47 - 2000 - PHD - Influence of LI To Insulating Systems PDF
47 - 2000 - PHD - Influence of LI To Insulating Systems PDF
47 - 2000 - PHD - Influence of LI To Insulating Systems PDF
discussions, stats, and author profiles for this publication at: https://www.researchgate.net/publication/255701107
READS
187
1 AUTHOR:
Sonja Monica Berlijn
Statnett
36 PUBLICATIONS 111 CITATIONS
SEE PROFILE
INSTITUT FR HOCHSPANNUNGSTECHNIK
MIT VERSUCHSANSTALT
Dissertation
For the academic degree
Doctor of Technical science
Permitted by the
Faculty of Electrical Engineering
of the
Technical University Graz
Submitted by:
1. Expert & Supervisor: O.Univ.-Prof.Dipl.-Ing.Dr. Michael Muhr
2. Expert: Univ.-Prof.Dipl-Ing.Dr. Ernst Gockenbach
Arnhem, The Netherlands May 2000
Preface
Thanks
The EC is thanked for the financial
support
of
the
project
Digital
measurement of parameters used for
lightning impulse tests for high voltage
equipment, contract no. PL95120-SMT4CT96-2132.
Last but not least I want to thank my two dogs Romy and Orso for
always being there, keeping me company and making me laugh.
Kurzfassung
vi
Abstract
Abstract
Lightning strokes have caused a considerable number of failures of
high voltage equipment installed in medium and high voltage grids.
In order to prevent these failures several studies have been performed
and several measures have been taken. One of these measures is to
test high voltage equipment with lightning impulse voltages.
The measurement of the applied voltages and the evaluation of the
parameters characterising these lightning impulse voltages have to be
performed accurate and uniform all over the world, since high-voltage
equipment require large capital assets and they are exported all over
the world.
vii
Kurzfassung
Keywords
lightning impulse voltage, evaluation methods, standard and nonstandard lightning impulses, k-factor function, test with lightning
impulses, IEC 60060-1
viii
Abstract
Kurzfassung
Blitzeinschlge in Mittel- und Hochspannungsnetze haben in der
Vergangenheit zu einer groen Anzahl von Fehlern an
Hochspannungsgerten gefhrt. Um diesen Fehlern vorzubeugen,
wurden einige Studien und verschiedene vorbeugende Manahmen
durchgefhrt.
Eine dieser Manahmen ist die Prfung der
Hochspannungsanlagen oder -gerte mit einer Blitzstospannung.
Die Messung der angelegten Spannung und die Auswertung der
Parameter, die die Blitzstospannung charakterisieren, mssen sehr
genau und in der ganzen Welt gleich ausgefhrt werden, damit die
Ergebnisse vergleichbar sind.
Bei Blitzstospannungsprfungen an Hochspannungsgerten knnen
Oszillationen und/oder berschwingungen im Anstiegsbereich oder
nahe des Scheitelwertes des Blitzstoimpulses entstehen. Die
Messung
der
Blitzstoimpulse
ohne
Oszillationen
und
berschwingungen kann heute mit zufriedenstellender Genauigkeit
durchgefhrt werden. Probleme bei der Auswertung entstehen bei
abgeschnittenen Blitzstoimpulsen oder wenn der Blitzstoimpuls
kleine berschwingungen oder Oszillationen aufweist.
Noch
schwieriger wird die Auswertung, wenn es sich um einen nicht
standardisierten Blitzstoimpuls handelt. Die Ursache fr die
Probleme beim Auswerten ist darin begrndet, da fr
Blitzstoimpulse mit berlagerten Schwingungen oder Oszillationen
keine eindeutigen Meverfahren in den Standards definiert sind. Im
Fall von nicht standardisierten Blitzstoimpulsen gibt es gar keine
Lsungsanstze in den aktuellen Standards.
Schlgwrter
Blitzstospannung, Auswertung, standardisierter und nicht
standardardisierter Blitzstoimpuls, k-Faktor Funktion, NennstehBlitzstospannungsprfung, IEC 60060-1
ix
Contents
Contents
1
Introduction _______________________________________________________________________ 1
xi
Contents
xii
Semi-range value
Pressure [mbar]
Confidence limit [%]
Capacitance
Capacitance to earth
Overshoot duration
Electric field strength [V/m]
Frequency [Hz]
Force [N]
Assigned scale factor [1]
Distribution Function
Humidity [g/m3]
Factor by which the amplitude of the applied impulse should be
attenuated
Coverage factor
Air density correction factor
Humidity correction factor
Atmospheric correction factor
Inductance [H]
Virtual origin of a standard lightning impulse voltage
Pressure [bar or Pa]
Power [W]
Probability
Distribution function
Resistance [Ohm]
Residual Curve
Experimental standard deviation
Standard deviation of systematic contributions that have a
rectangular distribution
Standard deviation of systematic contributions that have Gaussian
distribution
Time delay between the origin of the impulse and the origin of the
superimposed oscillations [s]
Time to peak [s]
Temperature [C]
Students t factor
Time to chopping [s]
Front time of a lightning impulse voltage [s]
Time to half value of a lightning impulse voltage [s]
Time at which the lightning impulse is 30% of it peak value
Time at which the lightning impulse is 90% of it peak value
Overall uncertainty
Measured curve [V]
Mean curve [V]
Peak value of a lightning impulse voltage [V]
Reference mean curve [V]
Systematic contributions to the overall uncertainty
Random contributions to the overall uncertainty
Value of the test voltage [V]
xiii
U50(peak)
U50(RMC)
dU/dt
W
Z
(x;,2)
(x;,2)
CIGRE
Disruptive discharge
Flashover
IEC
Impulse
MLM
Non-standard lightning impulse
voltage
OPV
PE
PSM
Puncture
RMC
SD
SE
Sparkover
Standard lightning impulse voltage
Surge
TDG
VPV
XLPE
xiv
Base Line
a lightning impulse voltage during which a disruptive discharge
causes a rapid collapse of the voltage, which then falls to zero or
nearly zero, with or without oscillations
International Conference on Large High Voltage Electric Systems
phenoma associated with the failure of insulation under electrical
stress, in which the discharge completely bridges the insulation
under test, reducing the voltage between the electrodes practically
to zero. It applies to electrical breakdowns in solid, liquid and
gaseous dielectrics and combinations of these.
a disruptive discharge over the surface of a dielectric in a gaseous
or liquid
International Electrotechnical Commission
intentionally applied aperiodic transient voltage or current which
usually rises rapidly to a peak value and then falls more slowly to
zero.
Multiple Level Method
lightning impulses with large overshoots or oscillations
overshoot peak value [V]
Polyethylene
Progressive Stress Method
Disruptive discharge in a solid medium
reference mean curve
Standard Deviation
Single Exponential of Tail
disruptive discharge in a gaseous or a liquid medium
the lightning impulse voltage as defined in IEC 60060-1
transient occurring in electrical equipment or networks in service
Test Data Generator
virtual peak value
Cross-linked polyethylene
Introduction
1 Introduction
Lightning strokes have caused a considerable number of failures of
high voltage equipment installed in medium and high voltage
networks. In order to prevent these failures much research has been
performed and several measures have been taken. One of these
measures is to test high voltage equipment with lightning impulse
voltages to verify the withstand capability.
Lightning impulse voltages represent surges i.e. transients occurring
naturally in high voltage systems under operation. A full lightning
impulse voltage (without oscillations or overshoot) is, currently in
IEC-60060-1 [1], defined by its peak value Up, its virtual origin O1,
and its time parameters, the front time T1 and the time to half value
T2. Tests with lightning impulse voltages are made using a standard
lightning impulse having a front time of 1,2 s and a time to halfvalue of 50 s, described as a 1,2/50 s lightning impulse voltage.
Introduction
and do not consider the introduction of new insulating materials as for
instance SF6. Besides this, the problems with the evaluation of
parameters of standard and non-standard lightning impulse voltages
are dealt with separately.
The most ideal solution for the evaluation problems will be a solution,
which is applicable to both standard and non-standard lightning
impulse voltages, which uses the possibilities of modern processing
techniques and which is founded on the breakdown behaviour of
insulating materials.
To find this most ideal solution or a solution based on the breakdown
behaviour of insulating materials or systems, theoretical and
experimental investigations were necessary.
Therefore this research was started. The main topics of the PhD
study of which the results are presented in this thesis are:
1. study of basic literature;
study towards tests with lightning impulses
study and evaluation of already existing evaluation methods
2. theoretical investigation towards the breakdown behaviour of
insulating materials and systems
3. experimental investigation towards the breakdown behaviour of
different insulating materials for different lightning impulse wave
shapes
4. proposal for a new evaluation method
Ad 1:
Besides a summary of the information found in the basic literature
also international developments will be explained. Because some of
the newest information is not available yet in official publications,
results will be presented of activities within CIGRE WG33.03 and
TC12/WG 33.03
Ad 2:
Besides the literature investigation performed at KEMA, also the
results are presented of a literature investigation performed in the
framework of the European project on Lightning Impulses.
Ad 3:
The experimental investigations on different materials were
performed at different locations and within different projects:
Lightning Impulses
2 Lightning impulses
2.1
Introduction
In this chapter it is described why and how lightning impulse test are
performed. Attention is paid to the evaluation of parameters
characterising lightning impulse voltage, to the problems that arise
during evaluation and to the current state of the art to solve these
problems.
2.2
Lightning
It has always been the case that people are at the same time astonished
and afraid for lightning and thunder [5]. About 200 years ago (in
1754) it has been proved that lightning that occur during
thunderstorms is an electrical discharge. At this moment still not all
the aspects of thunderstorms are revealed although it is known that
they are caused by the complicated process of air flows. 60%-70% of
the lightning discharges occurs between or in clouds of different
charge. These cloud-cloud discharges can be dangerous to airplanes.
The most dangerous discharges for human beings and equipment are
the discharges between clouds and earth and earth and clouds (also
called lightning strokes) [6]. In Figure 1 a thundercloud is shown in
the stage before lightning occurs. In 90-95% of the cases, especially
in the Netherlands, the cloud is negatively charged at the bottom.
A lightning stroke is an impulse current. The voltage value and the
voltage shape of the stroke are determined by the impedance the
current meets on its way to ground and are therefore situation
dependant. Important factors of lightning strokes are the maximum
current value, the charge, the energy contents and the current
steepness (some typical values for the Netherlands are given in
Table 1) [6].
Table 1 Typical stroke parameters in the Netherlands
Parameter
Normal
High
Extreme
100
200
400
Charge in C
100
300
1000
Energy in MJ/Ohm
10
100
50
200
300
2
Figure 1 An example of a thundercloud
(rain is not necessarily present)
The number of lightning strokes, the number of damage cases and the
losses due to lightning strokes vary from country to country. In the
Netherlands thunderstorms occur on 107 days per year and on average
about 2 to 3 lightning strokes occur per km2 per year.
Some extreme cases of damage can be mentioned, for instance strokes
that occurred at 13 July 1997 in New York caused a damage of
1 billion US Dollar and it was the reason that 10 million people didnt
have electricity for 20 hours.
Detailed information about the process of lightning, atmospheric
overvoltages and the influence to power grids is given in [5].
Lighting Impulses
2.3
2.3.1
2.3.2
Applicable standards
Lightning Impulses
2.3.3
Lighting Impulses
2.3.4
Tests procedures
Procedure A
Three impulses of the specified shape and polarity at the rated
withstand voltage level are applied to the test object. The
requirements of the tests are satisfied if no indication of failure is
obtained, using methods of detection specified by the relevant
Technical Committee (This procedure is only recommended for tests
on degradable or non-self-restoring insulation.).
Procedure B
Fifteen impulses of the specified shape and polarity at the withstand
voltage level are applied to the test object. The requirements of the
tests are satisfied if not more than two disruptive discharges occur in
the self-restoring part of the insulation and no indication of failure in
the non-self-restoring insulation is obtained by the detection methods
specified by the relevant Technical Committee.
Procedure C
Three impulses of the specified shape and polarity at the withstand
voltage level are applied to the test object. If no disruptive discharge
occurs the tests object has passed the test. If more than one disruptive
discharge occurs the tests object has failed to pass the test. If one
disruptive discharge occurs in the self-restoring part of the insulation,
then nine additional impulses are applied and if no disruptive
discharge occurs the tests object has passed the test. If any detection
of failure in a non-self-restoring part of the insulation is observed
with the detection methods specified by the relevant Technical
Committee during any part of the test, the test object has failed to pass
the test.
Procedure D
U10 U 50 (1 1,3z )
Equation I Relation between U10 and U50
Lightning Impulses
The following test methods can be used to evaluate U50:
the multiple-level method with n 4 voltage levels and m 10
impulses per level
the up-and-down method with m = 1 impulse per group and n 20
useful applications
To evaluate U10, the up-and-down method, with m = 7 impulses per
group and at least eight useful groups can be used.
In all cases the voltage interval U between levels should be
approximately 1,5 to 3% of the estimated value of U50.
2.3.5
General requirements
The general requirements for an Approved Measuring System are
given on the next page, more detailed requirements and the methods
for Performance Checks and Tests can be found in IEC 60060-2:
to measure the peak value of full impulses with an overall
uncertainty within 3%
to measure the peak value of chopped impulses with on overall
uncertainty which is depending on the time to chopping as follows:
for front chopped impulses (0,5 s Tc 2 s) within 5%
for tail-chopped impulses (Tc 2s) within 3%
to measure the time parameters which define the waveform with an
overall uncertainty within 10%
to measure oscillations which may be superimposed on an impulse
to ensure that they do not exceed the permitted levels given in
IEC 60060-1
the scale factor shall remain constant over long periods. More
specific, the scale factor of the converting device and the
transmission system shall not vary by more than 1% for the ranges
of the ambient temperature and clearances given in the Record of
Performance
the measuring instruments shall for oscilloscopes and peak
voltmeters comply with IEC 60790 and for digital recorders with
IEC 61083-1.
Evidence that the Measuring System meets the requirements is given
in its Record of Performance.
Lighting Impulses
Lightning Impulses
With some test circuits, oscillations or overshoot may occur at the
peak of the impulse, see Figure 4 a) to d). If the frequency of such
oscillations is not less than 0,5 MHz or the duration of overshoot not
more than 1 s, a mean curve should be drawn as in Figure 4 a) and
b). For the purpose of measurement, the maximum amplitude of this
mean curve is chosen as the peak value defining the value of the test
voltage.
Overshoot or oscillations in the neighbourhood of the peak, measured
by a system according to IEC Publication 60060-2, are tolerated
provided their single peak amplitude is not larger than 5% of the peak
value.
Front Time T1
The front time T1 of a lighting impulse is a virtual parameter defined
as 1,67 times the interval T between the instants when the impulse is
30% and 90% of the peak value Up, (points A and B, Figure 3).
Time to half-value T2
The time to half-value T2 of a lighting impulse is a virtual parameter
defined as the time interval between the virtual origin O1 and the
instant when the voltage has decreased to half the peak value.
Time to chopping
The time to chopping Tc is a virtual parameter defined as the time
interval between the virtual origin O1 and the instant of chopping.
The instant of chopping is that at which the rapid collapse of voltage
which characterises the chopping first occurs.
The instant of chopping is different if the impulse is chopped in the
front or in the tail, see Figure 6 and Figure 5.
non-standard
Lighting Impulses
2.3.7
2.3.8
Measurement uncertainty
10
2.3.8.1 General
Uncertainty is a statement of [9]:
the limits (U) of the range of values within which the true value
of a measurement is expected to lie in relation to the recorded
result and
the probability of the true value lying within these limits; this
probability is expressed as the confidence level (B)
Lightning Impulses
In most measurement, the overall measurement uncertainty will result
from a combination of several contributions that are classified into
two categories according to the method used to evaluate their
numerical values [8]:
systematic contributions
random contributions
The overall uncertainty is calculated from these contributions.
As a high-voltage laboratory, one has to comply with several
standards dealing with measurement uncertainty. These standards are:
IEC 60060-2 annex H [9]
STL-guide [10]
EAL-2
These standards are in general identical, however they differ on a few
points, mainly the calculation of the random contributions. At KEMA
High-Voltage laboratory the measurement uncertainty is calculated
with the method described in IEC 60060-2, since this is the most
precise. Therefore only this standard is explained here.
U U s2 U r2
Equation IV Calculation of the overall
uncertainty out of the two contributions,
when Us and Ur are calculated at the same
confidence level
s sa
a
3
2
ss s sa2 ssg
2
2
U s k ss k ssa
ssg
sr
1 n
( xi xm ) 2
n 1 i 1
11
Lighting Impulses
Ur
t sr
n
Ur
k sr
n2
U k
U
1
ai2 i
3
ki
t sr
k n
2.4
2.4.1
U k
U
1
ai2 i
3
ki
t sr
12
Lightning Impulses
2.4.2
2.4.3
2.4.4
13
Lighting Impulses
For front chopped impulses, measurement uncertainties in the peak
value and the time to chopping of larger than 6% were seen.
A comparison of software showed that, by using different methods a
large spread of some parameters determined from different mean
curves has been obtained [13]. In paper [17] different methods, all
acceptable to the standard, have been compared and differences from
each other up to 1,7% for the peak value, 18% for the front time and
3% for the time to half value have been obtained when case no 11 of
the TDG of IEC 61083-2 (see Figure 11) was analysed.
Figure 11 Case no. 11 of the TDG of
IEC 61083-2
Both comparisons showed that there are problems with the evaluation
methods given in IEC 60060-1. It seems right now that the hardware
is good enough for the accuracy required nowadays, but that the
software or evaluation methods are the major contribution to the
measurement uncertainty due to the ambiguous definitions
2.4.5
Full Lightning
Impulse
Determination
of Mean Curve
No
Determine
Oscillations or
Overshoot ?
Non Standard
Lightning
Impulse
Yes
Special Case
T 1 and T 2
T 1 =1,2 s 30%
T 2 =50 s 20%?
No
Yes
Yes
Standard Lightning
Impulse
No
TC determines
Amplitude
> 5%?
Test voltage
Yes
Determine
T 1 and T 2
No
Yes
No
Test voltage = Peak voltage
14
Evaluate
T 1 and T 2
Lightning Impulses
One of the main problems with the evaluation of parameters
nowadays is the determination of the mean curve. The standard
allows different mean curves, resulting in different values for the
parameters characterising the same lightning impulse voltage [12].
The reason for the ambiguousness in the standard is that the
evaluation guidelines given in IEC 60060-1 were introduced in the
time there were mainly analogue oscilloscopes were available and the
evaluation of the parameters had to be done manually using pencil,
ruler and engineering judgement.
By eye it was decided if overshoot or oscillation appeared and in case
of overshoot and oscillation appeared outside the allowed limits, a
mean curve was drawn. The thickness of the oscilloscope trace in
conjunction with the thickness of the line drawn as the mean curve
made it impossible to discriminate between different mean curves
and therefore the problems with the evaluation guidelines did not
arise. Since then a lot has changed.
in 1994 a new standard, IEC 60060-2 ed. 1994, was introduced in
which the requirements towards measurement uncertainty for the
measurement of lightning impulse voltages are more strict than
they were before. The cause for this is that the interest of
manufacturers and purchasers of high voltage equipment are
higher and because the measuring technique has been improved,
the need for the reproducibility and traceability of the test results
has increased, because of the interest of manufacturers and
purchasers of high voltage equipment and because of the
introduction of EN 45001. The results of the evaluation of the
parameters should be person independent, it should not be possible
that the results are influenced by clients and one should be able to
calibrate the evaluation methods used,
digital recording instruments (digitizers and digital oscilloscopes)
have been introduced and nowadays the evaluation of the
parameters is mainly done by software. The software that
evaluates the parameters is used to save on the one hand time and
on the other hand to be sure that the evaluation of the parameters is
reproducible and traceable. A negative, but also positive side of
using software is that this software needs clear algorithms for the
evaluation of parameters. An advantage of using software for the
evaluation of parameters is that the engineering judgement and the
experience of engineers can be put into the computer (expert
systems) and that it permits a wider range of parameters than was
previously practical.
The three changes mentioned above, are the reason that the
requirements to the evaluation guidelines for standard lightning
impulse voltages have increased and that the need for evaluation
guidelines for non-standard lightning impulse voltages arose. They
are the reason that the problems with the interpretation of IEC 600601 have increased.
15
Lighting Impulses
2.4.6
2.4.7
16
Lightning Impulses
2.4.7.1.1
Manufacturers laboratories
2.4.7.1.2
Testing laboratories
17
Lighting Impulses
2.4.7.1.3
Calibration laboratories
2.5
International work
In this paragraph the state of the art will be given of the international
work that is being carried out at this moment on the field of the
evaluation of parameters characterising lightning impulse voltages.
Basically there were two approaches, one approach tried to solve the
problems in the evaluation of the standard lightning impulse voltages
and the other one tried to solve the problems with the evaluation of
the non-standard lightning impulse voltages. The author introduced a
third one.
18
Lightning Impulses
voltages would be solved. The definition of the mathematical function
of the mean curve is however not so simple and people have
proposed also different solutions (see Chapter 2.6). Besides new
methods for calculating the mean curve also other methods like the
tolerance band have been introduced. The disadvantage of most of
the proposals explained in Chapter 2.6 is that these do not solve the
problem for non-standard lightning impulse voltages.
2.5.2 Current status of evaluation guidelines for nonstandard lightning impulse voltages
In September 1996 CIGRE WG33.03 and IEC SC 12 proposed to
formate a joint task force with SC 12. The objectives of this joint task
force are:
to set the parameters to be measured and the limits of uncertainty
which should be achieved
to develop and evaluate a Test Data Generator, similar to the one
used in IEC 1083-2, but for lightning impulse voltages that
represent those which can occur in transformer tests
preparation of a report from CIGRE 33.03 to IEC TC42, providing
technical basis for a new IEC publication
At the first meeting of the joint task force a start was made to list the
parameters which are considered to be either essential, or useful, to
determine the result of a test with lightning impulse voltages on a
transformer (see Chapter 2.6). The consideration of these parameters
was based on the breakdown processes due to the effect of the applied
lightning impulse voltage. It was taken into account that the use of
digital recorders and the processing facilities now available permits
the measurement of a wider range of parameters than has been
practical before [16].
This proposal has been discussed in the relevant committees and a
Test Data Generator is being made. The join task force has been set
on hold, because it was found best to wait for the results from the
European research project, that is discussed in the next paragraph.
2.5.3
According to the author the two approaches were too much based on
mathematical models and assumptions. When maintaining these two
approaches a solution or two solutions that would be accepted by the
many parties would never be found. To solve the problems with the
evaluation for both standard and non-standard lightning impulse
voltages as discussed in CIGRE WG 33.03 and the joint taskforce
TC12/WG33.03, the relevancy of the parameters had to be proven.
This required research. Therefore the author, as an employee of
KEMA Nederland BV, initiated to propose, together with FFII/LCOE,
the Schering Institute and NGC, to the European community DG XII
in the SMT fourth framework, a research project. The title of this
project is Digital measurement of parameters used for lightning
impulse test for high voltage equipment. The project has started at
January 1 1997 and the author was the project leader and thought
about what to do in the project. The duration of the project was two
and a half years.
19
Lighting Impulses
The aim of this project was to:
define one or more sets of parameters to characterise lightning
impulse voltages
write a report in which the relevancy of the proposed parameters
are explained
establish unambiguous algorithms to calculate these parameters
write a proposal for the relevant parts of IEC 60060-1 and
IEC 61083-2
At KEMA the author was responsible for carrying out the work, she
was the supervisor of the students involved in the project, built the
test set-up together with M. Kvarngren and carried out most of the
investigations and tests herself.
Besides the work performed in the framework of this European
project, more work has been performed. The author made an
additional literature investigation and was responsible for and
evaluated the measurement results of the investigations on paper-oil
samples provided by Siemens made at TU-Graz.
All the work explained before in this paragraph is presented in this
thesis.
2.6
2.6.1
20
Lightning Impulses
2.6.1.1.1
U mc p1 t p2 t p3 t p4
3
2.6.1.1.2
U mc A e t e t
Digital filtering
There are two methods of digital filtering which have been applied for
the evaluation of parameters of impulses:
moving window filtering [32], [33]
low pass FIR filtering [34]
2.6.1.1.3
F U m i U c i
i 1
Before analysing the R(t) it is clear that the best reference mean curve
should be chosen, preferably by a mathematical procedure.
There are several methods for determining the best RMC (reference
mean curve), this is to minimise the:
absolute mean value of the residual curve within a specific time
interval (MP)
root mean square of the residual curve within a specific time
interval (RMSP)
least mean square error between the measured impulse and the
RMC (LMS), see Equation XIII [29]
Also generetic algorithm models have been used to select the
reference mean curve [35].
U mc A e t e t B 1 cost e t C sint e t
21
Lighting Impulses
peak value.
2.6.2
Other methods
22
Lightning Impulses
Figure 14 Tolerance band for a 1,2/50 lightning impulse voltage (on the left the zoom of the full tolerance band on the right)
calculated with a computer and requires less computing time than the
calculation of reference mean curves.
2.6.3
Conclusions
The present rules indicated in IEC 60060-1 are insufficient and many
different interpretations are possible. In addition, very high accuracy
is required for the present definition and for the set of the limit of the
overshoot or oscillation. Therefore there are two possibilities, either
to give better and more useful definitions of the parameters of interest
or to completely change the approach [17]. In case of the first option
better and clearer requirements should be included in the standard to
determine the parameters of an impulse. But independent of the
method chosen, more extensive discussion and experimental evidence
is needed to establish the requirements for the evaluation of
parameters characterising lightning impulse voltages to be included in
the revision of IEC 60060-1.
23
Lighting Impulses
24
Breakdown
Introduction
Before the goal of the investigations will be explained and the tests
performed and their results will be described, a theoretical
investigation towards the disruptive discharge behaviour of insulating
systems, or better materials, will be presented.
Disruptive discharges (also called breakdowns) are phenomena
associated with the failure of insulation under electrical stress, in
which the discharge completely bridges the insulation under test,
reducing the voltage between the electrodes practically to zero. It
applies to electrical breakdowns in solid, liquid and gaseous
dielectrics and combinations of these. The theoretical investigation
was also focussed mainly on the influence of the wave shape of a
lightning impulse to the discharge. At the end of this chapter
attention is paid to statistical techniques used when performing
breakdown tests.
3.2
3.2.1
Insulation systems
General
3.2.2
Transformers
Breakdown
Particularly in the region of the windings, strong electric fields occur
in transformers, were high temperatures and short-circuit forces can
also act simultaneously.
26
Breakdown
The goal of this investigation was to
find a method to transfer the
breakdown behaviour under standard
lightning impulse conditions to that
under restriking surge (Figure 17) and
intruding lightning surge voltages (Figure 18) as are occurring in
modern substations.
The result of this investigation was that the following method could
be used. Determine the time to peak (of the first peak) and the peak
voltage of the wave shape that occurs. In case of Figure 17 this would
be 0,42 s and 1129 kV. From the results presented in Figure 19 it
follows that the transfer factor is 1,27. This implies that the stress
caused by the surge presented in Figure 17 is equal to the stress
caused by a standard impulse with an amplitude of
1129/1,27 = 889 kV.
3.3
3.3.1
Gases
Avalanche
Figure 20 Electron
homogeneous field
avalanche
in
27
Breakdown
For a sufficient long mean free path and appropriate field strength,
electrons can, in collision with other neutral molecules, have such a
large kinetic energy W, that the molecule is ionised with the release
of further electron. If the ionisation condition (E Wi/e) is fulfilled,
an independent multiplication process of the electrons by collision
ionisation sets in. This exponential increase of the electron number is
called an electron avalanche [41]. At the head of the avalanche the
electrons may be very densely packed. Behind the head of the
avalanche the positive ions remain, see Figure 20.
3.3.1.2.1
Townsend Mechanism
3.3.1.2.2
Streamer Mechanism
28
Breakdown
The transition of a discharge from Townsend growth to streamer
growth can, for a given spacing, be promoted by several parameters
such as the product of pressure and gap distance, high field strengths
caused by steep fronted impulses, density of the gas, inhomogenity of
the field, ionising radiation [38].
A schematic description of the formation of a streamer is shown in
Figure 22 and Figure 23. In Figure 22 the following is illustrated: A:
and external photon triggers an avalanche, B: a positive ion strikes the
cathode and starts an avalanche C. D: the avalanche tip reaches the
anode. E: photons originating from the avalanche produce free
electrons both from the cathode and in the gas. F: the positive space
charge close to the anode increases the geometrical electrical field
and a streamer is bound to be formed. The sequence is followed in
Figure 23. G: plasma of positive ions and electrons forms the streamer
channel. H: streamer tip. I: production of free electron by photons, J:
streamer close to the cathode [40].
3.3.1.2.3
Leader
3.3.2
Liquids
29
Breakdown
As a consequence of this there is no unified breakdown theory,
although certain mechanisms are beyond doubt. [41] Two of the most
important types, the intrinsic breakdown and the breakdown by fibrebridging, will be described.
30
Breakdown
comparatively lower voltages, can be described as local thermal
breakdown at a defect. This mechanism is of such great technical
significance that in electrode arrangements for high voltages pure oil
sections have to be avoided. This is achieved by introducing
insulating screens perpendicular to the direction of the field strength.
In the extreme case consistent application of this principle leads to
oil-impregnated paper insulation, which is the most important at very
highly stressable dielectric for cables, capacitor and transformers.
[38]
3.3.3
Solids
31
Breakdown
curves of the input and output power exists. Point A represent a
stable working condition and point B, on the other hand, is unstable.
If the voltage is increased at a constant ambient temperature u, both
point of intersection move closer until, at U=Uk, they coincide in C.
This voltage is referred to as the critical voltage; or above Uk a stable
condition is impossible. [38].
3.3.4
Vacuum
32
Breakdown
33
Breakdown
3.4 Influence
breakdown
of
lightning
impulse
voltage
to
the
3.4.1
Gases
The literature has been investigated with the goal finding as much
information as possible about breakdown behaviour under lightning
impulses in general for all types as gases. Especially for air and SF6 a
literature study has been performed towards the effect of polarity
and wave shape.
Many thanks to LCOE, Fernando Garnacho and Pascual Simon, who have
contributed to the results presented here
34
Breakdown
For the calculation of the voltage-time curves, the equal area criterion
[48] has proven to be a useful assumption in many cases.
For weakly inhomogeneous fields, the reference voltage (Ud in
Figure 32, Ub in Figure 33) becomes equal to the inception voltage Ue.
If the reference voltage is known, the equal area criterion, therefore
permits an approximate calculation of the impulse voltage-time curve
of an electrode configuration for a few measured values.
Effect of polarity
For SF6; plate-plate, rod-plate and for needle plate configurations, the
breakdown voltage for negative lightning impulse voltage is higher
than the breakdown voltage for positive lightning impulse voltage (in
case of the rod-plate configuration and the needle-plate configuration,
the high voltage is applied to the rod) [50], [51].
Also for switching impulses and a non-uniform field, the breakdown
voltage is for negative impulses higher than for positive [51].
35
Breakdown
breakdown voltage as for a standard 1,2/50 impulse. In all cases the
damping of the oscillating wave was around 40%.
3.4.2
36
Breakdown
Effect of polarity
For oil, the breakdown voltage in a strong non-uniform field is for
positive oscillating waves lower than for negative oscillating waves
[56]
3.4.3
Solids
Many thanks to the Schering Institute Hannover, Peter Werle, Klaus Hackemack
and Ernst Gockenbach who performed this study.
37
Breakdown
2,3 s and the time to half value T2 from 6 s to 95 s does not
influence the tree inception voltage, which is similar for other solid
insulation materials like e. g. ceramic [65, 66 and 67].
The conclusion of the literature investigations about research
concerning the breakdown strength of polyethylene under lightning
impulse stresses allow the statements given in the next three
paragraphs concerning the main parameters of a breakdown test.
Maximum voltage
The maximum voltage of the lightning impulses is a decisive
parameter. For rising temperatures or different environmental test
conditions the maximum voltage of a lightning impulse that a
polyethylene specimen is able to withstand can be reduced.
About the influence of superimposed oscillations or overshoots at the
lightning impulse on the breakdown behaviour of polyethylene no
information is available. However, the investigations indicate that the
breakdown process depends like for other solid materials on the lifetime-law, which describes an exponential relation between the
breakdown strength and the time of the applied voltage stress.
3.4.4
Vacuum
Effect of polarity
For vacuum the negative impulse has a lower breakdown voltage than
the positive impulse. The difference between the breakdown voltage
for negative and positive impulses is larger for a lightning impulse
voltage than for a switching impulse. The difference between the
breakdown voltage for positive and negative impulses is also a
function of the gap distance. For a smaller gap distance the difference
is smaller. [68]
Effect of waveshape
In [69] breakdown voltage values are reported for different wave
shapes for a stainless steel hemispherical electrode configuration. A
summary of the results is presented in Table 2.
38
Breakdown
F ( x) P( x x)
f (t )dt
T1/T2
1,2/50 s
250/450 s
0,75/4,5 ms
1/4,5 ms
2,6/15 ms
3,6/15 ms
2,0 mm gap
80 kV
70 kV
80 kV
95 kV
150 kV
150 kV
1,5 mm gap
75 kV
65 kV
70 kV
80 kV
140 kV
120 kV
1,0 mm gap
45 kV
45 kV
45 kV
45 kV
80 kV
105 kV
0,5 mm gap
20 kV
20 kV
20 kV
20 kV
3.5
3.5.1
39
Breakdown
If n identical samples will be subjected to a certain voltage stress, the
number of breakdowns nd will depend upon the voltage magnitude U.
The observed breakdown probability (P) nd/n is a function of U as
shown in Figure 35. Ud-0 or U0 is the withstand voltage. Ud-50 or U50 is
the 50% breakdown voltage, Ud-100 or U100 is the assured breakdown
voltage.
In technical set-ups in general the distribution function P(U) is not
known, but experience showed that the actual distributions, in case of
medium probabilities, are very well approximated by a normal
distribution function. For very small probabilities, the Weibull
distribution function has proven to be good.
The distribution function P(U) is often referred to as F(x). The
distribution function at a point x, indicates the probability with which
the variate X will assume a value below the boundary x. The
distribution function of continuous variates can be represented in the
form as given in Equation XV.
The normal distribution function and density function are given by the
formulas presented in Equation XVI and Equation XVII. In Figure 36
the normal distribution is presented in a graphical way.
3.5.2
f ( x)
Application
d
F ( x)
dx
( x; ; 2 )
e ( x )
/ 2 2
( x; ; )
2
1
2
(t )
e
2 / 2 2
dt
40
Breakdown
3.5.3
Independence
41
Goal of investigations
4 Goal of investigations
In Chapter 2 of this thesis, lightning impulse tests, applicable
standards, their interpretation and implementation have been
described in detail. In Chapter 3 of this thesis, the breakdown process
in materials and statistical techniques to be used when performing
breakdown tests have been explained in detail. In this Chapter the
goal of the investigations, the insulating systems and the materials to
be investigated will be described. At the end of this Chapter, some
research questions and hypothesis are formulated.
4.1
Introduction
Goal of investigations
voltage with a good accuracy. Precisely for these cases where nonstandard lightning impulse voltages occur, no evaluation rules are
given. Most of the time these measurements are carried out by
experienced engineers, who use engineering judgement to evaluate
the lightning impulse voltages. However two engineers may obtain
different measurement results. This assumption is being supported by
a questionnaire made amongst different laboratories. The result of
this questionnaire was quit surprising, many laboratories do not only
use very different evaluation methods, but also methods quit far from
the present standards (see Chapter 2.4.7).
Not only in the case of lightning impulse voltages with large
superimposed oscillations and/or overshoot differences between the
measurement results may occur even when using evaluation methods
according to present standards. Results of round-robin tests showed
that even large differences (up to 2% for full and 7% for chopped
impulses) occur when lightning impulse voltages with small
overshoot and/or oscillations are evaluated.
Up to now, several evaluation methods have been proposed, but as
may have become clear, no satisfactory solution has been found.
4.1.2
4.1.3
44
Goal of investigations
overshoot could be seen, discussing took place between the test
engineers to draw the best mean curve.
Nowadays the measurement of lightning impulse voltages is mostly
performed using digital oscilloscopes and measuring systems with a
higher bandwidth. Because of this, small overshoot and oscillations
can easily be made visible. The evaluation of the parameters is
mostly done using computer programs, that have difficulties with the
implementation of evaluation rules made for manual evaluation, since
they need more precise instructions. Because of that in some cases
still a manual evaluation is used. The advantage of using computer
programs for the evaluation of parameters is that on the one hand
more parameters can be evaluated than were previously practical or
possible and on the other hand that the evaluation is performed more
uniformly.
The developments in the measuring technique have made it possible
to measure with more accuracy and so the requirements towards the
accuracy have increased.
Intercomparisons and questionnaires
however showed that the present evaluation rules are ambiguous,
causing large differences in the obtained measurement results. It
seems right now that the hardware is good enough for the nowadays
required accuracy, but that the software or evaluation methods are the
major contribution to the measurement uncertainty.
Some blame the computers and digital recorders for the problems
occurring nowadays, but the problems are not new. The introduction
of digital recorders and computers made it only possible to see and to
recognise the problems.
4.2
45
Goal of investigations
4.3
4.4
46
Goal of investigations
Right now, there are two problems with the evaluation of lighting
impulse parameters:
In the standard for some cases a mean curve has to be drawn for
the evaluation of the peak value.
Cable and transformer manufacturers do not agree that the peak
value of this mean curve is a relevant parameter. They claim that
the absolute peak value is a more relevant parameter.
Therefore the major problem is nowadays the definition and the
validity of the mean curve in case oscillations and overshoot occur.
For the international acceptance, one has to prove first whether a
mean curve is really relevant. Perhaps there are also other parameters
that are more relevant. When the present peak value of the mean
curve is proven to be a relevant parameter, then it is appropriate to
look into ways to define this parameter without having to draw a
mean curve. This is because it seems not to be possible to define a
mean curve which is valid for all lightning impulse voltage that occur
during testing of high voltage equipment.
As a way to prove which parameters are relevant and which are not,
breakdown tests and the determination of the U50% were chosen. A
list of parameters that were thought or assumed to be relevant was
made, see Chapter 5.3.5. In order to be able to prove whether the
mean curve is relevant, lightning impulse voltages with oscillations
and overshoot of different frequencies and amplitudes superimposed
have to be applied. Above all the wave shapes generated should
cover the wave shapes that occur during actual testing of
transformers.
There are several ways to design a generating circuit in which these
wave shapes can be generated. One of the important criteria is, that in
case different amplitudes or frequencies are applied the mean curve is
not varied. The only circuit for which this was possible is the circuit
described in Chapter 5.2.2, it is the generating circuit that consists out
of two generating circuits. One circuit generates the standard
lightning impulse voltage and the other generates the oscillations or
overshoot. This circuit has many advantages, one disadvantage might
be that the circuit has some influence to the result, so this should be
checked first
Since oil and oil paper are the insulating materials used, attention
should be paid to the statistical spread in the measuring results, due to
the properties of oil and oil-paper. This means that sufficient checks
and comparison measurements have to be made.
Detailed attention to the generating circuit, the test cell, the measuring
circuit and to the experimental parameters will be paid in Chapter 5 of
this thesis.
4.5
Goal of investigations
either homogeneous or inhomogeneous. One has to consider the
voltage distribution in a complex insulating system such as a
transformer in case a lightning impulse voltage is applied.
What at least will be done is to check the hypothesis on samples that
are representing some typical parts of transformers.
4.6
Questions/hypothesis
48
Introduction
The goal of this work is to find parameters and clear evaluation rules
that are applicable to both standard and non-standard lightning
impulse voltages, taking into account the possibilities and limitations
of modern computers.
The goal of the theoretical and experimental investigations is to prove
that the parameters chosen are of physical relevance for different
types of practical insulating systems in case lightning impul7se
voltages are applied. In previous Chapters the results of theoretical
investigations have been presented. The result of this theoretical
investigation was that experimental investigations were necessary.
49
1
2 LC
5.2.1
5.2.1.1 Principle
The principle of the generating circuit based on a conventional
generator, called the modified conventional circuit, is shown in Figure
38. For this conventional circuit, simulations have been made to
dimension the components for the different lightning impulse voltage
to be generated. The circuit has been built and impulses have been
generated. The results are explained in detail in [73 and 74] and
summarised in this paragraph.
Rs
Cs2
Rf
Object Divider
Rp
Cp
Cs1
Trigger circuit
Computer, digitizer
and attenuator
By varying the front resistor Rf, the front time will mainly be varied.
A smaller front resistance will result in a smaller front time. By
varying the parallel resistor, Rp, the time to half value will mainly be
varied. By increasing the parallel resistance the time to half value
will increase.
The frequency of the oscillations or the duration of an overshoot can
be varied by varying the inductance and the capacitance, because in
general this frequency in given by Equation XVIII.
50
5.2.2
5.2.2.1 Principle
One of the most important requirements for the generating circuit is
that the mean curve does not change when oscillations and
overshoot are generated and that oscillations of different frequencies
and amplitudes can easily be generated. Since the influences of the
oscillations and overshoot are expected to be small, one has to be
absolutely certain that the differences in measuring results are not
caused by the differences in mean curves. Therefore the generating
circuit shown in Figure 43 was designed (combined generating
circuits). Generator 1 generates the full lightning impulse voltage and
generator 2 generates the overshoots or oscillations. At the object the
two voltages are superimposed to each other.
By varying the resistors in generator 1, Rp and Rf, the front time and
the time to half value of the lightning impulse voltage can be varied.
By varying the inductance Ls and the resistor Rd of generator 2,
Generator 1, lightning impulse
Divider 1
Rf
Cs
Rp
Cp
Test cell
Ampl. 1
Atten. 1
Trigger box
Digital
Oscilloscope
Computer
Atten. 2
Ampl. 2
Ls
Rd
Divider 2
51
52
Zobject
Zg1
Zg2
The result of these five measurements performed was that the average
U50 was -42,95 kV. All results were within 0,2% of that average. In
addition to this no influence on the time to breakdown could be
detected.
Therefore, the conclusion is that using the combined generating
circuits instead of the modified conventional circuit has no influence
on the results of the breakdown tests.
5.3 Test set-up and test method used for the tests at
KEMA
5.3.1
Generating circuit
Z object Z g1
Z onject Z g 2
Equation XIX requirements to be met for
minimum influence between the two
generating circuits
The generating circuit used for the breakdown testing of oil and air at
KEMA is the combined measuring circuit. In this paragraph the
circuit used, its design criteria, the test and simulations made and
some of the problems encountered are described in detail. Most of
the work was performed by the author, but she was assisted by others.
54
55
56
5.3.2
Trigger delay
5.3.3
Test cell
The test cell was designed for performing breakdown tests on the
insulating materials, oil and air (at normal pressure or below).
57
58
59
To be able to replace the electrodes and fix them in the test cell, the
body of the electrodes is made of brass. The effective surface of the
electrode (about 1 cm in diameter) had been replaced by a tungsten
inlay because of severe surface deformation of the brass caused by
breakdowns. To check how large the surface deformation of the
tungsten inlay would be a number of breakdowns (around 100) have
been applied to the electrodes. From both the visual check with the
aid of a microscope, see also Figure 57, and the results of the
measurements it can be concluded that the deformation of the
tungsten can be neglected.
60
5.3.3.2.1
Air
During the test with air, the pressure, the humidity, the temperature
and the availability of free electrons have influence on the test results.
Therefore these factors should be maintained constant or known.
Also the test cell should fulfil the criteria of IEC 60052 [75]. It
should be possible to place a UV lamp so the gap can be radiated.
5.3.3.2.2
Oil
61
5.3.4
Measuring circuit
For measuring the applied voltage to the test cell that is generated by
the combined generating circuit, two Measuring Systems are
necessary. The Measuring System that measures the lightning
impulse is henceforth named MS1 and the Measuring System that
measures the superimposed oscillations and overshoot is henceforth
named MS2. The applied voltage to the test cell is the difference of
the two measured voltages. The voltage measured with MS1
represents the base curve, the voltage measured with MS2
represents the residual curve R(t) in case the base curve is taken as
the mean curve.
5.3.4.1 Requirements
In principle both measuring should fulfil the requirement of
IEC 60060-2. This implies that the overall measurement uncertainty
should be within 3%. Besides the following requirements:
the cable length of the two measuring systems should be equal and
the time delay between the two measuring systems should be
checked.
the divider of MS2 should have protection in case of a breakdown
both measuring systems should not influence the generating circuit
MS1 should be an approved measuring system and should be able to
measure standard full lightning impulse voltages and chopped
lightning impulse voltages with a maximum of 100 kV.
Figure 58 Photograph of the test cell
62
63
5.3.4.2.1
MS1
For MS1, one part of a mixed (RCR) divider for LI, SI, AC and DC
was taken. The original divider comprises of three HV-parts, when
used together (in series), the rated voltages of the complete divider are
1550 kV LI, 1175 kV SI, 343 kV DC and 220 kV AC.
Photo of the divider (one HV-part of the original) and its connection
to the test cell is shown in Figure 59.
Most difficult in the construction of this measuring system was to get
rid of the interference that was picked up at the bottom of the divider
and the tuning of the low voltage part. It appeared from measurement
that the scale factor of the measuring system was lower for higher
frequencies and therefor amplified the disturbances. By tuning the
low voltage part and to use two zener diodes (that were intentionally
meant to protect the inputs of the digitizer, but appeared to have a
bandwidth limit effect), the interference could be reduced with a
factor hundred to an acceptable level without disturbing its
capabilities of being able to measure standard LI, see Figure 60.
The dark line is the impulse measured using a filter, the gray line is
the impulse measured not using the filter. The topline is the difference
between them.
5.3.4.2.2
MS2
Ri
Vh
Vout
R
Cp
Ci
Vout
RC
Vh
Ri Ci
64
Resistive divider
Because of the requirements to the bandwidth (at least 35 MHz) and
the value of the estimated parasitic capacitance, the resistance of the
divider should be in the range of 5 k. The resistances should be low
inductive. After some investigations it turned out that the optimal
design and construction for the divider is the one that is shown in
Figure 63. Before the construction and the design of this divider was
as it is shown in this figure, a lot of investigations and measurements
were carried out. It appeared that very small things had major
influence on the frequency characteristic and the measurement itself,
e.g. type of coaxial cable, aluminium tape placed on the corners of the
test cell. Also there was a difference between the values obtained by
using a spectrum analyser to establish the frequency characteristic and
the values obtained by using a sinusoidal wave shape generator. But
in both cases the divider appeared to meet the requirements.
A photograph of the divider is shown in Figure 64.
5.3.4.2.3
Digitizer
The digitizer used is a Nicolet Power Pro 610, see Figure 75. MS1 is
connected to Channel 1 of the digitizer. MS2 is connected to Channel
2 of the digitizer. The digitizer has a bandwidth of 35 MHz and a
minimum sampling time of 13,3 ns per sample. To reduce
interference to the digitizer and the low voltage part an EMC-screen
was built, see Figure 75.
65
Nominal Epoch
Up: 100 kV 500 kV
T1: 0,8 s 2,5 s
Scale factor
F = 15580
Overall Measuring Uncertainty
LI 0,84/50 Up:0,93%, T1:6,7%, T2:2,3%
LI 5/50
Up:0,93%, T1:1,6%, T2:2,0%
Last Performance Test
PTB 07-02-1996
Details of divider
Manufacturer
Type
Resistance HV arm 5 k
Resistance LV arm
Damping resistor
5.3.4.3.1
Calibration of MS1
Scale factor
Haefely
R500 REF
19,1
400
First, the scale factor has been measured using DC on 7 July 1998.
The scale factor was according to that measurement 19526. For
linearity tests and the comparison measurement, the scale factor was
set to 19530. A comparison measurement against LIR 1 was carried
out on 18 January 1999 at 96 kV. The result was that the scale factor
was 19950 for 100 kV positive polarity. The measurement uncertainty
of this calibration was 0,94%. From the linearity measurements it
appeared that the best scale factor would be 20060. This value was
used for all breakdown tests performed later.
Linearity
A linearity test of MS1 in comparison with LIR 1 was performed for a
voltage level of 2,5 kV up to 96 kV. The result of this linearity test is
presented in Figure 65. The contribution to the measurement
uncertainty caused by the non-linearity is 0,921%.
Dynamic behaviour
The dynamic behaviour of the measuring system was checked by
measuring the rise-time by applying a high voltage step (rise time of
2,5 ns) and by measuring the scale factor in a frequency range 50 kHz
to 20 MHz when a sinusoidal wave of 10 Volt amplitude.
A photograph of the latter measurement in presented in Figure 69.
The results of the latter test are presented in Figure 66. The error
caused by the dynamic behaviour of the measuring system in the
range of 50 kHz to 0,7 MHz, i.e. for time parameters from 5 s to 0,5
s is 1,5%.
1,1
1,05
0,95
0,9
0,85
0,8
0,75
0,7
10,0E+3
66
100,0E+3
1,0E+6
Frequency [Hz]
10,0E+6
100,0E+6
Scalefactor [1]
100,0E+3
1,0E+6
10,0E+6
100,0E+6
Frequency [Hz]
Interference
Investigations performed demonstrated that the most important
contribution to the interference to MS1 is the triggering of the spark
gaps and is picked up by the low voltage part of the divider. The
interference caused by the measuring cable itself is negligible.
In case a 5,8 kV oscillation of frequency 2 MHz is generated, the
MS1 measures a voltage of 56,9 mV. When multiplied with a scale
factor of 20060 this equals to 1,14 kV. In relation to the expected 70
kV LI, this means that the interference is 1,6 %. (see Figure 67)
In addition to this measurement, also a simultaneous measurement
(MS1 and MS2) was performed while applying a lightning impulse
voltage. The amplitude of the interference is in the same range as the
previous measurement (see Figure 68). The applied voltage is 12,5
kV.
67
5.3.4.3.2
Calibration of MS2
Scale factor
First, the scale factor has been measured using DC on 7 July 1998.
The scale factor was according to that measurement 3077. For the
linearity test and the comparison measurement, the scale factor was
set to 3040. A comparison measurement against LIR 1 was carried out
on 18 January 1999 at 19 kV. The result was that the scale factor was
2996 for 19 kV negative polarity. The measurement uncertainty of
this calibration was 0,94%. From the linearity test it appeared that the
scale factor of 3040 was a good scale factor.
2,0%
1,5%
1,0%
Error
0,5%
0,0%
-0,5%
-1,0%
Positive polarity
Negative polarity
-1,5%
0
10
12
14
16
18
20
Voltage [kV]
Linearity
A linearity test of MS2 in comparison with LIR 1 was performed for a
voltage level of 2,5 kV up to 19 kV. The result of this linearity test is
presented in Figure 70. The contribution to the measurement
uncertainty caused by the non-linearity is 1,62%.
Dynamic behaviour
Figure
71
Dynamic
behaviour
measurements using a spectrum analyser
68
1,05
0,95
0,9
0,85
0,8
0,75
0,7
10,0E+3
100,0E+3
1,0E+6
10,0E+6
100,0E+6
Frequency [Hz]
Interference
For MS2, also three interference measurements have been performed
(interference on the measuring cable, interference caused by generator
1 and interference caused by generator 2). The interference caused by
the trigger of the gap when applying a standard impulse was the
largest. The measuring system measured 12 mV (see Figure 68). The
oscillations to be measured will be between 4 and 14 kV, therefore
the interference is maximum 0,9%.
Short-term stability
To establish the short-term stability of MS2, 60 1,2/50 impulses of
19 kV with a time interval of approximately half a minute were
applied to MS2. Simultaneous readings were take of LIR1 and MS2.
The results are presented in Figure 73. The average scale factor of
the 60 applied impulses is 0,9872. The maximum and minimum scale
of the graph is this value with respectively +1% and 1%. From the
figure it can be seen that the short term stability of MS2 is well within
the required limits. The average scale factor of the first 10 impulses
is 0,9866 the average scale factor of the last 10 impulses is 0,9883
this means that the uncertainty contribution of the short term-stability
is 0,09%. At the same time the uncertainty of the short-term stability
for the time parameters was determined, for T1 this was 0,27% and for
T2 this was 2,15%.
0,9972
0,9947
scale factor
0,9922
0,9897
0,9872
0,9847
0,9822
0,9797
0,9772
1
11
16
21
26
31
36
number of impulses
41
46
51
56
69
70
5.3.4.6.1
MS 1
With:
a1 =
a2 =
a3 =
a4 =
a5 =
a6 =
a7 =
a8 =
a9 =
sr =
Uk =
0,55%
0,92%
estimated: 0,1%
estimated: 0,2%
estimated: 0,1%
no effect: 0%
1,5%
1,6%
0,4%
0,15%
0,94% for k=2
U k
sr
1 2
U ts
Rn R x2 k r
3
k k n
Fm
n 1
Therefore, the measurement uncertainty for k=2, B=95% for MS1 for
one measurement is 3,1%.
U k
5.3.4.6.2
MS2
U
1
ai2 i
3
ki
t sr
With:
a1 =
a2 =
a3 =
a4 =
a5 =
a6 =
a7 =
a8 =
a9 =
sr =
Uk =
1,47%
1,62%
0,09%
estimated: 0,2%
estimated: 0,1%
no effect: 0%
0,7%
0,9%
0,4%
0,066%
0,94% for k=2
The measurement uncertainty for k=2, B=95% for MS2 for one
measurement is 3,1%
71
5.3.5
computer
and
72
2.
73
With some of the measurement series (in oil and in air) it has been
investigated which distribution showed the best results. In most cases
in air the Weibull and the normal distribution function showed similar
and good result. In most cases for oil, the normal distribution showed
good results. To make sure that the difference between the test results
in the work at KEMA and within the European project was not
influenced by the difference in distribution function, one distribution
function had to be chosen. Therefore, in all cases in this thesis and in
the European project a normal distribution function is chosen for the
approximation function.
5.3.6
45,6122
U50 in [kV]
45,5122
If the voltage is set to a certain value 10 times, eg. 41,7 kV, the
average of these 10 voltages was 41,6758, the maximum voltage
differed 0,12%, the minimum voltage 0,16% from this value.
45,4122
45,3122
45,2122
45,1122
45,0122
990119 990120-2 990121-2 990205-1 990205-3 990208-2
Measurement number
74
5.3.7
After the generating circuit, the test cell, the measuring systems and
the evaluation methods have been explained, the test method and the
test procedure of the breakdown tests will be explained.
It appeared that after all problems associated with the generating
circuit, the measuring systems and the software had been solved,
finding a suitable and reliable test procedure was more difficult than
expected. The results of the several investigations made are not
presented in this thesis, only the procedure finally chosen is explained
here.
Test method
From the many investigations performed towards the best test method
for oil, it could be concluded that the best suitable and most reliable
and independent method was the multiple level test for establishing
the U50. Because of the limitations of the test set-up it was not always
possible to have 6 levels, but only 5 levels (one with all breakdown,
one with all withstands and three with withstands and breakdowns)
with equal intervals can be obtained. Each level consists of at least
10 shots.
5.3.7.2.2
Test procedure
75
5.3.7.2.3
As mentioned before, for each test series fresh and conditioned oil
will be used.
Because at KEMA no treatment unit for oil was available the fresh oil
is take from a barrel of new oil and it is not regenerated. After the oil
was used for one test series, it was removed from the test cell and
discarded.
The conditioning of the oil comprises of the following steps:
1. filling the test cell with oil
2. conditioning of the oil before starting the test series
3. conditioning of the oil during the test series
76
When there is enough oil in the vessel, the valves to the barrel will be
closed and the test vessel will be pumped vacuum, so that the air
inside the oil gets out. After this, the oil is being circulated, for some
time by the pumping system, and it is again pumped vacuum. This is
repeated for two times.
2. every time the pump starts, you might get some small air bubbles,
to prevent these air bubbles, the pumping is continuously
3. to get rid of the charges in the oil. For this the oil is pumped
through a hose containing three ring electrodes. The outer ones
are on earth potential, the middle on 30 V DC, see Figure 81
(Investigations pointed out that 1 kV DC was decreasing the
properties of the oil, AC voltage was equally worse. If 30 V DC is the
optimum, we do not know since we are not making investigations to
this and the 30 V DC gave very stable values)
Standard deviation
Because of several physical reasons, the standard deviation in the
obtained results is around 4 kV for a breakdown voltage of 70 kV
(around 5%). For the purpose of this project it is rather large, but
comparing the results to values heard from other institutions
performing breakdown tests in oil (around 20%), it is rather low.
77
5.3.8
Conclusions
5.4
5.4.1
78
Cs in nF
Re in
Rd in
Ld in H
Cb in nF
a) Standard
Impulse
35
400
375
b) Overshoot
1,4 s
35
400
300
165
c) 200 kHz
Oscillations
35
400
41
13,6
d) 1000 kHz
Oscillations
35
400
50
78
0,24
e) Damped
sine wave 200
kHz
35
400
2,5
5,6
5.4.2
Test vessel
79
5.4.3
Samples
5.4.4
Since the samples consist of, amongst others, paper material it is very
important that the paper contains as less as possible moisture, since
this has a effect on the breakdown behaviour. It is also very important
that each sample is of the same quality. If this is not the case, it will
be almost impossible to evaluate the results because of the wide
spread in the results.
Figure 87 The samples
To reduce the moisture, the samples were dried under vacuum, 1 mbar
at 105C (2C) for 24 hours. After the samples are dried, they were
places in oil for 24 hours. After that this process was completed the
tests were started.
To find the breakdown voltage the progressive stress method was
used with 3 shots at the same level. For each test series at least 10
samples were used.
The tests were started at 85% of the U20 (20% breakdown voltage)
and the voltage was raised in steps of 5% until breakdown occurred.
After each shot 2-3 minutes was waited before the next impulse was
applied.
5.4.5
For the tests performed at TU-Graz, the same digitizer and evaluation
software was used as that used at KEMA. Also for the evaluation of
the U20, the same software was used as that one used at KEMA.
80
Introduction
In the previous chapter the test set-up, the test methods and test
procedure used at KEMA and TU Graz are explained in detail. In this
chapter the results of the investigations performed at KEMA and at
TUG are explained. The results of the investigations performed by
the other partners in the European project, Schering Institute, LCOE
and NGC, are explained as well. The author was the project-leader
and initiator of the European project, performed the measurements at
KEMA and evaluated the results performed at TU-Graz.
6.2
Test to be performed
Before the breakdown tests were started at the different location, took
place on which test should be performed. Redundant tests should be
prevented, but on the other hand there were a lot of research questions
that had to be solved. In this paragraph the test that were intended to
be performed are explained. Of course, like in every other research
project, on the road, some more or some fewer tests are performed,
since the information available from the tests already performed
changes the view and the number of open questions.
81
New parameters
Another assignment in this project is to investigate totally new
parameters. In case that one finds out that the present parameters are
either not relevant or too difficult to implement one does not have to
perform all test over again, since one has the data already available.
Therefore it was also agreed upon that all test data should be stored
digitally so that post processing was possible.
Overshoot
duration
1,2/50
200 kHz
0,625 s
20%
on the peak
1,56/50
500 kHz
1 s
10%
on the front
1,84/50
800 kHz
2,5s
5%
1,56/40
2 MHz
5 s
0,84/40
5 MHz
83
6.3
Kt k1 k2
Equation XXIII atmospheric correction
factor
The measured disruptive discharge
voltages U are corrected to U0
corresponding to the standard reference
atmosphere by dividing by Kt:
6.3.1
U0 U / Kt
k1 m
b 273 t0
b0 273 t
Equation XXV
humidity correction factor k2
k2 k w
Equation XXVI
84
Up(RMC),50 in [kV]
-41,5
-42
-42,5
-43
-43,5
-44
-44,5
0
45,61
U50 in [kV]
45,51
45,41
45,31
45,21
45,11
45,01
990119
85
48,0
U50 in [kV]
47,0
46,0
Up(RMC),50
45,0
Up,50
44,0
43,0
42,0
990120-1
990205-2
990208-1
Measurement number
6.3.2
86
6.3.3
Initial measurement
Two measurements carried out in March 1999, showed the following
results. The spheres used had a diameter of 150 mm and the distance
between the spheres was 35 mm. The T1 and T2 of the impulse were
1,19 s and 50,17 s. The frequency of the oscillation superimposed
was 2,14 MHz, its amplitude 9,76 kV and the delay was 2,46 s.
The Up(RMC),50 of the impulse with oscillations was 98,64 kV with a
standard deviation of 0,86 kV. The Up,50 of the impulse with
oscillation was 109,25 kV with a standard deviation of 1,27 kV.
Therefore the amplitude of the oscillations is 10%.
The Up(RMC),50 of the full impulse was 98,0 kV with a standard
deviation of 0,62 kV.
The conclusion of this measurement was that oscillations of
frequency 2,14 MHz, 10% amplitude and with a delay of 2,46 s have
no significant influence on the Up(RMC),50 (the influence is in the range
of the standard deviation).
Additional measurements
In order to study the influence of the trigger delay on the Up(RMC),50,
the trigger delay has been changed between 1,2 s and 3s for an
impulse with superimposed oscillations of a fixed frequency (2 MHz)
and fixed amplitude (A1 = 10%). This study has been carried out for
the homogeneous field.
When the trigger delay, to, is inside the interval 1,2 s and 3,0 s the
breakdown voltage of the mean curve Up(RMC),50 decreases. The
highest decrease of around 3% was obtained for to = 2,3 s, see
Figure 91.
Figure 91 Influence of the trigger delay
towards the influence of superimposed
oscillations
87
Up(RMC),50/U1,2/50 [1]
1,01
1
0,99
0,98
0,97
1
1,5
2,5
6.3.4
88
6.4
The measurements in oil were carried out using the test set-up and
76
U50 in [kV]
74
72
70
68
66
64
62
0
0,5
1,5
2,5
89
Figure 92 Influence of the front time
towards the U50 of transformer oil.
80
U50 in [kV]
76
72
68
64
60
30
35
40
45
50
55
60
to 50 s.
90
Up(rmc), 50
76,2
Up,50
U50
74,2
72,2
70,2
R
68,2
B
66,2
M
64,2
1
91
Up,50 [kV]
75
70
65
60
50
250
450
650
850
1050
1250
1450
1650
1850
2050
80
Up(RMC)50 [kV]
75
70
65
60
55
50
250
450
650
850
1050
1250
1450
6.5
92
1650
1850
2050
93
120
110
U50 [kV]
100
90
80
70
50
0
0,5
1,5
2,5
T1 [us]
94
95
U50pk, A=5%
U50pk, A=10%
U50pk, A=20%
U50mc, A=5%
U50mc, A=10%
U50mc, A=20%
80
75
U50 [kV] 70
U50ref
U50ref-5%
U50ref+5%
65
60
55
0,1
1
Oscillation frequency [MHz]
10
110
U50pk, A=5%
U50pk, A=10%
100
U50pk, A=20%
U50mc, A=5%
90
U50mc, A=10%
U50 [kV]
U50mc, A=20%
80
U50ref
U50ref-5%
70
U50ref+5%
60
0,1
10
130
U50pk, A=5%
U50 [kV]
120
U50pk, A=10%
U50pk, A=20%
U50mc, A=5%
110
U50mc, A=10%
U50mc, A=20%
100
U50ref
U50ref-5%
90
U50ref+5%
80
0,1
10
96
The influence of the front time towards the 50% breakdown voltage
for PE is presented in Figure 104. Conclusions of these investigations
were that:
Front times T1 between 0,5 s and 1,56 s do not have a
significant influence on the breakdown behaviour of the tested PE
specimens.
The time to half value T2 is not a significant parameter for this
kind of test because almost all breakdowns in the tested PE
specimen occur at the front or at the peak.
175
U50%
150
125
100
0
0,5
1,5
T1
U50%
Upeak
200 kHz
kV
190
180
170
160
Upeak (mean curve)
150
0
10
15
Amplitude of oscillation
200
U50%
Upeak
800 kHz
kV
190
180
170
160
150
0
10
15
Amplitude of oscillation
frequencies used.
97
U50%
Upeak
2000 kHz
kV
190
180
170
160
150
0
10
15
Amplitude of oscillation
U50%
Upeak
Aosc= 5 %
kV
190
180
JB
170
J
J
U
(mean curve)
peak
160
150
0
98
200
400
600
800
U50%
Upeak
Aosc= 10 %
kV
190
180
B
JB
170
160
150
0
200
400
600
800
200
U50%
Upeak
Aosc= 15 %
kV
190
180
B
J
JB
170
Upeak (mean curve)
160
150
0
6.7
200
400
600
800
240
150
35
900
325
325
99
Tables and figures corresponding to the influence of the front time on the U p,50%
Homogeneous field.Positive Polarity
T1 ( s )
Up,50%(kV)
z (kV)
Up,50%(kV)
z (kV)
Up,50%(kV)
z (kV)
Up,50%(kV)
z (kV)
0,5
100,32
0,29
0,5
101,14
0,30
0,5
108,89
1,61
0,5
62,30
2,88
0,8
99,56
0,42
0,8
98,82
0,29
0,8
107,02
0,25
0,8
64,76
2,15
1,2
98,85
0,40
1,2
98,73
0,30
1,2
107,19
0,67
1,2
62,67
2,19
1,56
98,76
0,38
1,56
98,95
0,18
1,56
107,57
1,05
1,56
61,73
3,41
98,94
0,32
98,38
0,27
107,39
0,41
59,96
1,51
105
115
115
112,5
112,5
110
110
70
104
103
67,5
102
Up,50%(IEC52) = 98,5 kV
65
105
Up, 50%
107,5
Up,50
100
Up
107,5
Up,50
Up,50%(IEC52) = 98.0 kV
101
105
62,5
99
102,5
102,5
100
100
98
60
97
98,5
97,598.0
96
95
95
0,5
0,75
1,25 1,5
1,75
0,5
T1 ( s )
57,5
97,5
0,75
1,25
1,5
T1 ( s )
1,75
95
0,5
0,75
1,25
T1 ( s )
1,5
1,75
55
0,5
0,75
1,25
1,5
1,75
T1 ( s )
290
4
150
10
40
50
900
325
260
100
1,1
Up,50%
1,05
U50%
0,95
Up(RMC),50%
0,9
Positive Polarity
Negative Polarity Up
0,85
0,8
0
Positive Polarity
Negative Polarity Up(RMC)
0,5
1
1,5
2,5
3,5
4,5
f(MHz)
1,1
Up,50%
1,05
U50%
0,95
Up(RMC),50%
0,9
0,85
Up
Up(RMC)
0,8
0
0,5
1,5
2,5
3,5
4,5
f(MHz)
101
6.8
V( ud ) 1 m 1
Two different types of samples have been tested, Sample type A and
Sample type B. As explained in paragraph 5.4.4, the progressive
stress method is used and at each voltage level, three voltage
applications are done. As can be found in [72], if the test data is used
as input in the PSM statistical program it is not the U50 value that is
found, but the U20. That it is like that can be calculated with the
performance function in Equation XXVII. If the equations is known
for m=1, one can calculate by using this formula the equation for
m=3.
S (ud ) S (ud u )
1 S (ud u )
Sample type A
Sample type B
Up,20
SD
Up(RMC),20
SD
Up,20
SD
Up(RMC),20 SD
[kV]
[kV]
[kV]
[kV]
[kV]
[kV]
[kV]
[kV]
Standard impulse
-172,6
8,0
-172,6
8,0
-168,0
7,2
-168,0
7,2
-182,0
8,1
-151,4
6,6
-191,0
5,7
-149,5
4,4
-180,5
4,7
-112,0
3,2
-179,0
8,3
-111,9
5,3
-178,0
7,5
-152,2
6,7
-184,0
4,3
-158,1
3,4
-168,6
7,6
-173,6
10,3
102
6.9
6.9.1
6.9.2
Only for oil and PE, a conclusion can be drawn concerning the time to
half value.
For oil the conclusion is that no significant influence on the 50%
breakdown voltage can be detected when the time to half value is
varied from 40 s to 50 s.
For PE the time to half value T2 is not a significant parameter for this
kind of test because almost all breakdowns in the tested PE specimen
occur at the front or at the peak.
6.9.3
For the insulating materials oil, PE, SF6 and air it has been confirmed
that no difference can be detected between the influence of overshoot
and oscillations of corresponding frequency and duration.
Therefore all conclusions drawn concerning oscillations are also valid
for overshoot.
6.9.4
The position of the oscillations, i.e. on the peak or on the front has an
influence on the 50% breakdown value for air and for oil. The
influence increases when the position of the oscillations is closer to
the peak of the lightning impulse. Most relevant seems to be the
increase of the peak value of the curve with oscillations compared to
that without oscillations.
103
104
105
6.10.3 Evidence of the matching of the linearity and the kfactor statement
One of the ways to demonstrate that the two hypotheses are not
contradicting to each other is to use some mathematics.
From the k-factor hypothesis it follows that:
(1)R=Ut=k(A)+(1-k)B
(2)R=Ut=k(L)+(1-k)M
From the linearity hypothesis it follows that:
L
78,2
Up(rmc), 50
76,2
Up,50
U50
74,2
(3)A=x(L-R)+R
(4)B=x(M-R)+R
72,2
filling (3) and (4) in equation (1) gives the following result:
70,2
R
68,2
R=k(x(L-R)+R) +(1-k)(x(M-R)+R)
B
66,2
M
64,2
1
Or xR=x(k(L)+(1-k)M)
Measurement no.
This means that the two hypotheses are not contrary to each other.
Figure 116 Linearity statement and kfactor
Since both the k-factor and the linearity hypotheses are validated with
measurement results, it can be concluded that both hypotheses
correspond and are therefore correct.
This seems a very simple statement, but it is rather fundamental.
106
k-factor [1]
1,2
1
0,8
0,6
0,4
0,2
0
-0,2
10
100
1000
10000
107
k-factor [1]
10
100
1000
10000
k-factor [1]
1,2
1
0,8
0,6
0,4
0,2
0
-0,2
10
100
1000
10000
k-factor [1]
10
100
1000
108
10000
k-factor [1]
1,2
1
0,8
0,6
0,4
0,2
0
-0,2
10
100
1000
10000
Figure
122
k-factor
inhomogeneous field
for
k-factor [1]
air,
1,2
1
0,8
0,6
0,4
0,2
0
-0,2
10
100
1000
10000
k-factor [1]
1,2
1
0,8
0,6
0,4
0,2
0
-0,2
10
100
1000
10000
Note that the test with the damped sine is not presented in this figure.
In case a pure 185 kHz oscillations is applied, the Up,20 = 168,6 kV, in
this case the k-factor is 0,956. Because of the standard deviation it is
difficult to make a statement about this result, but it seems to fit very
well.
109
k-factor [1]
1,2
1
0,8
0,6
0,4
0,2
0
-0,2
10
100
1000
10000
Note that the test with the damped sine wave is not presented in this
figure. In case a pure 185 kHz oscillations is applied, the Up,20 =
173,6 kV, in this case the k-factor is 0,956. The test voltage should
be 168 kV. With the k-factor one calculates 166 kV, which is a very
good result, considering the standard deviations.
1,00
air inhom
Figure 125 k-factors
of all materials
hom oscillations or
investigated valid airfor
SF6 hom frequency and
overshoot of corresponding
PE
amplitudes up to 15-60%.
k-factor [1]
0,80
0,60
0,40
IEC 60060
0,20
SF6 inhom
Sample A
Sample B
0,00
-0,20
10
100
1000
10000
110
1,20
0,80
0,60
0,40
0,20
0,00
-0,20
10
100
1000
10000
oil
air inhom
air hom
SF6 hom
SF6 inhom
IEC 60060
PE
proposal(1)
Sample A
Sample B
Because all k-factors are best fittings of the measurement point for
each material it is interesting to see how the average k-factor will fit
between all the measurement results. This is presented in Figure 127
1,20
proposal (1)
oil
air hom
SF6 hom
SF6 inhom
PE
sample A
Sample B
k-factor [1]
1,00
0,80
0,60
0,40
0,20
0,00
-0,20
10
100
1000
10000
111
112
Proposal
7 Proposal
7.1
Introduction
7.2
113
Proposal
7.2.1
Test voltage
U t k U p (1 k ) U p ( RMC )
Equation XXIX
1,20
IEC 60060
proposal(1)
1,00
0,80
0,60
0,40
0,20
0,00
-0,20
10
100
1000
10000
In the previous chapter, the best k-factor for the different insulating
materials investigated has been calculated. From the several graphs
presented, it is concluded that the behaviour of the breakdown voltage
as function of the oscillation frequency and the amplitude of the
superimposed oscillations are more or less similar, but not identical
for all materials. In Chapter 6.10.4 the average k-factors, the k-factor
for each material investigated and the IEC 60060-1 factor are
presented. In Figure 128 the average k-factor and the IEC 60060
factor are presented once more. An interesting fact is that the IEC
60060-1 and the average k-factor cross at 0,56 at 500 kHz.
The average k-factor is:
1 for frequencies below 80 kHz
0 for frequencies above 5 MHz
given by the formula k=-0,2479*ln(freq in kHz) + 2,1056 for
frequencies in between these two values.
114
Proposal
115
Proposal
7.2.3
1,2
1
0,8
H(w)
0,6
0,4
0,2
0
0
500
1000
1500
2000
2500
Frequency [kHz]
1,2
original
MV
filtered
0,8
1
(100 %)
0,6
0,4
0,9
(100,5%)
0,2
0
0,8
9
10
11
12
-0,2
0
116
10
15
20
25
13
30
Proposal
Figure 134 and Figure 135 and Figure 133 are respectively the cases
13 and 14 from the IEC-TDG, which represent measured impulses of
lightning impulse tests performed on a transformer. The filtered
curve of the impulse with a long duration overshoot shows no
influence of the filter and the test voltage is the peak value of the
measured curve.
The filtered curve for an impulse with short duration shows a
reduction of the test voltage of about 1,5 % which is in accordance
with the used practice of evaluation of such kind of impulses, but not
in accordance with the present standards.
Concerning the proposed evaluation procedure it is not of importance
that the amplitude of the superimposed oscillations is above 5% and
therefore outside the allowed range.
0,2
original
-0,8
MV
filtered
-0,9
-0,2
(100 %)
-1
-0,4
-1,1
10
11
12
13
(100,5%)
14
-0,8
-1
-1,2
0
10
15
20
25
30
0,2
original
-0,7
MV
filtered
-0,8
U
-0,2
-0,9
-0,4
-1
-1,1
-0,6
10
11
12
(101,4%)
-0,8
-1
-1,2
0
10
15
20
25
30
117
Proposal
Figure 134 and Figure 135 are examples of impulses with
superimposed oscillations, as obtained in the European project. The
oscillation frequency is respectively 2 MHz and 0,8 MHz.
As can be seen from the figures, filtering the curves with the k-factor
works quite good and easy. Of course the proper function of the
implementation of the k-factor by filtering has to be proven in a more
accurate way, but for the cases tested the results look quite promising.
Since the filtered curve is very smooth, the definitions of the
parameters for T1 and T2 can be kept the same.
0,2
MV
-0,7
-0,8
original
filtered
-0,9
-0,2
(100 %)
-1
-0,4
-1,1
-1,2
-0,6
10
11
(113,2%)
12
-0,8
-1
-1,2
0
10
15
20
25
30
0,2
original
-0,7
MV
filtered
-0,8
-0,9
-0,2
-1
(100 %)
-0,4
-1,1
-1,2
-0,6
10
11
12
(101,8%)
-0,8
-1
-1,2
0
10
15
20
25
118
30
Proposal
7.3
7.4
The proposal will be checked with some wave shapes that occur in
testing. The four examples that are selected are presented in the next
paragraph and the voltage levels are summarised in Table 6.
Table 6 Summary of the examples
Example no.
Up
Uprmc
Ut
168,50
139,36
150,72
166,86
103,36
153,53
3 (standard LI)
165,25
165,25
165,25
119
Proposal
4 (LI with overshoot)
120
175,15
149,50
Proposal
Example 1
A wave shape typical for transformer testing is presented in Figure
136. The peak voltage of the curve is 168,50 kV, the peak voltage of
Example 2
Another wave shape typical for transformer testing is presented in
Figure 137. The peak voltage of this wave is 166,86 kV, the peak
voltage of the RMC is 103,36 kV. The frequency of the oscillation is
200 kHz. The k-factor is 0,79. This means that the test voltage will
be 153,53 kV.
Example 3
The example shown in Figure 139 is a standard lightning impulse.
The peak voltage and the test voltage are equal in this case and are
equal to 168,25 kV.
Example 4
A standard lightning impulse with superimposed overshoot is
presented in Figure 139. The duration of the overshoot is 1,36 s.
This means that the test voltage is equal to 165,97 kV.
121
Proposal
then be read into the PARAMETER program and the parameters like
the test voltage, front time and time to half-value can be evaluated.
Figure 139 Standard lightning impulse
voltage with peak voltage 165,28 kV and a
front time of 1,28 s and a time to half
value of 47,69 s.
The filters that are available within Labview and might be useful are:
FIR windowed filter, with windows:
- none
Hann
Hanning
Triangular
Blackman
Exact Blackman
Blackman-Harris
Kaiser-Bessel
Flat top
Bessel filter
Elliptic filter
Inverse Chebyshev filter
Butterworth filter
Chebyshev filter
A few of these filters have been used to check the proposal, the results
are presented in Table 7.
Table 7 Results of the different filters
Filter type
Waveshape
Chebychev
Chebychev
Chebychev
Chebychev
order 1
order 1
order 1
order 2
60 kHz
100 kHz
90 kHz
200 kHz
Butterworth Bessel
order 2
290 kHz
400 kHz
Standard impulse
1MHz oscillations
1,369 us overshoot
165,25
150,72
153,53
165,97
164,58
165,06
165,03
169,35
165,27
1,77
1,47
1,52
1,55
2,06
1,83
47,14
46,80
46,83
44,46
47,60
46,89
144,53
155,32
152,67
150,79
140,77
143,66
0,85
0,69
0,71
1,03
1,56
1,20
44,61
39,93
41,05
41,17
46,59
45,12
159,20
163,82
163,16
165,79
154,10
158,36
1,92
1,87
1,88
1,88
1,97
1,96
27,95
28,33
28,34
27,18
30,01
28,32
162,30
168,58
155,34
1,27
1,17
1,37
39,66
37,22
42,50
From the results presented in this table it can be seen that the type of
filter can have significant influence on the front time. This is logical
because the standard impulse has the same frequency components as
that of superimposed oscillations that have to be reduced slightly with
the k-factor function. Different types of filters have different effects
on the wave shape. For instance compare the results of filtering of the
standard impulse using the Chebychev order 1, 100 kHz to that using
the Bessel order 2, 400 kHz. Although the peak voltages are within
122
163,76
Proposal
10% when 1 MHz oscillations are applied the front time is twice as
large in the latter case.
From the results presented it can be concluded that it must be possible
to design a filter (combined in the measuring system and the software)
that can be used during impulse tests and that implements the k-factor.
In this thesis this investigation is not further made. Most important
was to demonstrate that it is possible to use a filter. Which filter type
in combination with the measuring system should be used should be
the topic of another study.
From the results presented in Table 7 it can be seen that a first order
Chebychev filter with a cut-off frequency of 90 MHz is not a too bad
choice. This original and the filtered wave shapes using this filter on
the four examples are presented in Figure 140 to Figure 143.
123
Proposal
124
Proposal
7.6
1,20
Figure 144 K factor function and the
frequency characteristics of two different
Measuring Systems
1,00
H(freq) [1]
0,80
0,60
0,40
0,20
Meetsysteem (1)
Proposal
0,00
Meetsysteem (2)
-0,20
10
100
1000
10000
145.
125
Proposal
1,20
Figure
145
k-factor,
frequency
characteristic of the Measuring System and
the necessary software filter
1,00
H(freq) [1]
0,80
0,60
0,40
0,20
Proposal
Meetsysteem (2)
0,00
software filter
-0,20
10
100
1000
10000
7.7
126
Proposal
7.8
Influence of time to half value in oil when the time to half value is
changed in a wider interval
To verify whether the k-factor is also valid for other than the
investigated materials and for insulating systems, more experimental
investigations have to be performed for other complex insulating
system and other materials. But considering the measurement results
obtained so far, no results that are far from the measurement results
obtained within this project are expected.
The results obtained from new investigations performed can be
incorporated in the table for the k factor or new k-factors can be
defined.
One of the most important topics to solve before the k-factor can be
implemented is the bandwidth of measuring systems used. If the
bandwidth of measuring systems used is equal to the k-factor than it is
of course obviously that filtering techniques should not be used and
that always the peak value of the impulse should be taken as the test
voltage.
In case the bandwidth requirements of Measuring Systems are stricter
than the k-factor, than filtering techniques can be used. Which filter
will suit the best has to be investigated.
Many investigations have already been performed towards the use of
filtering techniques in impulse measurements. In [80] some of the
techniques with their advantages and disadvantages are described as
well what to do in case of chopped impulses.
Perhaps it needs to be proven that the method is valid also for
oscillation amplitudes >20%, but it seems not to be necessary.
127
129
130
131
Appendices
Appendices
Appendix 1
Appendix 2
Appendix 3
133
Appendices
Appendix 1
Evaluation of parameters by
the software package PARAMETER
The following flowchart (Figure 146) presents the steps to calculate
the standard and complementary parameters of lightning impulses.
The user enters by visual examination of the wave if it is a full,
chopped in the front or on the crest or chopped in the tail impulse.
Figure 146 flowchart of steps to take to
evaluate parameters
Impulse acquisition
Step 1
Output parameters
Step 4
Step 5
134
Appendices
The origin (O) is the time when a sample of the recorded impulse first
exceeds the base level by 2% of the peak value.
Note: In order not to consider as the origin (0) a sample with an amplitude > 2% Up
due only to superimposed noise, the amplitude of the next samples must be also
greater than the 2% Up.
I=I 2
W(I)
U p=
I=I1
( I 2 I 1 + 1)
BL + 0,5
In order to avoid with this method a peak value lower than the real
one when high frequency superimposed oscillations appear, the two
following conditions must be satisfied:
1. |MAX W (I1)| < NOISE BAND, Noise band is defined as the
maximum difference between any two samples of the base line
(BL)
2. The samples I2 and I1 must belong to the same oscillation. If these
two conditions are not satisfied the peak value Up is the maximum
absolute amplitude (MAX).
135
Appendices
For impulses chopped in the front or on the crest, in general, it is not
possible to remove the noise in the peak zone by means of the above
criterion (see Figure 149). In these cases, the greatest amplitude of the
impulse will be the peak value.
The main frequency, f, and the amplitudes, Ai, of the oscillations can
be evaluated by determining the main frequency and amplitudes of the
wave acquired by means of the channel 2, for instance, by means of
the FFT. The amplitudes Ai are calculated after the superimposed
noise is removed. If during the record length the CH2 curve is not
damped inside the noise band, in order to avoid calculation errors, it
is advised that the FFT is calculated with an integer number of
periods of CH2.
136
Appendices
The algorithms to determine these parameters are described in
internal Document of the European project: Doc. Partner 2/10 Rev 1
and are not explained here.
Front time, T1 :
The virtual origin, O1, is the instant where the straight line which
passes through the points (t30, 30% Up) and (t90, 90% Up), cuts the
baseline, BL.
For lightning impulses chopped in the front or on the crest, the instant
to chopping, Tc, is the intersection point of the straight line through
90% and 30% of the peak voltage and the horizontal line that passes
through the impulse peak voltage (see Figure 151).
The times t90%, t30% at the zone of decay voltage are determined by linear
interpolation between the closest samples.
137
Appendices
For impulses chopped in the tail, the instant of chopping, T c, can be
determined also as the intersection point of two straight lines. One
straight line is the regression line of the ten samples before Tc, taking
into account that, when oscillations appear, the ten samples are taken
from the RMC. The second straight line is the one defined by the
points of the 90% and 30% of the voltage at the instant of chopping,
Uc at the zone of decay voltage.
Note:
138
Appendices
Test no.
Temp.
[C]
Air
press.
Humidity
Medium
[gH2O/m3]
[hPa]
gap
distance
wave
shape
Electro
de
conf.
U50(RMC)
sd
[kV]
[kV]
U50(RMC)/k
[mm]
[kV]
98-09-29
98-09-29
98-09-29
98-09-30
98-09-30
98-09-30
98-10-01
98-10-02
980929-3 23
980929-4 23
980929-5 23
980930-1 22
980930-2 23
980930-3 23
981001-1 22
981002-1 22
1003
1003
1003,5
1000
999,5
999,5
1004
1007
14
14
14
13
14
14
13
10,5
air+UV
air+UV
air+UV
air+UV
air+UV
air+UV
air+UV
air+UV
15
15
15
15
15
15
15
15,1
1,6/50
1,6/50
1,6/50
sphereplate
-42,123
sphereplate
-42,172
sphereplate
-42,172
-42,988
-43,028
-43,007
-42,875
-42,886
-41,022
-41,439
1,8/50
sphere-
-42,323
plate
-42,866
0,169 Scalefactor
19530
Scalefactor
19530
Scalefactor
19530
Scalefactor
19530
Scalefactor
19530
Scalefactor
19530
Scalefactor
19530
0,132 Scalefactor
19530
139
Appendices
Date of test
Test no.
[yy-mm-dd]
Temp.
[C]
Air
press.
Humidity
Medium
[gH2O/m ]
[hPa]
gap
distance
[mm]
wave
shape
Electro
de
conf.
U50(RMC)
sd
[kV]
[kV]
U50(RMC)/k
[kV]
99-01-19
990119-1
air+UV
15
sphere- 45,197
sphere
45,385
99-01-20
990120-1
air+UV
15
sphere- 42,659
sphere
42,879
99-01-20
990120-2
air+UV
15
sphere- 45,218
sphere
45,452
99-01-21
990121-1
air+UV
15
sphere- 45,195
sphere
45,281
99-01-21
990121-2
air+UV
15
sphere- 45,263
sphere
45,309
99-02-05
990205-1
air
15
sphere- 45,191
sphere
45,364
99-02-05
990205-2
air
15
sphere- 42,911
sphere
43,069
99-02-05
990205-3
air
15
sphere- 44,990
sphere
45,151
99-02-08
990208-1
air+cover 15
sphere- 43,228
sphere
43,422
99-02-08
990208-2
air+cover 15
sphere- 45,010
sphere
45,212
140
Lightning Impulses
Appendices
Results of tests performed in oil
All tests are performed using a gap distance of 1 mm and spheresphere configuration
Date of test
Test no.
[yy-mm-dd]
Temp Air
Humidity
press.
[C]
[gH2O/m3]
[hPa]
wave
shape
oscillatio
ns
oversh
oot
U50(RMC)
U50(peak) sd (rmc)
Sd (peak)
[kV]
[kV]
[kV]
[kV]
99-03-05
O990305a
19
986
1,2/50
no
69,494
5,506
99-03-11
O110399a
18
1015
1,2/50
no
68,815
1,748
99-04-22
O990422a
22
1002
11
1,2/50
no
71,659
3.051
99-04-26
O990426a
23
1015, 10
5
0,85/50
no
69,593
4,113
99-04-28
O990428a
22
1020
0,5/50
no
66,932
4,500
99-05-04
O990504a
22
1014
0,54/49
no
69,106
2,707
99-05-06
O990506a
21,5
1012
11
1,5/51
no
67,987
5,481
99-05-06
O990506b
21,5
1012
11
1,9/51
no
69,000
4,556
99-05-12
O990512a
21
1006
11
0,85/49
no
68,731
3,71
99-05-12
O990512b
21
1006
11
1,2/40
no
66,599
3,621
99-05-17
O990517a
21
1016
0,31/47
no
71,360
2,725
1999-06-22 O990622a
21
1018 10
1999-05-25 O990525a
1,2/50
1 s
65,237
76,638
4,248
4,192
1,2/50
1,2 s
60,612
87,99
5,357
6,104
1999-05-19 O990519a
22
1008, 9
5
1,2/50
2 MHz
70,002
77,632
4,116
3,948
1999-05-18 O990518a
22
1008, 9
5
1,2/50
800 kHz
65,514
77,656
4,136
4,036
1013 8
1,2/50
500 kHz
65,178
77,541
4,494
4,349
1028 9
1,2/50
200 kHz
61,54
75,196
5,261
5,15
1999-05-17 O990517b
1999-03-16 O990316a
20
141
Appendices
142
Lightning Impulses
Appendices
143
Appendices
144
Lightning Impulses
Appendices
145
References
References
The list of references is divided into two parts, public available
references and non-public available references. If the reference
number you are looking for is not in the first list, it will be in the
second. For example the reference numbers 1 to 4 and 7 to 9 are in the
public available list the missing numbers in the non-public available
list.
13
14
18
147
References
148
19
20
21
23
24
26
27
28
29
30
31
32
33
35
References
38
39
Kawashima, T., Okabe, S. and Zaima, E. Evaluation of steepfront overvoltage waveforms for oil-filled transformers 11th
ISH 1999, London, Volume 1, p. 1.279.P4-1.282.P4
40
41
42.
Lemke, E.:Ein Beitrag zur Abschtzung der rumlichzeitlichen Entwicklung des Durchschlags in langen
Luftfunkstrecken bei Schaltspannungen Wiss. Zeitschrift der
TU Dresden 26 (1977), 1, p.133-136.
43
44
45
46
47
48
51
52
53
55
149
References
150
56
57
58
59
Kahle,
M.:
Der
Einflu
von
Gleichspannungsvorbeanspruchungen
und
Erholezeit
auf
die
Stodurchschlagfestigkeit hochpolymer Folien Elektrie, 1971,
heft 25, S. 315-317
60
61
62
63
64
65
66
67
68
69
70
von vernetztem
Vorbelastung
References
72
Hauschild, W and Mosch, W.:Statistical techniques for highvoltage engineeringPeter Peregrinus Ltd., ISBN 0 86341 205
X
73
75
76
10
11
12
15
16
17
22
25
34
151
References
152
36
37
49
50
54
71
74
77
78
79
80
References
153
References
154
10
11
12
13
14
References
16
17
18
19
20
21
22
23
24
25
26
27
155
References
156
28
29
30
31
32
33
34
35
36
37
38
39
Kawashima, T., Okabe, S. and Zaima, E. Evaluation of steepfront overvoltage waveforms for oil-filled transformers 11th
ISH 1999, London, Volume 1, p. 1.279.P4-1.282.P4
40
41
42.
Lemke, E.:Ein Beitrag zur Abschtzung der rumlichzeitlichen Entwicklung des Durchschlags in langen
Luftfunkstrecken bei Schaltspannungen Wiss. Zeitschrift der
TU Dresden 26 (1977), 1, p.133-136.
References
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
von vernetztem
Vorbelastung
157
References
158
58
59
Kahle,
M.:
Der
Einflu
von
Gleichspannungsvorbeanspruchungen
und
Erholezeit
auf
die
Stodurchschlagfestigkeit hochpolymer Folien Elektrie, 1971,
heft 25, S. 315-317
60
61
62
63
64
65
66
67
68
69
70
71
References
72
Hauschild, W and Mosch, W.:Statistical techniques for highvoltage engineeringPeter Peregrinus Ltd., ISBN 0 86341 205
X
73
74
75
76
77
78
79
80
159