CA2 Group Assignment Complete
CA2 Group Assignment Complete
CA2 Group Assignment Complete
MATHEMATICS
BSc. (Hons) in Quantity Surveying
Assignment 1
Course code
: QUS 4205
Course Name
: Contract Administration 2
Lecturer
Date
Group members :
Name
Matric number
Mah Ker Yi
Yong Shu Teng
Yapp Ka Chee
Cheung Memtem
I14005119
I14004886
I12001445
I12001276
List and explain the difference and similarity between the following
clauses in the PAM standard form of Building Contract 2006 (with
quantities) and the JKR Building Contract with Bills of Quantity,
Form 203A.
a) Contract Document
The Contract Documents as aforesaid shall remain in the custody of the S.O. and shall be produced as
and when required by the Contractor.
Copies of Contract Documents
S.O. shall have two copies of such further working drawings or details as are reasonably necessary
either to explain and amplify the Contract Drawings or the Specification.
Contractor shall keep one copy of the Contract Drawings, the Specification (if any), unpriced Bills of
Quantities and documents on the Site and the S.O. shall at all reasonable times have access to the
same.
Return to the S.O. all drawings, details, specifications, unpriced copy of Bills of Quantities and other
documents of like nature after completion of work.
None of the documents hereinbefore mentioned shall be used by the Contractor for any purpose other
than this Contract.
The Similarity between PWD Form 203A and PAM Contract 2006
Contract
Documents
The Difference between PWD Form 203A and PAM Contract 2006
Sufficiency of
Contract
Documents
Copies of
Tender
Documents
Not stated.
Not stated.
Further
Drawings or
details
Works
Programme
Programme
not part of
Contract
Architects
acceptance or
programme
Not stated.
Not stated.
Availability of
document
Not stated.
Limitation of
use of
documents
Not stated.
As-built
drawings and
operation and
maintenance
manuals
b) Performance Bond
A performance bond, also known as a contract bond, is a surety bond issued by an insurance company
or a bank to guarantee satisfactory completion of a project by a contractor. A job requiring a payment
and performance bond will usually require a bid bond, to bid the job. When the job is awarded to the
winning bid, a payment and performance bond will then be required as a security to the job
completion.
For example, a contractor may cause a performance bond to be issued in favor of a client for whom
the contractor is constructing a building. If the contractor fails to construct the building according to
the specifications laid out by the contract (most often due to the bankruptcy of the contractor), the
client is guaranteed compensation for any monetary loss up to the amount of the performance bond.
Performance bonds are commonly used in the construction and development of real property, where
an owner or investor may require the developer to assure that contractors or project managers procure
such bonds in order to guarantee that the value of the work will not be lost in the case of an
unfortunate event (such as insolvency of the contractor). In other cases, a performance bond may be
requested to be issued in other large contracts besides civil construction projects. Another example of
this use is in commodity contracts where the seller is asked to provide a Bond to reassure the buyer
that if the commodity being sold is not in fact delivered (for whatever reason) the buyer will at least
receive compensation for his lost costs.
One of the performance bonds is Performance Bond/Performance Guarantee Sum in PWD Form
203A and Performance Bond in PAM Contract 2006.
PWD Form 203A
Clause 13.0 Performance Bond/Performance
Guarantee Sum
Clause 22.2 Design Guarantee Bond
Clause 42.1(f) Performance Bond Not
Affected
The Similarity between PWD Form 203A and PAM Contract 2006
Similarity
Documents
Amount
function
and
of
Performance
Bond
Extend
validity
The Difference between PWD Form 203A and PAM Contract 2006
Difference
Submission of
Performance
Bond
Form
of
Performance
Bond
Validity
of
Performance
Bond
Failure
to
extend validity
Not stated.
Not stated.
Difference
PWD Form 203A
Payment from According the Clause 13.6, in the
Performance
event that this Contract is terminated
Bond
under Clause 51 (Event and
consequences of default by the
contractor)
hereof
the
said
Performance Bond or any balance
thereof shall be forfeited.
Return
of
Performance
Bond
For the PWD Form 203A Clause 22.2 and 42.1 (f) didnt mention in the PAM Contract 2006, it is the
difference between this two forms of contract for performance bond.
Clause 22.2 Design Guarantee Bond
The Contractor shall provide a design guarantee bond issued by the licensed bank or financial
institution before the issuance of Certificate of Practical Completion, the amount of design guarantee
bond still be 5% of the value of the said part of the works as stated in the appendix. The design
guarantee bond still remain valid for 5 years from the date of practical completion of works.
If the defect or damage occur to that particular part of works as the result of any defect, fault,
insufficiency or inadequacy in the design including workmanship, materials and equipment which has
become defective due to design default. The government have the right to claim the design guarantee
bond according to the amount losses by the government. If the design guarantee bond is not provided,
the government have the right to claim on the performance bond which is equal to the 5% of the value
of the said part of Works that provided by the contractor.
Clause 42.1 (f) Performance Bond Not Affected
The Performance Bond or balance will safety released or refunded to contractor on the completion of
Making Good Defect. It will more similar with the Clause 13.5.
Work Programme
Work programme is a document for showing how the work will be carry out and showing the duration
of different task. Thought this work programme, the Main Contractor will plan the labour force for
different period, when to bring in the machinery and when the suppliers require to supply the
materials. Furthermore, the Quantity surveyor can plan the schedule of percentage work done and
schedule of issue interim certificate based on work programme.
The Similarity between PWD Form 203A and PAM Contract 2006
Similarity
Documents
Purpose
Revised of
Work
Programme
The Difference between PWD Form 203A and PAM Contract 2006
Difference
Date of
Submission
Consideration
for Part of
Contract
Not stated.
Fees of Extra
Document for
Client
Not stated.
Relevant
clauses
The Similarity between PWD Form 203A and PAM Contract 2006
Payment
Insurance
of
Default
Insuring
in
Risk Covered
The Difference between PWD Form 203A and PAM Contract 2006
Placing
Insurance
Validation
period
Insurance
Additional
risks to be
covered under
the insurance
Insurance
Works
Not stated.
Contract period
Date of Commencement
Date of Completion
3 months of Insurance
OR,
Contract period
Date of Commencement
Defect
Liability
Period
3 months of Insurance
NEW Date of
Completion
Date of Completion
Reference
1. Impacts On The Building And Construction Industry | Law Teacher. 2016. Impacts On The
Building
And Construction Industry | Law Teacher. [ONLINE] Available at:
http://www.lawteacher.net/free-law-essays/contract-law/impacts-on-the-building-andconstruction-industry-contract-law-essay.php. [Accessed 28 January 2016].
2. Lawteacher.net, (2016). Impacts On The Building And Construction Industry | Law Teacher.
[online]
Available at: http://www.lawteacher.net/free-law-essays/contractlaw/impacts-on-thebuilding-and-construction-industry-contract-law-essay.php [Accessed
2 Feb. 2016].