AUC Technologies: Project Management With PMP Exam Preparation
AUC Technologies: Project Management With PMP Exam Preparation
Agenda
Tools
1. Project
1.Change Requests
Management Plan
2. Performance
Reports
3. EEF
1. Expert Judgment
2.Project Management
plan updates
3.Project document
updates
OPA
Input
Output
Control Scope
controlling changes to the project scope
Control Scope
1.
Project
Management
Tools
Plan
2.
1. Variance analysis
Work
Performance Info
3.
Requirement
documentation
4.
Requirement
1. Work Perform
Measurements
2. Organizational process
assets updates
3. Change Requests
4. Project Management
Plan updates
5. Project document
updates
traceability matrix
5.
OPA
Input
Output
Control Schedule
Control Schedule
Tools
1. Project
management
plan
2. Project Schedule
3. Work
Performance
Information
4. Organizational
Process Assets
Input
1. Performance
reviews
2. Variance analysis
3. Project
management
software
4. Resource leveling
5. What-if-scenario
analysis
6. Adjusting leads
and lags
7. Scheduling
compression
8. Scheduling Tool
1. Work Performance
measurements
2. Organizational process
assets updates
3. Change requests
4. Project management
plan updates
5. Project document
updates
Output
Control Costs
Control Costs
Tools
1. Project
management Plan
2. Project funding
requirements
3. Work performance
information
4. Organization
process assets
Input
1. Earned value
Management
2. Forecasting
3. To-complete
performance index
(TCPI)
4. Performance
reviews
5. Variance analysis
6. Project
management
Software
1. Work performance
measurements
2. Budget forecasts
3. Organizational process
assets updates
4. Change requests
5. Project Management
plan update
6. Project
documentupdates
Output
Performance Reviews
Variance analysis
Compares actual performance to planned or expected
performance
Cost & schedule variances most commonly used
Project scope, resource, quality, risk are other areas of
importance
Trend analysis
Performance over time to determine improvement /
deterioration
Earned value technique
Compare planned performance to actual performance
Budget at completion
Actual Cost
Planned Value
Earned Value
No Formula
No Formula
No Formula
No
Cost Variance
Schedule Variance
Cost Performing Index
Schedule Performing Index
Estimate at completion
Estimate to complete
Variance at completion
EV-AC
EV-PV
EV/AC
EV/PV
BAC/CPI
EAC-AC
BAC-EAC
EVA Example
A $10,000 software project is scheduled for
4 weeks.
At the end of the third week, the project is
50% complete and the actual costs to date
is $9,000
Planned Value (PV) = $7,500
Earned Value (EV) = $5,000
Actual Cost (AC) = $9,000
Forecasting Costs
If the project continues at the current performance,
1. Project Staff
Assignments
2. Project
management Plan
3. Team performance
assessment
4. Performance
Reports
5. Organizational
process assets
Tools
1. Enterprise
environmental factors
1. Observation &
Conversation
2. Project
updates
2. Organizational Process
Assets updates
Performance
3. Change requests
Appraisals
3. Conflict Mgmt
updates
4. Issue Log
Input
5. Interpersonal skills
Output
disagreement
Quality Assurance
1. Project Mgmt plan
2. Quality metrics
3. Work performance
information
4. Quality control
measurements
Input
Tools
1. Quality Planning
1. OPA (updates)
Tools &
2. Change Requests
Techniques
3. Project Mgmt
2. Quality audits
3. Process analysis
Plan(updates)
4. Project document
Updates
Output
projects.
Distribute Information
Determines the information and communications
needs of the stakeholders
Getting the right information to the right people at the right time
Distribute Information
1. Project management
plan
Tools
1. Communication
2. Performance reports
3. Organizational
process assets
Input
methods
2. Information
1. Organizational
process assets
updates
distribution
methods
Outpu
t
Report Performance
The collection of all baseline data, and distribution of
performance information to stakeholders
Keeps stakeholders informed about how resources are being
Report Performance
Tools
1. Project
management Plan
2. Work performance
information
3. Work Performance
Measurements
4. Budgeted
Forecasted
5. Organizational
process assets
Input
1. Performance reports
1.Variance analysis
2.Forecasting method
3.Communication
methods
4.Reporting System
2. Organizational process
assets updates
3. Change requests
Output
stakeholders
Need to devise a way to identify and resolve issues
Two important tools include
Communication Methods
Issue log
1. Stakeholder
register
2. Stakeholder
Tools
3. Project
Management Plan
4. Issue Log
Assets updates
2. Change Requests
management
strategy
1. Organizational Process
1.Communications
Methods
2.Interpersonal skills
3.Management skills
3. Project Management
Plan updates
4. Project document
updates
5. Change Log
6. OPA
Input
Output
Tools
1. Risk Register
1. Risk reassessment
2. Project
2. Risk audits
Management Plan
3. Change Requests
3. Variance and
3. Work Performance
trend analysis
information
1. Performance
reports
4. Technical
performance
updates
5. Project document
updates
measurement
5. Reserve analysis
Input
6. Status meetings
Output
Conduct Procurement
The Process of obtaining seller responses, selecting a
seller, and awarding a contract
Team will receive bids and proposals
Conduct Procurement
1. Project management
plan
2. Procurement doc
3. Source Selection
Criteria
4. Qualified Seller List
5. Seller Proposals
6. Project Documents
7. Make-or-buy Decision
8. Teaming Agreement
9. OPA
Tools
1. Bidder Conference
2. Proposal evaluation
technique
3. Independent
estimates
1. Selected Seller
2. Procurement Contract
Award
3. Resource Calendar
4. Expert Judgment
4. Change Request
5. Advertising
6. Internet Search
7. Procurement
negotiation
Input
Output
Administer Procurements
Administrating contract by the buyer and the seller for
similar purposes
Administer Procurements
Tools
1. Procurement
documents
2. Project
Management Plan
3. Contract
4. Performance
reports
5. Approved change
requests
6. Work performance
Information
Input
1. Contract change
control system
2. Procurement
performance
reviews
3. Inspections and
audits
4. Performance
reporting
5. Payment systems
6. Claims
administration
7. Records
management
system
1. Procurement
documentation
2. Organizational
process assets
updates
3. Change Requests
4. Project management
plan updates
Output
Questions