Train Door System Analysis
Train Door System Analysis
Train Door System Analysis
and switch components. Part III includes train operations, rules governing delays and reliability calculations, and operating procedures. Part IV covers door
maintenance issues and practices for major door
components.
Following collection, review, and public presentation of data from the first questionnaire, the Train
Door team identified seven common door failures
and conditions that affect all the surveyed transit
agencies: (1) door fails to open or close when commanded from the operator location; (2) door status
interlock failures; (3) incorrect door opening; (4) incorrect door operation (operation/wayside error:
wrong side opening or open when not berthed): (5) obstruction detection failures/drags; (6) freewheeling
door panel; and (7) door fails to completely close and
lock and/or to indicate closed and locked.
The Train Door team then created a second questionnaire about component causes of the seven common door failures. For each failure, the questionnaire
lists generic door system components that could cause
the identified door failure. In addition to requesting
information on component causes, the questionnaire
asks for solutions to these common problems, including maintenance procedure changes, operational
changes, and/or equipment design changes.
The resulting data from both questionnaires
includes answers to 34 groups of questions, with
191 data items covering 21 railcar classes. The data,
collected in 2004, were unique, in depth, and of
great value. To permit processing and broad use of
the data, the Train Door team built a web-accessible,
Contribution (%)
100%
80%
60%
40%
20%
0%
A1
A2
A3
A4
B1
C1
C2
D1
D2
D3
D4
D5
D6
Car Class
Opening en Route
Phantom Operation
Sticking
Loss of Operator
No Motion Problem
Other
Rounding caused some totals to add to slightly less than or more than 100%.
E1
E2
E3
E4
1 INTRODUCTION
Starting in 2002, the APTA RSETF assessed
rolling stock problems that rail transit professionals
considered critical to their operations with the intent
to develop a project to help transit managers resolve
one set of those problems.
Transit industry managers from heavy rail, commuter, and light rail transit agencies identified critical
problems involving railcar body structures, doors,
propulsion and dynamic braking, air braking, trucks
Questions also cover the operating and maintenance responses to door incidents. To provide a visual
perspective of door opening and door operator locations, the questionnaire requests a door schematic
for each car class, showing plan and elevation views
of the car, side door openings (two, three, or four),
and door operator locations (under-seat, wall pocket,
or overhead).
The five participating transit agencies operate a
total of 32 car classes. Responses were provided for
21 of the car classes.
2.3.2 Part II: Door Equipment Survey
Part II covers door equipment and component
technical specifications for each car class. The survey
covers locations, types, manufacturers, models, and
original/retrofit condition for each of the following:
Door operators and master door controllers,
relays, cams, and micro switches
Wiring
Mechanical linkages
4
Door panels, sensitive edges, hangers, threshold plates, and bottom door-panel guides
Microprocessor/electronics equipment (at door
level and at car level)
Inter-car communications, train line wiring,
electric couplers, and electric portions
2.3.3 Part III: Operations
Part III covers train operations, applicable rules,
and standard operating procedures, including the
following:
The definition and calculation of train delays
Railcar performance reliability
Basis for calculating mean distance between
failures (MDBF) or mean time between failures (MTBF)
This part studies the distribution of door failures
in each car class. The questions on operational failures experienced, factors affecting satisfactory operations and reliability, and incidents leading to passenger injuries are rated on a percentile basis for
each, totaling 100%.
2.3.4 Part IV: Maintenance
Part IV covers door maintenance issues and practices for major door components: master door controllers, door operators, mechanical linkages, door
panels, door-panel sensitive edges, door hangers,
micro switches, relays, microprocessors, electronics
equipment, wiring, threshold plates and door guides,
and coupler electric portions and pins. Questions cover
the following:
Repair reporting method
Preventive maintenance (PM) intervals
Average time spent on door equipment during
each PM
Percentage that in-car system components
contribute to door incidents
Most common types of failure associated with
each door component
Percentage that trainline components contribute to door incidents
Details and elements of any car body/door
component interfacing problems that contribute to incidents
2.4 Getting Industry Data
In early 2004, the Train Door team began collecting data. With the full support of the transit
which enabled the project to develop a database for the collected train door information.
2.6 Second Questionnaire: Common Door
Failures and Component Causes
Following review of data from the first questionnaire and the Hold That Door session, the
Train Door team identified a set of seven common
door failures and conditions that affect all the surveyed transit agencies and contribute to delays and
other door problems. The team realized that further
information was needed to expand the understanding of the causes of these door failures. As a result,
the team created a second questionnaire. The second
questionnaire asks about the component causes of
the following seven common door failures:
Door fails to open or close when commanded from the operator location. The
questionnaire provides 14 choices for items
causing the failure, of which 11 are door
components.
Door status interlock failures. This serious
in-service failure is particularly troubling because door status interlocks are designed to
protect train passengers against other hazardous door open failures or conditions. Because
interlock functions are sensitive to operating
practices and driver actions, operator error was
included as a possible cause.
Incorrect door opening. This door system
failure is safety related and potentially dangerous. In this case, a single door opens without command because of a failure in the door
operator mechanism. This is a safety problem,
since one of the most important safety functions of train doors is to stay closed and locked
except when it is safe to open. As with interlock failures, preventive designs to address incorrect door openings have also gradually increased the complexity of door systems and
possibly reduced reliability.
Incorrect door operation (operation/wayside
error: wrong side opening or open when not
berthed). In this case, all doors on one side of
the train open on the wrong side or when the
train is not safely stopped at a platform. This
condition generally relates to operator, trainlevel, or wayside error. For passenger safety,
doors must open on the correct side at each
station, which poses real design and operational
5
in table form. For a question about door equipment, the table will give the responses for each
car class at each transit agency.
Export Data to Excel. This tab provides data
tables for further off-line analysis and processing by the user. The user can import the data
into a relational database and make combinational queries, bring the data into a spreadsheet
and plot distribution histograms, or undertake
any analysis which uses the base data.
Figure 4 shows typical data output from the Compare Data tab, a comparison of train door sensitiveedge equipment. The output shows, for each car
class, the type of door sensitive-edge equipment, its
basic configuration, and its retrofit status. Appendix
C shows examples of other types of output.
The capability to export data to Excel for offline analysis is an important one. The volume and
detail of data invite explorations of relationships
among equipment, operations, failures, climate, region, and other differences. The Train Door team did
not consider limiting or presetting the combinations
that could be analyzed to be practical or desirable.
Accordingly, the Export Data to Excel tab allows an
interested user direct access to the primary data.
12%
6%
9%
45%
6%
9%
7%
switch/sensor
interlock failure
local door controller
threshold/bottom guide
6%
70%
60%
50%
40%
30%
20%
10%
0%
A1 A2 A3 A4 B1 B2 B3 B4 C1 C2 D1 D2 D3 D4 D5 D6 E1 E2 E3 E4 E5
Railcar Class
Relative Impact
(1 = lo, 2 = med, 3 = hi)
0
A
Transit Agency
and Season
Ag
Summer
Spring
Fall
Winter
Such data are important to a specialized community. While the transit equipment engineering community is barely known in the broad world, its work
has a big impact on rail transit reliability and safety
and on the daily commuting experience of millions of
people, every day.
To the best of the teams knowledge, the collection of data presented on traindoors.com is unique in
the transit world. Nowhere else is it possible to access
detailed, usable, timely data on a rail transit vehicle
subsystem from leading transit agencies.
Contribution (%)
100%
80%
60%
40%
20%
0%
A1
A2
A3
A4
B1
C1
C2
D1
D2
D3
D4
D5
D6
E1
E2
E3
E4
Car Class
Opening en Route
Phantom Operation
Sticking
Loss of Operator
No Motion Problem
Other
Rounding caused some totals to add to slightly less than or more than 100%.
100%
Contribution (%)
80%
60%
40%
20%
0%
A1
A2
A3
A4
B1
C1
C2
D1
D2
D3
D4
D5
D6
E1
E2
E3
E4
Car Class
Environmental
Passenger Use
Employee Operations
Design
Maintenance
Other
6.3 Conclusions
The general conclusions from the teams collection effort to date have confirmed to the team the
following:
The steps reported here to collect, manage, and
report on train door data are effective in collecting transit industry information that can
provide important and useful results.
The common door failures questionnaire provides a valuable source of data to focus on specific door system components.
The data reported by the transit agencies point
to problems caused by switches, sensors, and
push buttons.
7 ACKNOWLEDGMENTS
The generous and energetic contributions of
scores of supporters and participants are recognized
and appreciated.
Thanks to the APTA RSETF, whose ranks produced many volunteers and contributors to this project. The team membership grew to include 30 participants, including rail car manufacturers Alstom
Transport and Kawasaki Rail Car; door equipment
manufacturer Faiveley Rail Corporation; engineering consulting firms BoozAllen & Hamilton, LTK
Engineering, Interfleet Technologies, Transportation
Systems Design, and Turner Engineering Company;
and transit agencies BART, CTA, Delaware Area Port
Authority (DRPA), NYCT, PATH, and WMATA.
15
These digests are issued in order to increase awareness of research results emanating from projects in the Cooperative Research Programs (CRP). Persons
wanting to pursue the project subject matter in greater depth should contact the CRP Staff, Transportation Research Board of the National Academies, 500
Fifth Street, NW, Washington, DC 20001.