Araneta Inc., vs. Phil. Sugar Estates, 20 SCRA 330

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 5

G.R. No.

L-22558

May 31, 1967

GREGORIO
ARANETA,
INC., petitioner,
vs.
THE PHILIPPINE SUGAR ESTATES DEVELOPMENT CO., LTD., respondent.
Araneta
and
Araneta
Rosauro Alvarez and Ernani Cruz Pao for respondent.

for

petitioner.

REYES, J.B.L., J.:


Petition for certiorari to review a judgment of the Court of Appeals, in its CA-G.R. No.
28249-R, affirming with modification, an amendatory decision of the Court of First
Instance of Manila, in its Civil Case No. 36303, entitled "Philippine Sugar Estates
Development Co., Ltd., plaintiff, versus J. M. Tuason & Co., Inc. and Gregorio Araneta,
Inc., defendants."
As found by the Court of Appeals, the facts of this case are:
J. M. Tuason & Co., Inc. is the owner of a big tract land situated in Quezon City,
otherwise known as the Sta. Mesa Heights Subdivision, and covered by a Torrens title
in its name. On July 28, 1950, through Gregorio Araneta, Inc., it (Tuason & Co.) sold a
portion thereof with an area of 43,034.4 square meters, more or less, for the sum of
P430,514.00, to Philippine Sugar Estates Development Co., Ltd. The parties stipulated,
among in the contract of purchase and sale with mortgage, that the buyer will
Build on the said parcel land the Sto. Domingo Church and Convent
while the seller for its part will
Construct streets on the NE and NW and SW sides of the land herein sold so
that the latter will be a block surrounded by streets on all four sides; and the
street on the NE side shall be named "Sto. Domingo Avenue;"
The buyer, Philippine Sugar Estates Development Co., Ltd., finished the construction of
Sto. Domingo Church and Convent, but the seller, Gregorio Araneta, Inc., which began
constructing the streets, is unable to finish the construction of the street in the Northeast
side named (Sto. Domingo Avenue) because a certain third-party, by the name of
Manuel Abundo, who has been physically occupying a middle part thereof, refused to

vacate the same; hence, on May 7, 1958, Philippine Sugar Estates Development Co.,
Lt. filed its complaint against J. M. Tuason & Co., Inc., and instance, seeking to compel
the latter to comply with their obligation, as stipulated in the above-mentioned deed of
sale, and/or to pay damages in the event they failed or refused to perform said
obligation.
Both defendants J. M. Tuason and Co. and Gregorio Araneta, Inc. answered the
complaint, the latter particularly setting up the principal defense that the action was
premature since its obligation to construct the streets in question was without a definite
period which needs to he fixed first by the court in a proper suit for that purpose before
a complaint for specific performance will prosper.
The issues having been joined, the lower court proceeded with the trial, and upon its
termination, it dismissed plaintiff's complaint (in a decision dated May 31, 1960),
upholding the defenses interposed by defendant Gregorio Araneta, Inc.1wph1.t
Plaintiff moved to reconsider and modify the above decision, praying that the court fix a
period within which defendants will comply with their obligation to construct the streets
in question.
Defendant Gregorio Araneta, Inc. opposed said motion, maintaining that plaintiff's
complaint did not expressly or impliedly allege and pray for the fixing of a period to
comply with its obligation and that the evidence presented at the trial was insufficient to
warrant the fixing of such a period.
On July 16, 1960, the lower court, after finding that "the proven facts precisely warrants
the fixing of such a period," issued an order granting plaintiff's motion for
reconsideration and amending the dispositive portion of the decision of May 31, 1960, to
read as follows:
WHEREFORE, judgment is hereby rendered giving defendant Gregorio Araneta,
Inc., a period of two (2) years from notice hereof, within which to comply with its
obligation under the contract, Annex "A".
Defendant Gregorio Araneta, Inc. presented a motion to reconsider the above quoted
order, which motion, plaintiff opposed.
On August 16, 1960, the lower court denied defendant Gregorio Araneta, Inc's. motion;
and the latter perfected its appeal Court of Appeals.

In said appellate court, defendant-appellant Gregorio Araneta, Inc. contended mainly


that the relief granted, i.e., fixing of a period, under the amendatory decision of July 16,
1960, was not justified by the pleadings and not supported by the facts submitted at the
trial of the case in the court below and that the relief granted in effect allowed a change
of theory after the submission of the case for decision.
Ruling on the above contention, the appellate court declared that the fixing of a period
was within the pleadings and that there was no true change of theory after the
submission of the case for decision since defendant-appellant Gregorio Araneta, Inc.
itself squarely placed said issue by alleging in paragraph 7 of the affirmative defenses
contained in its answer which reads
7. Under the Deed of Sale with Mortgage of July 28, 1950, herein defendant has
a reasonable time within which to comply with its obligations to construct and
complete the streets on the NE, NW and SW sides of the lot in question; that
under the circumstances, said reasonable time has not elapsed;
Disposing of the other issues raised by appellant which were ruled as not meritorious
and which are not decisive in the resolution of the legal issues posed in the instant
appeal before us, said appellate court rendered its decision dated December 27, 1963,
the dispositive part of which reads
IN VIEW WHEREOF, judgment affirmed and modified; as a consequence,
defendant is given two (2) years from the date of finality of this decision to
comply with the obligation to construct streets on the NE, NW and SW sides of
the land sold to plaintiff so that the same would be a block surrounded by streets
on all four sides.
Unsuccessful in having the above decision reconsidered, defendant-appellant Gregorio
Araneta, Inc. resorted to a petition for review by certiorari to this Court. We gave it due
course.
We agree with the petitioner that the decision of the Court of Appeals, affirming that of
the Court of First Instance is legally untenable. The fixing of a period by the courts
under Article 1197 of the Civil Code of the Philippines is sought to be justified on the
basis that petitioner (defendant below) placed the absence of a period in issue by
pleading in its answer that the contract with respondent Philippine Sugar Estates
Development Co., Ltd. gave petitioner Gregorio Araneta, Inc. "reasonable time within
which to comply with its obligation to construct and complete the streets." Neither of the

courts below seems to have noticed that, on the hypothesis stated, what the answer put
in issue was not whether the court should fix the time of performance, but whether or
not the parties agreed that the petitioner should have reasonable time to perform its part
of the bargain. If the contract so provided, then there was a period fixed, a "reasonable
time;" and all that the court should have done was to determine if that reasonable time
had already elapsed when suit was filed if it had passed, then the court should declare
that petitioner had breached the contract, as averred in the complaint, and fix the
resulting damages. On the other hand, if the reasonable time had not yet elapsed, the
court perforce was bound to dismiss the action for being premature. But in no case can
it be logically held that under the plea above quoted, the intervention of the court to fix
the period for performance was warranted, for Article 1197 is precisely predicated on the
absence of any period fixed by the parties.
Even on the assumption that the court should have found that no reasonable time or no
period at all had been fixed (and the trial court's amended decision nowhere declared
any such fact) still, the complaint not having sought that the Court should set a period,
the court could not proceed to do so unless the complaint in as first amended; for the
original decision is clear that the complaint proceeded on the theory that the period for
performance had already elapsed, that the contract had been breached and defendant
was already answerable in damages.
Granting, however, that it lay within the Court's power to fix the period of performance,
still the amended decision is defective in that no basis is stated to support the
conclusion that the period should be set at two years after finality of the judgment. The
list paragraph of Article 1197 is clear that the period can not be set arbitrarily. The law
expressly prescribes that
the Court shall determine such period as may under the circumstances been
probably contemplated by the parties.
All that the trial court's amended decision (Rec. on Appeal, p. 124) says in this respect
is that "the proven facts precisely warrant the fixing of such a period," a statement
manifestly insufficient to explain how the two period given to petitioner herein was
arrived at.
It must be recalled that Article 1197 of the Civil Code involves a two-step process. The
Court must first determine that "the obligation does not fix a period" (or that the period is
made to depend upon the will of the debtor)," but from the nature and the circumstances
it can be inferred that a period was intended" (Art. 1197, pars. 1 and 2). This preliminary

point settled, the Court must then proceed to the second step, and decide what period
was "probably contemplated by the parties" (Do., par. 3). So that, ultimately, the Court
can not fix a period merely because in its opinion it is or should be reasonable, but must
set the time that the parties are shown to have intended. As the record stands, the trial
Court appears to have pulled the two-year period set in its decision out of thin air, since
no circumstances are mentioned to support it. Plainly, this is not warranted by the Civil
Code.
In this connection, it is to be borne in mind that the contract shows that the parties were
fully aware that the land described therein was occupied by squatters, because the fact
is expressly mentioned therein (Rec. on Appeal, Petitioner's Appendix B, pp. 12-13). As
the parties must have known that they could not take the law into their own hands, but
must resort to legal processes in evicting the squatters, they must have realized that the
duration of the suits to be brought would not be under their control nor could the same
be determined in advance. The conclusion is thus forced that the parties must have
intended to defer the performance of the obligations under the contract until the
squatters were duly evicted, as contended by the petitioner Gregorio Araneta, Inc.
The Court of Appeals objected to this conclusion that it would render the date of
performance indefinite. Yet, the circumstances admit no other reasonable view; and this
very indefiniteness is what explains why the agreement did not specify any exact
periods or dates of performance.
It follows that there is no justification in law for the setting the date of performance at
any other time than that of the eviction of the squatters occupying the land in question;
and in not so holding, both the trial Court and the Court of Appeals committed reversible
error. It is not denied that the case against one of the squatters, Abundo, was still
pending in the Court of Appeals when its decision in this case was rendered.
In view of the foregoing, the decision appealed from is reversed, and the time for the
performance of the obligations of petitioner Gregorio Araneta, Inc. is hereby fixed at the
date that all the squatters on affected areas are finally evicted therefrom.
Costs against respondent Philippine Sugar Estates Development, Co., Ltd. So ordered.
Concepcion, C.J., Dizon, Regala, Makalintal, Bengzon, J.P., Sanchez and Castro, JJ.,
concur.

You might also like