EDF High Voltage Cable Insulation Testing Policy
EDF High Voltage Cable Insulation Testing Policy
EDF High Voltage Cable Insulation Testing Policy
Date: 10/03/2009
ENGINEERING INSTRUCTION
EI 09-0001
Network(s):
Summary:
This engineering instruction details the policy for the on-site insulation
testing of new and existing high voltage cables, switchgear and
transformers.
Originator:
Paul Williams
Date:
10/03/2009
Approved
By:
Colin Gardner
Approved Date:
28/04/2009
Review Date:
11/02/2011
This document forms part of the Companys Integrated Business System and its requirements are mandatory throughout EDF
Energy Networks Branch. Departure from these requirements may only be taken with the written approval of the Director of
Capital Programme. If you have any queries about this document please contact the originator of the current issue.
Document History
(The document history notes below are intended as a guide only and may not cover all of the changes. If you wish to make use
of this document it should be read in full.)
Version
Date
Details
Originator
5.0
1 of 14
Paul Williams
THIS IS AN UNCONTROLLED DOCUMENT, THE READER MUST CONFIRM ITS VALIDITY BEFORE USE
Version: 5.0
Contents
1
Introduction ............................................................................................................. 4
Scope ....................................................................................................................... 4
References............................................................................................................... 4
Testing ..................................................................................................................... 5
4.1
General ..................................................................................................................... 5
4.2
New Apparatus.......................................................................................................... 5
4.3
Existing Apparatus..................................................................................................... 5
4.4
Test Application......................................................................................................... 5
4.5
Test Methods............................................................................................................. 6
Cable Testing........................................................................................................... 6
5.1
5.2
5.3
5.4
5.5
New and Existing Cables 66kV and 132kV Oil and Gas Pressure Assisted
Cables ....................................................................................................................... 8
5.6
New and Existing Cables - 66kV and 132kV cables containing XLPE insulated
Cable......................................................................................................................... 8
5.7
5.8
5.9
Switchgear Testing................................................................................................ 10
6.1
6.1.1
6.1.2
Existing switchgear.................................................................................................. 10
6.1.3
6.2
Alternative Soak Test for 66kV and 132kV GIS Switchgear ..................................... 12
6.3
Transformer Testing.............................................................................................. 12
7.1
2 of 14
Tables
Table 1:
Minimum test voltages for new and existing cables up to and including 33kV ...... 6
Table 2:
Maximum voltage levels for fault location for cable up to and including 33kV....... 7
Table 3:
Table 4:
Minimum test voltages for new and existing fluid and gas filled 66kV and
132kV cables ....................................................................................................... 8
Table 5:
Minimum test voltages for new 66kV and 132kV XLPE cables ............................ 9
Table 6:
Minimum test voltages for 66kV and 132kV Cable System containing existing
sections of cable.................................................................................................. 9
Table 7:
Maximum voltage levels for fault location for 66kV and 132kV Cable Systems .... 9
Table 8:
Cable over-sheath test voltages for cables - 66kV and 132kV ........................... 10
Table 9:
3 of 14
Introduction
This engineering instruction details the policy for the on-site insulation testing of high voltage
cables, switchgear and transformers. The purpose of on-site insulation testing is to
demonstrate that apparatus can be safely connected to the system.
The testing regime detailed in this policy is designed to avoid unnecessary overstressing and
to prolong the life of the apparatus. It should identify any gross defect, damage or earths left
connected at a remote end. The testing regime is based on current practice from the
relevant British and International standards together with current practice used on the three
EDF Energy networks. Consideration has been given to safety of field staff, the availability of
test equipment and the relative merits of ac, dc and very low frequency (VLF) ac testing.
This policy supersedes the following documents:
EPN: EDM V12/S1/8 - Site Insulation Tests for High Voltage Equipment.
SPN: Site Testing & Commissioning Manual 2.N3 - On-site Insulation Testing of
Cables, Switchgear & Transformers.
Scope
This policy applies to the insulation testing of cables, switchgear and transformers from
1000V to 132kV on the EPN, LPN, SPN and private networks and includes:
New apparatus before it is connected to the system for the first time.
Existing solid cable after it has been de-energised for an extended period.
This policy does not seek to provide condition monitoring information or partial discharge
information.
References
4 of 14
Testing
4.1
General
After apparatus is installed (or re-installed) but before energisation for the first time.
After work on the insulation of apparatus, but not normally after routine maintenance.
After cable with solid insulation has been intentionally left de-energised for more than
one month
For new and re-commissioned equipment the interval between testing and energisation from
the system should be the minimum practicable:
Cable systems from 22kV and up to and including 132kV this should normally be no
longer than 72 hours.
However for cables at all voltages an extension to this period is available to the SAP
providing the integrity of the system can be assured by for example visual inspection of
the route or the completion of another successful sheath test.
Swinger transformers and other standby equipment that is left intentionally de-energised
will need to be energised monthly to avoid the need for isolation and testing.
Dispensation to vary from the test methods and voltage levels set out in this policy
for test voltages above nominal phase to earth voltages can be granted by the EDF
Energy Asset Optimisation and Technology Manager. Where the test voltage is lower
than the nominal phase to earth voltage, permission to test should be sought from the
Head of Asset Management.
4.2
New Apparatus
All new apparatus should, following installation, be successfully tested once at the voltage
specified in this policy. Where the manufacturer recommends tests that differ from this policy
guidance shall be obtained from Asset Management.
4.3
Existing Apparatus
All apparatus which has been de-energised and has knowingly had the insulation affected
(except changing oil and topping up SF6) shall be subjected to an insulation test as specified
in this policy.
4.4
Test Application
Where two or more items of apparatus are connected, the apparatus requiring the least
onerous test determines the test voltage.
Site engineers shall take account of the risks involved in disconnecting equipment compared
with the risks of a reduced voltage test.
Equipment installed to run initially at a lower voltage than its rating shall be tested according
to its rating before connection to the lower voltage system. If, after this test, the insulation is
5 of 14
in any way disturbed, e.g. a 33kV cable is jointed to an 11kV cable, an insulation test voltage
appropriate to the working voltage shall be applied before commissioning.
4.5
Test Methods
This policy includes both dc and ac test methods. A dc test is usually carried out using an
insulation tester with the appropriate voltage output, such as a Megger or dc pressure test
set. An ac test is usually carried out using an ac test set or test van to give the required
voltage. Where both dc and ac tests are specified for equipment or cables either test may be
used.
For cables it is necessary to apply the test voltage and allow the cable to fully charge up.
Generally with test sets the timing begins when the set has reached the required voltage and
for insulation resistance (IR) testers the time begins when the IR value has stabilised.
Also, with some newer IR test sets, the test is considered a pass if the cable remains at the
specified voltage for the duration of one minute - the voltage will drop if the insulation breaks
down during that time span.
Partial discharge testing methods are being developed and operational advice will need to
be followed.
Cable Testing
5.1
It is essential before energisation to ensure the cable is continuous from end to end. This will
check that the cable is laid as planned and that any route joints have been completed.
These voltages can also be used for testing transformer tails between the winding and earth
but see also section 7.1.
Table 1 shows the minimum voltages to be used. Voltages up to those mentioned in Table 2
are acceptable if site conditions require.
Table 1:
Minimum test voltages for new and existing cables up to and including
33kV
Rated Line
Voltage
(kV)
Cable
Type
6.6 (2 &
3.3)
All
Types
11
All
Types
Note 1
20 & 22
All
Types
33
All
Types
DC Test1
Test Application
Voltage
(kV)
Duration
(min)
6 of 14
Notes:
1.
Partial discharge mapping carried out in London, mainly at 11kV, is used as a commissioning test. These tests do
require the test voltage to be of the order of 1.5Uo ac at 0.1Hz for a period of up to 15 minutes.
5.2
Acceptable IR Values
It is not possible to specify a lowest acceptable insulation resistance value for dc testing (as
it depends on a number of factors including cable type/length, weather conditions, etc.) all
three cores should be similar and a different value on one core would indicate a problem.
The determining factor here will be whether any of the phases has an unacceptably low
reading (1M) or a drastically different reading. Engineering judgement needs to be applied
to the value obtained. If traditional fault location fails to indicate a fault then connecting the
circuit to the network for a 24 hour soak test is acceptable. If customers will be affected by
the fault occurring during this test the number of customers must be as low as reasonably
practical.
5.3
It is permissible to apply higher dc voltages for fault location up to the maximum shown in
Table 2.
Table 2:
Maximum voltage levels for fault location for cable up to and including
33kV
5.4
6.6
11
12
20 & 22
24
33
36
The test voltages for over-sheath tests are given in Table 3. Tests are required for new
cables (having an insulated sheath) prior to energisation. Also, when returning an insulated
sheath cable to service following diversion or repair then a sheath test as shown in Table 3
is required.
7 of 14
Table 3:
System
Nominal
Voltage (kV)
Minimum dc
Test Voltage
(kV)
Minimum dc
Test Voltage
(kV)
New cables
On return to
service
11
Test
Duration
(min)
Maximum
Leakage
Current
(mA)
Not
Applicable
5
20 & 22
33
10
Test
Application
Between
metallic
sheath and
earth
Note - specially bonded cable circuits complying with the requirements of ENA ER C55/4 may require further tests in addition to
the over-sheath tests above.
5.5
New and Existing Cables 66kV and 132kV Oil and Gas Pressure Assisted
Cables
It is essential before energisation to ensure the cable is continuous from end to end. This will
check that the cable is laid as planned and that any route joints have been completed.
The cable shall withstand a dc test voltage of negative polarity applied between the
conductor(s) and sheath with the sheath earthed.
Table 4 shows the minimum voltages to be used. No breakdown of the insulation shall occur.
Table 4:
Rated
Line
Voltage
(kV)
66
132
5.6
Minimum test voltages for new and existing fluid and gas filled 66kV and
132kV cables
dc Test
Voltage for
New Cable
Systems
Minimum dc
Test Voltage
for Systems
with old Cable
(kV)
(kV)
170
71
305
130
Duration
(min)
15
Test Application
New and Existing Cables - 66kV and 132kV cables containing XLPE insulated
Cable
It is essential before energisation to ensure the cable is continuous from end to end. This will
check that the cable is laid as planned and that any route joints have been completed.
The cable shall withstand an ac test voltage applied between the conductor(s) and sheath
with the sheath earthed. Where possible a Partial Discharge (PD) test shall be carried out
during the ac test.
The test will normally be provided by a series resonant test set operating close to power
frequency.
8 of 14
Table 5 shows the minimum voltages to be used. No breakdown of the insulation shall occur.
Table 5:
Minimum test voltages for new 66kV and 132kV XLPE cables
Rated
Line
Voltage
(kV)
Ac Test Voltage
for New Cable
Systems
66
72
132
132
Frequency Duration
(Hz)
(min)
(kV)
20 - 300
60
If the cable system contains sections of existing fluid filled, gas filled or XLPE cable the test
voltage should be reduced in line with table 6.
Table 6:
Minimum test voltages for 66kV and 132kV Cable System containing
existing sections of cable
Rated Line
Voltage
(kV)
Existing cable
Existing cable
Existing cable
ac Test
Voltage
Duration
(min)
(kV)
66
72
132
132
5.7
ac Test
Voltage
Duration
(min)
(kV)
60
61
114
ac Test
Voltage
Duration
(min)
(kV)
60
54
95
60
It is permissible to apply higher dc voltages for fault location up to the maximum shown in
Table 7.
Table 7:
Maximum voltage levels for fault location for 66kV and 132kV Cable
Systems
Rated Line Voltage
(kV)
5.8
66
50
132
50
The test voltages for over-sheath tests are given in Table 8. Tests are required for new
cables (having an insulated sheath) prior to energisation. Also, when returning an insulated
sheath cable to service following diversion or repair then a sheath test as shown in Table 8
is required.
9 of 14
Table 8:
System
Nominal
Voltage (kV)
Minimum dc
Test Voltage
(kV)
Minimum dc
Test Voltage
(kV)
New cables
On return to
service
66
10
132
Test
Duration
(min)
Not
Applicable
Maximum
Leakage
Current
(mA)
10
Test
Application
Between
metallic
sheath and
earth
Note - specially bonded cable circuits complying with the requirements of ENA ER C55/4 may require further tests in addition to
the over-sheath tests above.
5.9
It shall be established whether the switchgear is capable of withstanding the cable test
voltage, otherwise, the least onerous test voltage shall be used.
Note: the specification for new switchgear ensures that all cable test access points will
withstand the highest cable test voltages mentioned in this document.
Switchgear Testing
6.1
Test Voltages
6.1.1
New switchgear
The test voltages to be used for new switchgear are given in Table 9. These test voltages
shall apply to:
any non-extensible switchgear where work has been done affecting the insulation.
For non-extensible switchgear at all voltages (including, for example, dead and live tank
132kV circuit-breakers) which has been factory tested, and on which no work has been done
on the insulation a test voltage of 5kV dc shall be applied for one minute.
6.1.2
Existing switchgear
The test voltages to be used for existing switchgear are given in Table 10. These test
voltages shall apply to:
all switchgear where work has been done affecting the insulation.
10 of 14
6.1.3
Earth applied to
L1 and L2
L2 and L3
L3
L1
Earth applied to
L1, L2 and L3
If surge diverters, neutral voltage displacement (NVD), capacitor bushings, etc. cannot be
disconnected then the manufacturers advice should be obtained before proceeding.
Table 9:
Switchgear
Rated Voltage
Up to 11kV
12kV
22
20/22
24kV
40
33
36kV
56
66
72.5kV
112
132
145kV
220
Table 10:
ac Test
Voltage (kV)
Test Duration
(min)
1
1
1
1
1
Switchgear
Rated Voltage
ac Test
Voltage (kV)
2
Up to 6.6
7.2kV
10
11
16.5
20/22
33
33
66
132
3
3
36kV
50
72.5kV
99
145kV
198
11 of 14
Test Duration
(min)
1
2
2
2
Notes:
1. The ac test voltage for new extensible switchgear is 80% of factory test and should also include a 5kV IR result both before
and after the ac test.
2. The switchgear will withstand the full test voltage applied to new equipment but to reduce the stress for this and subsequent
tests the test voltage for existing switchgear has been reduced to 1.5 times the line voltage.
3. See alternative soak test for 66kV and 132kV GIS switchgear.
6.2
An alternative regime for retesting, following an earlier full test, 66kV and 132kV GIS
switchgear is to connect the switchgear to the network for a 24 hour period to soak test it
rather than apply a voltage test.
This test has been approved because:
The difficulty, expense and risk of providing full test voltage immediately prior to
energisation.
GIS equipment, connecting and disconnecting the test set involves work on the
equipment; consequently the reconnection and re-gassing after removing the test set is
not then tested.
This option is available to the SAP who will supervise the re-commissioning if:
The switchgear is GIS, requiring opening of gas compartments for connecting and
disconnecting the test connections.
The protection is arranged such that in the event of a fault on the equipment being tested
no loss of supplies to customers shall occur.
The system fault level is reduced to the lowest possible level and access to the plant
under test is restricted.
6.3
Testing of air insulated bus bars, air break isolators or post insulators, etc. is not required by
this policy providing a visual inspection is made prior to energisation.
Transformer Testing
12 of 14
Table 11:
Test
System
Nominal
Voltage (kV)
dc Test
Voltage
(kV)
Test
Duration
(min)
Test Application
Up to 6.6
11
22
Winding
Insulation
33
66
132
Core
Insulation
All
1 2.5 1
2.5
Notes: The test voltage specified in the manufacturers test documentation should be used.
Table 12:
6.6
6.6
11
11
22
22
33
33
66
66
66 (graded insulation)
30
50
Where test access is available transformer tails must always be tested. Where test access
requires the dismantlement of apparatus and the SAP considers the risk to personnel of
gaining the test access is higher than the risk of failure then the test may be omitted. This
will usually apply at 11kV primary substations where the cable tails are within the EDF
Energy site and there is no reason to believe there has been any damage.
13 of 14
Test Results
The results of the tests shall be recorded in the substation log book where available.
Additionally the EDF Energy Commissioning Policy (EI 05-1001) provides guidance.
14 of 14