Detail Engineering Scope
Detail Engineering Scope
Detail Engineering Scope
PROJECT SPECIFIC
PART 1
TABLE OF CONTENTS
Description
Page
Section 1
Section 2
Section 3
Project Description
Section 4
Section 5
Section 6
General Information
Section 7
Section 8
Submittals
18
Section 9
Contract Conclusion
23
ii
SECTION 1
PROJECT SPECIFIC INFORMATION
1.01 Planned Improvements. The general planned improvement is:
Between Rimrock Avenue and Grand Avenue
Increase capacity of I-70B by creating 3 through travel lanes in each direction. Improve the safety and
mobility of this stretch of I-70B by closing the median between the major intersections and providing a
dedicated left turn/ U-turn signal phase at each major intersection.
Evaluate and determine the best option to improve safety, access and mobility to and from the businesses
along I-70B. The possible options include acceleration/deceleration lanes outside of the three through lanes
in each direction of travel; improved frontage road system.
Between Grand Avenue and 2nd Street
Increase capacity of I-70B where needed by creating 3 through travel lanes in each direction or improving
intersections. Improve the safety and mobility of this stretch of I-70B by access control, revised lane
configurations, signalization, or other means.
Evaluate and determine the best option to improve safety, access and mobility to and from the businesses
along I-70B.
1.02 Project Goal. This project is intended to produce the following improvements:
1.03 Project Location. This project is located on I-70B from M.P. 4.2 to M.P. 5.4
1.04 Project Cost. The construction cost of this project is estimated at $ 21 million.
1.05 Work Duration. The time period for the design work described in this scope is approximately
700 calendar days.
1.06 Consultant Responsibility. The Consultant is responsible for: Survey, Sitemap, Utility Plans,
ROW Plans, Obtaining Title Services, Design of Stormwater Sewer System, Landscaping, Irrigation,
Erosion Control and Design Services during Construction. See work activity assignments.
.
1.07 Work Product. The Consultant work products are:
Field Inspection Review (FIR)Plans
Final Office Review (FOR)Plans
Right of Way Plans
AD Plans, Specifications, Cost Estimate
Construction Plan Package
1.08 Work Product Completion. All submittals must be accepted by the CDOT Contract
Administrator or his designee.
Page | 1
SECTION 2
PROJECT MANAGEMENT AND COORDINATION
2.01 CDOT Contacts. The Contract Administrator for this project is:
Dave Eller, Regional Transportation Director Region 3.
General administration of this contract will be delegated to Peter Mertes, West Program Engineer. Active day to
day administration and monitoring of contract task orders will be delegated to Regional Resident Engineers or
CDOT PEs within each task order.
Active day-to-day administration of the contract will be delegated to:
Name
Title
Address
Telephone
Fax
Jason C. Smith
Resident Engineer
606 S 9th Street, Grand Junction, CO 81501
970-683-6351
970-683-6369
SECTION 4
KNOWN EXISTING FEATURES
4.01 Utilities
The consultant will coordinate with U.N.C.C. at 1-800-922-1987 to obtain utility information. Other existing
features may exist and require additional coordination or data collection.
SECTION 5
ITEMS TO BE FURNISHED BY CDOT
5.01 Roadway Design files, CDOT Manuals, Specifications, Standards, etc. Electronic Files of
applicable standards All CDOT forms specified in this document
5.02 Project Specific Items
CDOT available accident history data
CDOT available traffic data
CDOT Roadway Design Model and Plans when developed
Designs of previous projects
As-constructed roadway, and existing ROW plans
Soil Profile and Pavement Design
CDOT Forms
I-70B West Environmental Assessment
I-70B West FONSI
Page | 3
SECTION 6
GENERAL INFORMATION
6.01 Authorization to Proceed. Work will not commence until the written Notice-to-Proceed is issued
by the State with certification from the Consultant that the work will be completed within the allotted time.
6.02 Project Coordination. The routine working contact will be between the CDOT Project Manager
(CDOT/PM) and the Consultant Project Manager (C/PM) as defined in Attachment C. Each Project
Manager will provide the other with:
a.
b.
Written synopses or copy of their respective contacts (both by telephone and in person) with
others.
Copies of pertinent written communications
b.
The periodic reports and billings required by CDOT Procedural Directive 400.2 (Monitoring
Consultant Contracts).
c.
Minutes of all Meetings: The minutes will be completed and will be provided to the CDOT/PM
within five (5) working days after the meeting. When a definable task is discussed during a
meeting, the minutes will identify the "Action Item", the agency responsible for accomplishing it,
and the proposed completion date.
d.
In general, all reports and submittals must be accepted by CDOT prior to their content being
utilized in follow-up work effort.
6.04 Personnel Qualifications. The Consultant Project Manager (C/PM) must be approved by the
CDOT Contract Administrator. Certain tasks must be done by Licensed Professional Engineers or
Professional Land Surveyors (PLS) who are registered with the Colorado State Board of Registration for
Professional Engineers and Land Surveyors.
Page | 4
InRoads
MicroStation
InRoads TMOSS
Transport, an ASHTO-sponsored software
Microsoft Word
b.
Specific Criteria. Attachment B is a list of specific project criteria. The list is comprehensive
and may include items that are not required for tasks defined in this scope. The Consultant shall
submit the pertinent criteria to the CDOT/PM at one of the periodic progress meetings prior to
initiating design.
c. Construction Materials/Methods. The materials specified for construction and any indicated
construction methods will be selected to minimize the initial construction and long-term
maintenance cost to the State of Colorado. Non-typical construction materials and methods must
be approved in writing by CDOT.
6.07 CDOTs Right Not to Have the Consultant Perform the work:
While it is anticipated that the Consultant will be asked to perform all the activities checked as performed by
Consultant, CDOT reserves the right to perform any or all of these tasks, or to provide assistance to the
Consultant on any or all such work.
Page | 5
SECTION 7
WORK ACTIVITY ASSIGNMENTS
7.01 Type of work may include all or parts of the following activities:
A.
General Engineering Services - The scope for general engineering and design services may include but
shall not necessarily be limited to:
a.
b.
c.
d.
e.
f.
g.
h.
B.
Provide conceptual drawings, graphs, data collection, or charts for the Regions planning,
environmental, or other units as needed.
Conduct Studies - transportation, environmental, etc.
Provide support for region planning activities, including assistance with public meetings.
Provide design support for off systems or other modes of transportation alternatives.
Provide drafting support or CADD services. All CADD work for CDOT will be conducted using
MicroStation and Inroads Software, latest versions used by CDOT.
Provide lighting plans and analysis.
Provide support research or search county, state or other areas for records or documents relevant
to the project or task.
Provide or acquire design services as required to complete tasks not specifically defined in the
outline, but that may be required by specific task order.
Perform surveys related to the horizontal and vertical alignment of the project.
Perform GPS control survey.
Perform topographical surveys.
Perform cross section surveys.
ROW support for design.
Perform utility surveys (include potholing).
Perform wetland survey.
Prepare project control diagram.
C.
Photogrammetric Mapping
D.
Right-of-Way Plan Preparation - The scope for right-of-way plan preparation may
include:
a.
b.
c.
d.
e.
f.
g.
h.
i.
j.
Determine parcels.
Write parcel legal descriptions.
Determine parcel size.
Prepare R.O.W. plan tabulation sheet.
Prepare R.O.W. plan sheets.
Prepare monument tabulation monumentation sheets.
Prepare land survey control diagram.
Prepare total ownership maps.
Title Research/Obtain Title Services.
Prepare Revisions to Legal Descriptions and R.O.W. Plan sheets.
Page | 6
E.
Bridge/Structural Design Activities - The scope of work for bridge design activities may include:
a.
b.
c.
d.
e.
f.
g.
h.
i.
j.
F.
Roadway Design Activities - The scope of work for roadway design activities may include:
a.
b.
c.
d.
e.
f.
G.
Provide design services including quantity calculations for the various components of roadway
construction, which could include intersection layout, interchanges, signals, structures, lighting,
landscaping, irrigation design, ditch design, waterline, and sanitary sewer design.
Furnish detailing and drafting services utilizing MicroStation and Inroads Software, latest CDOT
adopted versions utilizing CDOT format. Other software required for design services and
communication of information are Microsoft office products such as word, excel, power point. In
addition project wise or FTP sites may be required for file sharing. Other formats or software
products may be required for specific tasks such as traffic modeling or truck turning movements.
Attend scoping reviews, design office reviews, field inspection reviews, and final office reviews
and provide minutes as appropriate.
Prepare (PS&E Package) final plans, specifications and provide the CDOT project manager with
detailed estimates that can be entered into CDOT Trns-port application system.
Prepare revisions under-advertisement to plans or specifications when necessary.
Design and layout of intersections and interchanges.
Hydrology Activities - The scope of work for the hydrology activities may include:
a.
b.
c.
H.
Hydraulics Design Activities - The scope of work for hydraulics design activities may
include:
a.
b.
c.
d.
e.
f.
I.
Traffic Engineering Activities - The scope of work for traffic engineering activities may
include:
a.
b.
c.
d.
e.
f.
g.
h.
i.
J.
Architectural Activities - The scope of work for architectural activities may include:
a.
b.
c.
d.
K.
Furnish design and quantity calculations of the various components of highwayrelated facilities.
Furnish detailing and drafting services.
Prepare final plans and specifications.
Evaluation and assistance in the resolution of problems encountered during
construction of transportation-related facilities and/or state buildings.
Provide estimates of quantities of native seeding and mulching for the FIR plans.
Determine most economic landscape alternative, finalize concept, and complete
the plan.
Verify that an acceptable safe recovery distance exists between traveled way and
all trees to be planted.
Coordinate all special permits that may be required.
Coordinate ROW requirements.
Write Special Provisions and submit to the CDOT/PM with the completed roadside plans.
Submit the approved plan/special provisions to the Design Engineer for inclusion in the Project
Plans.
Verify availability of plant materials and submit letter to the CDOT/PM certifying that designated
plants are available.
Provide recommendations for alternative landscape designs and recommendations for Best
Management Practices for temporary and permanent erosion protection.
Provide Storm Water Plan Sheets with BMP locations and quantity calculations.
Page | 8
L.
Noise Study - The scope of work for noise study activities may include:
a.
b.
c.
d.
M.
Value Engineering (VE) - The scope of work for value engineering activities may
include:
a.
b.
c.
N.
Conduct VE meetings and provide minutes. The VE meetings should be considered for the
following efforts:
1. Brain Storming
2. Evaluating alternatives upon meeting the project purposes and need
3. Recommend alternatives based upon:
- Most benefit to purpose and need
- Minimal or mitigatable impacts
- Constructability
- Cost
- Best overall response to constraints and concerns
Collect and compile VE cost and workhour data.
Provide Final VE Report.
Geotechnical Services for Design - The scope of work for design services include:
a.
b.
c.
d.
O.
Provide field sampling and testing of existing pavements and soils necessary for proper pavement
design as per the CDOT Pavement Design Manual.
Perform boring and subsurface geotechnical investigations for Structure Selection Reports.
Provide testing results used in the design process that are certified by a professional engineer.
Provide other geotechnical services as requested in writing, including but not limited to
subsurface investigations, instrumentation, foundation reports, landslide evaluations, MSE wall
designs, soil nail designs, and retaining wall designs.
Environmental Services - The scope of work for environmental services may include:
a.
b.
c.
d.
Page | 9
P.
Design Services Under Construction the Scope of Work for design services under construction may
include:
a.
b.
c.
d.
e.
f.
g.
Q.
Other Services - As requested Design and/ or General Engineering SOW by the Regions and specified in
the task orders for other services not specified above may be requested on an as needed basis.
The scope of work for these services will include the details of the SOW and General Engineering
Requirements.
This following list establishes the consultant's individual responsibility for anticipated tasks. The
consultant shall maintain the ability to perform all work tasks which are indicated below by an 'X' mark
in the consultant column, in accordance with the applicable CDOT standards. Selected work tasks
shall be assigned only after coordination and consultation with CDOT. The Consultant is also
responsible for coordinating the required work schedule for those tasks accomplished by CDOT and
other agencies. CDOT reserves the right to perform any or all tasks or to assist the Consultant in the
tasks checked as Consultant tasks below.
PRECONSTRUCTION
CDOT/OTHER CONSULTANT
A. Project Initiation and Continuing Requirements:
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
X
X
X
X
X
X
X
X
X
Page | 10
X
X
X
X
X
X
12.
Project Management
CDOT/OTHER CONSULTANT
B.
Project Development:
1.
2.
3.
e.
f.
g.
h.
4.
N/A
X
X
Presurvey Conference
Survey Data Research
Secure Rights of Entry
Project Control Survey
(1) Locate or establish
HARN Stations
(2) Monumentation
(3) Project Control
Photogrammetry
Supplemental Surveying
Accuracy Tests
Review (by Registered
Professional Land Surveyor)
X
X
X
X
X
X
X
X
X
X
Conceptual Design
a.
b.
c.
d.
e.
5.
X
X
X
X
X
X
X
X
X
X
N/A
X
X
N/A
N/A
N/A
N/A
Traffic Related
(1) Traffic Study
X
Page | 11
X
N/A
N/A
N/A
N/A
X
N/A
N/A
CDOT/OTHER CONSULTANT
(4) Air Quality
(a) Air Quality Monitoring
(b) Air Quality Analysis
(5) Alternate Transportation Sys.
Archaeology
(1) Gather Data & Analysis
(2) Mitigation Implementation
Paleontology
(1) Gather Data & Analysis
(2) Mitigation Implementation
N/A
N/A
N/A
N/A
d.
N/A
N/A
e.
Water Quality
(1) Quality Analysis
(2) Quality Monitoring
N/A
N/A
N/A
N/A
b.
c.
f.
Ecological Assessment
g.
Historical
(1)Historical Bridge Clearance
(2)Historical Study & Clearance
Floodplain and Drainage Assessment
i.
Right-of-Way
(1) Early ROW
(2) ROW Review
(3) Prepare Legal Description
k.
l.
m.
X
X
X
X
h.
j.
N/A
N/A
N/A
N/A
N/A
X
__X___
4(f)/6(f) Activity
(1) Evaluation
(2) Clearance/Concurrence
X
X
X
X
Wetlands
(1) Wetlands Determination
(2) Wetlands Findings Report
X
X
Hazardous Materials
(1) Field Search
(2) Research
X
X
Page | 12
N/A
X
X
X
(3)
(4)
X
X
CDOT/OTHER CONSULTANT
n.
o.
p.
q.
r.
s.
t.
6.
7.
8.
9.
C.
N/A
X
X
X
N/A
N/A
N/A
N/A
X
X
X
N/A
N/A
N/A
N/A
N/A
N/A
X
N/A
N/A
N/A
Preliminary Design:
1.
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
2.
Traffic Engineering
3.
Materials Engineering
a.
Preliminary Soil Investigation
b.
Pavement Rehabilitation
c.
New Pavement Structure
d.
Pavement Justification
e.
Pavement Design Report
X
X
X
X
X
X
Page | 13
f.
g.
X
X
CDOT/OTHER
4.
5.
6.
Hydrology/Hydraulics Engineering
a.
Hydrology
b.
Hydraulics
c.
Preliminary Hydraulics Report
X
X
X
Utility Coordination
a.
Location Maps
b.
Reviews and investigations
(1) "Potholing"-Excavation
(2) "Potholing"-Surveying Utility
Locations
c.
Relocation recommendations
d.
Ditch Company coordination
7.
8.
9.
10.
X
X
X
X
X
X
c.
CONSULTANT
Lighting Plan
X
X
X
X
X
X
X
N/A
N/A
X
X
X
N/A
N/A
Right-of-Way
a.
Research
b.
Ownership Map
c.
Prepare Legal Description
X
X
X
X
X
X
X
X
X
Page | 14
l1.
12.
X
X
CDOT/OTHER CONSULTANT
D.
Final Design:
1.
Project Review
2.
Design Coordination
3.
Utility Coordination
4.
Hydraulic Design
a.
Data Review
b.
Storm Water Pollution Prevention
Plan
c.
Major Structure Channel Design
d.
Final Hydraulics Report
5.
6.
7.
8.
Interim Plans
a.
Initiate ROW Authorization Process
b.
Final Utility Plans
c.
Final Railroad Plans
X
X
N/A
N/A
Right-of-Way
a.
ROW Plans Content
b.
Title Insurance and
Closing Services
c.
Authorization Plan
d.
Appraisal Staking
e.
ROW Plan Revisions
(During Negotiations)
f.
Prepare Legal Description
g.
Title Commitments
X
N/A
X
X
X
N/A
X
X
X
X
X
X
X
Materials Engineering
a.
Materials Data
b.
Stabilization validity
c.
Stabilization Plan
X
X
X
Traffic Engineering
a.
Permanent Signing/Pavement
Marking Plans
b.
Signalized Intersections
c.
Traffic Control Plan
X
X
X
Page | 15
CDOT/OTHER CONSULTANT
9.
Roadside Planning
a.
Landscaping
b.
Other
Sprinkler systems
Bikepaths
Sound barriers
Truck escape ramps
Rest Areas
Guardrail and delineator
Safety analyses (CDOT help w/data)
c.
10.
Lighting Plans
E.
N/A
N/A
d.
e.
X
X
N/A
N/A
X
X
X
Roadway Design
c.
X
X
X
X
X
12.
13.
l4.
l5.
Design Control
Information Services
Budget Planning Support
(N/A)
(N/A)
(N/A)
Page | 16
F.
Value Engineering
(N/A)
_____
CDOT/OTHER CONSULTANT
SERVICES AFTER DESIGN
A.
B.
Construction Services
1.
Coordinate Schedule
2.
Provide field observation
a.
Pile driving/caisson drilling
b.
Major concrete pours
c.
Placement of girders
d.
Splicing of girders
e.
Post-tensioning duct and
anchorage placement
f.
Post-tensioning operations
X
X
X
X
3.
Technical assistance
4.
Submittals
a.
Diary
b.
Documentation/justification
c.
Progress reports
d.
Calculations, drawings, and
specifications
e.
Daily time sheets
C.
D.
E.
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
Construction Engineering
Page | 17
SECTION 8
SUBMITTALS
CDOT/OTHER CONSULTANT
A. Project Initiation and Continuing Requirements:
Part 1
A.1.
A.2.
Part 2
A.3
A.4
A.5
A.6
A.7
A.8
A.9
Project Schedule
Completed Specific Design
Criteria (Attachment B)
Survey Plan
Permissions to Enter (Form 730)
Traffic Control Plan
Initial Submittal of Inroads TMOSS
and/or InRoads Compatible Data
Initial Submittal of an
Original Plan Sheet
X
X
X
X
X
X
X
X
X
X
X
X
B. Project Development:
B.1.a.
B.3.
Public Communication
Contact List
Route Location Survey:
Electronic Survey Files
Survey Inroads TMOSS Data
Monument Records
Control & Monumentation
Plan Sheets
Aerial Photography
Index Map Sheets
Aerial Photography
Contact Prints
Aerial Photography Negatives
Photogrammetry
Electronic Data
Base Map Sheets
Base Map Index Sheet(s)
Page | 18
X
X
X
X
X
N/A
N/A
N/A
N/A
N/A
N/A
X
X
X
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
CDOT/OTHER CONSULTANT
B.5.b.(2)
B.5.c.(2)
B.5.e.(1)
B.5.f.(5)
B.5.g.(1)
B.5.g.(2)
B.5.h.(5)
B.5.i.(2)(b)
B.5.j.(2)(e)
B.5.k.(1)(c)
B.5.l.(2)(b)
B.5.m.(4)
B.6.a.(3)
B.6.d.(3)
B.6.e.
B.7.a.(2)
B.7.d.(3)
B.7.e.
B.8.b.
B.8.e.
Page | 19
X
X
N/A
X
N/A
N/A
N/A
X
X
X
X
X
X
X
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
X
X
X
X
CDOT/OTHER
CONSULTANT
Permits:
B.9.a.
B.9.b.
401 Permit
402 Permit
X
X
B.9.c.
B.9.d.
B.9.e.
404 Permit
Wildlife Certification
NPDES Storm Water Permit
X
X
__X___
_____
C. Preliminary Design:
C.1.
C.2.g.
C.3.a.(4)
C.3.e.
C.3.f.
C.3.g.(6)
C.3.g.(7)
C.4.c.
C.5.c.
C.5.d.
Electronic Survey
Traffic Data & Recommendations
Soils Investigation Report
Pavement Design Report
Existing Bridge Condition Report
Foundation Investigation Report
Engineering Geology Plan Sheet(s)
Preliminary Hydraulics Report
Utility Relocation
Recommendations
Ditch Structure Plans
N/A
X
X
X
X
X
N/A
X
X
X
Part 2
Right-of-Way:
C.7.a.
C.7.b.
C.8.c.
C.8.d.
C.10.c
C.10.d.
C.11.e.
C.12.
Memoranda of Ownership
Preliminary Ownership Map
(include in the FIR plan set)
Structural Selection Report
Foundation Investigation
Request
Preliminary Cost Estimate (CDOT run Transport)
FIR Plan Set
List of Deviations from Standard
Design Criteria
Corrected FIR Plan Set
Page | 20
X
X
X
X
X
X
X
X
X
X
CDOT/OTHER CONSULTANT
D. Final Design:
D.4.d.
D.5.a.
D.5.b.
D.5.c.(4)
D.5.c.(5)
X
X
X
N/A
N/A
D.6.b.(4)
D.6.b.(5)
D.6.b.(6)
Area Calculations
Authorization Plans
Legal Descriptions
X
X
X
Materials:
D.7.c.
Stabilization Plan
X
X
X
X
X
Right-of-Way:
Traffic Engineering:
D.8.a.
D.8.b.
D.8.b.
D.8.c.
Roadside Planning:
D.9.a.(6)
D.9.a.(7)
D.9.b.
D.9.b.
D.9.b.
D.9.b.
D.9.b.
D.9.c.
D.11.c.
X
X
X
X
X
N/A
N/A
X
X
D.12.
D.13.d.
D.13.e.
D.15.a.
D.15.c.
X
X
X
X
X
X
X
X
X
CDOT/OTHER CONSULTANT
Construction Plan Package:
D.15.d.(1)
D.15.d.(2)
D.15.e.
Page | 22
X
X
X
SECTION 9
CONTRACT CONCLUSION
9.02 Contract Completion.
This Contract will be satisfied upon acceptance of the following items if applicable:
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
Project Schedule
Project Progress Meeting Minutes
Traffic Control Plan(s)
All Documents Found In Research
All Permission to Enter Forms
Monumented & Surveyed Ground Control
Legally Deposited Control Survey Diagram(s)
Digital Inroads TMOSS Terrain and Topography Survey Data
Ownership Map
Original Field Notes
Survey Report (Including monument recovery forms)
Monumented and Sealed ROW Plans
Legally Deposited Survey Plans
Legal Descriptions (Signed and Sealed)
NOAA-NGS Blue Book
Final Record Set of Plans, Specifications, and Estimate
Construction Staking Data
Page | 23
A.
B.
C.
References
Specific Design Criteria
Definitions
Page | 25
ATTACHMENT A
Attachment A
ATTACHMENT A
References
REFERENCES
A.
B.
2.
3.
4.
5.
6.
7.
Standard Specifications for Transportation Materials and Methods of Sampling and Testing
- Part I, Specifications and Part II, Tests
8.
9.
Action Plan
2.
3.
4.
5.
6.
7.
8.
Attachment A
ATTACHMENT A
References, Continued
C.
9.
10.
11.
12.
Survey Manual
13.
14.
15.
16.
17.
Standard Specifications for Road and Bridge Construction and CDOT Supplemental
Specifications
18.
Item Description and Abbreviations (with code numbers)" compiled by Cost Estimate Unit,
CDOT (also available on the Internet)
19.
20.
21.
Utility Manual
23.
24.
25.
26.
ATTACHMENT A
References, Continued
No. 1601
No. 1700.3
No. 1700.7
No. 1700.8
No. 1905.1
D.
E.
2.
3.
4.
5.
6.
7.
8.
"Geometric Geodetic Accuracy Standards and Specifications for Using GPS Relative
Positioning Techniques.
AREA:
1.
Attachment A
ATTACHMENT B
Attachment B
ATTACHMENT B
Specific Design Criteria
SPECIFIC DESIGN CRITERIA
Note:
I.
The following criteria will be developed by the consultant and coordinated with the
CDOT/PM prior to starting the design.
ROADWAY
1.
BASIC DESIGN
The basis for design will be the data in CDOT Form 463, Design Data. A copy of the latest
applicable Design Data form will be furnished to the consultant.
2.
Attachment B
ATTACHMENT B
Specific Design Criteria
3.
INTERSECTIONS AT GRADE:
a. Type:
b. Special Considerations:
5.
TRAFFIC INTERCHANGES:
a. Type:
b. Ramp Type:
c. Special Considerations:
6.
7.
ROADSIDE DEVELOPMENT:
a. Specifications for Revegetating Disturbed Areas to be provided by CDOT.
8.
LIGHTING:
a. Type:
Attachment B
ATTACHMENT C
Attachment C
ATTACHMENT C
DEFINITIONS
DEFINITIONS
AASHTO-
Officials
ADT-
AREA-
ATSSA-
AT&SF-
BAMS-
BLM-
BNRR-
CA-
CAP-
CBC-
CDOT-
CDOT/PM-
CDOT/STR-
CEA-
COG-
Council of Governments
COGO-
CONSULTANT-
CONTRACT
Typically a Region Engineer or Branch Head. The CDOT employee directly
ADMINISTRATOR- responsible for the satisfactory completion of the contract by the Consultant. The
Attachment C
ATTACHMENT C
DEFINITIONS
C/PM-
Consultant Project Manager - The Consultant Engineer responsible for combining the
various inputs in the process of completing the project plans and managing the
Consultant design effort.
DEIS-
DHV-
DOR-
DRCOG-
D&RGW-
EA-
Environmental Assessment
EIS-
ESAL-
ESE-
FEIS-
FEMA-
FHPM-
FHWA-
FIR-
FONSI-
FOR-
GPS-
MAJOR
STRUCTURES-
Bridges and culverts with a total length greater than twenty feet (for walls 100 feet and
maximum exposed height at any section of over five feet). This length is measured
along the centerline of roadway for bridges and culverts, and is the horizontal distance
along the top of wall for retaining walls. Overhead structures (sign bridges, cantilevers
and butterflies extending over traffic) are also major structures.
Attachment C
ATTACHMENT C
DEFINITIONS
MPOMetropolitan Planning Organization Denver Regional Council of Governments Pikes
Peak Area Council of Governments Grand Junction MPO Pueblo MPO North Front
Range Council of Governments
NEPA-
NGS-
NICET-
NOAA-
PAPER
SIZES-
See Computer-Aided Drafting manual (CDOT); Table 6-13 and Table 8-1
PE-
PM-
Program Manager
PLS-
PRT-
PS & E-
PROJECT-
ROW-
ROWPR-
RTD-
T/E
SH-
Inroads TMOSS-
TOPOGRAPHY-
UD & FCD-
Note: For other definitions and terms, refer to Section 101 of the CDOT Division of Highways
Standard Specifications for Road and Bridge Construction and the CDOT Design Guide.
Attachment C