Management of Project Contingency and Allowance
Management of Project Contingency and Allowance
Management of Project
Contingency and Allowance
Jan Terje Karlsen and Jon Lereim
ABSTRACT: Cost overruns in engineering projects occur frequently because a certain margin of
risk is inherent in all projects. As a result, risk management is continuously gaining the attention of the engineering industries. Reserves or contingencies represent the additional funding
required to account for the cost of risk. However, many corporations have different practices for
estimating and managing such reserves. In addition to discussing and clarifying the risk reserves
terminology, this article presents several techniques and methods for estimating such reserves.
Authority to use the respective parts of the risk reserves is also discussed.
KEY WORDS: Contingency, cost overruns, estimating, and risk management
25
26
definitive scenario.
For a realistic
probability distribution of the total project
cost, 1000 to 10 000 cost sets or simulation
might be used. Any correlation between
the cost items or the risk items should be
specified in the program.
If such
correlations are ignored, the simulation
results tend to underestimate the variance
of the cost.
The result of the simulation is a
normal distribution curve of total cost as
shown in figure 5. From this curve the
cumulative probability distribution of total
project cost can be derived. This curve
gives information about the probability of
exceeding or not exceeding a specific cost
sum.
Build-up of Cost and Budget Figures
Most estimators tend to be
conservatively biased in their range
estimates [6]. As a result, the base estimate
tends to be less than the even chance
estimate (P50/50). The base estimate or
most likely value is an estimate where
theoretically no risk items are included.
27
5.
6.
RECOMMENDED READING
1. Burger,
Riaan.
Contingency,
Quantifying the Uncertainty. Cost
Engineering, 45, 8 (2003): 12-17.
2. Nassar, Khaled. Cost Contingency
Analysis for Construction Projects
Using
Spreadsheets.
Cost
Engineering, 44, 9 (2002): 26-29.
3. Rolstadas,
Asbjorn.
Praktisk
Prosjektstyring. Trondheim, Norway:
Tapir Forlag, 2001.
29