Araneta Inc., vs. Phil. Sugar Estates, 20 SCRA 330
Araneta Inc., vs. Phil. Sugar Estates, 20 SCRA 330
Araneta Inc., vs. Phil. Sugar Estates, 20 SCRA 330
L-22558
GREGORIO
ARANETA,
INC., petitioner,
vs.
THE PHILIPPINE SUGAR ESTATES DEVELOPMENT CO., LTD., respondent.
Araneta
and
Araneta
Rosauro Alvarez and Ernani Cruz Pao for respondent.
for
petitioner.
vacate the same; hence, on May 7, 1958, Philippine Sugar Estates Development Co.,
Lt. filed its complaint against J. M. Tuason & Co., Inc., and instance, seeking to compel
the latter to comply with their obligation, as stipulated in the above-mentioned deed of
sale, and/or to pay damages in the event they failed or refused to perform said
obligation.
Both defendants J. M. Tuason and Co. and Gregorio Araneta, Inc. answered the
complaint, the latter particularly setting up the principal defense that the action was
premature since its obligation to construct the streets in question was without a definite
period which needs to he fixed first by the court in a proper suit for that purpose before
a complaint for specific performance will prosper.
The issues having been joined, the lower court proceeded with the trial, and upon its
termination, it dismissed plaintiff's complaint (in a decision dated May 31, 1960),
upholding the defenses interposed by defendant Gregorio Araneta, Inc.1wph1.t
Plaintiff moved to reconsider and modify the above decision, praying that the court fix a
period within which defendants will comply with their obligation to construct the streets
in question.
Defendant Gregorio Araneta, Inc. opposed said motion, maintaining that plaintiff's
complaint did not expressly or impliedly allege and pray for the fixing of a period to
comply with its obligation and that the evidence presented at the trial was insufficient to
warrant the fixing of such a period.
On July 16, 1960, the lower court, after finding that "the proven facts precisely warrants
the fixing of such a period," issued an order granting plaintiff's motion for
reconsideration and amending the dispositive portion of the decision of May 31, 1960, to
read as follows:
WHEREFORE, judgment is hereby rendered giving defendant Gregorio Araneta,
Inc., a period of two (2) years from notice hereof, within which to comply with its
obligation under the contract, Annex "A".
Defendant Gregorio Araneta, Inc. presented a motion to reconsider the above quoted
order, which motion, plaintiff opposed.
On August 16, 1960, the lower court denied defendant Gregorio Araneta, Inc's. motion;
and the latter perfected its appeal Court of Appeals.
courts below seems to have noticed that, on the hypothesis stated, what the answer put
in issue was not whether the court should fix the time of performance, but whether or
not the parties agreed that the petitioner should have reasonable time to perform its part
of the bargain. If the contract so provided, then there was a period fixed, a "reasonable
time;" and all that the court should have done was to determine if that reasonable time
had already elapsed when suit was filed if it had passed, then the court should declare
that petitioner had breached the contract, as averred in the complaint, and fix the
resulting damages. On the other hand, if the reasonable time had not yet elapsed, the
court perforce was bound to dismiss the action for being premature. But in no case can
it be logically held that under the plea above quoted, the intervention of the court to fix
the period for performance was warranted, for Article 1197 is precisely predicated on the
absence of any period fixed by the parties.
Even on the assumption that the court should have found that no reasonable time or no
period at all had been fixed (and the trial court's amended decision nowhere declared
any such fact) still, the complaint not having sought that the Court should set a period,
the court could not proceed to do so unless the complaint in as first amended; for the
original decision is clear that the complaint proceeded on the theory that the period for
performance had already elapsed, that the contract had been breached and defendant
was already answerable in damages.
Granting, however, that it lay within the Court's power to fix the period of performance,
still the amended decision is defective in that no basis is stated to support the
conclusion that the period should be set at two years after finality of the judgment. The
list paragraph of Article 1197 is clear that the period can not be set arbitrarily. The law
expressly prescribes that
the Court shall determine such period as may under the circumstances been
probably contemplated by the parties.
All that the trial court's amended decision (Rec. on Appeal, p. 124) says in this respect
is that "the proven facts precisely warrant the fixing of such a period," a statement
manifestly insufficient to explain how the two period given to petitioner herein was
arrived at.
It must be recalled that Article 1197 of the Civil Code involves a two-step process. The
Court must first determine that "the obligation does not fix a period" (or that the period is
made to depend upon the will of the debtor)," but from the nature and the circumstances
it can be inferred that a period was intended" (Art. 1197, pars. 1 and 2). This preliminary
point settled, the Court must then proceed to the second step, and decide what period
was "probably contemplated by the parties" (Do., par. 3). So that, ultimately, the Court
can not fix a period merely because in its opinion it is or should be reasonable, but must
set the time that the parties are shown to have intended. As the record stands, the trial
Court appears to have pulled the two-year period set in its decision out of thin air, since
no circumstances are mentioned to support it. Plainly, this is not warranted by the Civil
Code.
In this connection, it is to be borne in mind that the contract shows that the parties were
fully aware that the land described therein was occupied by squatters, because the fact
is expressly mentioned therein (Rec. on Appeal, Petitioner's Appendix B, pp. 12-13). As
the parties must have known that they could not take the law into their own hands, but
must resort to legal processes in evicting the squatters, they must have realized that the
duration of the suits to be brought would not be under their control nor could the same
be determined in advance. The conclusion is thus forced that the parties must have
intended to defer the performance of the obligations under the contract until the
squatters were duly evicted, as contended by the petitioner Gregorio Araneta, Inc.
The Court of Appeals objected to this conclusion that it would render the date of
performance indefinite. Yet, the circumstances admit no other reasonable view; and this
very indefiniteness is what explains why the agreement did not specify any exact
periods or dates of performance.
It follows that there is no justification in law for the setting the date of performance at
any other time than that of the eviction of the squatters occupying the land in question;
and in not so holding, both the trial Court and the Court of Appeals committed reversible
error. It is not denied that the case against one of the squatters, Abundo, was still
pending in the Court of Appeals when its decision in this case was rendered.
In view of the foregoing, the decision appealed from is reversed, and the time for the
performance of the obligations of petitioner Gregorio Araneta, Inc. is hereby fixed at the
date that all the squatters on affected areas are finally evicted therefrom.
Costs against respondent Philippine Sugar Estates Development, Co., Ltd. So ordered.
Concepcion, C.J., Dizon, Regala, Makalintal, Bengzon, J.P., Sanchez and Castro, JJ.,
concur.