QUS 101 - Intro To Measurement
QUS 101 - Intro To Measurement
UNESCO
VOCATIONAL EDUCATION
REVITALISATION PROJECT
PROJECT-PHASE II
NATIONAL DIPLOMA IN
QUANTITY SURVEYING
INTRODUCTION TO MEASUREMENT
COURSE CODE:
CODE QUS 101
YEAR I - SE MESTER I
THEORY/MEASUREMENT
Version 1: December 2008
GENERAL OBJECTVES:
1.0
2.0
3.0
4.0
TABLE OF CONTENTS
General Objectives
1.0
2.0
3.0
4.0
Roots in Britain
1.2
1.3
1.4
1.5
1.6
2.2
The Architect
2.3
2.4
2.5
3.2
3.3
General rules
Quantities
4.2
Descriptions
4.3
4.4
Drawn information
4.5
4.6
4.7
4.8
5.0
6.0
7.0
8.0
7.1
Taking-off
7.2
Descriptions
7.3
Spacing of dimensions
Applied Mensuration I
Work Group D
Groundwork
15.
14.
13.
Introduction
12.
11.0
Introduction
Applied Mensuration II
9.1
10.0
Cross referencing
Measurement procedures
8.1
9.0
Cross referencing
Classification rules
1.1
Roots in Britain
The Quantity Surveying profession has its root in Britain during the 17th century although the
earliest recorded firm, Henry Cooper and Sons of Reading was established in 1785. The first
recorded use of the term quantity surveyor was in 1858.
EARLY DAYS
IN TIME
CONTRACT SYSTEM
INDUSTRIAL
REVOLUTION
THE BILL OF
QUANTITIES
THE
QUANTITY
SURVEYOR
THE
INDEPENDENT
QUANTITY
SURVEYOR
This was the origin of the independent and impartial quantity surveyor as it is found today.
1.2
1802
1918
1922
1927 - 1998
1991
1.3
Quantity Surveying originated in Great Britain and was imported into Nigeria by the British
who colonised Nigeria. It can be implied that the first set of quantity surveyors who practised
in Nigeria were British citizens.
FIRST QUANTITY
SURVEYORS
Soon after its formal set up, the Institute initiated efforts for the
TRAINING IN
NIGERIA
GOVERNMENT
RECOGNITION
PRACTICE IN
NIGERIA
1.4
1.5
The practice of the profession of quantity surveying has evolved dramatically starting from
the 1970s from that of measurement and valuation to cover much wider areas of expertise in
the procuring and management of various types of construction projects. This evolution has
come about as a result of changes in:
Construction markets
Construction industry
Clients needs
Professions
Advent of ICT
Today the quantity surveyor is the financial consultant to the construction industry and more,
providing services ranging from:
Cost management
Life cycle costing
Project management
Construction management
Procurement
Value management
Facilities management, etc
1.6
1.
The likely cost of the scheme however complicated or unusual it may be.
The quantity surveyor can, from the clients brief, prepare a realistic budget and a cost plan
showing the distribution of costs over the various elements.
2.
Cost Planning
Cost planning is a specialist technique used by quantity surveyors, which aims to help all
members of the design team to arrive jointly at practical and efficient designs for the project
and to keep within the budget. Once a realistic estimate is set from the cost plan, constant
monitoring reduces the risk of overspending by noting problem areas at an early stage and
applying prompt corrective action.
3.
Contractual Methods
The quantity surveyor can advise on the best type of tendering and the best form of contract
that will best suit a specific project. The quantity surveyor prepares the documents for
obtaining the tenders and arranging the contract.
4.
Bill of Quantities
Competitive tendering remains a common basis for selection of contractor and bills of
quantities are fundamental to the process. Bills translate the drawings into a document listing
in detail all the component parts required for a project so that each contractor can calculate
tender prices on exactly the same basis as his competitors.
During construction, the bill forms the basis for preparing interim valuations, pricing of
variations and effective cost control.
5.
Choice of contractor
The quantity surveyor analyses tenders and makes recommendations to the client for
contractor selection after taking into consideration other factors such as the contractors
reputation and past performance.
6.
Contract Administration
The quantity surveyor acts with the architect or engineer to ensure that the financial
provisions of the contract are properly interpreted and applied so that the clients financial
interest is safeguarded and that the builder is paid the proper price for the work.
He also exercises control during construction so that the cost is not exceeded without
authority.
7.
The quantity surveyor prepares interim valuations, values variations and prepares financial
statements during construction. He will also settle the final accounts at project completion. He
may also prepare statements of expenditure for tax or accounting purposes and assess the
projects replacement value for insurance purposes.
8.
Construction management
9.
10.
Dilapidations
The quantity surveyor prepares schedule of conditions at the beginning of a tenancy or lease
and a schedule of dilapidations at the end giving details of an outgoing tenants liability.
11.
Arbitration
Facilities management
This involves all aspects of providing, operating, maintaining, developing and improving
facilities which are property where people are accommodated and work.
13.
Contractor Organisations
The main function of the contractors quantity surveyor is to secure maximum payment for
work done by the contractor at the earliest possible time to avoid cash flow problems and to
maximise profits. These however have to be done within the provisions of the contract. The
contractor cannot receive more than he is entitled to by the contract.
In contrast with the consultant quantity surveyor who claims impartiality between the client
and the contractor, the contractors quantity surveyor will be representing his employers
interests alone. Wise contractors therefore always employ quantity surveyors to look after
their interests and in particular rely on them in the most controversial contractual areas.
The quantity surveyor working in a contractors organisation will therefore carry out the
following functions among others:
For design and build contracts or civil engineering contracts, the quantity surveyor
works with other professionals in the contractors organisation to produce initial plans,
drawings and estimates for the project and helps to calculate the most economical way
to do the job.
Prepares bills of quantities from which an estimation of the cost of a project can be
drawn up by the contractor
Assessing the quantity of labour, materials and equipment required to complete the
project
Follow the progress of the work to ensure that it is completed within budget
Represents the contractor when interim valuations and final accounts are prepared
Ensure that they receive the correct payment at the appropriate time for the work done
on site.
Site measurements for internal and external valuations, final accounts, cost and
bonusing, sub-contract payments and final accounts.
Interpreting and progressing contractual issues and settlement of disputes and claims
Plant control
The quantity surveyor is essentially an expert on construction cost and construction contracts
whose prime task is to ensure that the project is kept within budget and that the client gets
value for money. Although the quantity surveyor is employed by the client and is part of the
architects team, he must have a close relationship with the contractor during construction. He
must ensure that in his valuations of payments due to the contractor, he remains impartial to
both the client and the contractor and so produce harmony in his role as project accountant.
2.1.2
Post-contract period
The quantity surveyor works with the architect or engineer to ensure that the financial
provisions of the contract are properly interpreted and applied so that the clients
financial interest is safeguarded and that cost is not exceeded without authority.
Values variations
Evaluates all financial claims made by the contractor who is allowed to be present at
such times so that agreement is ensured and disputes are avoided
He also prepares financial statements that keep the client informed as to the running
cost of the project.
2.1.4 Completion
He prepares the final account, again, with the assistance of and in agreement with the
contractor.
2.2
The Architect
The architect is regarded as the leader of the building team. However, project managers and
other professionals are currently taking over this traditional role. He often receives the
commission to design and supervise the construction of the building.
The complexities of modern construction require specialised knowledge, which no architect
can provide. He therefore requires the assistance of specialists such as structural engineers to
design the structural frame, mechanical engineers to design the M&E services and quantity
surveyors to advice on cost and contractual aspects. He will also need advice on ground
investigations, landscaping etc.
2.2.1 Pre-contract stage
He determines the clients requirements for a project, which is known as the clients
brief. If the client is unsure of what he wants, the architect can help in formulating
this brief.
Prepares the preliminary designs based on the brief with inputs from quantity
surveyors on comparative costs of alternative design proposals and from consulting
structural and service engineers on aspects of complex buildings.
After approval from the client, he produces detailed architectural designs while the
engineers produce detailed structural and service designs and the quantity surveyor
produces a cost plan based on which he cost checks to keep costs within clients
budget.
Decides which aspects of the work are to be carried out by nominated subcontractors
and suppliers.
Calls for tenders from suitable contractors either based on a bill of quantities or other
contractual arrangement.
He receives the tenders and advises the client on selection of contractor usually based
on quantity surveyors recommendation.
Supervises the work, ensuring that the contractor keeps to the design and specification
Chairs site meetings, which are held regularly on site where problems and difficulties
are discussed and resolved.
Issues instructions to the contractor in relation to the work execution and any
variations required.
2.2.3 Completion
At the end of the project the architect issues:
The certificate of making good defects usually six months after practical completion
The final certificate not later than two months after the end of the defects liability
period.
2.3
On large complex building projects the architect will recommend to the client the
employment or appointment of consulting engineers, usually specialist in structural work and
mechanical and electrical services.
The engineer prepares designs and specifications within the scope of their specialist
fields advising the architect on the buildability of his concepts. For instance, the
structural or building engineer must ensure structural stability with economy in mind
and avoidance of obstruction by structural members and also assist in producing a
logical and systematic construction process.
2.3.2 Post-contract
During construction, the consulting engineers assist the architect by supervising their
specialist area of the work, modifying or re-designing work as may become necessary.
2.4
These are specialists in civil engineering design and construction. In civil engineering
contracts they assume the leadership role in the design and construction team. Like architects
in building contracts they may require the inputs of other consultants, such as architects,
quantity surveyors, service engineers etc.
2.5
The professional holds himself or herself out as an expert in a specified field. The person
must have the training, skills and experience to back up such a claim.
Professionals usually come together to form associations to protect members and advance
their interests. Governments on the other hand seek to regulate professions in a bid to protect
members of the public in relation to the activities of the professionals.
In some countries, the government allows the professional groups self-regulation whereas in
others, the government sets up a government agency that has the responsibility of regulating
the practice of the profession in that country.
COUNTRY
PROFESSIONAL BODY
REGULATORY BODY
United Kingdom
Hong Kong
Malaysia
Singapore
Australia
South Africa
Kenya
Nigeria
Nigerian
Institute
Surveyors (NIQS)
of
Quantity
Surveyors
Board of Registration of
Architects and Surveyors in
Kenya
The regulated and other Provisions) Act of 1978 recognised quantity surveying as one of the
scheduled professions. Decree No. 31 of 1986 gave legal backing and recognition to the
quantity surveying profession and also established the Quantity Surveyors Registration Board
of Nigeria (QSRBN) to regulate the profession.
The vision of the NIQS is To be the profession in Nigeria responsible for total cost and
procurement management, for the achievement of clients objectives in all types of capital
projects and developments, from conception to commissioning and maintenance, in all sectors
of the economy, for the attainment of sustainable national development and goals.
(a)
To promote the science and practice of the quantity surveying profession in all its
ramifications.
(b)
To provide a platform or forum for meeting and discussing matters of mutual interest
to quantity surveyors in Nigeria and to preserve and further the interest of quantity
surveyors.
(c)
To promote and stimulate the improvement of the technical and general knowledge of
persons engaged in the profession of quantity surveying.
(d)
(e)
To undertake research study and to collate information from any quantity surveying
bodies from any part of the world on the latest developments and technologies in the
practice of quantity surveying and to make available such information to its members.
(f)
To cooperate with the QSRBN in training of quantity surveyors and regulating and
controlling the practice of quantity surveying in Nigeria.
(g)
bodies in Nigeria.
(h)
(a)
(h)
Facilities management
(b)
Cost modelling
(i)
(c)
(j)
Arbitration
(d)
(k)
Expert witness
(e)
(l)
(f)
(m)
Dilapidation
(g)
Project management
The vision of the NIOB is to provide Nigeria with the profession that will be responsible for
the complete construction of new buildings, maintenance of existing buildings and building
production management utilising high standards of practice and provide modern and
appropriate construction techniques with more emphasis on improved training, safety, quality
and value management for the benefit of the fatherland.
Statutorily, a professional builder cannot practice the profession in Nigeria unless he/she is
registered with CORBON and remains registered throughout his/her professional career.
Environmental
Geotechnical
Industrial
Mechanical
Metallurgical
Petroleum
Structural
Association of Professional Women Engineers in Nigeria (APWEN)
The objective NSE is to promote the advancement of engineering education, research and
practice in all its ramifications. This is with a view to maintaining and enhancing the
professional capabilities of its members so as to better equip them to fulfil the needs of the
profession for the good of the public and the nation.
Accept that it is the commercial world that is the leading edge but use its position and
authority to influence and create and spot trends
Reflect the need for individuals to remain champions of property and fairness and
uphold the charter
Constantly upgrade professional skills, business skills and knowledge to a level which
is envied by other professionals
Promote the benefits of employing a chartered surveyor so that the currency value of
belonging to the RICS is as high as possible
Improve communications and develop the single profession culture among its
members
3.1
Definition
The standard method of measurement is a document that sets out the rules for the
measurement and description of construction works.
Purpose
Its main purpose is to provide a uniform basis for measuring construction work. When bills of
quantities are prepared based on a particular standard method of measurement, all the parties
concerned are aware of what is included, assumed or not included. All contractors tendering
therefore tender on the same basis and their tenders can easily be evaluated and compared.
3.2
The BESMM3 is made up of two main parts. The measurement and description rules in each
part are grouped under main headings as follows:
Preliminaries/General Conditions
Existing site/Buildings/Services
Ground work
Masonry
Cladding/Covering
Waterproofing
Linings/Sheathing/Dry Partitioning
Windows/Doors/Stairs
Surface finishes
Furniture/Equipment
Paving/Planting/Fencing/Site furniture
Disposal systems
Transport systems
General items
Ground work
Paving Highways
Transport systems
The section preceding the two chapters contains general rules guiding the use of the standard
method. These rules need to be properly understood by the student before commencing actual
measurement and will therefore be treated studied in detail in for the next three weeks.
For this course we shall be treating the general rules covering the measurement and
description of building works only.
The use of the SMM will be studied under the following headings:
Tabulated Rules
Quantities
Descriptions
Drawn Information
Fixing, base and background
Procedure when inadequate information is provided
Symbols and abbreviations
Cross referencing
Tabulated Rules
The rules of the BESMM3 are set out in tables. Rules covering each work group or section are
set out under three headings:
Information to be provided
Classification tables
Supplementary rules
The horizontal lines divide the classification tables and supplementary rules into zones to
which different rules apply. Fig 1 shows a typical page from the BESMM3.
MEASUREMENT RULES
M1 The rules within this
section apply to works in
existing buildings as
defined in the General rules
M2 any operation to
existing buildings involving
removal of existing
materials (other than for
bonding purposes or
renewal) is measured within
this Section
CLASSIFICATION TABLE
1 Removing
1. Details
components, fittings
sufficient for
and fixtures
identification
stated
2. Removing plumbing
and engineering
2. Dimensioned
installations
description
sufficient for
3. Removing finishing
identification
including type and
4. Removing coverings
thickness of
existing building
5. Cutting openings or
recesses
Item
6. Cutting back
projections
7. Cutting to reduce
thickness
8. filling openings
9. Temporary roads
10 Temporary screens
Fig 1
1. Dimensioned
description
tem
DEFINITION RULES
D1 Materials arising from
alterations spot items
are the property of the
Contractor unless
otherwise stated
D2 Location is stated
relative to the existing
building
COVERAGE RULES
C1 Shoring and scaffolding
incidental to the work and making
good all work disturbed is deemed
to be included within each item
C2 Alterations spot items are
deemed to include:
(a0 disposal of the materials other
than those remaining the property
of the Employer or those for re-use
(b) work incidental to alterations
spot items which is at the
discretion of the Contractor
(c) all new fixing or joining
materials required
SUPPLEMENTARY INFORMATION
S1 Method of operation, where by
specific means
S2 Setting aside and storing materials
remaining the property of the Employer
or those for re-use
S3 Employers restrictions on methods
of disposal of materials
S4 Employers restrictions on methods
of shoring and scaffolding to be used
Information to be provided
This section ensures that details about the work at hand which the tenderer requires to make accurate
estimates are provided either in location drawings, bill diagrams, specifications or preambles as the
case may be.
E.g. E05 In-situ concrete states that the relative position of concrete members, size of members,
thickness of slabs and permissible loads in relation to casting time must be clearly shown on location
drawings or bill diagrams.
Classification Tables
This section has five columns. The fourth column from the left which contains units of measurement
is usually not referred to when cross-referencing. For this reason, the classification table is in some
texts said to have four columns.
Column 1
works
Column 2
Column 3
contains more descriptive features that are meant to enhance the quality of the
These rules are meant to guide the user of the SMM to properly measure the physical quantities and
to compose and phrase the work item descriptions appropriately.
Suspended slab with attached beam & suspended slab with column drop heads
4.1
Quantities
Quantities of work are taken net, that is, as they will be when fixed in position in the building unless
the rules state otherwise. Dimensions used in calculating quantities are taken to the nearest 10mm. In
other words, measurements are taken to two places of decimal when calculating quantities.
When calculations have been completed, quantities are entered into the bills as whole unit with
decimal points rounded up to the nearest whole number. The exceptions are:
4.2
Quantities that are less than one unit which are always rounded up to one unit
Descriptions
Each measured item consists of a quantity and a description. As a general rule, where an item is
measured:
Volumetric/m3
Superficial/m2
Linear/m
Enumerated/Nr or No.
4.3
In building up a description for an item, one descriptive feature is taken from each of the first three
columns and as many as are applicable from the fourth column. Headings of groups of items in the
SMM are read as part of the description.
Example 1:
Work item: Suspended in-situ concrete slab
Group heading:
In situ concrete
Classification table:
Column 1: Rule 5 - Slabs
Column 2: Rule 2 Thickness 150 450mm
Column 3: Non of the rules apply
Column 4: Rule 1 Reinforced
Supplementary information:
Column 8: Rule 1 mix details
Description should then read something like this:
In-situ concrete (1:2:4)
Slabs, thickness 150-450mm, reinforced
Cross reference or Coding: E05:5.2.0.1
Example 2:
Work item: Formwork to soffit of suspended slab
Group heading:
Classification table:
Column 1: Rule 8 Soffits of slabs
Column 2: Rule 1 Slab thickness 200mm
Column 3: rule 1 - Horizontal
Column 4: Rule 2 Height to soffit 1.50m 3.00m
Column 8: Non of the rules apply
Example 3:
Work item: Bar reinforcement in suspended slab
Group heading: Reinforcement for in-situ concrete
Classification table:
Column 1: Rule 1 - Bar
Column 2: Rule 1 Nominal size stated
Column 3: Rule 1 - Straight
Column 4: Rule 1 Horizontal length 12.00 15.00m
Supplementary information:
Column 8: Rule 1 kind and quality of materials
4.4
Drawn Information
The SMM requires that the bills should be read in conjunction with drawings which are provided in
the form of location drawings, component drawings, dimensioned diagrams and schedules.
Site plans which show the position of construction in relation to setting out points, access to
the site and general site layout
Plans, sections and elevations which show the various spaces and location of the principal
elements
2. Component drawings show information required for the manufacture and assembly of a
component
3. Dimensioned diagrams that show the space and shape of work items which may be used in a bill
of quantities in place of a dimensioned description
4. Schedules deemed to be drawings when they provide required information
4.5
A precise and unique cross-reference to a catalogue or standard specification can reduce or replace
the requirements for an item description or component drawing. For instance, a precise reference to a
British standard (BS) or Cope of Practice (CP) can take the place of a detailed description for a work
item.
4.6
The SMM rules may require that the nature of each type of base be identified separately where
required
Where it is required that the nature of background to which an item is to be fixed be identified
then the type of background shall be stated in the description of the item as follows:
(a) Timber which shall also include all building boards such as hardboard, celotex, etc.
(b) Masonry which includes concrete, brick, block and stone
(c) Metal
(d) Metal faced items
(e) Vulnerable materials which shall be deemed to include glass, marble, mosaic, tiled
finishes and the like
4.7
Where work can be fully defined as to description but the quantity of work cannot be accurately
determined, an estimate of the quantity is given and marked as a provisional quantity.
Where work cannot be described and the quantities cannot be adequately determined, it shall be
given as a provisional sum. Provisional sums may be of two types:
In such cases, the Contractor is expected to make allowance for the work in his programming,
planning and pricing of preliminaries
4.8
During the process of taking-off or measurement words entered in the description column are
abbreviated to shorten descriptions, save space and also save time. The symbols and abbreviations
range from those in general use to those that are specifically used by quantity surveyors.
Metre
m2
Square metre
m3
Cubic metre
Mm
Millimetre
Nr or No.
Number
Kg
Kilogram
Tonne
hour
Specialised abbreviations
a.b.d
As before described
av.
average
Blk
Block
blkwk
Blockwork
c/c
Centres
col.
Column
conc.
Concrete
c.w.
Cold water
ddt
Deduct
dp
Deep
dpc
ditto/do
As above
e.o.
Extra over
exc.
Excavate
fdn
Foundation
fwk
Formwork
g.l.
Ground level
hwd
Hardwood
Int.
Internal
isol.
Isolated
Jt.
Joint
k.p.s
matl.
Material
max.
Maximum
m.s.
Mild steel
o/a
Overall
p.c.
Prime cost
reinfd
Reinforced
sprd
Spread
s.s.o
susp.
Suspended
swd
Soft wood
t&g
thk
Thick
vert
Vertical
wdw
Window
wk
Work
wrot
Wrought
wt.
Weight
xtg
existing
Cross Referencing
Cross referencing or coding of work item descriptions within the classification tables are given in the
form:
Work
Number
Number
Number
Numbers
section
from the
from the
from the
from the
number
first
second
third
fourth
column
column
column
column
Example 1:
D20: 2.1.1.0
Excavating and filling
Excavating
Column 1, number 2
Column 2, number 1
Column 3, number 1
Column 4, no relevant entry
14.85
16.45
0.15
NOTE!
An asterisk (*) within a cross reference represents all entries in the column in which it appears
A zero (0) within a cross reference represents no entries from the column in which it appears
Cross referencing of descriptions is useful for abstracting and billing using the computer.
Example 2
D20:2.6.3.1
Excavating
Column 1, number 2
42.44
0.68
1.75
Excavating trenches,
width exceeding 0.30m,
maximum depth not
exceeding 2.00m,
commencing 0.45m below
ground level
(D20:2.6.3.10)
Column 2, number 6
Column 3, number 3
Column 4, number 1
Example 3
D20:7.2.1.1
Excavating and filling
Earthwork support
Column 1, number 7
2 42.44
1.75
Example 4
E05:9.1.2.1
Eartnwork support,
maximum depth not
exceeding 2.00m,
distance between
opposing faces not
exceeding 2.00m, curved
(D20:7.2.1.1)
Column 2, number 2
Column 3, number 1
Column 4, number 1
In situ concrete
Beams
Column 1, number 9
Isolated
Column 2, number 1
5.65
0.23
0.30
Column 3, number 2
Column 4, number 1
Reinforced in-situ
concrete in isolated
beams, 0.03-0.1m2 cross
sectional area
(E05:9.1.2.1)
Example 5
E20:1.1.2.1
Formwork to in situ concrete
Sides of foundation
Column 1, number 1
Plain vertical
Column 2, number 1
Height 250mm
Left in
5.65
0.23
0.30
Column 3, number 2
Column 4, number 1
Reinforced in-situ
concrete in isolated
beams, 0.03-0.1m2 cross
sectional area
(E05:9.1.2.1)
Example 6
E30:4.1.0.0
Reinforcement
Fabric
Column 1, number 4
Steel to BS 4483 ref. A193; weighing 3.02 kg/m2
Column 2, number 1
Column 3, no entry
Column 4, no entry
14.50
16.10
Example 7
M10:5.1.1.1
Cement: sand screed
Floors
Column 1, number 5
Level and to falls only 150 from horizontal
50mm thick, one coat
Laid in bays 1.20m x 1.20m
5.65
0.23
0.30
Column 2, number 1
Column 3, number 1
Column 4, number 1
CLASSROOM EXERCISE
Identify the relevant clauses in the BESMM3 to measure the following items, frame appropriate
descriptions and insert sample dimensions of the appropriate units:
1.
2.
3.
4.
Hardcore filling of broken blocks to make up levels under floors 300mm thick
5.
White glazed vitreous china wash hand basin size 460 x 405
6.
7.
Walls
Column 1, number 1
225mm thick
Column 2, number 1
Vertical
Bonded to glass block walling
55.55
3.00
Column 3, number 1
Column 4, number 2
Example 9
F10:2.1.1.0
Brick/Block walling
Isolated piers
Column 1, number 2
450mm thick
Vertical
Column 2, number 1
Column 3, number 1
Column 4, no entry
32
0.45
2.70
Example 10
G20:9.2.1.1
Carpentry/Timber framing/First fixing
Roof members
Column 1, number 9
Pitched
Column 2, number 2
50 x 150mm
Exceeding 6.00mm in continuous length
2
15
6.88
Column 3, number 1
Column 4, number 1
Example 11
H72:1.1.0.0
Aluminium strip/sheet coverings/flashings
Roof covering
500 pitch
Column 2, number 1
Column 3, no entry
Column 4, no entry
2
27.35
6.90
Example 12
J41:2.1.0.0
Built-up felt roof covering
Roof covering
Pitch 1:40
Column 2, number 1
Column 3, no entry
Column 4, no entry
14.32
7.88
Example 13
L10.1.0.1.0
Windows/Roof lights/Screens/Louvres
Column 1, number 2
Column 2, no entry
Dimensioned diagram Fig 22
Column 3, number 1
Column 4, no entry
12
Example 14
L20.1.0.1.0
Doors/Shutters/Hatches
Work section
number
Doors
Column 1, number 1
Column 2, no entry
Dimensioned diagram Fig 38
Column 3, number 1
Column 4, no entry
Example 15
M60.1.0.1.0
Painting/Clear finishing
General surfaces
Column 1, number 1
Column 2, no entry
Girth > 300mm
Column 3, number 1
Column 4, no entry
6
6
0.84
1.98
0.93
2.03
CLASSROOM EXERCISE
Identify the relevant clauses in the BESMM3 to measure the following items, frame appropriate
descriptions and insert sample dimensions of the appropriate units:
1.
2.
3.
4.
5.
6.
7.
Taking-Off
This implies reading off dimensions form drawings and setting them down in a specific order on
special paper known as dimension paper and inserting an appropriate description.
Standard Dimension Paper
1.
2.
3.
4.
1.
2.
3.
4.
On the left-hand side is a narrow binding margin. The remainder of the sheet is divided into two
identical halves each containing three narrow columns and a wider one; the timesing column, the
dimension column, the squaring column and the description column respectively. The columns are
used as follows:
1.
Timesing column is used for multiplying (timesing) the dimensions when necessary, each
multiplying factor followed by an oblique stroke. A factor followed by a dot indicates
addition instead of multiplication.
4
3.45
7.59
0.15
.
1
2.08
4.44
0.15
2.
Dimension column is used for recording the dimensions in metres and centimetres.
Each linear dimension is underlined.
7.59
LINEAR
Length
AREA
3.45
Length
7.59
Width
VOLUME
3.45
Length
7.59
Width
0.15
Depth
NUMBER
Length
2.
Width
3.
Depth/height
Item indicates an item of cost for which a quantity cannot be calculated. A sum of money is usually
estimated and allowed for in the bills.
3.
Item
ITEM
Squaring column: the resulting areas and volumes inserted in the timesing and dimension
columns are subsequently calculated and entered into the squaring column opposite their
respective dimensions.
3.45
7.59
15.71
0.15
2
4.16
4.44
0.15
4.
2.08
Description column: This wide column is for entering descriptions of the measured work.
3.45
7.59
0.15
.
1
2.08
4.44
0.15
5.
Waste column: This is an imaginary column occupying the right had side of the description
columns in which the taker-off inserts any preliminary calculations (waste) which may be
necessary in order to arrive at his dimensions.
All preliminary calculations must be shown in waste. They need to be set down accurately
and carefully so they can be checked. They should be written either above or below the
description not level with it to avoid confusion.
Waste calculation is necessary for each dimension except in the following situations:
a) When a scaled or figured dimension can be transferred direct from the drawing to the
dimension column
b) When a dimension has been derived from a previous waste calculation
c) When a dimension has been copied from a previous dimension
d) In all other instances the preliminary calculation however simple should be shown on
waste.
Waste calculation should be done in millimetres or to three places of decimal. Final figures
are then rounded off to the nearest 10mm before being transferred to the dimension column.
7.2
Descriptions
The first line of each description should start at the same level as its first dimension. Standard or
common abbreviations are allowed in taking off but descriptions must be written in full in BOQs.
Descriptions must be concise, brief and free from grammatical errors. Terms used must comply with
current technical usage and an estimator must be able to read, understand and price it quickly and
accurately.
The following points should be noted:
Descriptions should not be broken at the bottom of the page or column to continue overleaf
Instead, repeat the first phrase in the description followed by as before described or
abd,
Anding-on: Where two descriptions apply to one dimension, they are separated by an & in the centre
of the description column. Any number of descriptions may be anded-on in this way but not so as to
extend to another column.
15.67
0.68
Plain in-situ
conc (1:3:6) abd
0.23
7.89
&
0.68
0.23
13.99
0.45
Ddt
Backfill exc.
matl. Abd
0.15
&
Add
Remove excvtd
matl. from site
Deductions
Each item to be deducted requires the description to start with the word Deduct or Ddt (underlined).
A description must follow the word Ddt. It should not be written on its own. The next positive
description should be preceded with the word Add (underlined) in order to emphasise the change
from deductions to additions.
Bracketing
A bracket should be used wherever:
(a)
(b)
The bracket is written in the description column just next to the squaring column.
Niling
In order to delete, cancelling of dimensions is not allowed. Instead, the word NIL is written in the
squaring column opposite the offending dimension or dimensions. Arrows are usually used to denote
the extent of the deletion.
32.89
0.68
0.23
15.67
0.68
0.23
7.89
0.68
0.23
13.99
0.45
0.15
25.54
0.45
0.15
NIL
Annotations
Annotations are short or abbreviated words written beside waste calculations and dimensions to
denote from where the figures have been derived.
Side notes to dimensions require a single bracket on the left hand side only.
Example:
7.55
5.50
4.50
300 x 300 x
6mm Floor flex
tiles on trowelled bed
(master BDR
5.89
( BDR 1
4.40
(BDR 2
3.60
4.50
(BDR 3
(BDR 4
3.77
4.55
3.45
Spacing of dimensions
All measurements and descriptions should be spaced well apart so that it is quite clear where one
begins and the other ends. Moreover it is not unusual for the taker-off to realise an omission and to
want to insert it in its proper place. If dimensions are well spaced out, he will be able to squeeze it in,
but otherwise he will have to insert it elsewhere and resort to cross-referencing which only confuses
things.
8.1
Introduction
Determination of quantities for work items in construction work involves calculating geometric
quantities such as lengths, areas and volumes from dimensions and angles that are known. Doing this
will require a healthy knowledge of the formulae for calculating the perimeters, areas and volumes
for various shapes.
These various shapes form the building blocks for most components found in construction work.
For instance, the area of the concrete floor slab below is a combination of rectangles of different
sizes.
The archway below is made up of a half circle and a rectangle and the gabled wall is made up of a
triangle and a rectangle.
The hipped roof below is made up of two triangles and two rectangles
The following are useful formulae for calculating volumes, areas and perimeters of various shapes
SHAPE
Rectangular prism
FIGURE
VOLUME
TYPICAL BUILDING
COMPONENTS
Slabs
Beams
Columns
Trench excavations
Pit excavations
Basement excavations
Filling
Cylinder
Circular slabs
Circular columns
x (radius)2 x height
Filling
SHAPE
Rectangle
FIGURE
AREA
PERIMETER
Length x breadth
(Length + breadth) x 2
x (radius)2
x radius x 2
x base x height
Circle
Triangle
SHAPE
FIGURE
AREA
PERIMETER
Arc of circle
2 x x radius x /3600
Sector of a circle
Segment of a circle
Chord
SHAPE
FIGURE
AREA
Bellmouth
Ellipse
0.7854 x (A x a)
Sphere
4 x x (radius)2
PERIMETER
SHAPE
FIGURE
AREA
A
Trapezoid
Hexagon
2.6 x (side)2
Octagon
4.83 x (side)2
Perimeter
9.1
Relationship between shapes and Building Measurement
Measurement of a building or item of construction involves calculating lengths, areas or volumes of
different shapes and sizes. It may also involve counting or enumerating some types of components.
Invariably, most components can be analysed into some common shapes that the formulae are
known.
For instance, measuring the volume of excavation for a foundation trench involves calculating the
area of a rectangle (cross section of the trench) and multiplying by the length of trench.
d
l
w
5m
3m
7m
2.5m
5m
4m
The surface area of the floor would naturally divide into three rectangles. If the thickness of the floor
was 150mm (0.15m), then,
Volume of concrete = (5 x 5 x 0.15) + (3 x 2.5 x 0.15) + (7 x 4 x 0.15) m3
= 13.28m3
Setting out the above figures on a dimension sheet will be as follows:
5.00
5.00
0.15
3.75
3.00
2.50
0.15
1.13
7.00
4.00
0.15
8.40
13.28
An area of a component of wall would usually be the area of a rectangle, length of wall multiplied by
the height. If the wall is a gable wall then it would be rectangle topped by a triangle.
A wall would also usually have openings for windows, doors, arches, fixed lights, etc. The usual
thing is to measure the whole wall overall as if there were no openings and then systematically
deduct for openings that are rectangles, triangles and circles or parts thereof.
8m
0.9m
0.9m
3m
1.2m
0.9m
2.1m
1.2m
Area of wall = (8m x 3m) { (1.2 x 0.9) + (0.9 x 2.1) + (1.2 x 0.9)}m2
= 24m2 (1.08 + 1.89 + 1.08)m2
= 24m2 4.05m2 = 19.95m2
8.00
225
mm
hollow
3.00 24.00 sandcrete block wall in
c.m (1:4)
1.20
0.90
0.90
2.10
Ddt
2.16 Ditto
1.89
4.05
Formwork to an isolated concrete column 225 x 225mm sectional size, 3m long. Formwork will go
round all four sides.
225mm
225mm
Perimeter of rectangle or square
= 225 + 225 + 225 + 225mm
3m
OR
On dimension sheets:
4 0.23
3.00 2.76
2.7m2
In this case, formwork is only on three faces of the concrete, on the two sides and on the wide face
face.
Perimeter of rectangle excluding one side = 225 + 450 + 225mm
225
= 0.900m2
Area of formwork
= 3m X 0.9m2
= 2.7m2
On dimension sheets:
Length
225
450
225
900
0.90
3.00
Formwork to slabs
attached to slabs, 225 x
21.60 300mm plain
rectangular shape (in 8
Nr)
Any irregular-shaped area to be measured is usually best divided into triangles, the triangles being
measured individually and added to give the area of the whole. A line can be drawn through an
irregular or curved boundary in such a way that the area excluded by the line is compensated for by
the area that is included by it.
10.1
Introduction
The perimeter of a shape without thickness is simple to compute arithmetically using the principle of
(length + breadth) x 2. Whilst the simple arithmetic concept is always to be used, the computation
often proves to be somewhat complex for most students when a thickness is attributed to the shape as
is always the case when the perimeter of a wall or a trench is required to be computed.
To compute the perimeter of a wall, we will need to work out the perimeter of the internal line of the
wall and the perimeter of the external line of the wall and then compute the average of the two
perimeters. This procedure will turn out to be clumsy if not cumbersome. Hence the need for the
systematic computation of centre line as set out in the foregoing examples.
The importance of centre line computation cannot be over-emphasised as the result of the
computation will subsequently be found to be useful for the measurement of several items all
through the take-off stages.
Simple rectangular plan shape
10m
8m
Centre Line
2/10.000
2/8.000
20.000
16.000
2 x length
2 x width
36.000
External perimeter
As this is a longer
than the perimeter
of the line running
through the centre
of the width of the
wall, Deduction
should be made as
follows:
Ddt
4/2/ /200
0.800
35.20
At a corner, we
lose
1 x the thickness
in each of two
directions. This is
repeated in all the 4
x corners
2m
3m
8m
10m
Centre Line
2/10.000
20.000
2/8.000
16.000
36.000
2 x length
A drag of the 3.50m
length to complete
the 10m run on the
length
2 x width
A drag of the 2.5om
length to complete
the 8m run on the
breadth
Ddt
4/2/ /200
0.800
35.200
Centre line
RULE 1
A CORNER RECESS DOES NOT
ALTER THE PERIMETER OF THE OF
THE SHAPE
Student should
note that
regardless of how
dimensions are
recorded in the
drawings,
quantities when
transferred to the
waste calculation
column shall be
recorded to 3
places of decimal
or in millimetres (if
recorded without
decimal) without
any indication given
of the actual unit of
measurement
CLASS EXERCISE
Give students a rectangular shape with recesses at two corners (all dimensions given) to work out the
centre line for the recessed shape.
8m
3m
2m
Centre Line
2/10.000
20.000
2 x length
A drag of the 3.50m
length to complete
the 10m run on the
length
2/8.000
16.000
2 x width
A drag of the 2.5om
length to complete
the 8m run on the
breadth
36.000
The 3.00m horizontal
in the recess drops
down to fill up the
10.00m on the length.
Add
2/2.000
4.000
40.000
Ddt
4/2/ /200
0.800
39.200
To determine the
number of corners,
we count the external
corners as +ve and
the internal corners
as -ve
+6 x external corners
-2 x internal corners
This gives us a net
+4 corners
RULE 2
AN ALONG THE WALL RECESS
ALTERS THE PERIMETER OF
THE SHAPE BY 2 X THE DEPTH
OF THE RECESS
CLASS EXERCISE
1.
Give students a couple of rectangular shapes with recesses at two or more locations along the
wall (all dimensions given) to work out the centre line for the recessed shape.
2m
200mm thick walls
3m
8m
3m
2m
10m
Centre Line
2/10.000
20.0000
2 x length
A drag of the 3.50m
length to complete the
10m run on the length
2/8.000
16.000
2 x width
A drag of the 2.5om
length to complete the
8m run on the breadth
36.000
Add
2/2.000
4.000
40.000
Ddt
4/2/ /200
0.800
39.200
To determine the number
of corners, we count the
external corners as +ve
and the internal corners
as -ve
+7 x external corners
-3 x internal corners
This gives us a net +4
corners
RULE 3
A MIX OF A CORNER
RECESS AND AN ALONG
THE WALL RECESS ALTERS
THE PERIMETER OF THE OF
THE SHAPE BY 2 X THE
DEPTH OF THE ALONG
WALL RECESS. THE
CORNER RECESS DOES
NOT HAVE ANY AFFECT.
CLASS EXERCISES
1.
Give students a couple of plan shapes with complicated recesses asking them to count how
many external and internal corners are present. Do this until the lecturer is confident that
students have a clear understanding of this concept
2.
Give students a rectangular shape with recesses at two or more locations along the wall (all
dimensions given) to work out the centre line for the recessed shape.
Groundwork
This work section is covered by Section D20 of the BESMM3 and some of the clauses will be looked
at closely over the next three weeks as a prelude to measurement of substructures.
Generally
Forming bulk, pit, trench and surface area excavation other than those for
services supplies, M & E services and drainage;
Filling holes and excavations other than those for services, etc. and
Features retained would include trees which are retained and protected, stating
any required method of protection
D20 rule M3
D20 Rule M7
This rule explains when it is necessary to measure working space and must be
read together with D20:6.1 and D20:6.2-4
D20 Rule D5
D20 Rule C2
This rule refers to the measurement of working space and apart from the
additional excavation needed, all the additional items such as earthwork
support, disposal, backfilling, work below water level, and breaking out
required as a result of the excavation of working space are deemed to be
included in the with the item.
Classification Rules
D20:1.1-2
D20 Rule M1
Trees, girth measured
1.00m above gl
D20.1.3.4
D20 Rule M2
Stumps, girth
measured at top
Clearing site vegetation is defined in D20 Rule D1. A full description is required with
sufficient detail to allow identification of vegetation types. These items are measured
over area (i.e. in square metres)
D20.1.4.1
Turf is apiece of grass sod cut from the ground and preserved for future use. The
method of preserving should be given in the specification and referred to in the
description.
D20.2.1.1
excavating topsoil for preservation need not be given as a separate item except where
it is specified that topsoil is to be preserved.
Ground level
Topsoil
D20.2.2.
Topsoil depth
(if for preservation)
Reduced level
(say 250mm)
excavation maximum depth n.e. 0.25m
Formation level
If topsoil is not to be preserved then reduce level excavations commence at existing ground level (gl)
Ground level
Maximum depth
ranges of reduce
reduce levels
excavating
n.e. 0.25m
n.e. 1.00m
n.e. 2.00m
Formation level
Formation level
Formation level
thereafter
in 2.00m
stages
D20.2.3
A basement is a useable area of a building below ground level. These are areas which
can be occupied areas, car parks and plant rooms.
n.e 0.25m
Maximum
depth stages
n.e.1.00m
n.e. 2.00m
and thereafter in 2.00m stages
D20.2.4-7
n.e. 0.25m
n.e. 1.00m
Depth of pit
/trench
n.e. 2.00m
n.e. 4.00m
D 20.2.8
Excavating to bench sloping ground to receive filling This is done in the face of
sloping ground to prevent slippage
D20.3
The rules under this clause cover items extra over any type of excavation irrespective
of depth.
The items under this rule are measured as extra over previously measured
excavations:
D20.3.1
Excavation
The excavation is measured as if there was no water and then the bit excavated below water level is
then measured as extra over the excavation in which it occurs.
D20.3.4.1
Excavation
Gas service
pipe
Electricity
Cable duct
D20.3.5.1
Excavation
Gas service
pipe crossing
excavation
Electricity cable duct
EXERCISE
Go through all the Groundwork rules and identify the following:
1.
2.
Classification Rules
Breaking out existing rock, concrete, reinforced concrete, brickwork, blockwork or
stonework shall each be measured and described separately in cubic metres as extra
over any types of excavating
Rock is defined as any material which is of such size or position that it can only be
removed by special plant or explosives (D20: Definition Rule 5). Special plant are
defined as mentioned last week
D20.5.
D20.6
Pits
Trenches
The measurement is taken as the girth or length of the formwork, rendering, tanking
or protective wall, multiplied by the height measured from the commencing level of
excavation to the bottom of the formwork, etc.
Note: An area is measured not a volume as the estimator is left to make a judgement
as to the width required giving due regard to the nature of the work involved.
C
If formwork required to face C, then working space is measured as:
Length or girth of the formwork on plan multiplied by height of the excavation A
B
E
Less than 600mm
F
More than 600mm
Ground level
B
Section of pit/trench/pile caps and ground beams
If the formwork is required to face B, the edge of the concrete foundation, then the
working space is measured to the full depth of the pit/trench. If no formwork is required
to face b then no working space allowance to excavation is measured.
D20.7
Earthwork Support
Earthwork support must be measured to the face of any excavation to be upheld
whether it will actually be required or not. This is to cover the contractors
responsibility to uphold the sides of excavations. It is left to the contractors discretion
to decide the extent and strength of support required or to use no support at all after
due consideration of the nature of the soil.
Earthwork support in measured in square metres to the whole face of excavations in
trenches, pits and the like except for excavations not exceeding 250mm depth and
pipe trenches which are measured linear. Earthwork support to pipe trenches is
deemed to be included in the item. Maximum depth is stated in the description in
stages. Earthwork support is also classified by the distance between opposing faces:
Not exceeding 2.00 metres
2.00m 4.00 metres
Exceeding 4.00 metres
Earthwork support left in, curved, next to a roadway, below ground water level or to
unstable ground shall be described and measured separately.
The various classifications of depth and distance between faces are illustrated as follows:
1.
2.
A is less than 1.00m and B is greater than 2.00m, but less than 4.00m
3.
4.
A is greater than 1.00m but less than 2.00m and B is less than 2.00m
5.
A is greater than 1.00m but less than 2.00m and B is greater than 2.00m but less than 4.00m
6.
A is greater than 1.00m but less than 2.00m and B is greater than 4.00m
7.
A is greater than 2.00m but less than 4.00m and B is less than 2.00m
8.
A is greater than 2.00m but less than 4.00m and B is greater than 2.00m but less than 4.00m
CLASSROOM EXERCISE
1.
A pit has been excavated for a reinforced concrete column base, 1000mm x 2500mm size on
plan. Column base will require formwork. Depth of excavation from ground level to
underside of column base is 1.85 metres:
(a)
Sketch a section of the pit excavation
(b)
Work out the allowance for working space
(c)
Calculate the area for earthwork support and identify the classifications for maximum
depth and distance between opposing faces.
2.
A foundation trench excavation has a mean length of 56.78m, width, 675mm and depth,
2.20m:
Calculate the area for earthwork support and identify the classifications for maximum depth
and distance between opposing faces.
D20.8.1
D20.8.2
D20. 8.3
Stored on site
Unless there are specific handling requirements in the specifications or for health
and safety regulations in connection with active material or toxic/hazardous
material then the handling of the excavated material will be at the discretion of the
contractor.
Where materials are disposed of on site the information provided under the fourth
column should state specific requirements for the location of such deposits and the
average distance from the excavation in metres.
D20.9-11
Filling
Filling to excavations
Filling can be obtained from different sources, these should be referred to in the specification
particularly in respect of material obtained off site
Surface Treatments
D20.13.1
Applying herbicides is measured over the surface area of the excavation and `relates
to the use of chemicals to stop the growth of vegetation. Application of anti termite
treatment can as well be measured under this rule.
D20.13.2
Compacting
acting would include the former traditional description level and ram. This
includes the compacting of bottoms of excavations and compacting of filling and
subsequently levelling their surfaces in readiness to receive concrete. Compacting is
classified into:
Compacting ground
Compacting filling
D20.13.2.*.1 Where blinding is intended to fill the interstices in the filling material only and has no
specific thickness then it can be included with surface treatment
Specific blinding beds of a given thickness should be measured as filling under item
D20.10.3
D20.13.3.1.1 Trimming sloping surfaces is only measured where the slope is greater than 150 from
horizontal. If trimming in rock, this should be stated in the description
D20.13.4 & 5 Trimming to produce fair or exposed face & preparing subsoil for topsoil
The specification should include the requirements and how to achieve these. This
should then be referred to in the descriptions.
CLASSROOM EXERCISE
Extract the quantities for excavation, filling and disposal in a few bills of quantities and cross check
that: