Formwork Handbook DLF Capital Greens
Formwork Handbook DLF Capital Greens
Formwork Handbook DLF Capital Greens
L&T Construction
L&T Construction
INDEX
SL.
Topic
1)
2)
3)
4)
5)
6)
7)
8)
9)
Stacking (Housekeeping)
10)
11)
12)
Formwork safety
13)
Accident Prevention
14)
15)
L&T Construction
Formwork Strategy
Structure
System proposed
Total scope
(Sqm)
Catering area
(Sqm)
Isolated footings
Wall / Column FW
4838
227
Wall / Column FW
443544
7819
Retaining Wall
Wall / Column FW
5155
254
400697
10595
Flex System
447817
11841
Staircase
Flex System
23524
871
1325575
31608
Total FW Scope
L&T Construction
L&T Construction
Work
Platform
Lifting Bracket
Steel
Waler
H-Beam
Alignment
System
Ply
L&T Construction
Formwork Erection:
Making of shutter panels
1) Drill holes in H-beams for fixing beam clamp, lifting
bracket & Working platform bracket.
2) Make shutter panels (without/with fixing of walers
and accessories) of required size including cutting
plywood for stitching with H-beams.
3) Fix of wooden planks (40mm) at top & bottom sides
of shutters. Minimum size of column that can be
done is 300mm x 300mm.
4) The shutter panels can be combined as an L
shaped panel using angle plate& lifted to next location.
5) Fix starter suitable to column size.
6) Remove the forms for starter after concreting is
over.
7) After concreting clean the shutters with water jet for any excess / over concreting.
Assembly of formwork:
1) Fix both shutter panels in position.
2) Fix tie rod, anchor plates and wing nuts at the corner of shutters in each waler level.
3) Fix Alignment props/supporting brackets with Head adaptor assembly and
foot adaptor assembly on the adjacent sides of the shutters.
4) Plumb the shutter panels as required and checking the column size as per requirement.
5) Fix the stop anchor, anchor cone with PVC sleeve to facilitate for fixing of climbing
bracket for next lift.
Deshuttering of column formwork:
1) Remove side panels in after removing the alignment props, tie rods/accessories only.
2) Clean, apply oil and shift.
6
L&T Construction
WALL FORMWORK
SYSTEM DESCRIPTION:
Formwork Erection:
Making of shutter panels
1) Lay waler @ distance (or) predetermined location over the leveled surface. (Either a
timber platform or with lean concrete to accommodate the size of the shutter panel)
2) Drill holes in H-beams for fixing beam clamp, Lifting bracket & working platform bracket
at predetermined locations using suitable power drill.
3) Drill holes in H-beams with Drilling plate & safe guard for fixing M 6 x 70 bolts with
waler.
4) Place the H-beams above the waler and connect the same with beam clamp / M6 bolts.
5) Place the Plywood (the grains should be perpendicular to the timber beams) and ensure
proper butting of plywood with the Assembly.
6) Use only screws (1.5 long) for fixing plywood with H-beams. (approx. 8 nos for 8 x 4
plywood size )
7
L&T Construction
7) Fix wooden planks (40mm thk. x 160 mm) at top & bottom sides of shutters. Provide slot
in the top plank of lifting bracket location.
8) All the above should be done with an accuracy of ( + or -) 2mm
9) Any lengths of panel to suit the required dimension of walls can be formed using the
available lengths of waler, splice plate & connecting pins, if the system is to be crane
handled.
Erection of wall formwork:
1) The wall panels should be placed on the outside first and all the gaps to be filled
appropriately using fillers/sponge etc. for maintaining the form finish, then reinforcement can be tied and inner shutters be placed.
2) The wall panels should be placed alongside each other & aligned properly; edges
checked using plumb bob and line threads.
3) The joints of the wall panels should be filled with sponge or appropriate filler material
so that the slurry leakage is arrested.
4) The tie rod hole locations shall be made prior to erection of shutters so that the
alignment &pattern of hole locations is to be maintained uniformly. No other holes
should be allowed to drill later.
5) The grout check has to be fixed to the shutters at the top so that the concrete level can
be maintained in a straight line for the pour and it also acts as a starter for the second
pour above.
6) Fix timber spacers to maintain the wall thickness at top.
7) High strength tie system bears large concrete pressures and avoids load-bearing struts.
8) Panels can be made in large units for handling by crane and in smaller ones to facilitate
manual handling.
9) Panels can be used along with Climbing Formwork system for the more height.
De-shuttering of wall formwork:
1) First remove Wing nut, Anchor plates, Tie rods, Head adaptor assembly, Alignment
struts, Supporting Brackets, Foot adaptor assembly.
2) Remove shutters (each separately) with the help of crane or manually.
3) In case of subsequent lifts remove climbing brackets, Suspended platforms handrail post,
accessories.
4) In case of shutter being used for subsequent lifts the Alignment struts head adaptor
assy., Foot adaptor assy., Supporting Brackets need not be removed.
5) Stacking of wall shutters shall be done vertically with fabricated steel racks (Ref. fig vertical stacking of formwork).
L&T Construction
FLEX SYSTEM
SYSTEM DESCRIPTION:
The forms shall be made with plywood backed by H-beam & supported by using props. Props
take the load and shall be erect in position using tripods for lateral stability. The spacing between the timber beams shall be in accordance with design criteria & should be properly
screwed to the plywood and safely placed over the props to avoid toppling.
The props are designed to take care of the vertical loads which are tested under maximum
loading conditions. The spacing of CT prop will be decided based on the thickness of the slab
i.e. load coming from the slab & the prop height required. More the height, the lesser will be
the capacity so it should be ensured that use of props in the fully extended condition should
be avoided.
Formwork Erection:
Erection of FLEX SYSTEM:
1) Mark Props location.
2) Place main Props I step, Tripods, - II step, Four way heads III step.
3) Use four way heads over props at the lapping joints of primary H-beams.
4) Place primary & secondary layers of H-beams.
5) Place plywoods and screw with H- beams.
6) No need to place tripod at all the prop Location but should provide at ends and joints
of primary H-Beam
9
L&T Construction
CUPLOCK SYSTEM
SYSTEM DESCRIPTION:
L&T Construction
STEP-1
11
STEP-2
L&T Construction
STEP-3
STEP-5
STEP-4
STEP-6
L&T Construction
13
Minimum distance
3 feet (0.9)
10 feet ( 3.1m)
10 feet (3.1m) plus 4
inches
10 cm for each 1 kv
over 50 kv
Alternatives
2 times the length of
the line insulator
but never less than
Minimum distance
Alternatives
10 feet (3.1m)
10 feet (3.1m) plus 4
inches
10 cm for each 1 kv over
50 kv
10 feet (3.1M )
L&T Construction
14
L&T Construction
SYSTEM DESCRIPTION:
The L&T-Formwork Climbing System are used for tall structures like cooling towers,
etc. where very uneconomical & unsafe to provide staging or scaffolding for supporting
the external or internal wall formwork.
In this system bracket is hanged on anchors called lost stop anchors provided in the already casted wall and supports/alignments are taken from these brackets. The brackets
are suitably braced to prevent any sway and are provided with walkways/working platforms / handrails etc. for safety and ease of working.
15
L&T Construction
16
L&T Construction
--
SEQUENCE
After dismantling the shutters from the 1st pour of concrete, remove anchor cone using DK spanner
and fix climbing cone in the stop anchor.
Assemble Climbing bracket 150 A 2 no's (max distance should be 2.0 to 2.40 m) and brace with NB
40 pipes and couplers to form as a unit.
Provide working platforms with 4X 4 (or) timber as supporting member and 2 thick planks.
Brace the primary member and climbing bracket with brace stirrup.
Fix Handrail post on each bracket and hand railing at 2 levels should be done with NB 40 pipes &
couplers.
Lift the entire assembly of climbing bracket 150 A with the help of crane and place over the climbing
cone correctly and lock the pin.
Follow the procedures described in the assembly of wall formwork; however the alignment props to be
fixed in the climbing bracket platform.
Suspended platform 80 A should be fixed in the predetermined holes provided in the climbing bracket
and brace the suspended platforms with NB 40 pipes and couplers. Provide 2 thick planks as working platform.
Cover the open face of suspended platform with safety net.
Check the verticality of the shutter using plumb bob.
Dismantling
17
L&T Construction
18
L&T Construction
Stair towers outer frame has been modified to accommodate mesh so as to prevent both men
and material from falling.
COMPONENTS
19
L&T Construction
20
L&T Construction
Description
Moisture content
3
4
5
Dimensional
Tolerances
Thickness of
face veneer
layer
Timber
Mass
Adhesives
7
No. of ply in
a board
Tensile
Strength
10
Test Report
Specifications
Reference / Remarks
Length=+6mm,-0mm,
Width= +3mm, -0mm,
Thk. tol.=for > 6mm = +/-5% & for < 6mm = +/10%
Edge straightness & squareness 2mm per 1000mm
i.e 0.2%,
7-ply / 9-ply
not < 32.5 N/mm2 parallel to grain direction of the
face veneers
not < 22.5 N/mm2 right angles to grain direction of
the face veneers
sum of the tensile strength in both directions shall
be not < 60.0 N/mm2
Shall conform to IS 1734
(Part 4) :1983
Each consignment shall be supplied along with
Test Report on the above parameters
21
L&T Construction
L&T Construction
+ 12 mm
- 6mm
1) Dimensions in plan
+ 5omm
- 12 mm
0.02 times the
width of the footing
in the direction
of deviation
but not more than
50mm
+ 0.05 times the
specified thickness
2) Eccentricity
3) Thickness
23
L&T Construction
WORK
BENCH
MEASURING
TAPE
CLAW
HAMMER
CHISEL
PLUMB
BOB
TUBE LEVEL
AUGUR
24
SCREW BAR
ADJUSTABLE
SCREW
SPANNER
TRY
SQUARE
LINE
THREAD
DOUBLE END
SPANNER
HAND
SAW
SPIRIT
LEVEL
RING
SPANNER
HAND
PLANNER
TWO WAY
RATCHET
PLYWOOD
TRY SQUARE
( BIG)
L&T Construction
JIG SAW
DOUBLE END
SPANNER
HEAVYDUTY DRILLING
MACHINE
RING
SPANNER
( HSS ) DRILL
BIT
WOODEN
FLAT DRILL
BITS
CONCERETE
DRILL BITS
HAND PLANNER
(ELECTRIC)
25
HEAVY-DUTY HSS
DRILL BITS
COUNTER SUNK
DRILL BITS
L&T Construction
Use tripods only where the H-beams are lapping and at the ends.
All the legs of the tripods to rest on firm ground.
Props to rest on the ground firmly and should be compacted.
Ensure sufficient lap of H-beam in primary & as well as in secondary.
Ensure the Correct spacing of H-beam & Props. According to FW design (FW Scheme
drawing).
26
L&T Construction
40mm thick
Timber plank as
compression
strut
Angle should
not be less
than 60
27
L&T Construction
STACKING (Housekeeping)
Stack the materials properly when not in use & protect them.
It helps
In easy reconciliation
Faster retrieval of material & reconciliation.
Better space management
Improves work culture
Avoids wasteful expenditure
Safety- prevention & loss of material
Protection to materials- improves life of materials
Enables easy maintenance
28
L&T Construction
29
L&T Construction
30
L&T Construction
31
L&T Construction
Shuttering oil sprayer machine can be used for easy application of shuttering oil on both horizontal and vertical shuttering panels. It sprays oil when compression pressure is maintained by
pumping. It is easy handling for workers; they can hold it in hand or hang on their back.
Benefits:
32
L&T Construction
FORMWORK SAFETY:
Inbuilt safety features in L&T System Formwork
Flex System
Clear passage for workmen & inspection, self-standing with tripods.
Beam Forming Support
Safe and easy fixing removal mechanism, no loose components.
Column Wall /Formwork system
Walkway Passage for tying of reinforcement, concreting & vibrating. Lifting hooks for
mechanical handling, double nut props for alignment in both directions.
Cup Lock System
Simple connections- no loose components, easy vertical alignment on uneven ground
also, self-locking pins.
Stair Tower System
Access to heights up to 100 m with adequate tying to structure at 6.0 m. Handrail at
all locations, Regular and comfortable risers, Uniform Head room, Proper arrangement of landing at regular intervals, Multiple entry possible on sides of buildings .
33
L&T Construction
34
L&T Construction
Columnstaging arrangement
Proper access
Guard rails
Intermediate Landing
Workmen equipped
with all required
Personal Protective
equipment.
Safety Net
provided
to protect
from fall of
workman
& Material
35
L&T Construction
36
L&T Construction
Approach walkway
Flex System
Do not use
Reinforcement
instead of locking pin
37
L&T Construction
Working Platform
38
L&T Construction
Working Platform
39
L&T Construction
Floor Openings
Cover the openings
Provide guard rails
Safety net with fishing net
to trap falling materials
Provide toe-guard to prevent materials falling
through openings
Guarded Edge
L&T Construction
41
L&T Construction
Safe Access for the Concreting of wall / Column with the help of
brackets & NB pipe
42
L&T Construction
Dismantling of Scaffold
1. Cordon off the area and deploy
only experienced men. Provide
Red Tag
2. Start dismantling from top.
3. Each tier shall be completely
dismantled and the material lowered to the ground before beginning to dismantle the next tier.
4. Use Derrick and Pulley for lowering materials if at heights.
5. While removing jammed or rusted scaffold components, anchoring safety belt is essential.
6. At the end of the day, if a scaffold is going to be left halfdismantled, it is essential to lower all the loose scaffold materials
down and ensure that the scaffold is braced adequately to the
building.
43
L&T Construction
Cover completely
and
securely
If no cover,
should
guard with a
guardrail
L&T Construction
Accident Prevention
1.
2.
3.
4.
Safe Design
45
L&T Construction
46
L&T Construction
Allowable
Tolerance
DESCIRIPITION
OK
NOT OK
REMARKS
Verticality ( plumb )
Every Joint
with
Using of
m6 bolts
Verticality of props
1
2
47
L&T Construction
Height of screw jack adjusted, so that bottom level of all verticals is same.
Screw jack with base plate to be fixed in rigid surface
Coupler with 2 nos of connecting pins at each joints of vertical
leg.
3
4
5
11
11
d) Diagonal
e) Radius
48
L&T Construction