EE742 Chap2 System Components
EE742 Chap2 System Components
Generation: 12-25 kV
Transmission: above 138 kV
Sub-transmission: 69-138 kV
Distribution: 4.16-69 kV
Utilization: below 4.16 kV
https://www.nvenergy.com/renewablesenvironment/renewables/images/renewables_map.pdf
1000
0
Hour of Day
Time (mm/dd/yy)
9/28/2008
9/21/2008
9/14/2008
9/7/2008
8/31/2008
8/24/2008
8/17/2008
8/10/2008
8/3/2008
7/27/2008
7/20/2008
7/13/2008
7/6/2008
6/29/2008
3000
6/22/2008
4000
6/8/2008
6/1/2008
5000
6000
6/15/2008
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
Demand
6000
5000
4000
3000
2000
2000
1000
Generation-load balance
As electricity itself cannot presently be stored on a large scale, changes in
customer demand throughout the day and over the seasons are met by
controlling conventional generation, using stored fuels.
Frequency is maintained as long as there is a balance between resources
and customer demand (plus losses). An imbalance causes a frequency
deviation.
The overall daily profile of load in a given area can be predicted reasonably
well using forecasting tools.
A day-ahead generating schedule can be developed based on the
predicted next-day load profile.
Source: Alec Brooks, Ed Lu,Dan Reicher, Charles Spirakis, and Bill Weihl,Demand Dispatch IEEE Power &
Energy magazine, May/June 2010
4000
3000
2000
Base Load
1000
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
Hour of Day
Unit # x
Unit # y
Unit # z
Interchange error
Customer demand and generation are constantly changing
within all BAs.
BAs will have some unintentional outflow or inflow at any
given instant.
A Balancing Authoritys internal obligations is to control an
instantaneous value called the Area Control Error (ACE) by
keeping it within acceptable limit that is proportional to the BA
size (44 MW for NV Energy South?).
Conceptually, the ACE informs the Balancing Authority what the
frequency is doing in the Interconnected system. For example,
over-generation makes ACE go positive and puts upward
pressure on Interconnection frequency.
Tie-line
M
Scheduled net flow: 350 MW
Actual net flow: 340 MW
(due to load reduction)
Reduce generation
Note that the regulation ramps (i.e. slopes) are significantly higher
than those of load following
Rise time
Time to reach peak value
Settling time
overshoot
HW # 2
Assume the following transfer function relating the
generator terminal voltage to the reference voltage:
V (S )
100
2
Vref ( S ) S 10S 100
Hydro Turbines
Francis Turbine
Turbine Characteristics
See graph below: unregulated turbine (line 1-2), regulated turbine (line 4-3-2)
Role of turbine governor: stable operation in line 3 (with small droop).
Droop (or speed droop coefficient) :
K 1/
HW # 3
Derive the transfer function of the system
below.
Transformers
Step-up transformer: connects generator to the transmission network.
Transmission transformer: connects transmission networks with different
voltage levels
Substation transformer: connects the transmission network to the
distribution network
Distribution transformers: connects the distribution network to
customers
Auto-transformer: typically used when the voltage ratio is less than 2.
Two-winding Transformer
Auto-Transformer
Regulating Transformer
The under-load-tap-changing transformer(ULTC), also called the on-load
tap Changer (OLTC) or load tap changer(LTC), allows the taps to be
changed while the transformer is energized. A typical range of regulation
is 10% with 32 steps - each corresponds to (5/8)%.
Phase-Shifting Transformer
Phase shifting transformers change the phase angle between the primary
and secondary voltages in order to control the flow of real power. They can
also be used to control the voltage ratio, hence reactive power flow.
System Protection
Protective equipment needs to detect a
fault and disconnect the faulty element.
Protection equipment consists of current
and/or potential transformers, relays,
auxiliary power supplies for the relays,
and circuit breakers.
Operation of the protection scheme
must be
fast,
reliable,
and selective.
Differential current protection (for short line) uses pilot wires and analog
signals.
Interlock scheme (for longer lines) uses power line carrier (PLC) - high frequency
(20-200 kHz) logic signals need for line traps.
Phase comparison scheme (i.e., phase angle between currents at both ends of
the line) also use PLC.
Fiber optics placed inside the ground wire are replacing pilot wires and power
line carriers.
Transformer Protection
The main form of transformer protection is differential current
protection (similar to the current differential protection used to
protect a transmission line).
The protection scheme takes into account
The magnitude and phase angle of the current on each side.
The presence of large magnetizing inrush currents
The transformer is protected against inter-turn faults by the
Buchholz protection a safety device that detects the build-up
of gases inside the transformer.
Transformers are also equipped with ground fault protection
(supplied with zero-sequence current), overload protection, and
thermal protection.
Generator Protection