CM OLTC Operating Instruction-HM0.460.301

Download as pdf or txt
Download as pdf or txt
You are on page 1of 45

ON-LOAD TAP CHANGER

TYPE CM
Operation Instructions
HM 0.460.301

SHANGHAI HUAMING POWER EQUIPMENT CO.,LTD

IN1/571/412

Tap changer

Upper gear unit

Rain-proof cover

Motor drive unit

Bevel gear

Drive shaft

Thank you for using our on load tap changer


Prior to use our on load tap changer, make sure to pay attention to the following item:
1. Dont remove Pins on diverter switch and tap selector before tap changer start up.
2. Check 6 lead wires on tap selector, if loosen, the fixing screw under lead wire must be secured.
3. Diverter switch, tap selector and motor drive must be connected at the same position.
4. The tap selector mustnt be operated after it has been dried but not filled with oil. If the operation is
inevitable, the turn part and touch part of diverter switch and tap selector must be lubricated with grease.
5. The tap selector must be checked and the motion angles must be adjusted after the drive shaft has been
installed on transformer (See operation instruction for details).
6. The drive shaft must be exactly fit for operation, cant be too short in order to prevent from falling off.
7. Tap changer head worm and worm gear reducer can be adjusted according to customers need. Loose
press bolt to adjust angle. Please be sure to secure the press bolt upon the completion of adjustment.

IN1/571/412

Table of contents
1. General4
2. Structure of OLTC!9
3. Operating principle13
4. Installation method of OLTC14
5. Operation supervision 22
6. Packing22
7. Maintenance and repair23
8. Appendix26
Appendix 1 CM OLTC head flange for standard tank type, overall dimensions26
Appendix 2 CM OLTC head flange with pressure relief valve, overall dimensions27
Appendix 3CM OLTC head flange installation for bell-type, overall dimensions28
Appendix 4 The overall dimension of bevel gear29
Appendix 5 Transformer connection flange for CM OLTC, overall dimensions30
Appendix 6 Dimension of lifting plate for bell type31
Appendix 7 Diagram for the installation of horizontal and vertical drive32
Appendix 8 Structure diagram of bypass pipe33
Appendix 9 Overall dimension of protective relay34
Appendix 10 CM(10070) operating position table and connection diagram35
Appendix 11 CM(10071W) operating position table and connection diagram36
Appendix 12 CM(10191G) operating position table and connection diagram37
Appendix 13 CM(10191W) operating position table and connection diagram38
Appendix 14 CM(10193W) operating position table and connection diagram39
Appendix 15 CM(12233G) operating position table and connection diagram40
Appendix 16 CM(12233W) operating position table and connection diagram 41
Appendix 17 CM(14273W) operating position table and connection diagram 42
Appendix 18 CM(18353W) operating position table and connection diagram 43

1. General
CM on load tap changer (OLTC) applies to power and
rectifier transformers with rated voltage 35kV, 63kV,
110kV,150kV and 220kV, maximum rated through
current 600A for three poles and 1500A for single pole,
to change the taps under load for the purpose of voltage
regulation. Three phase OLTCs are used at the neutral
point of the Y connection, the single phase OLTC may
be used for any connections. CM OLTC is a typical OLTC
of combined structure, which consists of diverter switch
and tap selector.
CM on load tap changer is to be fastened to the

Fig.1. Outline view of CM OLTC

transformer tank cover by its tap changer head which


serves also for connecting to the motor driver CMA7 or
SHM-III via the worm wheel reducer and bevel gear box
for the purpose of tap changing.
When CM OLTC is used without a change-over selector,
the maximum operating positions available will be 18,
and will be up to 35 when it is used with a change-over
selector. (special design is exclusive).
This operating instruction includes all the necessary
information for the installation and operation of CM
OLTC.

Fig.2 Perspective view of CM OLTC

IN1/571/412

1.1 Type designation


CM! . 0 !!!!!
Mode of voltage regulation
Number of mid-position
Number of operating position
Tap selector pitch
Class of insulation of tap selector
Highest voltage for equipment (kV)
Max. rated through current (A)
Number of poles
Type
1.1.1 Indication of voltage regulation steps for OLTC
a. Linear voltage regulation: It is indicated by 5-digit
number. For example, 14140 represents an OLTC with
14 inherent contacts, 14 operating positions, and the
number of mid-position is 0.
b. Reversing voltage regulation: It is indicated by a 5digit number plus a suffix W. For example, 14131 W
represents an OLTC of reversing voltage regulation with
14 inherent contacts, 13 operating positions and a mid
position of 1.
c. Coarse and fine voltage regulation: It is indicated by
a 5-digit number plus a suffix G. For example, 14131 G
represents an OLTC of coarse and fine voltage regulating
with 14 inherent contacts, 13 operating positions and a
mid-position of 1.
1.2 Indication of insulation class of tap selector
The insulation for the tap selector can be classified into
4 grades, namely B,C,D,DE. Table 2 shows the data of
the different insulation grades. The symbol for insulation
distance is shown in Fig.4.

1.4 Technical data of CM OLTC


See table 1.
1.5 Mode of voltage regulation
There are 3 modes of voltage regulation of CM OLTC,
namely linear voltage regulation, reversing voltage
regulation, coarse and fine voltage regulation. See Fig 4
for the mode of connections.
1.6 Under max. rated through current of OLTC, the
temperature rise of each of the long term current
carrying contacts and the current conducting parts
should not exceed 20K.
1.7 OLTC, under 1.5 times of the maximum through
current, when continuously change from the first
position for half a cycle, the maximum temperature rise
of the transition resistor shall not exceed 350K (in oil)
1.8 The long term current carrying contacts of OLTC
shall withstand the short circuit
current test as shown in Table 3.

1.3 The operating condition of OLTC


The temperature of oil which the tap changer operates
must not exceed 100 and not lower than -25.
The ambient temperature within the tap changer operates
must not exceed 40 and not lower than -25
The non-perpendicularity of OLTC on the transformer
with the ground level should not exceed 2%
The space for mounting OLTC should be free from
serious dust and other explosive and corrosive gases.

1.9 OLTC shall be able to switch a load under rated


step capacity as shown in Table 1, the electrical life
of its contacts should not be lower than 200,000 times.
1.10 OLTC should withstand 2 times of the rated
current in breaking capacity test for 100 times as
shown in table 1.
1.11 The mechanical life of OLTC should not be lower
than 800,000 times.

Table 1 Technical data of series CM on load tap changer


Item

Specification

1
2

Max. rated through-current(A)


Rated frequency(Hz)

Connection

6
7

Max.Operating Without change-over selector


With change-over selector
Positions
Highest voltage for
equipment Um
Insulation
Rated power frequency
to ground
withstand voltage(50Hz,1min)
(kV)
Rated lightning impulse
withstand voltage(1.2/50s)
Tap selector
Mechanical life

10
11

Oil
compartment
12

of diverter
switch

CMJ!1500

600

1200

1500

Single-phase for any selectable winding connection


3300
1400
1500
2000
3100
3500
8
8
16
24
24
20

20

40

60

60

18(special linear regulation can be up to 34)


35(special multiple coarse regulation can be up to 107)
72.5

126

170

252

140

230

325

460

350

550

750

1050

4 grades of B,C,D and DE according to insulation level


Not less than 800,000 operations
Not less than 200,000 operations

Contact life
Service pressure

0.03MPa
No leakage under 0.06MPa for 24 hours

Leakage test
Over pressure protection

Bursting cap bursts at 300 20%kPa


Oil flow speed set at 1.0m/s 10%

Protection relay
Motor drive unit

13

800

50 or 60
Three-phases for neutral point of star connection

withstand current(kA) Dynamic (peak)

CMJ!1200

500

Max. rated step voltage(V)


Rated step capacity(kVA)
Short-circuit
Thermal (3s)

CMJ!600 CMJ!800
CMJ!500
CMJJJ!500 CMJJJ!600

SHM-III or CMA7

Note: Step capacity equals to step voltage times load current


Rated step capacity refer to the max. allowable continuous step capacity.
Table 2 Insulation grade of tap selector
Designation
code
a
b
a0
a1
c1
c2
d

Tap selector size B


1.2/50 s
265

Tap selector size C

(unit:kV)

Tap selector size D

Tap selector size DE

50Hz 1min 1.2/50 s 50Hz 1min 1.2/50 s 50Hz 1min 1.2/50 s 50Hz 1min
350
82
550
120
50
460
105

265
90

50
20

350
90

82
20

460
90

146
20

550
90

160
20

150
485

30
143

150
545

30
178

150
590

30
208

150
660

30
230

495
265

150
50

550
350

182
82

590
460

225
105

660
550

250
120

a0 : The inherent insulation level refers to insulation level with spark gap protection when full voltage impulse is
130kV, the spark gap will response 100%

IN1/571/412

steps
steps
steps

steps

steps

steps

steps

steps

steps

steps

steps

steps

steps

steps

steps

steps
steps
steps

steps

steps
steps
steps

steps

steps

steps

steps
steps

steps

steps

steps

steps

steps

steps

steps

steps

steps

steps

steps

steps

steps

steps

steps

steps

steps

steps

steps

steps

steps

steps

steps

steps

steps

steps

steps

steps

steps

steps

steps

steps

steps

Fig.3 Basic Circuit Diagram

10 10 0 !18 18 0

10 09 1W !18 17 1W

10 19 1G !18 35 1G

10 19 1W !18 35 1W
10 19 3W !18 35 3W

10 19 3G !18 35 3G

10 09 1W !18 17 1W

10 10 0 !18 18 0

10 19 1G !18 35 1G
10 19 3G !18 35 3G

10 19 1W !18 35 1W
10 19 3W !18 35 3W

a. Linear regulation

b. Reverse regulation

c. Coarse & fine regulation

d. Diverter switch
Explanation of insulation distance symbol:
a Between max. tap and mini. tap of the same phase
b Between taps of different tap windings
a0 Between two adjacent taps
c1 Between beginning of coarse winding and output of fine winding
c2 Between beginning of coarse tap windings of different phases
d Between beginning and end of the coarse tap winding of the same phase
Fig 4 Basic connection mode of tap winding
8

IN1/571/412

2. Structure of OLTC
This product is a type of in tank combined structure on

principle and consists of eccentric wheel driven upper

load tap changer. It consists of diverter switch unit, oil


compartment and tap selector (with or without changer-

slide, lower slide, energy storing compressing spring,


guide rail, chuck, cam wheel and bracket, as shown in

over selector), as shown in Fig. 1 and 2.

Fig 6. The chuck, controlled by the side wall of the upper


slide locks the cam wheel in place so as to maintain the

2.1 Diverter switch unit


Diverter switch unit consists of driving unit, insulation

lower slide in its original position. When the eccentric


wheel moves the upper slide along the guide rail, the

shaft, energy accumulation mechanism, switching


mechanism (contact system) and transition resistor. The

spring is compressed for energy storage. As soon as the


side wall of the upper slide makes the corresponding

energy accumulation mechanism is placed on the top of


the switching mechanism and driven by the insulation

chuck to move away from the locked cam wheel, the


plate of the lower slide will actuate the rotating force to

shaft and the transition resistor is installed on the lower


part of the switching mechanism, thus if forms a

the shaft sleeve of the cam wheel, thus makes the diverter
switch to operate.

complete plug-in set which facilitates to be installed in


the diverter switch oil compartment, as shown in Fig.5.

Fig.6 Energy accumulating unit


2.1.3 Contact mechanism
The contact system of the diverter switch employs dual
resistor transiting, parallel double break tapered tail
compensation split contact. The contact system
comprised of stationary contact system and moving
contact system. Fig 7 and 8 illustrate the actual
Fig.5 Diverter switch unit

mechanism.

2.1.1 Insulated rotating shaft


Insulated rotating shaft consists of specially fabricated
insulating bar, corona ring and shaft pin. The shaft itself
is not only a driving shaft, driving the diverter switch
and the tap selector, but also represents the main
insulation of the switch which withstands the voltage to
ground of the tap changer.
2.1.2 Energy accumulating unit
The operation of the diverter switch is realized by the
energy accumulating unit. This unit employs triggering

Fig.7 Contact structure of diverter switch

Fig.10 Arrangement of transition resistor


When the switching mechanism operates, the moving
contacts make linear motion along the guiding groove
of the guiding plate, and carry out switching operation
Fig.8 Contact shell
(stationary contact of the diverter switch)

according to specified sequence with the stationary


contacts arranged on the inner wall of the contact shell.

Moving contacts are installed in the guide slot of the


upper and lower guide with good insulation strength,
and are connected to the curved slot of the converting
sector with rolling pins. The stationary contacts are
separated by arc extinguish chamber and placed on a
contact shell, as shown in Fig.8.
There is a compensating spring installed at the tail of
the sector, so that the switching sequence will not be
disturbed after the contacts are burned.
2.1.4 Transition resistor
Transition resistors are made of high heat resistant nickel
chromium wire wound in spiral form and are separated
by ceramic clamping plates mounted inside and
insulating frame. See Fig.9.
Fig.11 Diverter switch oil compartment
2.2 Diverter switch oil compartment
Diverter switch oil compartment functions isolate oil
carbonized by the electrical arc of the switch from the
oil in the transformer oil tank, so as to maintain the
cleanness of the transformer. It is composed of four parts:
head flange, top cover, insulated cylinder and bottom of
the cylinder. See Fig.11.
2.2.1 Head flange
Fig.9 Resistor units of insulating frame

10

Head flange is precision casting of aluminum alloy and


riveted to the insulation cylinder. It is divided into tank

Transition resistor are arranged evenly in radial direction


and connected to the transition contacts of the diverter

top type and bell type. Tap changer is installed on the


transformer tank cover by means of the head flange.

switch. See Fig.10.

There are three elbow pipes and a through tube on the

IN1/571/412

tap changer head flange. The elbow R is connected to


the conservator via the tap changer protective relay. Oil

mechanism will be self-locked during lifting the diverter


switch unit so that the position will be self-locked and

suction elbow S is used to suck the oil from the bottom


of the oil compartment for oil change of the diverter

the position will not be disturbed. See Fig.13.

switch. It connects to an insulating oil pipe through tap


changer head flange. This oil suction pipe extends straight
down to the bottom of the oil compartment. The oil filling
elbow Q acts as the oil return pipe for the diverter switch.
Another through pipe E acts as the vent pipe for
transformer oil overflow. (See Appendix 1)
2.2.2 Top cover
A bursting cap is installed on the tap changer top cover
to prevent the oil compartment from overpressure. Also
on the top cover are installed horizontally driven worm
wheel reducer, inspection window for tap position and
bleeding screw. See Fig.12. O ring is employed for sealing
against leakage of tap changer.

Fig.13 Bottom of compartment


2.3 Tap selector
Tap selector is composed of step-by-step drive mechanism
and contact system. Tap selector can be installed with or
without change-over selector. See Fig.14.

Fig 12 Top cover


2.2.3 Insulating cylinder
Insulating cylinder is made of epoxy fiber glass,
possessing excellent insulation property and mechanical
property. The upper end of which is riveted to the head
flange, while the lower end is riveted to the cylinder
bottom. O rings are used for sealing the joint.
2.2.4 Bottom of compartment
The bottom is made of precision casting aluminum alloy,
a driving shaft passed through the bottom. The upper
end of the shaft is connected to the diverter switch unit
via a connector and the lower end drives tap selector

Fig 14 Tap selector (with change-over selector)

though the gearing on the cylinder bottom. There is a


self-locking device for tap position indication on the

2.3.1 Step-by-step dive mechanism (also referred to


as Geneva wheel mechanism)

cylinder bottom. The position indication driving

It consists of two grooved wheels and a driving piece.

11

During each tap changing operation, the driving piece


rotates a half turn, the motion of it is transformed into an
irregular step-by-step drive motion of 72or less, thus
moving the bridge contact of the tap selector from one
tap to the other. The two Geneva wheels run alternately.
The mechanical pin in the groove wheel mechanism is
used to prevent the tap selector from overriding at the
start and end position. See Fig.15.
Fig 16 The contact of tap selector
2.3.3 Change-over selector
Change-over selector is classified into reversing
regulation and coarse and fine regulation. See Fig.17
and 18. It is a simple and compact device. The insulating
bars of the stationary contact are arranged on the upper

Fig.15 Geneva wheel system

and lower flange periphery of the tap selector.


Change-over selector is operated by the Geneva wheel.

2.3.2 Contact system


The tap selector contact system employs cage type outer
sleeve inner draw shaft sleeve construction, including
a central insulating cylinder with current ring, insulation
bars with stationary contacts, driving shaft, bridge contact
and upper and lower flange.
The insulation bars are arranged around the periphery of
the upper and lower flanges. Odd and even number
stationary contacts are installed in the bars. In addition,
a corona ring is also installed, so as to even the surface
electric field. The stationary contacts connect to the
current ring on the central insulating cylinder through

Fig.17 Contact system of reversing


change-over selector

the bridge contact.


The connecting wire of the contacting ring is leading
out of the central insulating cylinder and connecting to
the diverter switch.
Tap selector bridge contact adopts an upper and lower
clamping structure. It is driven by the Geneva wheel
mechanism through the driving shaft, which makes it
rotating around the contacting ring, thus contacts the taps
on the selector insulation bars in sequence. Because the
two main springs tensely compress on the moving
contacts, therefore, a four-point contact is always
maintained as shown in fig.16, realizing adjustment-free
and efficient cooling.

12

Fig.18 Contact system of coarse changeover selector

IN1/571/412

3. Operating principle
On load tap changer employs resistor transition principle.
It can change under load the taps of transformer tap
winding. The switch of a tap changer is realized in the
combination of the odd and even numbered contacts
switching and switching of diverter switch. The
sequence of tap change is shown in Fig.19 and 20. The
bold line represents the path of the current.
Example 1 switching sequence from tap position 45

(a) 4 is under conduction before switching operation of


the tap changer. The odd number contact group of the
tap selector are first switched from tap position 3 to tap
position 5.
(b) diverter to bridge connection K2, K3 a circulating
current is generated between the transition resistors. The
load current will then runs through the contacts K2 and
K3.

Fig 19 Switching sequence from tap position 4 6

Fig 20 Switching sequence from tap position 4 4!or 4 6


13

(c) The diverter switching is completed, tap 5 is now


under conduction.

the Geneva wheel mechanism of the tap selector. The


rotation of Geneva wheel makes the contacting bridge

Example 2 switching sequence from tap position 43.


Because the switching of diverter switch is carried out

to rotate an angle corresponding to one step, thus the


connecting bridge will connected to the desired tap of

either to the left or to the right for each switching. If the


switching is from tap position 4 to tap position 3, the

the tap winding without load.


In the same time, the eccentric wheel of the energy

moving contacts of the tap selector may stand still.


However, in case the continuous switching is from tap

accumulation mechanism makes the upper slide to move


along the guide rail. The spring between the upper and

32, then the sequence and operation will be restored


entirely to the same as that of example 1.

lower slide is compressed to store energy, the cam wheel


is locked by the clutch to hold the lower slide in its

3.1 Mechanical operation principle of the tap changer

original position. When the upper slide moves to the


release position, the side wall of the upper slide makes

The operation of tap change begins with the electric


motor of the motor drive unit. The driving force is

the corresponding jaw to move away from the locked


cam wheel, thus releases the energy storage mechanism

transferred to the worm wheel reducer on the top cover


of the tap change through driving shaft and belt pulley

and operates the diverter switch. At this time, the lower


slide moves to the new position, the clutch jaw again

box. After the reducer, it is actuated to the energy


acumulation mechanism and the shaft which passes

engages with the cam wheel, the mechanism is locked


to prepare for the next tap change operation.

through the diverter switch sown to the cylinder bottom.


There the cylinder bottom gear clutch is connected to

The motor drive mechanism automatically stops after


performing one tap change.

4. Installation method of OLTC

14

4.1 The overall dimension of OLTC


4.1.1 Mounting dimension of the on load tap changer

changer separately on a level surface.

The installation diagram of the tap changer and its


mounting dimension are shown in the enclosed drawings

4.1.3.2 Remove the connecting screws (6 M12)


between the diverter switch and the tap selector.

of Appendix.
4.1.2 The tap changer is installed on the transformer oil

4.1.3.3 Remove the red painted dowel pin from the


sliding connector of the tap selectors step-by-step

tank cover with the aid of its head flange. Therefore, a


mounting flange with 650mm inner diameter will be

Geneva wheel mechanism. Do not move the connector.


4.1.3.4 The conductor of the tap selector has been

required on the tank cover together with oil resistant


sealing gasket (supplied by the user). The thickness of

installed during factory delivery.


4.1.3.5 Lift the diverter switch and put it on the tap

the sealing gasket may be the same as the sealing gasket


of the transformer oil tank cover (see Appendix 5).

selector. Take care not to damage the sliding connector


of the step-by-step Geneva wheel mechanism.

Studs will be used with its one end threaded into the
mounting flange, the stud should project at least 45mm

4.1.3.6 Tighten six M12 recessed cap screws between


the supporting stand of the tap selectors Geneva wheel

above the mounting flange.


4.1.3 The installation of OLTC tank-top type

mechanism and cylinder bottom of the diverter switch.


Pay attention to the perpendicularity of the diverter

transformer tank cover.


The detailed installation procedures are as follows:

switch and tap selector.


4.1.3.7 Thoroughly clean the bottom surface of the tap

4.1.3.1 Put the diverter switch and tap selector of the tap

changer head flange and the sealing surface of the

IN1/571/412

mounting flange. Put an oil-resistant sealing gasket on


the mounting flange.

c. Unscrew the five M8 fixing nuts from the diverter


switch upper supporting plate in the area without red

4.1.3.8 Lift the complete tap changer and carefully insert


it into the transformer through the mounting hole on the

paint.
d. Carefully lift out the diverter switch proper. Pay close

transformer tank cover. Take care not to damage the


terminals on the tap selector and corona rings on the

attention not to damage it. Keep the switch proper in the


upright position.

diverter switch compartment.


4.1.3.9 Check the head position and its setting position.

e. Remove the oil suction pipe. Take care of the O ring


on the suction pipe head when the suction pipe is taken

Secure the tap change head flange to the mounting flange.


At last, remove the red-painted dowel pin from the

out of the tap changer.


f. Remove the 17 M8 nuts from the red painted area

intermediate gear wheel connecter at the cylinder bottom


of the diverter switch. (See fig 21)

of the tap changer head flange.


g. Lift out tap changer head flange from the intermediate

positioning pin

flange. Pay attention to the sealing gasket.


4.1.4.2 Fasten the tap selector to the bottom of the
diverter switch oil compartment.
a. Remove the joining screws between the diverter switch
and the tap selector.
b. From the sliding connector of the stepped grooved
wheel mechanism of the tap selector remove the redpainted dowel pin.

Fig 21 Diverter switch set positioning pin

Do not move the connectors groove moving piece.


c. With the lifting plate (see Appendix 6) provided by

4.1.4 Installation of OLTC on the bell type


transformer cover

the factory, lift the diverter switch and place it on the


tap selector. Take care not to damage the sliding

The bell type installation of OLTC has specially


designed tap changer head which is able to be dismantled

connector of the Geneva wheel mechanism.


d. Tightening 6 M12 cylindrical head socket screw

(See Appendix 3). It is composed of two parts: one is an


intermediate flange temporarily installed on the

between the supporting stand of the tap selectors


Geneva wheel mechanism and the diverter switch oil

transformer supporting structure. The insulating cylinder


of the diverter switch oil chamber is installed on that

compartment bottom.
e. Fix the connecting conductor with M10 hexagonal

flange; the second is the head flange secured on the bell


type transformer tank cover. These two flanges are firmly

screw. Be sure to directly stick the lead wire level with


contacts on insulation cylinder. Dont clip the screening

connected together by means of sealing gasket and


fasteners.

cover between them (See figure 22).


f. From the intermediate gear connector at the oil

The procedures for installing OLTC on the bell type


transformer tank cover are as follow:

compartment bottom remove the red-painted dowel pin


(see fig 18). To ensure the proper operation of the tap

4.1.4.1 Dismantle the tap changers head


For installing the tap changer. It is required to separate

changer and the correct mounting position, the bell type


tap changer should be pre-assembled. The actual

the tap changers head flange from the oil chamber.


a. Remove the top cover of the tap changer. Take care

procedure for pre-assembling are as follows.

the O ring on cover.


b. Remove the position indicator. Save the spring
washers for future reassembling.

15

15

Fig.22 Diagram of connection between tap selector


lead wire and diverter switch

To ensure electrical insulation performance of switch,


the distance between connecting lead wire and cylinder
bottom metal element must be over 15mm

a. Pre-matching of intermediate flange and head flange

supporting structure of transformer has been confirmed

(alignment of!

!on both flange). For the installation


and connection

correct, connect the leading wire between tap changer


and tap coil as per the section 4.2 of this manual.

To ensure electrical insulation performance of switch,


the distance between connecting lead wire and cylinder

After the tap leading wire has been connected, preinstall


once again, if the position of tap changer is unchanged

bottom metal element must be over 15mm


bell type tap changer, there should be an adjustable

and the leading wire is in conformity with requirement


(with suitable length, without the deformation and

supporting structure in the transformer. Temporary


mounting of tap changer on the supporting structure: By

enforced on tap changer), it can ensured that the position


of two flanges is correct when assembly the tap changer

means of the lifting plate (see Appendix 6) supplied by


the factory, place the assembled tap changer on the

transformer.

supporting structure. Allow the intermediate flange to


install temporarily on the supporting structure. Alignment

4.2 The connection of leading wire between voltage


regulation tap winding and tap changer

of pre-installed flange and intermediate flange:


Move head flange to the flange installed on the cover of

4.2.1 Tap selector and connection leading wire


The tap windings should be connected according to the

transformer, pay attention to the alignment of


symbol, adjust the position of tap changer and supporting

wire diagram supplied along with delivery. The terminals


of the tap selector are on the insulating bar where the

structure, which allow the head flange to be aligned


naturally with intermediate flange, thus confirm the

contact position are marked.


There is a M10 bolt on each of tap selector terminals,

installation position of tap changer on supporting


structure.

the connectors of the tap winding can be installed directly

b. Adjusting the assembly space between intermediate


flange and head flange.
To adjust flexible supporting structure, rise or lower the
installation position of intermediate flange to ensure the
installation space between intermediate flange and head
flange conform to 5~20mm (see Appendix 3).
When the pre-installation of tap changer on the

16

Fig.23

IN1/571/412

on this bolt. Corona rings are employed and locked the


M10 nuts.

mediate flange on the supporting structure, then put the


pad between the intermediate flange and the head flange,

After tightening the connecting bolts, turn up the washer


of the shield cover for 90,thus lock the nut from

so as to obtain the required actual assembly gap, then


the lead will be wire and after that the temporary pad

loosening.(see figure 23)


The positive and negative () connecting terminals of

will be removed. Check for the degree of tightness of


the lead wire and whether the tap changer is affected by

the tap selector is a tongue shaped connecting plate,


there is a hole for the hexagonal bolt on the plate. The

force.
4.2.1.2 Dont damage the connecting terminal of the tap

connecting terminal K is an extension of the connecting


terminal of the tap selector also has a hole for the

selector during installing the lead out wire.


4.2.2 The connecting wire of the tap changer

hexagonal bolts.
Attentions during the lead wire connection between the

4.2.2.1 Three phase tap changer


For three phases tap changer, the interior of the diverter

tap selector and the tapped winding:


4.2.1.1 The terminal wire should not apply any force

switch will be Y connected. Therefore, there is only one


neutral point on the oil compartment of the switch. The

to the tap selector (see figure).


a. The connection wire should be wired to the tap winding

neutral point connecting terminal has a M10 threaded


hold.

in dual directions from the tap selector. Avoid stressing


the lead wire in single direction causing twist

4.2.2.2 Single phase tap changer


A single phase tap changer, formed by parallel

deformation of the cage of the tap selector.


b. The connecting wire between the end clamping of tap

connection of the contacts of three phase tap changer,


on the oil compartment of the diverter switch, there is a

selectors terminal and the transformer lead wire should


not too short. It should be soft and should not be coated

conducting ring. The lead out wire of the tap changer is


connected to the conducting ring. On this ring, there are

with insulating paint to avoid the hardening of the coated


paint after drying which makes the insulating bar to

three 12.5 through holes, screws pass through these


holes and connect with the lead-out wire and are locked

deform under force.


c. The end of the lead wire connecting the tap selector

by the corona rings together with the M10 nuts. After


tightening up the nuts, the lock washer of the corona

should take the form of an expanded ring (circled), so


that the insulating bar of the tap selector will not be

rings is to be turned up to stop the nut from loosening.

influenced by force.
d. The terminal wire of the tap selector should be led out

4.3 Transforming ratio test


Before drying the transformer, a transforming ratio test

from the exterior of the cage. Never allow the wire


passing through the interior of the cage.

should be carried out with alternating voltage. To operate


the tap changer, insert a short pipe of 25mm nominal

e. The terminal wire of the change-over selector should


be led out from the exterior of the insulating bar of

diameter into the horizontal shaft of the worm wheel


reducer on the head of the tap changer, and fastened with

change-over selector. Adequate clearance shall be


maintained between the lead wire and the insulating bar

a M8 set screw. A crank handle is filled on the other end


of the short pipe. 16.5 turns of the horizontal driving

of the change-over selectors moving contacts, so that


the obstruction to the operation of the change-over

shaft are required for each tap transforming operation.


Because the tap changer is not oil immersed, so the

selector can be avoided.


f. The bell type tap changer shall be lifted up 5-20mm

number of tap change should be reduced to a minimum.


After the ratio test, the tap changer must be turned to the

after the connection of lead wire. Therefore, special care


should be given to the degree of tightness of the

set position set at factory. This position can be seen from


the set position diagram supplied together with the tap

connecting wire. It is recommended to install the inter

changer during delivery.

17

18

4.4 Drying and oil filling


4.4.1 The purpose of drying is to maintain the insulation

Raise the temperature of kerosene vapor with a


temperature of 10/h. Max. temperature is 125.The

level of the tap changer. Generally the tap changer is


dried together with the transformer, however, it can be

time for drying basically depends upon the time required


for transformer drying.

dried separately means of the same drying process. The


process is as follows:

b. Drying in the transformer oil tank


If the transformer is vapor-phase dried in its oil tank,

4.4.2 Vacuum drying


a. Drying in the oven room

the head cover of the tap change should be tightly closed


during the whole drying process. At the time, kerosene

During drying in the oven room, the tap changers cover


must be removed.

vapor for drying should enter the transformer oil tank


and the diverter switch oil compartment in the same time.

Care to keep the oil pipe unobstructed.


The tap changer is entered the oven room with a

To accelerate the rate of drying of diverter switch oil


compartment and its mechanism, at least one 50mm

temperature of about 60,and heated in the air under


atmospheric pressure. The rate of temperature rise is 10

kerosene vapor inlet pipe should be used to connect to


the tap changer oil filling pipe flange and the oil suction

/h and the max. heating temperature is 110.


Preliminary drying:

pipe flange.
After the vapor phase drying, check the oil drain screw

Drying is carried out in the circulating air, max.


temperature is 110, duration 20 hours.

at the bottom of the oil compartment for tightness.


Attentions after the drying process of a tap change:

b. Drying in the transformer oil tank


When the transformer is vacuum drying in its oil tank,

a. The tap changer without oil filling after drying process


must not be operated. If operation is required after drying,

the top cover of the tap changer is kept tightly closed,


throughout the whole process. To enhance the rate of

then the diverter switch oil compartment shall be fully


filled with transformer oil and the tap selector oil

drying of diverter switch oil compartment and switch


mechanism, by-pass pipe supplied by our factory (see

lubricated.
b. Check the tightness of fasteners. Of any fastener is

Appendix 8) must be used to connect the oil filling flange


on tap changer head to the overflow pipe flange on the

found loose, it must be retightened and locked against


looseness.

transformer oil tank (see Appendix 1 for the flange


position).

4.4.2 Oil filling


The head cover of the tap changer is again close. Tighten

4.4.2.1 Vapor phase drying


When vapor phase drying is employed for drying the

the 24 bolts M10. Take care the correct position of the O


ring. Both the transformer and diverter switch are filled

transformer and tap changer, the oil drain screw at the


bottom of the oil compartment should be unscrewed to

under vacuum. New transformer oil is filled into the tap


changer up to the level of the transformer top cover. For

facilitate the draining of kerosene vapor condensate.


After the vapor phase drying, the drain screw should be

this reason, by pass pipe supplied by our factory should


be used to install between the tap changers head oil

tightened again.
a. Drying in the oven

filling flange and the transformer oil overflow pipe


flange, in order that the oil compartment of the diverter

In the case of oven drying, the top cover of the tap


changer must be removed. Care to keep the oil extraction

switch and the transformer can be vacuum extracted in


the same time.

pipe unobstructed.
Heating:

4.5 The installation of connection pipes

Under the kerosene vapor temperature of 90, the


duration of heating is 3-4 hours.

The head flange of the tap changer is equipped with three


connection pipes. The orientation of these connection

Drying:

pipes can be determined as required by the customer

IN1/571/412

that is after loosening the clamping ring, the connection


pipes can be turned at will. So it is very easy to install

4.6.3 The installation of the motor drive unit should be


square to transformer oil tank wall. No obliquity is

the connection pipes.


4.5.1 Tube connection of protective relay

permitted. Care not to be affected by the excessive


vibration of the transformer. Adjust its horizontal and

Protective relay can be installed on the connection tube


between the head of the tap changer and the oil

vertical position.
Attention: The mounting plate of the motor drive unit

conservator, and should be as close as possible to head


of the tap changer. Frequently it is connected directly to

should be flat, otherwise it will be deformed by twisting


and its operation will be affected. For the actual

the flange of the elbow pipe R. It must be installed


horizontally with the arrow pointing to the oil

installation of the motor drive unit, see the operation


instruction of motor drive unit.

conservator.
4.5.2 Oil suction pipe connection

4.7 Installation of bevel gear box

The tap changer is equipped with an oil suction


connection pipe. It is used to suction the oil in the diverter

The overall and mounting dimension of bevel gear box,


see Appendix 4.

switch oil compartment during maintenance or oil


changing. Therefore, a pipe must be installed at a level

4.7.1 Bevel gear box is mounted on the supporting


bracket of the transformer tank cover with 2 bolts M16

below the bottom of the oil compartment. The upper end


of the pipe is connected to the oil suction pipe flange,

4.7.2 Driving shaft


4.7.2.1 Installation of horizontal driving shaft

and the lower end is fixed with an oil drain valve.


This oil suction connection pipe may also be used as the

a. Loose the sleeve (6 bolts M8) of the worm wheel


reducer on the tap changers head. Swiveling the reducer

oil discharge pipe of an oil filter.


4.5.3 Oil filling connection pipe

to align its horizontal shaft with the horizontal shaft of


the bevel gear box.

This pipe is used as the oil return pipe of the oil filter. It
is sealed when no filtering is required. It is recommended

b. Find out the actual length of the horizontal shaft


between the horizontal shafts of the worm wheel reducer

that as pipe is also connected with the lower end filled


with an oil drain valve. Thus circulating oil filtering

of the tap changer and the bevel gear reducer. A clearance


(a total of about 2mm) is reserved at the connection of

through the oil suction and oil filling pipe may be


performed by the oil filter.

the two horizontal driving shafts after taking into account


of the expansion and contraction.

4.6 The installation of motor drive unit

c. Install the sleeve on the horizontal driving shaft. Adjust


the worm wheel reducer and tighten the sleeve.

The motor drive unit performs the position control and


the starting of the tap change of on-load tap changer.

d. After installing the horizontal driving shaft, cut off


the extra dimension of the guard plate according to the

Within the box of the motor drive unit are installed


complete set of mechanical and electrical components

gap between the two connection flanges.


4.7.2.2 Installation of the vertical driving shaft:

required to operate the tap changer. Electrical and manual


operation are possible.

a. According to the dimension between the bevel gear


driving box and the vertical driving shaft of the motor

Attentions during the installation of motor drive unit.


4.6.1 The serial number of the motor drive unit should

drive unit, determine the actual length of the vertical


driving shaft. Cut the shaft to the require length, taking

be same as that of the tap changer.


4.6.2 The motor drive unit must be of the same setting

account of the expansion and contraction. Certain


clearance (a total of clearance about 2mm) should be

position as that of the tap changer. This position is


indicated in the wiring diagram delivered with the

reserved for connection of vertical driving shafts.


b. Install the vertical driving shaft, the connection pin

equipment.

near the motor drive unit can only be fixed after checking

19

the connection of the motor drive unit.


c. In case the length of the vertical driving shaft exceeds

Example:
The verification of connection of Type CM tap changer

2m, to avoid swaying, the shaft shall carry an


intermediate bearing. This can be supplied if requested

and Type CMA7 motor drive unit: Turn from position


10 (setting position) to position 11, m=5 turns, Turn

during ordering.

backward from position 11 to position 10 ( the original


setting position ), k=3 turns. The difference of turns of

4.8 Verification of the connection of the tap changer


and motor drive unit

the handle m-k=5-3=2 turns.


Turns to be adjusted 1/2(m-k)=1/2(5-3)=1 turn.

Having connected the tap changer with the motor drive


unit, the mechanism should first be manually turned a

Loosen the connection between the vertical driving shaft


and the motor drive unit. Turn the handle in the direction

full cycle of operation.


When the tap changer has been connected to the motor

10 11for one turn.


Then again make connections.

drive unit, the time elapsed between the instant of


switching of the diverter switch and the ending of

Check that the difference of turns in both directions has


been balanced.

operation of the motor drive unit should be the same in


both direction of rotation. Generally, the verification of

a. Record number of turns m and k under connected


condition.

the connection of the tap changer to the motor drive unit


has been done in the factory and is positioned and lead

b. Turn 1/2(m-k) turns in the direction in the increment


of turns during loosening of connection.

sealed in the setting position. However, for proper


operation of the tap changer, the verification shall still

c. Again make connection and verify until m=k.

be performed.
The verification of connection is carried out according

4.9 Operating test of the tap changer


4.9.1 Mechanical operating test

to the following procedure:


4.8.1 Rotate the handle in the 1N direction. After the

Before voltage is applied to the transformer, 5 complete


cycles of mechanical operating test ( no less than 200

diverter switch has operated (start when the sound of


switching is heard), turn the handle continuously and

times) must be performed. There should be no damage


to the tap changer and motor drive unit. The position

record the number of turns until a red mark within the


green belt area on the indicating wheel of the motor drive

indication of the motor drive unit, its remote position


indication and the position indication of the tap changer

unit appears in the middle of the inspection window.


Take the number of turns as m.

should be the same. Both the mechanical and electrical


limit protection should be reliable.

4.8.2 Turn the handle in the reverse direction N 1 to


return to its setting position. Record the number of turns
K in the same way as mentioned above.
4.8.3 The connection will be correct if m=K. If m K
and m-K>1, then the difference of turns shall be
compensated. Loosen the vertical driving shaft, turn the
handle 1/2 (m-K) turns in the direction of increment of
turns, and finally connect the vertical driving shaft to
the motor drive unit.
4.8.4 Check the difference of turns between the motor
drive unit and the tap changer in the same way as
mentioned above, until the same number of turns, i.e.
m=k is obtained.

20

Fig.24 Schematic diagram of exhaust on top


cover when filling tap changer with oil

IN1/571/412

4.9.2 Final oil filling


Final oil filling is done after the operating test of the tap

pipe flange of the transformer (the position of the flange


is shown in the Appendix 1), so that the static pressure

changer. Before oil filling, loosen the bleeding screw


on the suction pipe and the top cover of the tap changer.

caused by the oil expansion can be balanced.


If transformer is required to be transported or stored

Use a spanner to pry up vent oil overflowing in on the


top cover of tap changer. (See figure 24)

without oil filling, then the oil in the oil compartment of


the diverter switch must be completely drained. The

4.9.3 Grounding
Bevel gear box grounding screw (M12) should be

bypass pipe must be installed at that time so that the oil


compartment and the transformer oil tank will subjected

connected to the cover of transformer tank.


The grounding screw (M12) on tap changer head should

to the same pressure (nitrogen sealing).


In order to avoid damaging the tap changer caused by

also be connected to the cover of transformer tank.


The grounding screw (M12) on motor mechanism box

the displacement of moving parts, they must be


temporarily secured.

should be connected to the cover of transformer tank.


Grounding screws for protective relay shall be connected

Note: The bypass pipe shall be removed from the tap


changer head when the transformer is installed on-

to the transformer tank cover.


4.9.4 Transformer electrical test

site and before putting it into operation.

After completing the above-mentioned operation, the


transformer acceptance test can now be performed. The

4.11 Put into operation on-site


When the transformer is installed in site, the installed

tap changer should be tested with the conservator


connected.

position of the tap changer and the tightness of the


connecting wire should be checked either by lifting the

4.9.5 The setting position of the tap changer:


When the test is completed, the tap changer and the motor

iron core or by entering into the transformer oil tank,


especially for the bell type tap changer, detailed

drive unit should be turned to the set position during


equipment delivery.

examination shall be done as to the deformation under


force of the tap change due to the displacement of

4.10 Transportation of transformer together with the

transformer core during transportation, so that the proper


operation of the tap changer can be assured.

tap changer
When the tap changer is assembled to the transformer,

Before putting into operation of the transformer, the


operating test of the tap changer and motor drive unit,

careful consideration shall be given to safety of


transportation (for example, to increase the temporary

must be done according to section 7.10, and in the same


time, check the proper functioning of the protective relay.

supporting). The tap changer is of the immersed type, it


is not necessary to remove it for transportation. If there

The protective relay should be connected to the tripping


circuit of the line circuit breaker, in case the relay trips,

is trouble which requires to dismantle the motor drive


unit should be loosened at the setting position, so that it

it will instantly cut off the transformer circuit.


Transformer Off test button on the tap of the relay can

can be transported in the horizontal position. After


arriving on site, the motor drive unit can be restored by

be used to test the function of the line circuit breaker.


Open all the valves between the conservator and the tap

means of the method mentioned above.


If the transformer is transported or stored without the

changer to prepare the tap changer for operation, at that


time, the gas accumulated the tap changer top cover will

conservator, then the bypass pipe (see Appendix 8)


supplied by our factory can be installed between the oil

expel a slight amount of oil. When the tap changer is


determined to the everything all right, then it can be put

filling supplied by our factory can be installed between


the oil filling flange of the tap changer and the overflow

into operation.

21

5. Operation supervision
Periodic examination of the contamination of oil in the
insulating cylinder of the diverter switch is an effective

5.3 The tripping contact of the protective relay is set to


operate at an oil speed of 1.0m/s! 10%. This contact

measure to monitor the normal operation of the on load


tap changer.

should be connected the tripping circuit of the


transformer circuit breaker. In case a fault occurs with

5.1 For periodic examination of the oil in the insulating

the on load tap changer, then large amount of gas will


generate, causing a rush of oil flow to move the relay

cylinder of the diverter switch for the newly energized


transformers, we recommend to carry out oil sampling

flap, which breaks the tripping contacts, and cuts off the
transformer incoming current, thus avoid the fault to

for each 1,000 times of operation under rated current to


ascertain that the voltage endurance valued is not under

extend.

30kV.

5.4 On the top cover of the tap change is installed an


overpressure explosion protection cover which should

5.2 Do not operate the on load tap changer frequently


when the transformer is overloaded. If the customer has

not be damaged during ordinary tap change operation


of the diverter switch. Only when a fault is generated

installed fully automatic controls, then the tap must be


equipped with over current tripping device, so that the

within the switch, then the cover bursts when the pressure
in the oil cylinder exceeds 2 105 Pa, thus it functions

tap changer will not be operated when the load current


exceed 2In.

as overpressure protection to avoid extension of the fault.


During installation and maintenance of the on load tap

6. Packing

22

changer, always pay special attention not to damage the


bursting cover.

6.1.1 Scope of delivery of the complete set of

6.1.2.5 Motor Drive Unit

equipment
The tap changer and the motor drive unit are packaged

6.1.2.6 Accessories including remote position indicator,


etc

separately for delivery after they have been conducted


routine test and set at the specified position.

Check the contents according to the packing list. Place


the tap changer equipment in a well-ventilated weather

6.1.2 Scope of delivery of the tap changer equipment


6.1.2.1 Diverter switch: Including oil compartment of

proof warehouse with relative humidity of less than 85%


and temperature between -25and +40. There should

the switch and the diverter switch unit installed in the oil
compartment.

be no corrosive gas.
Note: the six lead wires on the tap selector may be

6.1.2.2 Tap selector including change-over selector


6.1.2.3 Protective relay

loosened due to transportation, therefore, at the time


connecting the lead wires to the tap change, the selector

6.1.2.4 Driving shaft and conical gear driving box

end shall also be checked. Tighten it if it is loosened.

IN1/571/412

7. Maintenance and repair


7.1 Periodical maintenance
The transformer oil in the diverter switch oil compartment

position, however, we recommend that the diverter


switch unit will be drawn out in its position. (See

will become carbonized after certain times of switching


and its voltage endurance value will decrease, so it is

Appendix for the table of setting positions)


7.3.1 Close all the oil valves on the conservator,

recommended that periodic oil sampling should be done


according to Section 5.1 for laboratory test. The

transformer oil tank and the head of tap changer.


7.3.2 Loosen the vent and overflow screw, lower the oil

transformer oil shall be replaced when its voltage


endurance value is less than 30kV.

level of the tap changer head until it is flushed with the


surface of the transformer tank cover.

During the oil changing, the contaminated oil is


completely removed from the oil compartment, then the

7.3.3 Loosen the horizontal driving shaft of the motor


drive unit and the tap changer.

insulating cylinder and the diverter switch are flushed


with clean oil, this oil is again completely removed.

7.3.4 Dismantle the grounding connection of the tap


changer head, loosen the connection bolts of the head

Finally it is filled with clean oil.


If the number of tap change operation exceeds 20,000

cover. Remove the cover, take care of the sealing ring.


7.3.5 Remove the position indicator from the diverter

times annually, it is recommended to install an on line


oil filter to the tap changer.

switch.
7.3.6 Carefully lift out the diverter switch unit, dont

The oil conservator and the breather in the safety duct of


this on load tap changer is maintained usually the same

damage the oil suction pipe and the driving shaft of the
position indicator.

as the transformer.
7.4 Cleaning
7.2 Periodical maintenance
During the long term operation of the on load tap changer,

7.4.1 Cleaning of diverter switch oil compartment


Thoroughly drained the dirty oil from the diverter switch

only the diverter switch required to be repaired


periodically. Table 6 shows the time interval of the period

oil compartment and flush it with new. If necessary,


brush away the carbon powder stuck to the inner wall of

maintenance. To enhance the reliability of the tap


changer, it should be maintained after five years

the insulating cylinder. Then again flush it with new oil,


drain away all the dirty oil.

operation, even if the number of operation has not been


reached.

After cleaning, tightly close the top cover of the diverter


switch.

The item for maintenance includes lifting out the diverter


switch unit, cleaning the entire switch properly,

7.4.2 The diverter switch can be washed with new oil


after it has been lifted out. It can be brushed if necessary.

measuring the contact wear, replacing the contacts of


the diverter switch, etc. Small capacity lifting equipment

The thorough cleaning of the diverter switch can be done


after it has been dismantled.

may be used to lift out the diverter switch unit.


During the maintenance, the time of exposure of diverter

7.5 Preliminary examination of the diverter switch


unit:

switch unit shall not exceed 10 hours or it shall be dried


as specified in section 4.5.

7.5.1 Check all fasteners for looseness.


7.5.2 Whether the main spring, reset spring and jaw plate

7.3 Lifting of diverter switch unit

of the energy storage mechanism are deformed or broken.


7.5.3 Whether the braided lead of each contact is not

All the terminals shall be shorted and grounded offer the


transformer has been cut from the network.

damaged.
7.5.4 Check the wear of moving and stationary contacts

The diverter switch unit can be drawn out in any operating

of the diverter switch.

23

7.5.5 Check for any breaking of the flat wire of the transition resistor and whether its resistor value is identical to

7.7 Reassembly of diverter switch unit


The contact mechanism of the diverter switch shall be

that stamped on the nameplate (The resistor value should


be measured at the open side of the transition contact.)

reassembled when the mechanism has been dismantled


for cleaning and parts replacement.

7.5.6 Measure the contact resistor of the odd and even


number contacts of each phase and the neutral lead-

a. Install the contacts arc-isolating chamber.


b. Assemble the contact shell of the diverter switch

out point.
7.5.7 Measure the switching sequence of the moving

stationary contacts. Tighten and lock eight M6 bolts.


c. Shift the energy storage mechanism to the opposite

contact.

side of the original operating position. Hook up the lower


sliding plate of the mechanism and shift the eccentric

7.6 Dismantle the diverter switch unit for cleaning,


examination and parts replacement.

wheel of the upper sliding plate, allowing the spring of


the energy storage mechanism to shore energy. When

Prior to dismantle, pay attention to the following items:


7.6.1 Note the current operating position of the diverter

the upper sliding plate is shifted to the highest point of


the eccentric wheel release the lower sliding plate, so

switch, so that it can be restored to the original operating


position during reassembly.

the energy storage mechanism is again latched.


d. Check the switching sequence of he diverter switch

7.6.2 When the contact mechanism of the diverter switch


is dismantled for examination and cleaning, it should be

(by oscilloscope)
The switching time of the diverter switch (direct current

done on each phase. Never dismantle the three phase in


the same time to avoid confusion.

oscilloscope) will be 35-50ms. The bridging time for


the transition contacts will be 2-7ms, as shown in Fig25.

The sequence for dismantling diverter switch unit is as


follows:
a. Release the jaw of the energy storing mechanism. Place
the mechanism to a bridging position of the transition
contact so as to facilitate dismantling and reassembling.
b. Loosen the connecting screw on insulating arc plates
of the diverter switch stationary contacts. Remove the
insulating arc plates.
c. Remove the arc isolating chamber of the contacts of
the diverter switch.
d. Thoroughly clean the dismantled contact shell.
e. Check the amount of contact wear.
When the amount of wear of any one of the diverter
switch arcing contacts exceeds 3mm, then all arcing

24

Fig25. The switching sequence of diverter


switch contacts

contacts must be replaced.


f. Check the lead-out braided lead of the main arcing

7.8 The installation of the diverter switch unit

contacts and transition contacts.


g. Check for looseness of the M6 18 countersunk

When the diverter switch unit has been verified to be


acceptable, it is returned to its original operating position

screws connecting to the arcing contacts.


After 250,000 times of operations of the tap changer,

before maintenance, then carefully lifted it into the


diverter switch oil compartment. Fasten the five bolts

the lead-out braided lead must be replaced even if they


are not damaged and regardless whether the contacts are

on the head and installed the position indicator, and after


replace the tap change head cover. Take care to place

replaced or not.

properly the sealing gasket.

IN1/571/412

7.9 Oil filling


Fill the diverter switch oil compartment with new oil up

Press the trip test button, this should cut off the power
source of the transformer. The transformer can be put

to the horizontal surface of the tap changer head. Open


the valve between the protective relay and the

into operation after pressing the reset button.


7.10.3 Check if the position indicator of the tap changer

conservator, so as to allow the oil flows smoothly into


the oil chamber of the tap changer which is vented

and that of the motor drive unit are identical. Connect


the tap changer to the driving shaft of the motor drive

through the bleeding hole on its head cover. Open all


the valves of the conservator and transformer oil tank,

unit, and conduct connection check according to 4.8


section.

the conservator shall be replenished with new oil up to


its original oil level.

7.10.4 Mechanical operating test of on-load tap changer


Ten cycles of operations by motor drive should be

7.10 Check before operation

conducted, the result of which shall show no


malfunctioning. The maintenance of the tap selector can

7.10.1 Connect all the grounding screws on the head


cover.

only be performed along with the overhaul of the


transformer. No separate repair is usually required.

7.10.2 Check the tripping function of the protective relay.


Intervals of maintenance of CM on load tap changer
PMUD!Npefm

Nby/!sbufe

Pqfsbujpot

uispvhi!dvssfou

Xjuipvu!pjm!gjmufs

Xjui!pjm!gjmufs

461B

211-111

261-111

461B

211-111

261-111

611B

91-111

261-111

461B

211-111

261-111

711B

91-111

261-111

DN 461

461B

211-111

261-111

DN 611

611B

211-111

261-111

DN 711

711B

211-111

261-111

611B

211-111

261-111

911B

91-111

261-111

911B

91-111

261-111

2-311B

81-111

251-111

2-311B

81-111

251-111

2-611B

71-111

231-111

DN 461
DN 611
DN 711

DN 911
DN 2311
DN 2611

8. Appendix

25

Appendix 1 CM OLTC head flange for standard tank type, overall dimensions

In mm

26

IN1/571/412

Appendix 2 CM OLTC head flange with pressure relief valve, overall dimensions

In mm

27

Appendix 3 CM OLTC head flange installation for bell-type, overall dimensions

Lifting plate

28

IN1/571/412

Appendix 4 The overall dimension of bevel gear

In mm

29

Appendix 5 Transformer connection flange for CM OLTC, overall dimensions

30

IN1/571/412

Appendix 6 Dimension of lifting plate for bell type

In mm

31

Appendix 7 Diagram for the installation of horizontal and vertical drive

32

IN1/571/412

Appendix 8 Structure diagram of bypass pipe

In mm

33

34

Uzqf!RK7.36!Cvdiipm{!sfmbz
Uzqf!RK5H.36!Cvdiipm{!sfmbz

Appendix 9 Overall dimension of protective


relay

IN1/571/412

Appendix 10 CM(10070) operating position table and connection diagram

35

Appendix 11 CM(10071W) operating position table and connection diagram

36

IN1/571/412

Appendix 12 CM(10191G) operating position table and connection diagram

37

Appendix 13 CM(10191W) operating position table and connection diagram

38

IN1/571/412

Appendix 14 CM(10193W) operating position table and connection diagram

39

Appendix 15 CM(12233G) operating position table and connection diagram

40

IN1/571/412

Appendix 16 CM(12233W) operating position table and connection diagram

41

Appendix 17 CM(14273W) operating position table and connection diagram

42

IN1/571/412

Appendix 18 CM(18353W) operating position table and connection diagram

43

SHANGHAI HUAMING POWER EQUIPMENT CO., LTD


Address: 977 Tong Pu Road, Shanghai, China
Tel: 86 (0)21-5270 2715 5270 3965
Fax: 86 (0)21-5270 2715
Post code: 200333
Email: [email protected]
Http://www.huaming.com
Printing: 2009.8

You might also like