FPSO-FSO State of The Art
FPSO-FSO State of The Art
FPSO-FSO State of The Art
Review article
FPSO/FSO: State of the art
Yoshihide Shimamura
MODEC Inc., 4-2-8 Kohinata, Bunkyo-ku, Tokyo 112-0006, Japan
1 Introduction
1.1 What is an FPSO system?
In recent years, offshore oilfield developments have
been moving toward deeper water and more remote
areas, and now these fields are located in water depths
of over 5000 feet, which were once thought impracticable to develop economically. In addition, the fast
diminishing rate of discovery of new giant fields, the
so-called big elephants, necessitates the development of
the smaller oil fields. The FPSO system is one concept
that can lower the minimum economic field size, and
make possible the development of these small or remote oil fields in deeper water.
60
61
62
tem, the external turret mooring system, and the conventional spread mooring system. The reasons for this
change will be discussed in a later section.
Riser system. For riser systems, the advance in analysis
tools is similar to that for mooring analysis tools. In
addition, the material and construction of flexible risers
is now more fully developed, and larger-diameter
products are available for ever-increasing water depths.
Also, various configurations of risers have been developed and used in order to accommodate different design considerations, such as the need for multiple risers,
and varying environmental conditions, such as shallow
or deep water, a harsh environment, etc.
Hull structure. The advance in hull structural analysis
is an application of site-specific design conditions. As
the FPSO system will be stationed on-site for several
years, it is reasonable to use site-specific environmental
criteria for hull structure design instead of applying
the traditional design criteria for conventional merchant vessels, which have typically been for the winter
season in the North Atlantic. For example, for benign
areas such as the South China Sea, the hull scantlings
can rationally be reduced by this site-specific design
approach. Classification societies are now accepting
this approach, which will be beneficial for design
optimization.
Drilling and production technology. The drilling and
production technology of the petroleum industry supports the deployment of FPSO systems. One technological advance has been in the design of the subsea
wellhead, which has improved reliability. In addition,
directional drilling and horizontal-well technology has
63
64
designs have been produced which are capable of remaining on-station during 100-year typhoon conditions.
Because disconnectable systems have a complex
mechanism for disconnection and reconnection, and
also because FPSO systems must maintained their
propulsion and navigation systems for sailing during
their operational period, CAPEX (Capital Expenditure) and OPEX (Operational Expenditure) become
very expensive. Therefore, new applications for discon-
65
A conversion has cost and schedule advantages. Although the purchase price of a tanker depends heavily
on the tanker market, there are several surplus fleets
available. A double-hull arrangement is not mandatory
for an FPSO system, except for some coastal areas, and
there are many single-hull tankers available because of
the recent requirement to phase out single-hull tankers.
66
In a conversion shipyard, extensive repair and lifeextension work can be carried out in parallel with
the integration of mooring and production facilities.
Redundant utility systems, such as the propulsion and
navigation system, can similarly be decommissioned.
The extent and schedule of conversion work will vary
depending on the field-specific design requirements. On
average, a conversion in a shipyard will take 1018
months, including commissioning activities.
Recent orders for FPSO systems require a lengthy,
continuous operating life at the field location, i.e., as
long as 15 years without dry-docking. In order to comply with this requirement, a thorough analysis of the
hull structure under specific environmental conditions
and a sustainable corrosion protection system are now
required. In addition, easy maintenance and rapid replacement of the utility systems is mandatory. In this
respect, a newly built FPSO system has advantages.
Although a newly built system requires a much higher
initial CAPEX and more time for the design and construction stages, it can be designed fit-for-purpose.
Further, the availability of shipyard space is another
consideration. Normal competent shipyards are busy
with traditional marine vessels, and dock availability is
limited depending on the state of the shipbuilding market. A newly built FPSO system will take about 1824
months for both design and construction.
To assess hull structures, classification societies have
developed sophisticated software for FPSO/FSO system
design assessment, based on site-specific environment
conditions. This has helped to rationalize structural designs for newly built systems. For conversions, an assessment of the existing structure is performed based on the
actual plate thickness, which is found by thickness gauging. To assess fatigue strength, the vessels accumulated
fatigue damage taken from its service records, is taken
into account. However, a thorough visual inspection by
experienced surveyors is very important, as localized
corrosion, pitting, and damage normally need to be
assessed.
The design of a corrosion protection system is a critical part of the structural design and integrity of FPSO
system. This is especially important for submerged
areas and tank linings. A failure in these areas caused
by corrosion will result in an extensive shut-down of the
FPSO system coupled with high repair costs. For the
submerged areas, the traditional corrosion protection
has been conventional coal tar epoxy-based paint systems. This has proved to be very effective. However,
there is a need to develop new paint systems which have
higher abrasion resistance and give more durable corrosion protection for the boot-top area. In addition,
ecofriendly and long-life antifouling paint needs to be
developed. For tank areas, coal tar epoxy-type paint
systems are generally used, and they work very effec-
67
68
the operators technical requirements. However, on delivery, the contractor and operator will part company
and sometimes the original design intent, or its basis,
will disappear. This kind of discontinuity can have a
crucial impact on overall safety and maintenance. Similarly, for the technical integrity of the entire FPSO system, if one part of the system is designed, constructed,
and operated without any consideration of the other
parts, these can again be serious repercussions.
To ensure technical integrity, several review sessions
are held during the project period with participants
from several disciplines. For example, during the design
phase, a design review meeting will be held with the
design engineers from both the operator and the contractor, and representatives from the construction supervisors and the operation team. The design review
meeting will identify the problems of safety, operability,
and maintainability prior to construction and operation.
During the construction phase, project review meetings
will be held to check the physical implementation of the
design and review any problems that have materialized.
This is also the right time to check operations and maintenance manuals against design intent, as well as the
competency and training programs for operational staff.
Although the Classification Society has a role as a third
party to ensure technical integrity, these sessions are
more oriented toward maintenance and operability.
In the case of a time charter contract, the contractor
will provide design, engineering, construction, commissioning, and operational services. This means that the
contractors engineering team is required to be heavily
involved in the eventual operations, as well as the operation team having input into the design and construction phases. Close communication is essential to ensure
eventual technical integrity. To support this technical
integrity program, a computerized database system
for document control is a valuable tool. As many
documents and drawings are generated and reviewed
throughout the project period, and all necessary information must be available during the eventual operations, the document control system is very important.
One successful method of document control is to compile the relevant information as part of a system-bysystem breakdown of the entire FPSO installation. This
means that each component or item of equipment of the
system will have a tag numbered, and its operation and
maintenance manuals, test reports, certificates, etc., will
be filed in a computerized database. Although one
bound hard copy needs to be delivered to the operations team as a back-up, the computerized system can
be accessed via the telecommunications network from
remote areas such as offshore and onshore bases. The
retrieval of essential information is very easy. As this
database will be generated and developed during the
project period, it will be helpful to communicate with
69
5 Conclusions
The current state of the art in FPSO system development has been reviewed, and new frontiers have briefly
been explained. As offshore oil and gas field developments are becoming more and more important, the
future of the FPSO system market is bright, with great
prospects for many new applications.
When I first worked on FPSO systems in 1983, there
were very few in existence and engineering knowhow was basically an extrapolation of existing tanker
and onshore-plant knowledge. Since then, the industry
has invented new technologies and accumulated the
70
References
1. England LT, Duggal AS, Queen LA (2001) A comparison between
turret- and spread-moored F(P)SOs for deepwater field developments. Deep Offshore Technology Symposium 2001
2. Yamada K, Kawase M, Shimamura Y (1999) Marginal field
development by adopting FPSO lease contract. J Jpn Assoc Pet
Technology 64:527532