IDC - HV Conf - Perth 2015 - Condition Monitoring of High Voltage Switchgear - KH
IDC - HV Conf - Perth 2015 - Condition Monitoring of High Voltage Switchgear - KH
IDC - HV Conf - Perth 2015 - Condition Monitoring of High Voltage Switchgear - KH
Session 5:
Condition Monitoring of High Voltage Switchgear
Karl Haubner
Part 1
CONDITION MONITORING OF METAL-CLAD SWITCHGEAR
Karl Haubner, Doble Engineering
Introduction
Metal Clad Switchgear is one of the key assets of the electrical distribution system.
An in-service failure has significant consequences on the reliability of supply.
In the case of a failure large amounts of energy are released. Faults on the board
can cascade to other compartments causing collateral damage within the switchgear
and consequent loss of adjacent circuits and in the worst case scenario loss of the
whole board. This is particularly true for switchboards with oil filled circuit breakers,
resin bonded paper insulated bushings and compound insulated busbars.
Modern switchboards are designed to eliminate the potential to cause injuries by
containing the arc by-products but older boards still in service are not designed to be
arc resistant and any failure there is associated with a high risk of personal injury.
This paper describes some common and not so common condition monitoring
techniques to assess the insulation condition of switchboards.
3.1.
Figure 2: Failure of paper insulated condenser type circuit breaker bushing. Failure
occurred when racking a spare breaker into the board. The breaker passed a
simple IR test.
3.2
kV
10
20
28
38
50
36
70
The Switchgear has passed the PFWT test if the test voltage can be maintained for
1 minute without puncture, flashover or disruptive discharge.
Observe and record:
In essence the PFWT is a go-no-go test and whilst it is essential that a newly
assembled switchboard passes this test, little information about the quality of the
insulation system is obtained. There are many examples of switchgear having
successfully passed a HV withstand test having serious assembly issues.
The DDF measurement is one the standard methods to characterise the condition of
insulating materials. The value can vary from 0.1% up to 15% depending on the
insulation system used. The method is most effective for older type switchgear in
particular when condenser foil type stress control methods are employed.
Impregnated paper insulation as found in older Metal-clad switchgear is prone to
absorb moisture and the Dielectric Dissipation Factor is a significant indicator of
moisture ingress. Many cases have been encountered where circuit breaker
bushings returned acceptable Insulation Resistance readings but the DDF
measurement revealed poor insulation values.
The following sketch -figure 4- indicates how the DDF measurement can detect
partial degradation within a multi-layer insulation system.
The voltage dependence of the insulation tested is the other important criteria. Good
insulation will show very little increase in DDF value up to 120 % of operating volts.
As the capacitance of the insulation under test increases, the ability of the DDF
measurement to detect incipient localised faults is reduced. When testing, for
example, the busbar insulation a large number of spout bushings are measured at
the same time and the results indicate the average DDF. The true DDF of e.g. a
single bushing with high DDF will be masked by the low DDF of the large number of
good bushings. Thats why on a circuit breaker each bushing is tested separately.
3.4
Gro
Figure 8
When the breakdown strength of the gas or air inside the void is exceeded the void
capacitance is temporarily shorted so the voltage across the void drops to 0 V and a
charge transfer from one side to the other side of the void occurs. Ca now needs to
supply the lost charge to Cb to compensate. This is associated with some current
pulses between Ca and Cb/Cc.
Figure 9
DAQ
vPD
PD-Signal
DSP
Filtering
Detection
Postprocessing
A
D
vU
Voltage Signal
PC
A
D
Computer
Software
User/ Panel
10
Figure 13
PD Test Circuit
In addition to the magnitude and type of discharges the other important parameters
such as PD inception voltage, PD extinction voltage and effect of time are recorded.
All these parameters need to be considered before a valid judgment can be made.
Displaying the PD data using the Phase Resolved Partial Discharge (PRPD)
patterns also called phi-q-n diagram is recognized as the one of most effective
methods to display the characteristics of PD signals and is used to classify different
types of PD and interference signals. The method produces patterns that can be
directly related to gas discharge events in the dielectric. The PD pattern reflects the
sum of all individual pulses correct in time (phase position) on the X axis, magnitude
on the Y axis and repetition rate which is color coded collected during a preselected
acquisition time. The user can also select to display the pulse polarity. From this
information the generation of 2 or 3 dimensional graphs is possible.
Figure 14
corona.
11
Figure 15
3.5
After a discharge has been detected, its location is beneficial. If, for example, a
single component can be identified for replacement without sectionalising the
switchboard, significant time & cost savings are possible. Location of PD is possible
with non-electrical and electrical means. Electrical measurements usually involve
comparing arrival times between different sensors (they may be TEV sensors or
Coupling capacitors) using a high speed oscilloscope. Non electrical methods uses
several acoustic sensors.
12
Figure 17 Non electric location methods use microphones to detect the panels that
return the loudest indication of PD activity.
If panels can be removed during off-line testing a corona camera can be helpful
determining the origin of the PD activity.
13
14
These pulses travel due to the skin effect on the surface of the metal and are able to
propagate through an opening in the metal cladding (such as a gasket) onto the
outside surface of the switchboard. The travelling steep current pulse can generate
a transient earth voltage on the metal surface, which can be measured by attaching
a capacitive probe to the metalwork.
This capacitive plate sensor probe is often integrated in handheld detectors
permitting quick scanning of the switchboards.
15
TEV Sensors can also be used with more sophisticated instrumentation such as
oscilloscopes, recorders or spectrum analysers.
Using an optimised spectrum analyser as shown in figure24 it is possible to display
the captured signal in both the frequency domain and in a time resolved mode.
16
Some instruments have additional post processing features that characterise the
type of PD activity. Algorithms automate the PD characterization process by analysis
in the time domain extracting the features of each PD event such as Pulse rise and
decay times, pulse width and other essential frequency components. These features
are determined by the type of discharge
17
Ultrasonic Detection
18
Figure 30- Examples of acoustic windows retro fitted to Metal Clad switchgear
19
20
The Laboratory tests indicate that by far the most sensitive method and the only
way the PD activity can be accurately characterised, the degree of severity
quantified and compared to standards is an off-line PD measurement in
accordance with IEC60270.
However surface PD activity can be detected with very good sensitivity using
Acoustic techniques. Here the airborne type acoustic sensors achieve a much
better sensitivity than the contact type sensors. The dedicated ultrasonic detector
used in the trial with the inbuilt variable frequency filter returned the best
performance in terms of clarity and using the filter being able to focus on different
types of activity and noise suppression.
The same surface PD activity can in general not be detected using methods that
rely on the transmission of electric magnetic radiation (TEV) unless PD activity is
above 1000pC.
Strong Void PD activity, Sparking type PD and severe PD activity from cable
terminations can be detected using TEV techniques. Representing the signals in
the time domain (phase resolved) can assist in separating interference from real
PD.
Considering that the main failure mode in air insulated epoxy resin based
switchboards is surfaces deterioration and subsequent tracking much more
emphasis should be placed on effective acoustic measurements. This can be
achieved by installing acoustic windows.
The corona camera is not useful for survey type assessments with Panel covers
fitted but is a good investigative pinpointing tool during off-line testing with covers
removed.
21
6
Test Criteria
It is impossible to establish a universal heath index or acceptance criteria that
covers the whole range of switchboards and insulation system employed.
Very often guidelines are only applicable to a specific type, manufacturer and
voltage range.
Modern Metal Clad Switchgear utilising gas or air insulation and epoxy resin
structures have negligible losses and Dielectric Dissipation Factor Measurements
(DDF) are not a significant indicator and not commonly applied but are still listed in
the table.
Some simple guide lines have been established using the hand held detectors.
Acceptance Criteria
Insulation
Resistance
> 20 000 M
Partial Discharge
Off-line IEC
values
Ultrasonic
TEV
DDF
22
Insulation
Resistance
Partial Discharge
Off-line IEC
values
> 200 M
< 100 pC @ 110% Uo but take into account type of PD from
Phase Resolved Signature
DDF
Ultrasonic
TEV
Figure 35- Acceptance Criteria older Oil/ Bitumen insulated boards with Paper
insulated Graded OCB bushings
For results falling in the bad category, remedial action is recommended, access to
the board is restricted and detailed contingency plans in case of failure are
prepared.
If the test results fall between a fair and bad category the time period between retests is shortened or if possible some permanent monitoring is utilised. For
switchgear older than 20 years with results in the good and fair category, a
combination of off- and on-line re-tests typically every 4 years are scheduled.
The value in most insulation diagnostic testing lies more in the survey of a trend than
in the measurement of absolute values. No decision should be made based on the
results of a single test (unless very high readings are discovered). For older bitumen
compound insulated boards, DDF and insulation resistance varies considerably with
temperature and humidity and only trending over a number of tests can provide a
realistic assessment if the insulation is stable or deteriorates further.
It is important to collect benchmark data early in life of the switchboard so that
effective trending is possible.
The data from these diagnostic condition-monitoring tests presents the Asset
Manager with a powerful tool that can help in the decisions making process to
accept, refurbish, replace or retain the new and ageing switchboard. Warranty
issues or defects can be addressed early before the switchboard is placed in
service.
23
24
7.
Case Studies
Case Study 1
25
Switchgear panels were then removed and the location of discharge activity was
exactly pinpointed using ultrasonics and a corona camera.
Figure 41- Pinpointing techniques using both acoustic and corona camera with
covers removed
The PD activity originated from the busbar support fibre glass rings that were not
sealed and had absorbed moisture at some stage. There was also evidence of white
power at the rings and the heat shrink / rubber interface typical for crystallisation
associated with PD activity. The fibre glass material itself showed discoloration.
26
Case Study 2
This case study portrays the findings on a 22kV switchboard which was removed
from service due to audible discharge and a strong ozone smell emanating from the
switchboard. Testing was requested by the Asset Manager in order to determine the
levels of partial discharge present before performing fault finding to determine the
source of the audible discharge.
27
28
The discharge in this case was clearly occurring over an extended period of time
which went undetected until discharge levels were severe enough to be audibly
heard during general substation inspections. This confirms the requirement for
regular monitoring of electrical apparatus both online and offline which helps to
minimise repair costs through early detection or in a worst case scenario save the
apparatus from catastrophic failure.
Case Study 3
This case study focuses on an older bitumen/pitch filled switchboard (oil circuit
breaker). During a scheduled outage on a single CB, audible discharge was heard,
upon racking down the CB. Testing staff were called to the site and through the use
of an ultrasonic detector were able to pinpoint the discharge to the Red phase Front
Bus spout. Based on the testers onsite assessment and recommendations, the
Asset Manager decided to de-energise the Front Bus in order to perform offline
testing and subsequent fault finding.
Figure 48 Switchboard tested showing Bitumen bus bar insulation & oil circuit
breakers
29
Figure 50
30
Figure 51
The switchboard was successfully returned to service, with follow up online testing
and acoustic surveys confirming that the discharge activity has not returned.
Case Study 4
This case study details the findings as a result of a switchboard which was deenergised after general substation inspections identified audible discharge and the
smell of ozone within the switch room. Offline testing of just the busbar was
discharge free but severe audible discharge was present with all CB closed (thus
including all circuits in the test). Simply closing one CB at a time allowed the
discharge activity to be attributed to a single circuit on the switchboard.
31
Figure 53
The CTs were replaced and secondary wiring damage repaired before retests were
completed but large level discharge was still measured. Further investigation
identified that the close proximity of the secondary wiring of the Top CT to the body
of the Bottom CT. The discharge activity was successfully rectified by simply
increasing the clearance of the secondary wiring from the CT body. It appears that
only the combined field strength of both CTs being energised together was enough
to create the discharge that was measured.
32
Case Study 5
This case study presented shows how the described tests helped to determine
defects on a CT busbar in an air and epoxy insulated 22kV switchgear.
Routine off-line testing of a section of the switchgear returned the following results:
DC Step
voltage test
(Ileakage @
30kV) A
Suspect
Section
Normal
Section
Dielectric
Insulation
Dissipatio
Resistanc
n Factor
e @ 5kV
%
G
@10kV
PD
(pC)
PD (pC)
@
12.7
@ 15.3
L
1
<0.2
0.8
>1000
<10
<10
L
2
1.37
260
510
600
L
3
<0.2
0.89
>1000
<10
<10
L
1
<0.2
0.88
>1000
<10
<10
L
2
<0.2
0.85
>1000
<10
<10
L
3
<0.2
0.91
>1000
<10
<10
33
Panels of the board were removed and PD activity was located (whilst the busbar
was energised from the test transformer) using a PD probe. It was interesting to
observe that no ultrasonic discharge activity could be detected as the defect was
internal to the busbar insulation. A visual inspection of the L2 CT busbar also
revealed pitting and burn marks of the screen conductor. It was concluded that the
PD activity already caused further deterioration of the insulation evident from the
reduction in insulation resistance and increase in DDF. The CT busbar was removed
and was retested in the Laboratory. Similar high levels of partial discharge activity
were found. The area of highest PD intensity was located to be at the end of the
internal screen.
Location of highest PD
activity
PD signature @ 16 kV
PD Pulse Rate - Phase
5
PD Number/Second
0
0
45
90
135
180
225
270
315
360
Degree
Figure 56
34
Rear
Busba
r
DC Step
voltage
test
(Ileakage
@ 20 kV)
A
Dielectric
Dissipation
Factor
Insulation
Resistance @
5kV
@7.5kV %
PD
(pC)
PD
(pC)
PD
@
6.3
@ 7.6
Inception &
Extinction
L1
6.8
4.42%
93.1
<20
<20
>7.6kV
L2
7.4
5.75%
45.2
<20
<20
>7.6kV
17.7
1500
1800+
8.38%*
L3
50
also high
DDF
2.4 kV inc
2.5 kV ext
tip-up
Figure 57 Test Results Off-line test
Figure 58
Case Study 7
Figure 59
35
By sectionalising circuits the activity was localised to one panel and a visual
examination showed insufficient spring contact between the busbar and the screen
of the bushing leaving it floating. After rearranging the spring acceptable discharge
levels were obtained.
Figure 60
Case Study 8 -
During Commissioning of the new Switchboard the L3 (C) Phase showed elevated
PD levels. Although the PD levels were relatively low the phase resolved PD pattern
suggested an internal void discharge with good symmetry between positive and
negative half cycles
Figure 61
Acoustic location was not possible but by switching off sections of the switchboard
and removing links and components the PD was pinpointed to originate from a faulty
voltage indicator. Separate tests at component level confirmed the defective part.
Figure 62
36
Figure 63
Figure 64 Showing some of the components that were not connected to ground
during the assembly.
37
Part 2
CONDITION MONITORING OF GAS INSULATED SWITCHGEAR GIS
1. Introduction
GIS can be defined as switchgear where the conductors and contacts are insulated
are by pressurised Sulphur Hexafluoride gas (SF6). The SF6 gas is used both as
switching and insulation medium.
Due to their compactness, immunity against environmental conditions such as
pollution, their very high reliability, low maintenance and long service life they are
now a popular choice for both distribution and transmission voltage levels.
There are now several GIS installations in Western Australia and the monitoring of
these installations in service is covered in this second part on Switchgear
monitoring.
Figure 65
38
Gas insulated Switchgear is considered as overall very reliable however failures still
occur.
Figure 66 Source: Cigre TB 513 Final Report of the 2004 - 2007 International
Enquiry on Reliability of High Voltage Equipment Part 5 GIS 2012
39
Particles
This is a common problem and exists in almost every GIS
Particle with several mm length can reduce the AC withstand level considerably.
If they settle on epoxy spacers and insulators surface treeing my result leading to
flashovers. Particles can be introduced from contamination during manufacturing or
assembly on site or from metal abrasion due to vibrations or from moving parts from
e.g. switching operations
Floating Components
Floating Electrical and mechanical loose shields or other metal parts not bonded to
either HV or ground potential can generate large discharges that degrades the SF6
gas.
Internal PD
Internal PD from Voids and defects in spacers and epoxy components such as
insulators are due to manufacturing issues and factory routine tests should detect
these before shipment.
40
P article on s pacer
Electrically floating
shield
Protrusion
Void in
s pacer
Protrusion on
earth potential
Free particle
Figure 70 Frequency tuned resonant bolt on test sets for on-site testing of GIS
(Source: Siemens)
Once energised the following monitoring options are available:
3.1 Chemical Analysis of SF6 gases
Permanent installed SF6 gas gauges usually monitor the Gas Density which
provides an indication that a sufficient quantity of gas is present in the chamber.
Monitored. These are typically equipped with relay contact that are connected to the
SCADA system to signal the state of the Gas pressure/density.
41
In addition it is common to conduct annual SF6 quality check using portable gas
analysers.
42
43
44
45
46
Acoustic Mode
47
Interval/particle mode
clearly shows a bouncing
particle inside the GIS
48
Part 3
Time, Motion and Travel Testing of switchgear
Whilst so far the discussions have been limited to the assessment of the insulation
quality of Switchgear it should be noted that the circuit breaker and its operating
mechanism itself is basically a mechanical device. Life expectancy of HV circuit
breakers is at least 30 years but under normal operating conditions the breaker will
operate less than 10 minutes and under fault conditions it will operate less than 1
minute throughout its service life.
During the Time and Motion test various timing and motion measurements are be
made. After the test is complete the results are compared to the manufacturers
specifications.
During the test we may identify problems in the:
Mechanism, Linkages & Shock Absorbers the most common problems
discovered are lubrication issues, mechanical binding, or mechanical
interference. These types of problems may be identified by abnormal timing,
travel, or velocity results.
Main & Resistor Arcing Contact Systems these types of problems are most
frequently identified by excessive contact bounce on the contact timing plots.
Control Circuit these types of problems can be found directly or indirectly
during the motion and timing test. Most frequently they are first identified
indirectly, where the problem in the control circuit causes the CB to fail to
operate or to fall outside the manufacturers timing specifications. During the
subsequent investigation problems in the control circuit can also be identified
directly using the instruments Analog or Auxiliary channels.
49
Figure 83 Plot & data from a TDR test showing parameters of all connected
channels
The numerical data for each test can be shown and if manufactures specification
are available in the test plan automated pass/fail indications are given.
For detailed analysis of circuit breakers Motion Channels are used to measure
motion of the circuit breaker using transducers. Motion transducers that
temporarily connected to predetermined points on the mechanism convert
measured mechanical motion into an electrical signal that is communicated to
Instrument.
the
are
the
the
50
51
References:
1. Balcombe, H. The assessment and management of older oil-filled switchgear,
Power Engineering Journal December 1997
2. Bradwell, A. and Bates, G. Analysis of dielectric measurements on switchgear
bushings in British Rail 25 kV electrification switching stations, IEE Proceedings,
Vol.132, Pt.B, No.1, January 1985
3. Brown, P. Non-intrusive partial discharge measurements on high voltage
switchgear
4. Caviagelli, G., Kopaczynski, D., Lachman, M. and Levi, R. AC Power Factor
Versus DC Insulation Resistance Measurements
5. Douglas, R. and Booth, N. Testing Ageing Switchgear, IE Australia Electric
Energy Conference, 1992
6. EA Technology PDM3, Ultratev+ User Manual
7. HVPD PDsurveyor Air & Longshot User Manual
8. Ultra probe 2000 User Manual
9. Hilder, D. Partial-discharge measurements for insulation quality, Power
Engineering Journal, March 1992
10. James, R., Phung B. and Blackburn, T. Partial Discharge Phenomena
Characteristics, Interaction With Materials, Interpretation, ESAA Short Course,
Brisbane, April 1999
11. Koenig, D. and Y. Narayana Rao Partial Discharges in Electrical Power
Apparatus VDE Verlag
12. Lachman, M., Doble Engineering , 1998 Seminar Course Notes
13. Lemke Diagnostics GmbH Differential PD-probe LDP-5 Users Manual
14. Lundgaard, L. Partial Discharge Part XIV: Acoustic Partial Discharge
Detection Practical Application, IEEE Electrical Insulation Magazine,
September/October 1992-Vol.8, No.5
15. Mettam, J. Insulation Aging In 12kV Switchgear A Users Perspective,
Proceedings of the 4th International Conference on Properties and Applications
of Dielectric Materials, July 3-8, 1994, Brisbane Australia
16. Neil Davies, Simon Goldthorpe Testing distribution switchgear for partial
discharge in the Laboratory and the field, Paper 804, CIRED Prague, 2009.
17. M. Boltze, S. Kornhuber, Various Methods of the partial discharge detection at
switchgears, 2011 Doble Engineering Company -78th Annual International
Doble Client Conference
18. Doble Lemke PD smart User Manual
High Voltage Conference 2015 IDC Technologies
52
53
36. Cigre Technical Brochure 556- SF6 Analysis for AIS, GIS and MTS Condition
Assessment (Feb 2014)
37. Cigre Technical Brochure 525- Risk Assessment on Defects in GIS based on PD
Diagnostics (2013)
38. Doble TDR 900-TDoble Manual.
39. Levi Jozef, Motion measurement and use of transducers for the Detection of
circuit breaker characteristics 2011 Doble Engineering Company -78th Annual
International Doble Client Conference
40. Levi Jozef, Radenko Ostojic Use of Micro Ohm Meter as a Power Source for
DRM testing of Dead Tank Circuit Breakers 2013 Doble Engineering Company 80th Annual International Doble Client Conference
Biography
Karl Haubner joined Doble Engineering in 2004 and is employed as the High
Voltage Test Application Engineer servicing the Asia-Pacific region. Prior to his
appointment with Doble Engineering he worked for the Utility Western Power. As the
Superintendent of the HV Test Laboratory he was responsible for all technical
aspects of the test group such as development and introduction of new condition
monitoring techniques on distribution, transmission and generating plant. In addition
to his employment with Doble Karl also provides testing and consultancy services to
the industry via his company High Voltage Solutions. He is the author of several
technical papers on condition monitoring of HV assets and cable fault location and
has delivered short courses on testing techniques at University and Industry level.
Karl has a Diploma in Electrical Engineering and is member of Cigre D1, AS
Committee EL-007, and of VDE.
54
Appendix 1
Verification of effectiveness and limitation of various on-line techniques used by conducting parallel on and off-line measurements using a range
of commercial detectors.
A ring main unit (RMU) that had been removed from service due to PD activity (signs of surface PD activity at the fuse holders evident) was
energised from a HV test transformer. The RMU is gas insulated and all defects (existing or simulated) relate to the exterior connection points
and not the busbar. The level of Discharge Activity present was measured via a 20nF coupling capacitor and an IEC 60270 type compliant PD
detector (Doble-Lemke PDsmart) operating in the frequency range between 100-500 kHz as prescribed in the standard. The total test circuit was
calibrated by injecting 10pC across the switchgear. The RMU was first energised as found and then measurements were taken at several
voltage levels. Several defects were then introduced to simulate other faults than the ones present already on the switchboard but commonly
found in switchgear
Whilst the off-line PD measurements provide more statistical parameters then the pC value shown below for the purpose of this exercise only
IEC pC values and the phase resolved PD patterns are listed. Phase synchronisation for the off-line measurement was via the coupling
capacitor (true phase position) whereas synchronisation for the hand held RFI/EMI Spectrum Analyser and the Ultra-Wideband TEV analyser
was from the Mains. Humidity and temperate conditions were recorded during the tests but are not shown as the aim was to compare
measurement techniques.
The transmission path from the PD source to sensor the metal cover was direct with the defect always in close proximity to the enclosure. This
represents an ideal situation compared to example busbar defects in Metal Clad Switchgear were the transmission path may be longer and
obstructed by other barrier material or additional covers.
55
TEV
Acoustics
Airborne Acoustics
Contact
RFI/EMI
UHF/TEV sensor
Full spectrum & point
on wave (phase
resolved)
Corona Camera
Ultra-wide Band
TEV Sensor
Test
(Background~15dB)
Measurement ~15dB
30pC
1-2dB
BG 14db
As found
at 3kV
Clearly
Audible Audible
audibl
17dbm 15dm
e
None
detected with
covers on
~15dB
150-200pC
As found
10kV
as found
@ 14kV
500-600pC
4dB
Clearly
Audible Audible
audibl
19dbm 20dbm
e
None
detected with
covers on
13dB
Pulse/
Cycle:
Clearly
Audible Audible
audibl
25dbm 20dbm
e
None
detected with ~15dB
covers on
56
1.5
Severity
5
With covers
removed
~15dB
800-1000pC
as found
@ 14kV
B Phase
13dB
Pulse/
Clearly
Cycle: Audible Audible
audibl
0-3
46dbm 31dbm
e
Severity
1
~ 15dB
Void
Discharg
e insert
insulator
with
voids
800-1200pC low
pulse count
24dB
Pulse/ -3dBV -3dBV Not
Cycle: 0 Not
Not
audibl
Severity audible audible e
0.16
N/A
57
700-800pC
Voltage
indicator
O/C
+2000pC
Cable PD
(Stress
Control
removed)
33dB
Pulse/
-3dBV -3dBV Not
Cycle:
Not
Not
audibl
56
audible audible e
Severity
2.08
25dB
Pulse/
Cycle: Audible
5.5
25dbV
Severity
84
~ 26dB
N/A
~
30dB
Audible
Clearly
fair to
audibl
poor
e
19dbV
58