Magic
Magic
Magic
GER-3954B
GE Power Systems
Generator In-Situ
Inspections
Dean T. Roney
Ronald J. Zawoyski
GE Power Systems
Schenectady, NY
ii
Total Cost
of Inspection ($)
GT24977
On-Line
Major Outage
STATOR
Stator Wedge Tightness
Bar Movement
Stator Winding Leaks
Core Insulation
Stator Winding Insulation Integrity
Greasing
Cracked Connections/Integrity
Oil Contamination
HV Connection Bolts
FIELD
Blocked Vent Ducts
RR NDT
Field Coil Distortion
Field Coil Loose Blocks
Field Wedge Migration
Field Winding Insulation Integrity
Thermal Sensitivity
Rotor Surface Heating
Periodic
On-Line
X
X
Minor
Outage
X
X
X
X
X
X
X
X
X
Major
Outage
X
X
X
X
X
X
X
X
GT25553
Continuous
On-Line
Retaining Rings
Outside Surface:
Eddy Current
Inner Surface:
Ultrasonic
GT25678
Common Problems
Stator/Core
Core Laminations
Space Blocks
Stator Wedges
Stator Bars
X
X
X
X
Instrumentation
Field
Field Surface
Body Weights
Looseness, staking
Field Wedges
Retaining Ring
General
All
X
X
Damaged Insulation
Circulating Current
Field Body
Stator Clearance
Measurement System
Retaining Ring
GT25775
Figure 8. Stator end winding viewed using GEs remote access camera
Test
Area
Test
Electrode
Copper
Conductors
Groundwall
Insulation
GT25552
access to the ID surface where eddy current testing is used to detect very small surface indications. Testing of the rings while installed on the
field can also be performed, however, with less
sensitivity to crack detection on the ID surface.
Other Testing
There are several other tests and inspections
recommended during minor and major outages in addition to those discussed. They
include electrical testing of the stator and field
windings and RTDs as well as hydraulic testing
of water-cooled stator windings. A complete
Qualification Efforts
Changing an Industry Mindset
Generator inspection for years consisted of a
minor outage every 2 1/2 years and a major outage with the field removed every five years. This
practice proved to be quite successful in maintaining a high level of reliability of the generator fleet. Deregulation is causing the power generation industry as a whole to rethink its philosophy on equipment maintenance and OEMs,
and utilities and insurers alike need to evolve to
meet the needs of this new marketplace. In-situ
inspection of generators is one way GE has
evolved to meet these demands, and GE needs
to work with customers and their insurers to
properly apply this technology. In-situ inspection will not be considered a complete success
unless it can provide an inspection with the similar accuracy, sensitivity and thoroughness of a
field removed inspection. In-situ inspection
must not bring with it a significant increase in
the risk of failure over traditional inspection
techniques.
Many GE customers with generators at nuclearpowered plants are required by their insurers to
remove the generator field at a specified interval to complete a major inspection. GE is currently working with several major insurers to
reconsider this policy as a result of in-situ
inspection technology. The first step toward
replacing traditional inspections with those performed in-situ is qualification of the inspection
techniques. GE has completed several qualification tests and is in the process of documenting
Qualification Testing
Qualification testing involved performing an insitu inspection on an actual generator and comparing these results with those obtained
through traditionally accepted inspection methods. MAGICs visual inspection system was the
first to be qualified. The MAGIC inspection was
performed on a GE generator at Georgia
Powers Plant Vogtle, during a scheduled major
inspection outage. An inspection report was
written which documented the condition of the
generator gas gap region as well as the collector
endwinding region which was inspected using
the remote access camera. A thorough visual
inspection was then performed with the field
out and the results were compared. GE found
the in-situ inspection results were completely
satisfactory with good image resolution, thoroughness and perspective. The field out inspection found no defects which had not been
detected with the MAGIC visual inspection.
MAGICs wedge tapping capability was developed by miniaturizing and remotely delivering
an industry accepted wedge tapping device.
This direction was taken so that wedge tightness
data, whether taken with the field in or out,
could be easily correlated. Data correlation is
important to the long term trending and condition assessment. MAGICs wedge tap system was
qualified on a large GE generator through
comparison of in-situ test results with field out
wedge tapping and hammer testing techniques. As a result of its wedge tapping development, GE added the ability to listen to the tap
test while in progress. This information is very
useful in assuring the test is being performed
10
Qualification Report
A detailed qualification report will be prepared
to document the results and provide the data
needed to demonstrate the validity of in-situ
11
Visual
Visual
And Wedge
Tightness
Visual, Wedge
Tightness
And EL-CID
Traditional
14 Shifts
16 Shifts
18 Shifts
In-Situ
6 Shifts
9 Shifts
12 Shifts
Savings
8 Shifts
7 Shifts
6 Shifts
Type of
Inspection
GT25550
12
Est. Cycle
(Shifts)
Est.
Craft Hrs.
Est. Cost
($1000)
1000/1500
$125
$20
$175
$160
$480
200/300
$40
$50
$60
$100
$250
6
4
6
2
5
2
Total Cost
$480
$250
$230
Traditional
Savings of $230,000
In-Situ
In Situ
Traditional
Inspection ($K)
In-Situ Inspection
($K)
13
Recommended maintenance schedules for traditional and in-situ inspection protocols are
compared in Table 4.
Conclusions
The power generation industry is undergoing
major changes requiring power producers,
OEMs and insurers to adapt. One way GE has
responded to these market changes is through
the development of tools that enable in-situ
inspection of generators. In-situ inspection
offers an acceptable, low cost alternative to the
traditional field out generator inspection in
many cases. GE has been and will continue to
work within the industry to gain acceptance of
in-situ inspection techniques. GE is presently
working on enhancing the capabilities of its insitu inspection service and expanding the application to smaller generators. In-situ inspection
will play an increasing role in reducing power
producers cost of generation.
2.5
Traditional
MAJOR
Visual
Wedge
ELCID
MINOR
Visual
MAJOR
Visual
Wedge
ELCID
MAGIC In-Situ
IN-SITU
Visual
Wedge
ELCID
IN-SITU
Visual
IN-SITU
Wedge
10
IN-SITU
ELCID
EL-CID
GT25551
First Year
Inspection
14
Figure 2.
Figure 3.
Figure 4.
Figure 5.
Figure 6.
Figure 7.
Figure 8.
Figure 9.
15
Inspection capabilities
Table 2.
Table 3.
Table 4.
16