Defects Liability - by CEM
Defects Liability - by CEM
Defects Liability - by CEM
Paper 3722V3-1
Defects liability
Contents
Aims and learning outcomes
1. Definition
2. Types of defect
2.1 Construction or design
2.2 Patent or latent
2.3 Claims in contract or tort
3. Latent defects
3.1 Limitation
3.2 Latent Damage Act 1986
3.3 Fraud, concealment or mistake
4. Subsequent owners
5. Economic loss
5.1 The law pre-Murphy
5.2 The effect of Murphy
5.3 Murphy in the Commonwealth
5.4 Exceptions to Murphy
5.5 Hedley Byrne v Heller and reliance
5.6 The Defective Premises Act 1972
5.7 Summary
6. Measure of damages
6.1 Contract
6.2 Employers claims for damages for contractors beach
6.3 Contractors claims for damages for employers breach
6.4 Tort
Defects liability
Explain the difference between design defects and construction defects and
where liability will lie in respect of each.
Explain how patent defects are usually dealt with in building contracts.
Discuss the limitation issues that arise in connection with such claims and how
the Latent Damage Act 1986 may assist a claimant.
Discuss the background to the decision in the case of Murphy v Brentwood, the
effect of that decision and the exceptions to it.
Explain the scope and limitations of the Defective Premises Act 1972.
Identify the difference between the measure of damages in contract and in tort.
Advise when a claimant will be able to recover general damages for distress
and inconvenience, and the limitations of such claims.
Defects liability
1 Definition
The Oxford English Dictionary defines a defect as: Lack of something essential to
completeness; shortcoming; failing; blemish; amount by which a thing falls short.
The definition of defective is: Having defects; incomplete; faulty; wanting or
deficient.
Remember that in talking of defects we mean not just those things which have been
done badly or incorrectly, but also those things which have not been done at all.
2 Types of defect
2.1 Construction or design
Defects in buildings are broadly of two kinds:
z
Design defects, which may be the fault of the architect, engineer, contractor or
even the employer himself, depending on who was responsible for the design
of the works. This is why it is important that the parties should clearly
understand who is to be responsible both for the design of the works as a
whole, and for the individual elements in it, and that this information is
recorded in the contractual documents.
Defects liability
3 Latent defects
3.1 Limitation
Where defects appear after the expiry of the Defects Liability Period, the employers
position will depend on whether a binding and conclusive final certificate has been
issued and whether that certificate is conclusive as to the particular work and/or
materials that are defective (cf Crown Estates Commissioners v John Mowlem &
Company Limited (1994)). If such a certificate has been issued, the employer has lost
any right of action against the contractor. He may, however, have a right of action
against the certifier, either in contract or in tort. In either case the relevant limitation
periods apply.
An action for breach of contract must be brought within six years of the breach
where the contract is a simple contract, and within 12 years if it is a specialty. This is
why employers prefer the building contract, the engagements of professionals and any
other related contracts all to be specialty contracts.
Defects liability
Different limitation considerations apply to claims in tort, due both to the case law
which has developed in this area and the intervention of statute law. Limitation in tort
(six years except for personal injury claims) starts to run from the accrual of a cause
of action, that is, when damage is suffered. Damage need not necessarily arise until
some time after a breach of contract, and hence the limitation period in tort may be
much longer than that in contract. Where the employer is unaware that he has
suffered damage within six or 12 years of the breach of contract, his only claim will
lie in tort.
The difficulty in this area is where the claimant is unaware that damage has occurred.
In Pirelli General Cable Works Limited v Oscar Faber & Partners (1983), a House
of Lords decision, the Court decided that limitation ran from the date of damage even
though the plaintiff did not discover the damage until some time afterwards. Clearly
this can operate harshly to exclude claims where, through no fault of his own, the
employer is unaware that the building is defective during the limitation period.
In Western Challenge Housing Association Limited v Percy Thomas Partnership and
Others (1995), the plaintiff purchased a development of terraced houses which proved
to be defective. It was held that their cause of action accrued at the date they
purchased the properties (since the damage to the plaintiff occurred at the point of
purchase). The fact that they were unaware of the defects until some considerable
time afterwards did not prevent time running against them, and hence their claim was
statute barred.
Defects liability
Defects liability
The cases we have considered here concern concealment by the defendant during the
limitation period which prevented the plaintiff or claimant bringing his action within
it. In Sheldon and Others v RHM Outhwaite (Underwriting Agencies) Limited and
Others (1995) the House of Lords took the matter further. They found that the
limitation period does not start to run against the plaintiff until he has discovered the
concealment (or could with reasonable diligence have discovered it), even when the
concealment took place after the expiry of the limitation period. The discovery of the
concealment restarts the limitation clock.
10
11
12
13
14
Contract
Date of breach:
6 years
Simple contract
12 years
Speciality contract
Tort
Date of damage:
6 years
Patent damage
Latent damage:
from date of discoverability of damage:
from actual date of negligent act:
3 years
up to a maximum of 15 years
no longstop
4 Subsequent owners
A person who purchases a building which turns out to be defective is unlikely to have
a cause of action against the seller or landlord. This is for two reasons.
z
Firstly, the maxim caveat emptor (let the buyer beware) applies, meaning
that a contract for the sale of land and buildings, unlike one for the sale of
goods, contains no implied terms relating to the quality of what is being sold.
15
Defects liability
5 Economic loss
This section deals with two cases where the employer or buyer is unable to sue in
contract:
z
The liability was for personal injury, damage to other property and dangerous
defects in the building itself.
In cases that followed, the definition of dangerous defects became very wide.
Local authorities did not owe a duty of care to subsequent owners and could
not be sued for negligently approving drawings or building work.
Defects liability
The rationale for this part of the decision was stated to be that damage to the building
itself is pure economic loss and therefore not recoverable in tort. The building is
simply worth less because of the defects.
To understand why the claimant cannot recover for damage to the thing itself, it is
helpful to reconsider the case of Donoghue v Stephenson. In that case the plaintiff
could recover damages in tort for the effect of the product on her, but she could not
have recovered in tort for the value of the defective product, because the defect was in
the thing itself and her loss was therefore economic.
The principle was succinctly stated by Lord Oliver in D & F Estates:
(No) cause of action in tort arises in English law for the defective manufacture of
an article which causes no injury other than the injury to the defective article
itself.
Most recently the highest appellate court of Australia (the High Court) declined to
follow Murphy in the case of Bryan v Maloney (HCA, 23 March 1995). Mr Bryan,
who was a professional builder, built a house in 1979 which was purchased by Mrs
Maloney in 1986, there having been an intermediate owner. Mrs Maloney noticed no
defects in the property, but about six months after she bought it cracks began to
appear: the result of inadequate foundations. Under Murphy the English courts would
not have allowed her claim in tort, since it would have characterised her loss as being
purely economic ie the defective house was simply worth less than it would have
been without the defects. However, after a lengthy review of previous authorities,
including D & F Estates and Murphy, the Court allowed her claim, describing those
cases as resting upon a narrower view of the modern law of negligence, and a more
rigid compartmentalisation of contract and tort than was acceptable under the law of
Australia.
Defects liability
The second exception is the complex chattel or structure situation. This is where
different elements of a building are constructed by different people and one element
is negligently constructed as a result of which another element is damaged. However,
this should perhaps not be seen as an exception: it is a case where the defect causes
damage to other property, which was never within the scope of Murphy in the first
place. An example would be where a plumbing or electrical installation causes flood
or fire which damages other parts of the building. In Jacobs v Morton & Partners
(1994) a house had defective foundations. It was held that where the defendants
negligently designed a scheme to remedy the defect and damage resulted, they would
be liable for the cost of repair. The proposed remedial work would damage the
original building.
However, in the recent case of Tunnel Refineries Limited v Bryan Donkin Company
Limited, Alsthom SA and others (1998), the Court rejected the complex chattel or
structure theory. In that case a defective fan wrecked the machinery of which it was a
component part. The court refused the plaintiffs claims for the cost of replacing the
machinery and for lost production. The loss was purely economic.
Defects liability
It is not just the professional team against whom a Hedley Byrne claim may be made.
In Barclays Bank v Fairclough Building Ltd (1994) a specialist subcontractor was
found liable to the employer in these circumstances.
In the case of White v Jones the House of Lords similarly relied upon the notion of
assumption of responsibility to hold that a solicitor who negligently failed to carry
out his clients instructions to make a new will was liable in negligence to the
deceased clients daughters who, but for such failure, would have obtained an
inheritance. Clearly the plaintiffs in this case had no contract with the solicitor and
had to sue in tort for what was undoubtedly pure economic loss. The solicitor was
held to have assumed responsibility towards them in accepting his clients
instructions.
Defects liability
The Act only applies to dwellings, and this severely restricts the scope of its
operation. However, it should be borne in mind that the CDM Regulations
largely exclude residential property from their ambit, which makes the
availability of the Act of more significance to residential owners and
occupiers.
The legal duty imposed by the Act is very wide, since it covers any work
connected with the provision of the dwelling, and that will include conversion
or enlargement of a building (eg the conversion of an existing building into
flats).
The duty is owed to subsequent owners and occupiers as well as to the original
owner or occupier (ie it will apply where there is no contract between the
parties and where a claim in tort is not available for whatever reason).
Not only is the work to be done properly with appropriate materials, but the
person on whom the duty is imposed must ensure that the dwelling will be fit
for habitation. This is very important, for it is very rare that a court will find an
implied term in a building contract that the completed building will be fit for
its purpose.
The duty is owed by every person involved in either the design or construction
of the building. This will include architects, engineers, contractors, suppliers,
property developers and local authorities.
The Act imposes strict liability (ie liability even where there has been no
negligence) on all these parties for their acts and also for their omissions (cf
Andrews v Schooling (1991)).
The Act does not apply where the aggrieved party has some other, alternative
and comparable protection under an approved scheme in practice this will
be rare.
In Thompson v Clive Alexander and Partners (1992) the nature of the duty imposed
by the Act was discussed. The Court held that it was not sufficient to show that the
workmanship or materials were defective: the plaintiff must show that their defective
nature was such as to render the premises unfit for habitation.
5.7 Summary
1 As between original parties under original contract
Patent defects.
z
Defects liability
Latent Defects.
z
3 In either case
The employer or owner cannot recover if only the building is affected, because loss is
economic except if:
z
z
z
Defects liability
6 Measure of damages
The measure of damages that may be recovered for defective work will be different
according to whether the claim is made in contract or in tort.
6.1 Contract
In contract the measure of damages is the amount required to put the claimant in the
position he would have been in had the contract been properly performed. It is not
the amount required to put the claimant in the position he would have been in had the
contract never been made. The distinction is important. For example, where an
employer is in repudiatory breach such as to entitle the contractor to terminate the
contract, the contractor is entitled to claim the loss of profit he would have made from
the contract.
In respect of each loss, the claimant has to demonstrate that it is not too remote from
the defendants breach of contract. Either the loss must have been likely to arise in the
normal course of things as a result of the breach (it was reasonably foreseeable), or
the loss must be one which could have been within the contemplation of the parties at
the time they made the contract. It should be noted that the claimant does not have to
prove that the loss was contemplated by the parties, just that it could have been: ie
that their state of knowledge was such as to have made that contemplation possible.
In Balfour Beatty Construction (Scotland) Limited v Scottish Power plc (1994), the
defendants contracted to supply electricity to the plaintiffs, who were constructing a
concrete aqueduct. The plaintiffs needed to pour the concrete in one continuous
operation. The electricity supply failed. Although the defendants were in breach of
contract as a result, since they had not known the requirement for a continuous pour,
they were not liable to the plaintiffs for the cost of demolishing the plaintiffs work.
The claimant also has to show that, where possible, it has mitigated its loss: that is, it
has taken all reasonable steps to minimise the damage caused to it by the defendants
breach. For example, in the case of City Axis Limited v Daniel P Jackson (1998) it
was held that the employers refusal to allow the contractor to return to site to do
snagging works was a failure to mitigate the employers loss, and thus the employer
was not allowed to claim from the contractor the cost of employing others to do the
work.
In the cases of St Martins v McAlpines (1993) and Darlington BC v Wiltshier
Northern Limited (1994), the Court held that there were exceptions to the general
principle that a plaintiff who has not suffered loss cannot recover substantial
damages, and cannot recover damages on behalf of a third party. Those decisions
were reaffirmed by the House of Lords in Panotown Limited v Alfred McAlpine
Construction Limited (2000). In that case Panatown employed McAlpines to
construct an office building and a car park. The works were defective and Panatown
sued McAlpines. As Panatown were not the owners of the land or buildings, they had
arguably suffered no loss. The Court of Appeal awarded substantial damages to
Panatown on the basis that it was within the parties intention or contemplation that
Panatown should be entitled to recover substantial damages for defective work,
notwithstanding that it had no proprietary interest in the land. Panatown was therefore
allowed to recover damages on behalf of a third party to the contract.
This decision was overturned by the House of Lords because McAlpine had executed
a duty of care deed in favour of the actual owner of the building (Unex Investment
Properties Ltd), and so they were in a position to sue on their own behalf.
Defects liability
These cases seem to demonstrate that the range of foreseeable and therefore
recoverable loss can, in certain circumstances, extend to third party losses. The
explanation given in the Darlington case for the exception to the general rule was that
it provides a remedy where no other would be available to a person sustaining loss
which under a rational legal system ought to be compensated by the person who has
caused it.
These decisions represent an acknowledgement by the Court of the complex financial
arrangements which are part and parcel of modern commercial life. A claimant
should be able to recover a third partys loss in circumstances where the defendant is
well aware of the true commercial interrelationships between the contracting and noncontracting parties and it would be unfair to allow him to escape liability simply by
relying on the doctrine of privity of contract. (Cf also Phillips Petroleum Company
(UK) Limited and Norsea Pipeline Limited v IT Corporation Limited and Flaretec
Alloys and Equipment Limited (1998)).
Defects liability
In addition to claiming specific damages for the cost of rectifying the defects or the
loss of value caused by the defects, the claimant may claim general damages for
inconvenience and distress where the building concerned is the claimants home. At
one time fairly considerable damages were awarded under this head. However, in the
case of Watts v Morrow (1991) the Court severely curtailed the award of damages
under this head. The case concerned a negligent survey. It will be appreciated that
claimants whose home proves to be defective will suffer anxiety and disappointment
at discovering that what was probably their largest investment is worth less than they
had believed, together with the discomfort and unpleasantness of living in a defective
property and the disruption and inconvenience in living in the property while the
remedial works are carried out. The Court held in the Watts case that the plaintiffs
were entitled to damages for:
z
the discomfort suffered as a result of having to live for a lengthy period in the
defective premises, and
6.4 Tort
The measure of damages is the amount required to put the claimant in the position he
was in before the tort was committed.
As we have seen, unless he can bring himself within one of the exceptions to Murphy
or can prove reliance on or an assumption of responsibility by the defendant (Hedley
Byrne v Heller), the claimant will be unable to recover economic loss and thus will
have no claim if the only damage is to the building itself.
Defects liability
However, in other respects a claim in tort may be more generous to the claimant than
a claim in contract, since different tests of remoteness will apply. In tort, the claimant
only has to show that the damage suffered was a reasonably foreseeable consequence
of the defendants negligence, even if the extent of the damage or the precise manner
of its occurrence were not reasonably foreseeable (Overseas Tankship (UK) v Morts
Dock & Engineering Company (The Wagon Mound No 1) (1961)).
The author of the 20th edition of Salmon and Heuston explains as follows:
In contract the rule is that the plaintiff can recover for loss which the defendant,
when he entered into the contract, ought to have contemplated, as a reasonable
man, was of a very substantial degree of probability or was not unlikely to result
from a breach. The plaintiff cannot recover, as he can in tort, for loss which is a
serious possibility or a real danger. The reason for this distinction between
contract and tort is that in contract, if one party wishes to protect himself from a
risk which to the other party would appear unusual, he can direct that others
attention to it before the contract is made. But in tort there is no such opportunity
available to the injured party, and so the tortfeasor cannot complain if he has to
pay for some very unusual but still foreseeable damage which results from his
wrongdoing. Therefore, liability in tort is normally wider than liability in contract
but not necessarily so, for the parties to a contract may expressly agree that there
shall be liability for some remote and quite unforeseeable head of damage.
Accordingly, loss of profit on a contract with a third party which the claimant is
unable to fulfil as a result of the defendants breach may not be recoverable in
contract if the defendant was unaware of such contract or the likelihood of its
existence should not have been obvious to him. In tort, the claimant is more likely to
recover in these circumstances.
SELF-ASSESSMENT QUESTIONS
1. Discuss the reasons why a claim in tort may be more attractive to a claimant than a
claim in contract.
2. Explain the different limitation periods applicable in contract and tort and how a
claimant may be assisted by:
a. the Latent Damage Act 1986
b. s.32 of the Limitation Act 1980.
3. Is the decision in Murphy fair?
4. What must a claimant prove in order to make a claim under Hedley Byrne v Heller
and what are the advantages of doing so?
5. Since the decision in Murphy v Brentwood, more claims are being made under the
Defective Premises Act 1972. Why is this?
The Act is both very wide and very limited in its application. Explain.
6. Explain the different ways in which a Court may awards damages for defects in
contract and in tort.