractor
Project
The Consultant
The Project
Manager
K-63-281-14-HSR
MALL OF QATAR
HOTEL
DRAWING REF:
SPEC. REF:
LOCATION/
AREA:
SR NO.
STATUS
REMARK
S
REE
KCT
ERGA
SIGNATURE:
NAME :
Document No.: REE-MS-MOQH-HVA-014 Rev-00
Page: 32 of 33
REE
P.O. Box 17540
Doha
MEP Contractor
Project
The Consultant
The Project
Manager
K-63-281-14-HSR
MALL OF QATAR
HOTEL
DATE:
Page: 33 of 33