Massie1976 3
Massie1976 3
Massie1976 3
ENGINEERING
VoLu m e I
B R E A K W A T E R DESIGN
C o a s t a L E n g i n e e r i ng G r o u p
Department
of CiviL
Engineering
D e L f t U n i v e r s i t y of TechnoLogy
D e L f t , The N e t h e r l a n d s
COASTAL ENGINEERING
Volume I I I - Breakwater
Design
e d i t e d by
astal
E n g i n e e r i n g Group
partnient of C i v i l
Engineering
I f t U n i v e r s i t y o f Technology
IFT
.le
Netherlands
976
november
1976
3,10
2.
3.
4.
5.
6.
7.
Introduction
1.1
Scope
1.2
Contributors
1.3
References
1.4
Miscellaneous Remarks
General Considerations
2.1
Purposes
2.2
2.3
2.4
Performance Requirements
2.5
Review
Types of Breakwaters
10
3.1
Introduction
10
3.2
Comparison of Types
10
3.3
Conclusions
19
20
4.1
Definition
20
4.2
Two D i s t i n c t Types
20
4.3
21
22
5.1
Introduction
22
5.2
Run-up Determination
22
5.3
24
5.4
25
5.5
Wave Overtopping
25
5.6
Wave Transmission
26
Construction Materials
28
6.1
Necessary Properties
28
6.2
Desirable Properties
28
6.3
29
6.4
30
6.5
Armor Selection
35
6.6
Methods to increase S t a b i l i t y
36
Armor Computations
37
7.1
History
37
7.2
Theoretical Background
37
7.3
40
7.4
Special Applications
42
7.5
S e n s i t i v i t y o f Hudson Formula
43
7.6
8.
9.
10.
44
7.7
45
7.8
Crest Width
47
7.9
Review
47
The Core
48
8.1
Function
43
8.2
Materials
48
8.3
Construction Methods
49
50
9.2
50
9.3
Design C r i t e r i a f o r F i l t e r s
51
9.4
Design C r i t e r i a f o r Toes
51
9.5
F i l t e r Layer Constructions
51
9.6
Toe Constructions
54
9.7
57
58
58
10.2
Construction Methods
58
10.3
60
10.4
62
10.5
Review
63
Optimum Design
64
11.1
Introduction
64
11.2
64
11.3
Given Data
65
11.4
Preliminary Calculations
68
11.5
72
11.6
78
11.7
81
11.8
Additional Remarks
84
12.
13.
Monolithic Breakwaters
13.1
13.2
14.
50
9.1
10.1
11.
Definition
General Features
Construction Materials
86
87
87
87
91
14.1
Introduction
91
14.2
Environmental Differences
91
14.3
Consequences f o r Materials
91
iii
15.
16.
17.
18.
19.
Introduction
92
15.2
Standing Waves
92
15.3
15.4
Comparative Results
15.5
96
15.6
Additional Comments
96
93
'
95
98
16.1
98
16.2
Types of Foundations
98
16.3
100
16.4
103
16.5
Breakwater Sliding
106
16.6
Example of Sliding
111
16.7
Breakwater Rotation
114
16.8
Example of Rotation
115
116
17.1
Introduction
116
17.2
Standing Waves
116
17.3
116
118
18.1
Introduction
118
18.2
118
18.3
121
18.4
Construction in Place
122
Optimum Design
19.1
20.
92
Introduction
123
123
19.2
Design Data
123
19.3
Preliminary Computations
125
19.4
128
19.5
130
19.6
Construction Costs
131
19.7
Determination of Damage
133
19.8
The Optimization
141
19.9
Additional Comments
151
152
20.1
Introduction
152
2.2
152
20.3
Proposed Designs
153
20.4
Evaluation of Designs
153
20.5
Construction Details
154
162
References
169
iv
LIST OF TABLES
Table
Title
Page
number
1.1
Contributing S t a f f
7.1
45
11.1 .
Storm data
67
11.2
68
11.3
Wave shoaling
71
11.4
76
78
11.5
breakwater
11.6
11.7
Cost Summary
80
81
82
16.1
104
16.2
Breakwater s l i d i n g parameters
109
16.3
S l i d i n g computation
113
19.1
Storm data
123
19.2
125
19.3
Wave computations
126
19.4
S t a t i s t i c a l calculation f o r Hd = 8.0 m
127
19.5
Element quantities
133
19.6
135
19.7
139
19.8
Optimization computations
143
20,1
154
LIST OF FIGURES
Figure
Title
Page
number
2.1
2.2
2.3
2.4
3.1
A i r bubble curtain
10
3.2
Composite breakwater
11
3.3
Resonant breakwater
16
4.1
Overtopping breakwater
20
4.2
21
5.1
Wave run-up
23
5.2
24
5.3
27
6.1
30
6.2
Cob
31
6.3
Concrete cube
31
6.4
32
6.5
Dolos
32
6.6
Tetrapod
34
6.7
Tri bar
35
7.1
37
7.2
40
7.3
43
7.4
45
9.1
Pressures w i t h i n breakwater
50
9.2
Woven f a b r i c mattress
52
9.3
53
9.4
55
9.5
A l t e r n a t i v e toe construction
56
9.6
56
62
10,1
11.1
66
11.2
Wave data at s i t e
70
11.3
73
11.4
75
11.5
79
11.6
83
vi
Figure
Title
Page
number
13.1
87
13.2
88
13.3
89
13.4
89
13.5
89
13.6
Composite Breakwater
90
15,1
93
16.1
98
16.2
Quicksand condition
99
16.3
99
16.4
100
16.5
Mass-spring system
102
16.6
104
16.7
105
16.8
Forces on breakwaters
106
16.9
Breakwater s l i d i n g parameters
110
16.10
Forces important to r o t a t i o n
114
17,1
117
18.1
119
18.2
120
18.3
120
18.4
121
19.1
124
129
19.2
quency of exceedance
19.3
Element details
131
19.4
Breakwater s l i d i n g parameters
138
19.5
19.6
145
148
solutions
19.7
149
19.8
150
20.1
155
20.2
156
20.3
Optimization curves
159
20.4
160
20.5
161
1.
INTRODUCTION
W.W. Massie
1.1. Scope
This t h i r d volume of the series on coastal engineering concentrates on a single specialized t o p i c : breakwater design. The subdivisions into four categories found i n the previous two volumes is not
found here; a l l o f t h i s volume relates to harbors i n some way. Of
course, some information presented here can be used elsewhere. For
example, knowledge of wave impact forces, important f o r the design
of monolithic breakwaters, can also be handy when designing offshore
structures.
A more d i r e c t t i e can be made between the design methods used
f o r breakwaters and those needed f o r coastal defense works - volume I ,
chapter 30.
1.2. Contributors
The primary authors are l i s t e d at the beginning of each chapter;
f i n a l editing and coordination was done by W.W. Massie, layout by
W. Tilmans, J . van Overeem and'J.D. Schepers. Table 1.1 l i s t s the s t a f f
members of the Coastal Engineering Group who contributed to t h i s volume.
1.3.
References
One general reference is so handy f o r breakwater design that i t
Manual
Manual.
Table 1.1
Contributors to t h i s volume
2.
GENERAL CONSIDERATIONS
W.W. Massie
2 . 1 . Purpose
Most generally speaking, breakwaters are b u i l t to change the coast
in some way.* The development o f the need f o r breakwaters has paralleled that of harbor and approach channel development outlined i n chapters 14 and 15 of volume I .
More s p e c i f i c purposes f o r breakwaters were described i n chapter 18
of volume I , but shall be treated i n more detail
here.
ships in harbors can be detrimental to cargo handling e f f i c i e n c y , especiall y f o r container ships. Wave action i n approach channels can increase the
danger f o r tugboat crews and make navigation more d i f f i c u l t . Furthermore,
dredging i n exposed locations is r e l a t i v e l y expensive - see chapter 16 o f
volume I . Figure 2.1 shows a small harbor protected by a breakwater.
A breakwater can also serve to reduce the amount of dredging required
in a harbor entrance. This can r e s u l t from the c u t t i n g o f f o f the l i t t o r a l
transport supply to the approach channel, or i t can r e s u l t from natural
scouring action i n an a r t i f i c i a l l y narrowed channel. This purpose was
highlighted b r i e f l y i n chaper 18 of volume I . Figure 2.2 shows such an
application constructed i n an attempt to increase natural channel scouring.
At locations where l i t t l e or no natural protection e x i s t s , breakwaters
often serve as quay f a c i l i t i e s as w e l l . Such dual usage of the breakwater i s
economical i n terms o f harbor area but requires a d i f f e r e n t type of breakwater s t r u c t u r e . This aspect w i l l be discussed f u r t h e r i n section 4 of t h i s
chapter.
A f o u r t h possible important purpose of a breakwater can be to guide
the currents i n the channel or along the coast. I t has already been shown
(volume I ch. 18) how the channel currents can be a r t i f i c i a l l y concentrated
to maintain depth. On the other hand, a breakwater can also be b u i l t to reduce the gradient o f the cross current i n an approach channel.
Ships moving at slow speed in a channel are r e l a t i v e l y d i f f i c u l t to
hold on course. A constant cross current makes the p i l o t ' s job more
d i f f i c u l t but can often be t o l e r a t e d . On the other hand, an abrupt
change i n cross current strength as the ship progresses along the
channel can cause dangerous navigation s i t u a t i o n s . This i s shown
schematically in f i g u r e 2.3. One of the primary considerations i n
the design of the Europoort breakwaters i n The Netherlands was the
l i m i t a t i o n of the cross current gradient. The r e s u l t i n g current patt e r n , observed i n a physical model is shown i n f i g u r e 2.4.
Obviously, a single breakwater can serve more than one of these
four main purposes. The design requirements implied by these functional
demands are discussed i n section 4; i n the f o l l o w i n g section we examine
the general design data required.
* This d e f i n i t i o n includes coastal defense works; the rest of the d i s cussion i s l i m i t e d to harbor breakwaters, however.
Figure 2.1
PLYMOUTH HARBOR, U.S.A.
Figure 2.2
COLUMBIA
RIVER ENTRANCE
CROSS
1.5
1.3
1.1
CURRENT
1.0
(KNOTS)
1.0
1.0
1.0
Actual Path
T
Desired Poth
Angle Relative
to Desired Path
16
13
11.5
10.5
9.5
Figure 2.3
Figure l.k
CURRENT PATTERN AT EUROPOORT ENTRANCE
HALF AN HOUR BEFORE H.W. HOOK OF HOLLAND
Manual.
quantity of overtopping by spray from the broken waves. When the inner side
of a breakwater serves as a quay, the ship mooring forces - dependent part i a l l y on wind influences - can be important in the design.
Temperature data can be important f o r the selection of construction
materials. Special concrete must be used i f repeated cycles o f freezing
and thawing are expected.
Special navigational aids may be needed on a breakwater i n a locat i o n where fog forms f r e q u e n t l y . These aids can range from radar
r e f l e c t o r s to radio beacon i n s t a l l a t i o n s .
Since every breakwater must have some sort of foundation
- how-
Performance Requirements
Several factors which can influence our choice o f breakwater type
have already been mentioned.. These have been grouped under purpose and
under design information i n e a r l i e r sections of t h i s chapter. In t h i s
section other factors a f f e c t i n g the choice of design type w i l l be considered. A catalog of types of breakwaters with t h e i r advantages and
disadvantages w i l l be presented i n chapter 3.
In contrast to dikes, the performance requirements f o r breakwaters
are usually much less s t r i n g e n t . For example, a breakwater may be needed
only temporarily such as those used to establish the beachheads i n World
War I I . On the other hand, a permanent structure may be desirable, but
t h i s structure need only be e f f e c t i v e i n t e r m i t t e n t l y . One can conceive
of a f e r r y harbor entrance which only need be protected from wave action
when the f e r r y is moving i n or out.
Available construction and maintenance methods can also r e s u l t i n
modified designs. I f , f o r example, navigational aids and the breakwater i t s e l f must be repaired q u i c k l y , then a higher crest elevation may be d i c tated by the need to move equipment along the dam during severe weather.
Indeed, f o r some purposes, a breakwater need not be much higher than the
s t i l l water l e v e l , while f o r others i t must be nearly as high as a dike.
I f quay f a c i l i t i e s are to be provided on the inner side of the breakwater,
special foundations w i l l be required to withstand the additional loads
from cargo handling and to l i m i t settlement.
Another contrast with dike is that a breakwater need not always be
impermeable. Some types of breakwaters such as a i r bubble curtains or
f l o a t i n g breakwaters do l i t t l e to r e s t r i c t currents.
2.5.
Review
The more important purposes and design and performance require-
ments of breakwaters have been outlined i n a general way. In the f o l lowing chapter, many types of breakwaters w i l l be described b r i e f l y
along with a summary of t h e i r advantages and disadvantages.
One of the most important tasks of the designer is to achieve a
solution to a problem having the lowest total
include much more than construction and maintenance costs of the breakwater; r e c r e a t i o n a l , environmental, and i n d i r e c t damages w i t h i n a harbor r e s u l t i n g from breakwater f a i l u r e should also be considered. This
concept of optimum design has been introduced i n chapter 13 of volume I .
10
3.
TYPES OF BREAKWATERS
J.F. Agema
W.W. Massie
3 . 1 . Introduction
The purpose of t h i s chapter is to review and compare the various
types o f devices and structures available as breakwaters. This comparison treats rubble mound and monolithic breakwaters i n a rather
summary way; these s p e c i f i c types - with many variations - are d i s cussed i n more detail i n l a t e r chapters. They are included here f o r
completeness; s u f f i c i e n t v a r i e t y is i l l u s t r a t e d to show t h e i r vers a t i l i t y . These comparisons are presented i n a sort of o u t l i n e form
in an e f f o r t to preserve the survey character of t h i s chapter. Twenty
d i f f e r e n t breakwater types are l i s t e d i n alphabetical order and compared i n the following section.
Specific references and examples o f many of the various types
are given. Two general references - Shore Protection
A i r Bubble Curtains
Description: Permanent submerged pipeline discharging a i r to
cause currents i n water which tend to cause waves
to break. Adapted to i n t e r m i t t e n t use to protect small
areas.
Advantages: Uses no space
Reduces density currents - see Vol I , ch. 23.
Can be quickly constructed.
Does not bother shipping.
Aesthetic - i n v i s i b l e .
Undamaged by large waves.
Disadvantages: Expensive i n operation.
I n e f f e c t i v e except f o r very short waves.
A i r pipe may become covered by sediment, i f used only
intermittently.
Figure 3,1
AIR BUBBLE CURTAIN
Beaches
Description: Permanent, often natural sand or gravel slopes
which destroy wave energy by breaking. Waves can be reduced i n channels by r e f r a c t i o n .
11
Advantages: E f f e c t i v e .
Use natural materials.
Usually very durable.
Usually very inexpensive to maintain.
Aesthetic - recreational value.
Disadvantages: Possible sand loss at exposed locations.
Need much space - slopes of 1:10 or f l a t t e r are usually
needed.
Examples: Europoort Entrance
References; Volume I I of these notes.
c.
d.
f i g u r e 3,2
Figure 3.2
COMPOSITE BREAKWATER
12
e.
Floating Flexible
Description: Temporary f l e x i b l e bouyant f l o a t i n g device which
absorbs wave energy by f r i c t i o n with water and from internal
deformation.
Advantages: Inexpensive, usually.
Easily moved from s i t e to s i t e .
Often very quickly f a b r i c a t e d .
Relatively independent of bottom conditions.
Disadvantages: I n e f f e c t i v e against long waves.
Must be anchored.
Some types such as brushwood mattresses require much s k i l l e d
labor f o r f a b r i c a t i o n .
Examples: Brushwood mattresses.
Floating auto t i r e s ,
f l o a t i n g p l a s t i c mats.
References: Wiegel, Friend (1958), G r i f f i n (1972), Kowalski (1974).
f.
Floating Rigid
Description: Usually a temporary solution consisting of a large
f l o a t i n g body. This may be a ship or a large shallow pontoon.
Advantages: Easily moved to new s i t e .
Usually consume l i t t l e space.
Can provide temporary quay f a c i l i t i e s .
Independent of bottom except f o r anchors.
Disadvantages: I n e f f e c t i v e f o r long waves.
Must be anchored.
Can resonate leading to poor performance at some wave f r e quencies.
Damaged when design conditions exceeded.
Examples: Large ships or pontoons.
References: G r i f f i n (1972), Kowalski (1974).
g.
Monolithic "Floating"
Description: Semipermanent concept f o r a monolithic breakwater
suitable f o r use on mud coasts where the bottom material
bearing capacity is l i m i t e d . The structure consists of a large
caisson or ship f l o a t i n g with i t s hull p r o j e c t i n g some meters
i n t o the mud.
13
Disadvantages: D i f f i c u l t to construct.
Need high q u a l i t y concrete and workmanship.
Even bottom needed.
I n t o l e r a n t of settlement.
Foundation problems on f i n e sand.
Severe damage when design condition exceeded.
Examples: Ekofisk storage tank, North Sea
Baie Comeau, Canada
References: Jarlan (1961)
Marks & Jarlan (1969)
G r i f f i n (1972)
chapters 13 through 19.
i.
14
15
Oil Slick
Description: very temporary emergency measure used at sea to reduce spray i n heavy seas. Effectiveness derives from surface
tension influences.
Advantages: Inexpensive .
Easily implemented under emergency conditions .
Disadvantages: L i t t l e , i f any, actual wave reduction.
Aesthetic - p o l l u t i o n source.
m.
Pile Row
Description; Permanent structure formed by d r i v i n g a row of piles
either close together or spaced apart. Suitable f o r groins as
well as simple breakwaters.
Advantages: Inexpensive.
Uses very l i t t l e space.
Well adapted to poor foundation conditions.
Can be incorporated in quay s t r u c t u r e .
Can be rather watertight or open as desired.
Disadvantages: wave r e f l e c t i o n .
Possible scour at bottom.
Wood piles attacked by worms and r o t .
Examples: Evanston, U.S.A.
References: Wiegel (1961).
16
n.
Resonant Breakwater
Description: A series of rectangular basins connected to a harbor
entrance such that each is tuned to absorb energy o f a given
commonly occurring wave period. In contrast to ch. 19 of Vol.
a seiche is encouraged i n these basins.
incident
vi/aves
harbor basin
Figure 3. 3
RESONANT BREAKV^/ATER
settlement.
17
Advantages: Durable.
Flexible - adapts to settlement.
Uses least material of rubble mound types.
Adapts well to i r r e g u l a r bathymetry.
Well adapted to "dry" construction.
Disadvantages: Armor units must be fabricated
Needs much s k i l l in construction.
Impossible to place armor under water.
Unsuited to very s o f t ground.
Needs underlayer i f b u i l t on sand.
Examples: N a w i l i w i l i Kauai, U.S.A.
References: Palmar (1960), Agema (1972)
chapters 4 through 12
q.
r.
18
19
3.3
Conclusions
I t Is obvious from the previous section that no one type o f break-
water is always best. Further, the choice of a breakwater f o r a given s i t u ation is dependent upon so many factors that i t is nearly impossible to
give s p e c i f i c rules of thumb f o r determing the "best" type. A few general
rules can be given, however:
- Rubble mound structures are the most durable, and as such are best
suited to extremely heavy wave attack.
- Monolithic structures use less space and material; t h i s is especially
true i n deeper water.
- Special types of breakwaters are usually best suited to s p e c i f i c
special applications.
Details o f rubble mound breakwaters are worked out i n the f o l l o w i n g
nine chapters; problems of monolithic breakwaters are taken up in chapters
13 through 19.
20
4.
J.F. Agema
4.1. Definition
What is a rubble mound breakwater? The cynic's description "a p i l e
of junk" is not too bad provided that a couple o f q u a l i f i c a t i o n s are
added. The f i r s t q u a l i f i c a t i o n i s that the "junk" must be some r e l a t i vely dense material such as stone or concrete elements
(compressed
scrap auto bodies have also been suggested). The second i s that the " p i l e "
must be b u i l t up i n a more or less orderly fashion. In the remainder
of t h i s chapter we b r i e f l y describe the parts of a rubble mound breakwater and t h e i r i n t e r r e l a t i o n s h i p s .
4.2. Two D i s t i n c t Types
The use to be made of the area d i r e c t l y leeward o f a rubble mound
breakwater plays an important role i n the choice between an overtopping
or non-overtopping rubble mound s t r u c t u r e . In general, the less important or c r i t i c a l the a c t i v i t y on the lee side, the more overtopping
that may be allowed. For example, i f containers are to be loaded i n the
immediate lee area (an operation very sensitive to harbor wave a c t i o n ) ,
very l i t t l e , i f any, wave overtopping would be acceptable. I f , on the
other hand, a breakwater served p r i m a r i l y to guide the current near a
harbor entrance, the regular overtopping would be of no consequence.
I f a breakwater i s designed to be overtopped, then special measures
must be taken to assure that the upper portion of the inner
slope is not
Figure / . . l
OVERTOPPING BREAKWATER
21
Crest
^ MSL
z
FILTER LAYERS
Figure 4.2
NGN OVERTOPPING BREAKWATER
22
5.
A. Paape
5 . 1 . Introduction
Reflection of waves against a slope or the breaking o f waves
on some form o f breakwater leads to water level f l u c t u a t i o n s on the
slope surface which can considerably exceed the amplitude of the
incident waves. For example, when waves are f u l l y r e f l e c t e d by an
impermeable v e r t i c a l b a r r i e r , the water level f l u c t u a t i o n at the
wall is t h e o r e t i c a l l y two times the height of the incident waves.
HiWhen waves break on a slope, a portion of t h e i r momentum i s
transferred to a tongue of water rushing up the slope. The run-up,
R, is defined as the maximum v e r t i c a l elevation reached by t h i s
tongue measured r e l a t i v e to the s t i l l water level - see f i g u r e 5 . 1 .
I t is implied i n t h i s d e f i n i t i o n that the crest of the slope is higher
than the run-up. Since the run-up is measured r e l a t i v e to the s t i l l
water l e v e l , the run-up, R, also includes e f f e c t s of wave set-up caused by tne r a d i a t i o n stress - volume I I .
5.2. Run-up Determination
When regular waves are considered, a unique r e l a t i o n s h i p exists
between the wave run-up, R, and the wave properties, height and period,
and structure c h a r a c t e r i s t i c s , toe depth, slope angle, roughness, poros i t y , and foreshore slope. These parameters are also shown i n f i g u r e 5 . 1 .
Thus:
R = f ( H . , T, h^, a, e, r , n) *
(5.01)
where:
Hi is the incident wave h e i g t .
i s the depth at the toe of the slope
ht
n is the porosity of the slope.
r
23
Figure 5.1
WAVE RUN-UP DEFINITION SKETCH
function
is the equivalent
en
Golfoverslag.''^
I t is obvious that a more complicated s i t u a t i o n exists when i r r e gular waves are involved. Because the wave properties now vary continuousl y the run-up also becomes a stochastic variable. d'Angremond and van
Oorschot (1968) report that the s t a t i s t i c a l properties of the run-up are
dependent upon more than j u s t wave characteristics f o r a given slope.
24
LOO
25
In spite of i t s r e s t r i c t i o n s , data
26
relate
are
needed.
When the crest elevation is s t i l l
(5.02)
for^ = 0 :
(5.03)
for^
1
H,
3
< - | : ^ > |
(5.04)
where:
Hj^ is the incident wave height,
H, is the transmitted wave height, and
is the elevation of the crest above the s t i l l water level,
The above equations can be used with regular as well as with i r r e g u l a r
waves i f the s i g n i f i c a n t wave height is taken to characterize the spectrum.
27
crest e l e v a t i o n , z^. The slope roughness and angle are only important f o r
gentle slopes and wide crests (10 m or more).
For a submerged structure (z^ negative), the most important
parameter is -pp . Figure 5.3 shows some experimental r e s u l t s . The e f f e c t of wave steepness is also indicated. Longer waves r e s u l t i n great e r wave transmission. Figure 5.3 does not disagree with relations 5.03
0.2 -i
<u
Manual but
not presented in a very handy usuable form. One must be very careful when
attempting to use t h e i r graphs such as m-fure 7.59 in that book; all of
the parameters must match those used to make t h e i r f i g u r e s .
A correct conclusion is that too l i t t l e information on wave transmission is available in the l i t e r a t u r e to allow accurate estimates to be
made during design. A f a c t o r which makes the establishment of allowable
l i m i t s f o r wave transmission even more d i f f i c u l t is the simultaneous presence of waves which penetrate through the harbor entrance. The r e s u l t i n g
t o t a l wave height is not simply the sum of the wave height components!
Even a sum based upon wave energy proves to be unreliable. Large scale
model tests can provide i n s i g h t i n t o the problem f o r s p e c i f i c harbors.
For completeness, we should realize that waves may also penetrate
through rubble mound breakwater. A f t e r a l l , i t i s , in p r i n c i p l e , often a
permeable s t r u c t u r e . In p r a c t i c e , t h i s permeability to wind waves is
usually low, due to the f a c t that the waves are r e l a t i v e l y short and the
possible presence of a breakwater core consisting of f i n e material - see
chapter 8. However, i f the breakwater is b u i l t almost exclusively from
coarse material (concrete blocks, f o r example) and the wave period is
long (more than 12 seconds in order of magnitude), t h i s wave penetration
may no longer be n e g l i g i b l e . Because of the nonlinear character of the
flow through such a coarse porous medium, scale e f f e c t s can cause severe
problems f o r the i n t e r p r e t a t i o n of model data. Veltman-Geense (1974) has
attacked the problem of wave penetration both t h e o r e t i c a l l y and experimentally.
Properties required of armor units used to protect the exposed faces
of breakwaters are discussed in the following chapter.
-1.0
,
-0.8
,
-06
.
,
-OM -0,2
Relative S u b m e r g e n c e
10.0
0.0
^
Figure 5.3
WAVE TRANSMISSION FOR
SUBMERGED BREAKWATERS
28
6.
CONSTRUCTION MATERIALS
6.1.
Necessary Properties
J.F, Agema
29
Materials which pack into rather porous layers (have high void
r a t i o ) tend to damp the waves more e f f e c t i v e l y . Also a savings i n t o t a l
weight of material results and wave forces acting on the outer layers
are reduced. On the other hand, t h i s desirable large porosity can be i n
c o n f l i c t with the containment property f o r armor layers l i s t e d above.
Armor units which more or less interlock can prove to be more res i s t a n t to wave forces since a l o c a l l y high wave force is d i s t r i b u t e d
throughout several u n i t s . I f , t h i s i n t e r l o c k i n g is disturbed, however,
severe damage can r e s u l t . Conservatism i n the design of breakwater crests
and ends is o f t e n advisable, since interlocking e f f e c t s are least pronounced where an armor layer curves sharply - see chapter 7.
6.3. Characterizing Coefficients f o r Armor Units
Now that the properties of rubble mound breakwater materials i n general and of armor units i n p a r t i c u l a r are well defined, we need to transl a t e these properties into quantitative parameter values suitable f o r
use i n computations. Luckily, these properties can be reduced to four parameters, two of which are important f o r s t a b i l i t y . These are each discussed a b i t below; values f o r them f o r s p e c i f i c armor units are given i n
the f o l l o w i n g section. Their use in computations is explaned i n chapter 7.
The most straightforward property of an armor u n i t to express quant i t a t i v e l y is i t s mass density, p ^ . Since the density is only dependent
upon the material used in the armor u n i t , densities of the common armor
u n i t materials w i l l be discussed here.
Granite, the most common natural armor stone ranges i n density from
3
3
3
2650 kg/m to 3000 kg/m with most sorts having a density near 2700 kg/m .
Basalt, another commonly used stone, has a density o f 2900 kg/m~^. Very
occasionally, limestone blocks are used i n a breakwater. I t s lower re3
sistance to environmental attack and lower density - 2300 to 2750 kg/m are a handicap.
Concrete f o r armor units usually ranges i n density between 2300 and
3
3000 kg/m . Special aggregates needed to achieve even higher concrete dens i t i e s usually prove to be too expensive to be economical. The concrete
2
30
Details about a variety of armor u n i t s , l i s t e d i n alphabetical order, are given i n the following section. Agema (1972) and Hudson (1974)
also give summaries of available block forms.
Unless otherwise s p e c i f i e d , damage c o e f f i c i e n t values are given f o r
a double layer of randomly placed armor units subjected to non-breaking
waves in the main body of the breakwater.*
the percentage of armor units i n the area exposed to attack which are
displaced so f a r that they no longer f u l f i l l t h e i r f u n c t i o n as armor. This
rather a r b i t r a r y damage measurement is chosen f o r i t s ease of measurement
(via counting) and u t i l i t y i n optimum design
procedures.
Akmon
An anvil shaped plain concrete block - the name comes from the Greek
value, a
K,
m
0
4.8
11.
12.
^ 17
F i g u r e 5.1
See
Froteot-Lon
Manual.
31
b.
Cob
The cob is a hollow concrete block made by casting only the edges
of a cube - see f i g u r e 6.2. They are normally placed i n a regular pattern i n a single layer; they must be placed with t h e i r sides touching.
Preliminary model test data indicates that cobs have very high
damage c o e f f i c i e n t values, but give no q u a n t i t a t i v e information. Instead,
i t is suggested that model tests be conducted when s p e c i f i c applications
are being considered. A monolithic crest construction w i l l be required
in order to guarantee t h e i r s t a b i l i t y .
Cobs have a porosity of about 58% and a layer c o e f f i c i e n t ,
of
1.33. This high porosity implies that a major part o f the core containment f u n c t i o n must be accomplished by lower armor layers.
Reference: Anon (1970): A r t i f i c i a l Armouring of Marine Structures.
c.
Cube
Cubes of stone or concrete have been used as breakwater armor f o r
centuries. As such, they are, with natural stone, the oldest u n i t s . F i gure 6.3 shows a photo of a concrete cube. Obviously, t h e i r density i s
dependent upon the concrete used. Cut stone cubes are no longer economical now that concrete can be worked so e f f i c i e n t l y .
Damage c o e f f i c i e n t values are l i s t e d below:
Damage
Kr,
(%)
0
3.5
7.
8.
^ 14
Figure 6.3
CONCRETE CUBE
32
d.
Cube, modified
Various attempts have been made to modify the cube form i n order
Vroteotion
Manual
Hudson (1974)
0 . BH 3 block
Figure 5. L
MODIFIED CUBE FORMS
e.
Dolos
Dolosse are anchor shaped plain concrete armor units designed to
interlock with each other even when placed randomly. Figure 6.5 shows
such a u n i t , developed i n South A f r i c a .
Figure 6.5
DOLOS
33
f.
g.
h
4.0
5-10
4.9
10-15
6.6
15-20
8.0
20-30
10.0
30-40
12.2
40-50
15.0
I t s porosity i n a layer, n , is about 37% and i t has a layer coeff i c i e n t , K ^ , of between 1 . 0 0 and 1 . 1 5 .
Reference: Shore
h.
Protection
Manual
h
2.4
5-10
3.0
10-15
3.6
15-20
4.1
20-30
5.1
30-40
6.7
40-50
8.7
34
i.
Proteotion
Manual
Figure 6.5
TETRAPOD
KD*
(%)
0-5
8.3
5-10
10.8
10-15
13.4
15-20
15,9
20-30
19.2
30-40
23.4
40-50
27.8
35
j.
Tribar
A t r i b a r is a plain concrete u n i t consisting of three v e r t i c a l
Kj^
{%)
0-5
10.4
5-10
14.2
10-15
19.4
15-20
26.2
20-30
35.2
30-40
41,8
40-50
45,9
36
I f , on the other hand, a r t i f i c i a l armor units are selected, then o f ten one having a r e l a t i v e l y high
prove most economical since the breakwater cross section can be made much
smaller and/or l i g h t e r units can be used. The monolithic crest construction
can even save t o t a l material cost by allowing - sometimes - a lower crest
and l i g h t e r lee side armor than would otherwise be possible.
In the following chapter, where computations of necessary armor unit
weights are presented, some of these items come up again.
6.6. Methods to Increase S t a b i l i t y
I t is conceivable that armor layers having even higher e f f e c t i v e
damage c o e f f i c i e n t values can be economical. What are the methods available to increase the Kp value of armor units?
One technique used on the breakwater extension at IJmuiden was to
add asphalt to the stone armor layer. This served as a binder causing
the armor layer to f u n c t i o n as a unit and was, t h e r e f o r e , more resistant to wave attack than the individual stones. Unfortunately, the
asphalt was also s u f f i c i e n t to form a w a t e r - t i g h t covering such as is
common on dikes. This required that the armor layer r e s i s t the r e s u l t i n g
hydrostatic u p l i f t forces. Further, the reduced porosity increased the
wave run-up the slopes. These l a s t two problems are, of course, detriment a l to a design.
A proposed a l t e r n a t i v e is to use smaller quantities o f asphalt placed
here and there on the armor layer surface to t i e individual armor units
together into larger units but not to form a closed
layer.
The hope is
expressed by proponents of t h i s that s u f f i c i e n t prorosity w i l l be maintained to prevent hydrostatic u p l i f t pressures and to s t i l l absorb the
wave energy.
Development of these concepts is proceeding slowly, p a r t i a l l y because
of the d i f f i c u l t y of scaling the e l a s t o - p l a s t i c properties of asphalt in
a model.
37
7.
ARMOR COMPUTATIONS
7 . 1 . History
Until less than f i f t y years ago, rubble mound breakwaters were
designed purely based upon experience, usually in prototype. Castro
(1933) seems to have published the f i r s t modern work on t h i s subject.
I n i t i a l attempts to compute necessary armor u n i t sizes were based
upon theoretical considerations of the equilibrium of a single armor
u n i t on a slope. One need only to visualize the complex flow patterns
in a breaking wave rushing up a breakwater slope to conclude that a
purely theoretical approach is impossible. The theoretical background
of the currently used formula is indicated in the following section.
7.2. Theoretical Background
Consider a single armor u n i t resting on a slope making an angle e
with respect to the horizontal as shown in f i g u r e 7 . 1 .
The wave f o r c e , F, acting on the block, can be approximated very
crudely by considering the drag force of the water excerted on the block.
This approach yields a force proportional to the u n i t weight of water,
the projected area of the armor u n i t and the water surface slope. When
we f u r t h e r l e t the surface slope be proportional to the wave height
(This is reasonable since the wave length is determined by the wave period
and water depth o n l y . ) then i n a mathematical form:
2
g, H, d )
a (p,
(7.01)
where:
F is the drag f o r c e ,
d is a c h a r a c t e r i s t i c dimension of the block,
g is the acceleration of g r a v i t y ,
H is the wave height,
p is the mass density of water, and
a denotes "is proportional t o " .
Other assumptions about the force description can be made; a l l run
into d i f f i c u l t i e s somewhere. Therefore, (7.01) w i l l be transformed i n t o an
equation by introducing a p r o p o r t i o n a l i t y constant,
F = a
a:
(7.02)
g H d^
(7.03)
38
y N
(7.04)
(7.05a)
(7.05b)
f 1 F - ^sub
.(7.06a)
f 1 F + Wg^j[j sin e
(7.06b)
and
p g H d^
(7.07a)
e - sin 8) ^ a p g H d^
(7.07b)
I t is assumed, f u r t h e r , that the volume of the armor unit may be expressed as some constant, b, times the cube of i t s c h a r a c t e r i s t i c d i mension, d. In equation form:
"sub = (Pa - P) g b d^
(7.08)
(7.09a)
(7.09b)
( ^ ) b d (y COS e + sin 6 ) ^ a H
(7.10a)
p , -'P
(7.10b)
39
- P
(7.11)
Substituting
b^d3>-^
b3
ijl
A ( u COS 6
+ sin
0)
A ( u COS
- sin
e)
^
G
(7.12a)
(7.12b)
(7.13)
W 1
A {\i COS
f o r uprush, and
Pa
W ^
A
3
(y
(7.14a)
(7.14b)
e + sin e)
3
9 7Z h2
COS
e - sin
6)
f o r backwash,
This is e f f e c t i v e l y the formula derived by I r i b a r r e n (1938).
A primary disadvantage of equation 7.14 is i t s abundance o f emperical
c o e f f i c i e n t s ; a, b, y , and p^ a l l must be determined f o r a given armor u n i t
type. This has led to many emperical a l t e r n a t i v e proposals to replace
I r i b a r r e n ' s formula with a simpler one.
While these a l t e r n a t i v e formulations have even less of a theoretical
background, they often prove to be more handy in p r a c t i c e . A summary of these
formulas is presented in a Report
of the Intemational
Commission
for
the
40
\
Kp A
.
C0t(6)
where:
g is the acceleration of g r a v i t y ,
H is the wave height,
Kp is the damage c o e f f i c i e n t ,
W is the weight of the armor u n i t ,
A is the r e l a t i v e density of the armor u n i t ,
, = - y
e is the slope of the breakwater,
pg is the mass density of the armor u n i t , and
p is the mass density of (sea) water.
(7.15)
41
b.
(6 < 3 3 . 7 ) .
breaking waves. This implies that the depth at the toe of the breakwater, h.^, is s u f f i c i e n t l y great that the oncoming waves are not
H
*
broken or unstable. When t h i s is not the case ( i . e . r - > 0.6) then
t h i s can be accounted f o r by lowering the value of
- see the
Shore
c.
Vrotectvon
* *
Manual,
Hudson's o r i g i n a l
tests were conducted with regular waves. Nijboer (1972) points out the
danger of replacing a monochromatic wave height with a s i g n i f i c a n t wave
height from a spectrum. He found in a model study of stone armor that
the damage caused by a spectrum of waves characterized by H^-jg was
greater than that caused by monochromatic waves of the same height.
This e f f e c t became more pronounced as the spectrum width increased.*
The f a c t that the c h a r a c t e r i s t i c wave f o r the Hudson Formula
is the s i g n i f i c a n t wave, Hg.|g, has a s i m p l i f y i n g consequence f o r the
optimum design of a rubble mound breakwater. The procedure f o r combining
the long-term and Rayleigh wave height d i s t r i b u t i o n s (volume I , chapt e r 11) can be skipped. Details of what must be done f o r the current
problem are given i n chapter 11 of t h i s volume.
^
Proteotion
Manual,
42
The Hudson Formula was developed f o r use on the outer layer of the
main (trunk) portion of a breakwater. Further, as already mentioned, i t
applies only to the f r o n t slope. While the formula is very helpful even
with these r e s t r i c t i o n s i t can sometimes be applied to other cases as
w e l l ; t h i s is discussed in the following section.
7.4. Special Applications
Breakwater ends
The convex shape of the end of a breakwater can be expected to i n crease the exposure of the armor units to wave attack. In a d d i t i o n , the
convexity can reduce the degree of i n t e r l o c k i n g between adjacent armor
u n i t s . Both e f f e c t s can be incorporated in the Hudson Formula, equation
7.15, by reducing the value of the damage c o e f f i c i e n t , K^, appropriately.
This reduction amounts to between ten and f o r t y percent depending upon
the type of armor u n i t . The reduction is usually greatest f o r armor units
having the higher Kp values (most i n t e r l o c k i n g ) . The Shore
Proteotion
Manual tabulates Kp values f o r ends of breakwaters (structure head). Often the lower Kp value is compensated by selecting somewhat f l a t t e r slopes
at the end so that the same armor size may be used.
Toe
The Hudson Formula can be applied d i r e c t l y to the design of the toe
of a breakwater exposed to breaking waves. This is discussed in more d e t a i l
in chapter 9.
Secondary armor
A breakwater must be stable during construction as well as a f t e r
i t s completion. Thus, i t is necessary that the inner layers d i r e c t l y
under the primary armor (secondary armor) be dimensioned to withstand
the waves that can be reasonably expected during the construction
period. The Hudson Formula may be applied d i r e c t l y to t h i s problem in
the same way that i t is used f o r the primary armor layer. Because of
the l i m i t e d exposure time, however, a somewhat less severe storm can
be used. Usually, t h i s secondary layer w i l l be made from stone having
a weight of about 1/10 of that of the primary armor.
When especially porous armor unit placement is used in a single
layer we must be especially aware of the containment f u n c t i o n of the
secondary armor. This extra function is most apparent when cobs or
t r i b a r s are used f o r the outer armor. See chapter 6.
Angular wave attack
As we have seen in volumes I and I I , the angle of wave approach
is very important to the s t a b i l i t y of a beach. For a breakwater, however, the angle of wave attack
43
attack
bor by winds or passing ships or may enter the harbor through the entrance
or by overtopping another portion
of the breakwater.
W
Kp A cot(e)
When the wave height increases by
increases by 33/. A 10% decrease i n wave height decreases the blockweight by 27%. Thus, the formula magnifies small errors i n wave height.
Increasing the density of the armor u n i t by 10% decreases the armor weight needed by about 30% f o r normal values of armor and water dens i t i e s ^ * Decreasing the density by 10% increases the necessary weight
by 55%: What i s the e f f e c t o f s u b s t i t u t i n g Swedish Granite (p^ = 2650 kg/m^)
f o r .Basalt (Pg = 2900 kg/m ) f o r armor units? The r a t i o of the armor weights
is:
* This is the reason t h a t the crest elevation was e a r l i e r assumed to
exceed the run-up.
1025 kg/m'^ and p
= 2600 kg/m'^.
w,sub
IN
Figure
7.3
EQUILIBRIUM
ALONG CONTOUR
44
'^granite
(2900 - 1025)^
2650
'^basalt
'^^^^
(2650 - 1025)''
= 1.40
,-,
(7.17)
Kp =
3'
WA
(7.18)
cot(e)
yielding:
H*=-\^/?.H
(7.19)
where:
H* is the unknown wave height causing a chosen experimentally
determined damage,
H
Kp
45
Thus,
1/3
TT
(7.20)
K,
D
Damage
Tetrapods
Tribars
TT
'^D
IT
{%)
(-)
(-)
(-)
(-)
0-5
8.3
1.00
10,4
1,00
5-10
10.8
1.09
14,2
1,11
10-15
13.4
1.17
19.4
1.23
15-20
15.9
1.24
26.2
1.36
20-30
19.2
1.32
35.2
1.50
30-40
2^3 .'4
1,41
41.8
1.59
40-50
27.8
1.50
45,9
1.64
10
20
30
Damage to A r m o r layer
AO
50
(%)
Figure 74
COMPARISON OF ARMOR UNITS
One must be careful about drawing conclusions based solely upon computations of the sort j u s t carried out. Nothing is indicated about the
absolute block weights required or about differences in capital costs of
various armor u n i t s .
Data necessary f o r determining f i g u r e 7.4 are available only f o r a few
types of armor u n i t s . For other armor, detailed model tests are needed too
determine the relationship shown i n the f i g u r e . Except f o r very small projects i t is strongly recommended that model tests always be used to v e r i f y
the given c o e f f i c i e n t s f o r the s p e c i f i c project under consideration.
Armor layer design considerations unrelated to the Hudson Formula
are considered in the following two sections of t h i s chapter.
7.7. Layer Extent and Thickness
Since the primary armor layer can be more expensive to construct
than other portions of the breakwater, i t is advantageous to l i m i t the
area covered by primary armor units as much as possible consistent
with s t a b i l i t y needs. Only a few rules of thumb exist to indicate the
necessary extent of t h i s armor layer. These should be confirmed by experiments i f the project is at a l l extensive.
Normally the primary armor units are extended downward on the breakwater slope to an elevation of 1.5 H below the s t i l l water l e v e l . Whether
an extreme storm f l o o d water level and a severe storm must be chosen or a
moderate storm with low water level depends upon which condition results
in the lowest absolute elevation f o r the bottom of the primary armor.
46
(7,21)
where:
m is the number o f layers of armor units - usually 2, sometimes
1 or 3,
is an emperical layer c o e f f i c i e n t l i s t e d f o r each type o f unit
in chapter 6, and
t is the layer thickness.
The number o f armor units needed per u n i t of primary armor layer
surface area can be estimated from:
C = m K,(l - n ) ( ^ ) 2 / 3
(7.22)
where:
C is the number of armor units per unit area o f armor l a y e r , and
n is the armor u n i t layer porosity expressed as a decimal and
l i s t e d i n chapter 5 f o r each type o f armor u n i t .
47
where:
B Is the crest width, and
m' Is the number of armor units across the crest - usually at least 3.
When a breakwater is to be constructed or maintained by construction
equipment working from the crest, then the crest width w i l l possibly be
dictated by the space needed f o r e f f i c i e n t use of the chosen equipment.
This w i l l be discussed again in chapter 10.
7.9. Review
The background and use of the currently popular semi-emperical
relations f o r rubble mound breakwater armor layer computations have
j u s t been presented.
48
8.
THE CORE
J.F. Agema
E.W.
8.1.
Bijker
Function
The primary function of the core material of a rubble mound
sandtight dam which wi.11 allow much water to pass through i t - at least
not
a v a i l a b l e , other core
49
permeable layers. Second, at best a breakwater need only be absol u t e l y impervious to sand; there is usually no need to prevent water
seepage - something which can be disasterous to a dike.
50
9.
E.W. B i j k e r
f i l t e r layer
Figure 9.1
REPRESENTATION OF PRESSURES
V^ITHIN BREAKVi'ATER
sections
51
flow v e l o c i t i e s
resul-
CM
LO
Figure 9.2
W O V E N FABRIC MATTRESS
can be achieved
Figure 9.3
WOVEN FABRIC MATTRESS
WITH CONCRETE BLOCK
Another p o s s i b i l i t y is to attach concrete b a l l a s t blocks to a woven
f a b r i c . A single layer of reeds sometimes separates the blocks from the
f a b r i c i n order to prevent damage from f r i c t i o n . Such a f i l t e r is s t i l l
thinner than the above types, and can be placed by unwinding i t from a
f l o a t i n g spool upon which the ballasted mat has been r o l l e d . Figure 9.3
shows a photo of such a mat.
54
Thus:
(9.01)
where
^sig d '^^"otes the design s i g n i f i c a n t wave height.
Using the rule of thumb presented in the previous chapter,
the
(9,02)
M=
g
3
(7.15)
(9.03)
(2650)(9.81)(4.5);
,3
rx,2650-
^g^^^^
1025,3,,
1Q2'5
) (1-5)
= 113 x 10'^ N
(9.05)
55
i-)^^^
(7.21)
(9.06)
which y i e l d s :
t=
(2)(1.15)(^2SyT^)'^'
= 3.8 m
(9.07)
(9.08)
= 1.7 m
(9.09)
(9.10)
thick.
A f i l t e r layer 1.5 m thick should be constructed under t h i s .
When a l l of t h i s is put together, a p i t 6.5 m deep, shown i n f i g u r e
9.4, w i l l be required.
Figure 9.A
CONVENTIONAL EXCAVATED TOE CONSTRUCTION
Scale: 1 ;200
Since t h i s excavation work w i l l be very expensive, i t can be advantageous to reduce i t . One method, shown in f i g u r e 9.5, is to reduce the
thickness of the primary armor layer near the toe. The toe supporting
stones of 5-6 ton mass are extended under t h i s single armor u n i t layer
as shown. The f i l t e r layer under the toe supporting stone has been i n creased in thickness to 2.0 m to compensate f o r the removal of the secon-
56
Figure 9.5
ALTERNATIVE TOE CONSTRUCTION
scaLe:1:200
dary armor layer i n that area. Even so, the depth o f the excavation has
only been reduced from 6.5 to 5.0 m, and t h i s solution involving the t h i n ner primary armor layer is d i f f i c u l t to construct under water.
S t i l l another a l t e r n a t i v e uses a heavily supported toe constructed
without excavation. This i s shown in f i g u r e 9.6. A r e l a t i v e l y large quant i t y of toe support stone is needed to give adequate support to the p r i mary armor. Some loss o f this stone from the toe support can be expected
and t o l e r a t e d .
Figure 9.6
TOE CONSTRUCTION WITHOUT EXCAVATION
scale; 1;20G
The maximum toe slope of this toe protection can be determined using
the Hudson Formula. The sketched slope of 1:7.5 i s somewhat f l a t t e r than
that required.
As i n the previous a l t e r n a t i v e , the f i l t e r layer under the toe has
been thickened to 2.0 m to support the coarser stone.
57
s o i l mechanics techniques.
In a d d i t i o n , rubble mound structures usually s e t t l e w i t h i n themselves. Wave action w i l l cause some displacement of breakwater
materials
breakwater.
breakwater.
58
10.
J.F. Agema
10.1. Introduction
Sometimes a logical sequence of project execution is to f i r s t complete a design and then to worry about construction techniques. Such an
approach to rubble mound breakwater design is irresponsible, however,
since the construction method chosen can have a s i g n i f i c a n t influence
on the cost of construction. Therefore, we now consider how rubble
mound breakwaters can be constructed and then, in the next chapter, combine a l l o f the information presented i n t o an optimum design.
The remainder of t h i s chapter w i l l be concerned with available cons t r u c t i o n methods and, t h e i r r e l a t i v e merits.
10.2. Construction Methods
I t is usually impractical to construct a breakwater working i n a
temporary dry building p i t .
59
6-92.
When armor units are used to protect the crest of the breakwater,
they can provide too rough a surface f o r e f f i c i e n t transport of materials
and equipment. Two solutions to the problem are possible: chinking of the
crest armor with f i n e r m a t e r i a l , and delaying of the placing o f the crest
armor u n t i l the rest of the structure is completed. This second technique allows equipment to travel over the smoother but lower underlayer.
Since chinking materials w i l l be washed away in time, both methods suggested w i l l
crest
60
can support special armor units which may possible be placed on a steeper slope or be of l i g h t e r weight. Either of these modifications (of
slope
used.
Special methods
Use of helicopters to place breakwater materials has been attempted
successfully on an experimental basis. A disadvantage of helicopters,
t h e i r extreme dependence upon favorable weather conditions, is o f f s e t by
t h e i r excellent maneuverability. Helicopters may prove to be very servicable in the future f o r maintenance work since they can easily place
small loads of material at a variety of places on the
breakwater.
Combinations of methods
Often the major portion of the deeper breakwater parts are constructed by dumping from barges. A f t e r t h i s lower portion has been
b u i l t up as high as conveniently possible in t h i s way, the
structure
Aspects
61
Core
The r e a l l y rough work i n a breakwater is the placement of the
core m a t e r i a l . I f waves and currents did not disturb the operation,
then the only problem would be that of achieving the desired slopes
when dumping material under water - either from a barge or from a
crane bucket. Of course, submerged portions of side slopes can be
r e - p r o f i l e d working from a f i x e d point using a crane, but i t can be
more economical to avoid t h i s i f possible. Protection o f the core
from waves and currents during construction is one of the topics d i s cussed i n section 10.4.
Armor units
Primary armor units are almost exlusively placed by crane - either
f l o a t i n g or f i x e d . Obviously, the crane used must be capable o f placing
an armor unit anywhere on the slope to be protected. The a v a i l a b i l i t y o f
cranes can influence the choice o f armor u n i t s . Even when random or p e l l mell placement of armor units is s p e c i f i e d , accurate placement of i n d i v i dual armor units is required i n order to guarantee a uniform covering.
Sometimes, placement plans specifying exact locations f o r each armor unit
are used even with so-called pell-mell armor placement. When s p e c i f i c
placement patterns are required f o r s t a b i l i t y - as with t r i b a r s , f o r example - extra care is called f o r ; so much care, i n f a c t , that t h i s cannot
be successfully accomplished under water.
When a r t i f i c i a l armor units of several d i f f e r e n t sizes are required,
time and confusion at the armor unit f a b r i c a t i o n s i t e can sometimes be
reduced by modifying the density o f the concrete used rather than by cast i n g a new size of unit - see chapter 7, This techniques can r e s u l t i n con
siderable savings at the f a b r i c a t i o n s i t e , and can r e s u l t i n a l i g h t e r wei
block than would otherwise be required which has, again, consequences f o r
the crane selection.
Details of armor u n i t placement schemes are usually worked out in models.
These may be the hydraulic models used to investigate d u r a b i l i t y or separate construction models may be b u i l t to determine exact cover layer properties such as porosity.
Crest
The crest o f the breakwater must be broad and smooth enough to accomo
date construction and material transport equipment i f over-the-crest cons t r u c t i o n or maintenance i s planned. The width needed during construct i o n is sometimes more than that needed f o r maintenance. Since much more
equipment is moving along the crest during construction a two lane roadway may prove economical, especially i f the breakwater is long.
Massive monolithic crest constructions are often used with special
armor units such as t r i b a r s and tetrapods. Such monolithic structures provide an excellent roadway, but are not without problems. Since a rubble
mound breakwater is more or less designed to s e t t l e a b i t , these monolit h i c crest elements must also be t o l e r a n t of t h i s . This means in practice
62
77XV
Figure
10.1
BREAKWATER
CONSTRUCTION
C O N S T R U C T E D WITH CORE
PROTECTION
P R O G R E S S E S IN N U M E R I C A L
SEQUENCE
2.
3.
63
more expensive than core m a t e r i a l . The success of t h i s construction technique depends upon the secondary armor ridges to protect the core material
s u f f i c i e n t l y to prevent i t s mass erosion. In some cases where currents are
very strong - closure o f estuaries, f o r example - the e n t i r e core of the
breakwater is b u i l t up of small armor u n i t s ; t h i s is an exception, however.
The economical construction o f a breakwater requires that materials
flow smoothly and that various production and transport units are well
adapted to each other. When, f o r example, lower portions of a breakwater
are constructed from ships with the upper position constructed from the
c r e s t , then even these two operations must be well coordinated.
Local a v a i l a b i l i t y o f labor and materials also influences breakwater
design and construction method choice. Concrete armor units are very often
used i n breakwaters i n The Netherlands,primarily because stone of armor
u n i t q u a l i t y would have to be imported from foreign countries while
concrete can be made l o c a l l y .
10.6. Review
In t h i s and the previous four chapters we have examined those factors which influence the design o f a rubble mound breakwater. The designer's
task is to combine a l l of these factors i n such a way that a l l portions of
the r e s u l t i n g breakwater are equally durable in r e l a t i o n to t h e i r individual
environmental attack This balanced design w i l l then i d e a l l y s u f f e r e i t h e r
no damage or w i l l be uniformly damaged by a severe storm.
The method f o r choosing the design storm is outlined i n the f o l l o w i n g
chapter on optimum design.
64
11.
OPTIMUM DESIGN
J.F. Agema
W.W. Massie
11.1.
Introduction
A. Paape
65
limited
Given Data
The f o l l o w i n g example is hypothetical i n that data have been taken
RECURRENCE
INTERVAL
(YRS)
67
Storm Data
'^STg
Interval
^0
Period
h'
(yrs)
(m)
0.1
4.5
7.4
0.5
5.5
(s)
5.0
10
7.0
11
20
8.0
12
100
9.0
13
(m)
3.2
4.6
Tides
The normal astronomical t i d e is such that high t i d e is 2.3 m above
mean sea level and normal low water is 2.0 m below mean sea l e v e l . Tidal
influences have been included i n the water level data j u s t given.
Site conditions
The depth at the design s i t e is 10.0 m r e l a t i v e to mean sea l e v e l .
The bottom material is sand having a mean diameter of 160 ym and the b o t tom slope is 1:100 at that depth.
Cost of materials
The f o l l o w i n g costs are assumed to be v a l i d and are l i s t e d i n table
11.2. Since the prices are intended only as a r e l a t i v e i n d i c a t i o n o f costs,
no monetary units are given. Costs would have to be determined i n d i v i d u a l ly by p r o j e c t , anyway, i n a real case.
68
Table 11.2
Material
Natural Stone
(p = 2700 kg/m~^)
Gravel
Normal concrete
Massive
(p = 2400 kg/m^'
Armor Cubes
Special Armor
Basalt Concrete
Armor Cubes
(p = 2650 kg/m^)
Special Armor
Unit
barge
over
dumped
cres"
ton
35.
45.
m^
40.
50.
3
m
3
m
150.
,3
m
3
m
3
m
200.
250.
230.
280.
230.
280.
260.
310.
(1-5.05a)
(11.01)
69
= 0.33p + 0.46
(1-8.03)
(11.02)
y i e l d i n g y = 0.49.
The value of H^-jg at the breakwater s i t e is computed using either
Hj^g = Y h
(11.03)
^sig = (S;)(Hsig^)
(11-04)
or
b.
p = 0 . 0 1 , at H.W.:
(11.05)
(11.06)
(11.07)
p
<=5
TABLE 11.3
Wave Shoaling
H.
Interval
h'
length
depth
h
0
H
H
total
frequency
%2
(-)
(- )
(-)
(m)
,storms X
^ year
"sig
(y^s)
(m)
0.1
4.5
7.4 2.8
85.
12.8
0. 1
0.49
4.1
10
0.2
4.9
2.9
100.
12.9
0. 1
0.49
4.5
0.5
5.5
3.0
126.
13.0
0. 1
0.49
5.1
6.0
10
3.2
156.
13.2
0. 1
0.49
5.7
7.0
11
3.7
189.
13.7
0. 1
0.49
6.7
0.2
10
7.5
11.5 3.9
207.
13.9
0. 1
0.49
6.8
0.1
broken wave
20
8.0
12
4.2
225.
14.2
0. 1
0.49
7.0
0.05
broken wave
broken wave
(s)
(m)
Wave
(m)
(m)
(-)
(-)
t'
broken wave
50
8.5
12.5 4.4
244.
14.4
0. 1
0.49
7.1
0.02
100
9.0
13
4.6
264.
14.6
0.0553 1.006
341.
0. 1
0.49
7.2
0.01
broken wave
500
10.0
14
5.1
306.
15.1
0.0493 1.025
327.
0. 1
0.49
7.4
0.002
broken wave
72
11.5.
Since the maximum available armor unit mass is 20 tons, the Hudson
Formula, equation 7.15, can be modified and solved f o r the slope:
P,
cot
(e) = ^
(11.08)
where:
g is the acceleration o f g r a v i t y ,
H is the design wave height,
Kp is the damage c o e f f i c i e n t ,
W is the weight of the armor u n i t ,
A is the r e l a t i v e density of armor,
Pg is the armor unit density, and
e- is the slope angle.
As an i n i t i a l guess, l e t us design f o r a storm having a frequence o f
0.05. From table 11.3 we see that the breakwater is attacked by breaking
waves with H^-jg = 7.0 m. For a double layer of rough quarry stone i n
breaking waves a damage c o e f f i c i e n t value of 3.5 is found i n tabel 7.6
of
the Shore
Protection
Manual,
This value of Kp is i n c o r r e c t , because i t is based upon an assumpt i o n that no overtopping occurs. Since there w i l l c e r t a i n l y be overtopping with the proposed design, t h i s assumption has been v i o l a t e d . Unfortunately, damage c o e f f i c i e n t values f o r overtopped breakwaters are not
available. Therefore, the suggested value of Kp w i l l be used f u r t h e r
with
specific
acknowledgement
of this
error
since a l l of the
computa-
(0) =
(9.81)(2700)(7.0)3
(3-5)(^^%3rV
or:
estimate.
( 2 0 x l 0 ^ x 9.81)
'
= 3.10
(11.10)
= 18"
(11.11)
" 75^ " 0.057 and a 1:3 rubble slope y i e l d s |^ of 0.84. For the crest
elevation we get:
73
i-)^^^
(7.23)
(11.13)
where:
B is the crest w i d t h ,
is the packing c o e f f i c i e n t , and
m' is the number of armor units across the crest.
Choosing m' = 3 and selecting K^= 1.02 from chapter 6 y i e l d s :
3
B = (3)(1.02)(^5^^g^)^/3
= 6.0 m
This is wide enough f o r construction equipment, i f necessary.
The thickness of the armor layer, t , comes from equation 7.21:
74
(7.21)
(11.15)
Vg
where
ni is the number of units in the layer.
Since m = 2 has already been chosen, 11.15 y i e l d s ;
+ - / ? ^ n n?^f20 x 10 ,1/3
t - (2)(1.02)( 2y-Q-Q- }
(11.16)
4.0 m
We can now s t a r t a sketch design shown i n f i g u r e 11.4,
This design needs a special toe construction on the f r o n t face.
The secondary armor units must be dimensioned. These would have a
mass of at least 1/10 of that of the primary armor but should also w i t h H- This i s important
during the construc-
t i o n phase.
(2700)(9.81)(4.1)''
W =
( 3 . 5 ) ( i M ^ ) 3
= 3,9
(11.19)
10^
(11,18)
(3,10)
t = (2)(1-2)((2700)(9?81))'^'
(11.20)
= 2,3 m
I f t h i s same stone i s used f o r toe protection then the slope of
t h i s toe w i l l
be:
im}iM}ShOjL
cot(e)=
(11.22)
( 3 . 5 ) ( 2 Z 0 0 ^ 1 ^ ) 3 (3.9 X 10^)
16.6
(11.23)
(2^)(^-)'
( 3 . 5 ) ( 2 M ^ ) 3 (3 , ,3)
(11.24)
10.35; 6 = 6'-
(11.25)
This is s t i l l pretty f l a t !
Figure 11./,
S K E T C H D E S I G N OF S T O N E
ORIGINAL
SCALE 1 :500
BREAKWATER
76
TABLE 11.4
Vol ume
Unit
Total
(m^/m)
price
price
F i l t e r Gravel
31
1.5
46.5
14
1.5
21.0
35
2.0
70.0
20/ton
137.5
40/m3
5 500.
60/m-'
3 390.
70/m^
22 785.
148.1
60/m
8 886,
12.6
90/m-^
1 134,
Toe Stone
23
1.5
34.5
22
22.0
X 1
56.5
Quarry Run (barge placed)
47
1.5
46
7.5
11
7.5
70.5
172.5
X 1
82.5
325.5
2.3
22-
2.3
16
57,5
50.6
i
40.0
1.4
2,3
13,8
2,3
13,8
2.3
16.1
3 278
43.7
Primary Armor (over crest)
37
148,0
30
120,0
6x4
24,0
292.0
15/m
21 900,
77
Pb = Pa (1 - n)
(11-26)
(11.27)
3
and 75,/m
for crane-placed stone. Quarry run stone is assumed to have a bulk dens i t y of 2000 kg/m^.
The cost f i g u r e j u s t obtained at the end of table 11.4 is the cons t r u c t i o n cost of a breakwater designed to withstand a s i g n i f i c a n t wave
height o f 7.0 m. In order to conduct an o p t i m i z a t i o n , we need to invest i g a t e the construction costs f o r a whole series of wave heights. This
involves, i n p r i n c i p l e , a whole series of cost determinations as j u s t
completed. We may, however, be able to short cut t h i s lengthy computat i o n f o r the problem at hand.
Since the crest elevation has been determined based upon an overtopping c r i t e r i a , that elevation w i l l remain r e l a t i v e l y f i x e d . Run-up
is rather independent of wave and slope parameters in t h i s range - see
f i g , 11.3.
Also, since armor stone o f maximum size is used, the crest width and
primary armor layer thickness w i l l
change,
then? The side slopes, the size of the secondary armor (and hence the
layer thickness), and the core volume w i l l change. The volume o f the
toe and f i l t e r constructions w i l l remain e s s e n t i a l l y the same.
The procedure used to compute table 11.5 from the data with
Hg.jg = 7.0 m is outlined as f o l l o w s :
a.
The new slope follows from (11.09) with the new wave height.
b.
c.
d.
e.
in slope length.
the wave height, 4,1 m, is maintained,
changes.
f.
g.
h.
Other volumes and a l l unit prices are assumed to remain the same.
ness change.
construc-
78
TaDle 11.5
Note:
numbers.
Item
Design Wave height (m)
Slope cot ( 6 )
5.7
6.75
7.0
7.25
7.50
1.68
2,78
3.10
3.45
3.82
267,1
292.
319.5
20 031.
21 900.
22 965.
Primary Armor
volume (m^/m)
cost/m
184.9
n
864.
348.9
26
187.
Secondary Armor
mass (kg)
layer thick.(m)
7400.
4500.
4000,
3600.
3300.
2.8
2.4
2.3
2.2
2.2
142.3
148,1
154,0
165,3
cost/m
8 540.
8 886.
9 242.
9 921,
3
crane volume (m /m)
cost/m
7 140.
42,9
43,7
44.5
47.4
3 219.
Z 278.
3 338.
3 555.
309,2
325,5
363,5
393.4
21 643.
22 785,
25 442,
27
539,
10 024.
10 024,
10 024,
10
024.
63 457.
66 873,
72 Oil,
77 206,
39.8
2 985.
Core
barge volume (m^/m) 220.1
cost/m
Other items cost(m)
Total cost/m
15 406.
10 024.
49 419.
79
profiles.
The equivalent damage c o e f f i c i e n t value follows from equation 7.20
modified to y i e l d the r a t i o of damage c o e f f i c i e n t s .
X
"D
,H*.3
ITD
(TT)
(11.28)
than the design wave there i s no damage; why i s this? See chap-
t e r 7'.
The damage costs are found by m u l t i p l y i n g the damage percentages
by the i n i t i a l cost of constructing that portion o f the breakwater
which must be repaired. Usually, f o r moderate damage, the cost of the
primary armor layer from table 11.5 i s chosen.**'This r e s u l t i n g f i g u r e
is then increased to compensate f o r the extra cost of mobilizing the
construction equipment f o r such a r e l a t i v e l y minor repair j o b . The
increase f a c t o r and cost basis used are l i s t e d i n the notes below table
arbitrairly
10
20 30 AO
Damage { % )
F i g u r e 11.5
DAMAGE RELATIONSHIP
ROUGH QUARRY STONE
FOR
TABLE 11.6
Wave Conditions
sig
P(H3ig)
(ra)
(-)
5.5
1.25
6.0
0.63
6.5
0.28
6.9
0.085
7.1
AP
Kp
Damage
Damage
Annual
cost
cost
(-)
{%)
(-/m)
(-/m)
0.62
1.05
8.0
2218.
1375.
6.3
0.35
1.35
18.
4991.
1747.
6.7
0.195
1.62
25.
8996.
7.0
0.065
1.85
31.
7.2
0.015
2.02
7.5
0.005
2.28
"sig
(m)
(Hsig)
(-)
5.8
-"^tio
Kp
Damage
ratio
Damage
Kp
Damage
Damage
Annual
cost
cost
cost
cost
ratio
(-/m)
(-/m)
(-)
{%)
(-/m)
(-/m)
12.
4807.
312.
1.00
2.5
1095.
71.
1.21
15.
6009.
90.
1.09
10.
4380.
66.
1.37
19.
7612.
_38.
1.23
15.
6570.
_33.
(-)
{%)
1754.
0.98
0.0
11155.
725.
1.12
36.
12954.
194.
43.
21250.
106.
0.020
7.3
0.005
7.7
0.000
5901.
170.
440.
13 864.
20 031.
21 900.
Total Armor
23 989.
31 790.
34 064.
Total Construction:
49 419.
53 457.
66 873-
Note: For damage up to 20%, the damage cost i s based upon 2 times the primary armor cost.
For damage o f 20% to 40%, the damage cost i s based upon 1.5 times the t o t a l armor cost.
For damage above 40%, the damage cost i s based upon the t o t a l construction cost.
CO
o
81
^,
p
co
O
O
C
C
<
OJ
cn
(
E
(
Q
E
O
un
>
-p
co
O
O
O)
Ol
IO
E
tO
O)
- 1\
co
O
1
^>
C)
O
co
C
Ol
CD
c\j
CTl
co
r^
r^
cn
CD
CTl
LO
I)
LO
ro
CM
CD
00
CM
t/)
OJ
4-)
n3
1-
4->
CO
O
O
E
\ .
1
t
c
c
<
0)
CT)
r
E
cO
LO
CNJ
*
0)
H->
CO
O
O
\ .
1
-
O)
Ol
(0
E
rO
>
Ii
I1
C
CJ)
rO
a
0)
Q
co
cri
1
l
!-
CU
<3
i.
CO
_Z
<_>
C
O
r4->
O
C
O
O
0)
>
(0
3
CD
1
CO
rc
~"
O
O
CL
E
O
CJ
'
OJ
CJl
<0
E
(0
- a
CD
1 , v
(/) E
'
r
.
CD
1
(/)
rn
c
O
4->
O
so
E
S-
io
E
<
D.
-O
CU
co
=J
CT)
rCO
nr
co
4->
co
O
O
O
O
O
O
rO
E
Z-
S4-)
CO
C
O
O
r
4->
O
c
-p
O
construc-
i f
(11.29)
82
where:
i is the i n t e r e s t rate per period expressed as a decimal, and
n is the number of periods.
Substituting an i n t e r e s t rate of 8% [i = 0.08) and a number o f periods,
n = I = 50, y i e l d s :
^
(1.08)^ - 1
pwf = ^
0.08(1.08)''''
pwf = 12.2335
(11.30)
(11.31)
This present worth f a c t o r is then m u l t i p l i e d by each t o t a l annual cost figure f o r each cross section. These r e s u l t i n g present
values
This data gathered and computed from tables 11.5 and 11.6 is
Table 11.7
Cost Summary
Item
Design Wave Height (m
5.7
6.75
7,00
7.25
7.50
5 901.
440.
170,
26.
7.
Capitalized Damage
72 190.
5383.
2080,
318.
86.
Construction Cost
49 419.
63 457,
66 873,
72 O i l .
77 206.
121 609.
68 840,
68 953.
72 329.
77 292.
Total Cost
An a l t e r n a t e , and equivalent t o t a l r e s u l t could be achieved by depreciating the construction cost over the l i f e ,
preciation f i g u r e would be added, then, to the t o t a l annual maintenance cost from table 11.6.
83
5.5
6.0
DESIGN
6.5
WAVE H E I G H T
7.0
75
(M)
Summarizing, the conclusion is use a 6,75 m design wave (recurrence i n t e r v a l of 5 years) i f construction capital is scarce and
design using a 7.00 m wave (recurrence i n t e r v a l 26 years) i f capital
is p l e n t i f u l .
84
What i s the e f f e c t of changing the economic l i f e , ., of the structure? As n decreases with a given i n t e r e s t rate, i , the pwf decreases
making maintenance costs less important. Thus, the optimum design point
s h i f t s to the l e f t i n f i g u r e 11.6; t h i s seems l o g i c a l . Reducing the
l i f e t o , say, 10 years yields an optimum nearer a design wave height
lower than 6.75 m. This is revealed by constructing a new table s i m i l a r
to table 11.7.
How does the i n t e r e s t rate a f f e c t the optimum? As the i n t e r e s t rate
decreases, the present worth f a c t o r increases making maintenance a more
important contributor to the t o t a l costs; the optimum s h i f t s to the
r i g h t i n f i g u r e 11.5. For example, with an annual i n t e r e s t rate of only 2%, and a l i f e of 50 years, calculation o f a new table s i m i l a r to
table 11.7 yields an optimum near 7.00 m; the t o t a l cost curve climbs
steeply to the l e f t of t h i s point. This was not so pronouncedin f i g u r e
11.6 and results from the r e l a t i v e l y high current (1976) i n t e r e s t
rate
used.*
For "normal" designs the optimum design storm wave w i l l have a
recurrence i n t e r v a l of about 10 to 20 years. I t is f o r t h i s reason that
the i n i t i a l guess f o r a design wave height was 7.0 m corresponding to
a recurrence interval of 20 years - see f i g u r e 11.2.
11.8. Additional Remarks
By now, everyone concerned with t h i s chapter (authors, t y p i s t ,
proofreader, students) thinks or hopes that the problem i s solved. Unf o r t u n a t e l y , t h i s is f a r from t r u e . In sections 5 through 7 o f t h i s
chapter we have found the optimum quarry stone breakwater consistent
with the rest of the preliminary harbor design. This is not
neoesscccily
85
this
is
certainty
not
the
case.
are i n t e r - r e l a t e d . I t
86
J.F. Agema
12.
W.W. Massie
publi-
87
13.
MONOLITHIC BREAKWATERS
13.1.
Definition
E.W. B i j k e r
General Features
The monolithic form of these breakwaters can be both an advantage
cross
section
^A^//=777
^v:;^77^ -77:^7,
elevation view
F i g u r e 13.1
T Y P I C A L MONOLITHIC
S C A L E 1 : 150
BREAKWATER
88
Figure
13.2
materials.
89
,+A.5
F i g u r e 13.5
HANSTHOLM
17. Since these problems are most severe when the foundations are shallow,
as with caissons, an alternate form of monolithic breakwater consists of
v e r t i c a l steel sheet p i l e c e l l s . When bottom conditions are favorable,
the i n t e r l o c k i n g sheet piles can be driven i n t o the bottom to s u f f i c i e n t
depth to avoid foundation problems. A f t e r the c e l l s are completed they are
A parapet wall can be used with any type of monolithic breakwater, however.
BREAKWATER
90
F i g u r e 13.6
COMPOSITE
SCALE
BREAKWATER
1:500
91
14.
CONSTRUCTION MATERIALS
14.1.
Introduction
W.W. Massie
presented
e a r l i e r i n chapter 6.
14.2.
Environmental Differences
In contrast to rubble mound breakwaters which usually absorb much
of the oncoming wave energy, monolithic structures, because they are less
permeable, tend to keep the wave energy "on t h e i r surface". In other words,
the oncoming wave energy is either r e f l e c t e d back away from the breakwater
or dissipated i n run-up on the (impervious) surface.
The large f l a t surfaces which characterize so many monolithic breakwaters must be constructed of materials specially selected to r e s i s t the
p a r t i c u l a r attack. S p e c i f i c a l l y , those waves which break against a monolit h i c structure can cause high (tens of atmospheres)
Consequences f o r Materials
Remembering Pascal's law and experiment from elementary f l u i d mecha-
nics one realizes that i f such a high hydrodynamic impact force should
occur on a water f i l l e d j o i n t or crack (even a h a i r l i n e crack is s u f f i c i e n t )
t h i s pressure w i l l act undiminished over a l l surfaces o f t h i s crack. This
can lead to progressive f r a c t u r e or s p a l l i n g of the m a t e r i a l . Obviously',
prevention of crack formation is the simplest cure f o r t h i s problem. Thus
granite or basalt stone used to construct a breakwater o f massive cut
blocks should be fine-grained and not j o i n t e d . *
Concrete used should have an especially smooth surface.
Further, since many monolothic concrete structures contain steel , e i t h e r
as r e i n f o r c i n g or as pre-tensioning, the surrounding concrete must be
s u f f i c i e n t to protect t h i s steel from d i r e c t chemical attack.
Since monolithic breakwaters are designed to behave as a single
massive u n i t , the density property of armor units f o r rubble mound breakwaters is much less important f o r monolithic structures.
92
15.
15.1.
Introduction
W.W. Massie
is
Standing Waves
As long as the water depth at the toe of the v e r t i c a l wall i s
s u f f i c i e n t , the approaching waves w i l l be r e f l e c t e d forming a nonbreaking standing wave. We may remember from short wave theory that
a standing wave results from the superposition of two t r a v e l l i n g
waves. An antinode of t h i s standing wave w i l l be found at the v e r t i c a l
wall l o c a t i o n . The pressure d i s t r i b i t i o n on t h i s wall follows from the
theory o f short waves presented i n volume I chapter 5. From equation
5.11 i n that volume:
P = - P9Z +
where:
l^^^
COS . t
(15.01)
g is the acceleration of g r a v i t y ,
H i s the wave height of the approaching wave,
h is the water depth,
k is the wave number =
p is the instantaneous
,
pressure,
93
F i g u r e 15.1
PRESSURE D I A G R A M FOR STANDING
WAVELENGTH
D I S T O R T I O N 1 : 2.5
WAVE
94
Continuous water j e t
We are well aware of the influence of a continuous water j e t impinging perpendicularly on a f l a t plate. This was the classis example
used to i l l u s t r a t e the momentum equation i n elementary steady flow
f l u i d mechanics. The r e s u l t i n g pressure on the plate was found to be:
p =
1 P
(15.02)
Water hammer
A second approach is based upon an assumption that a h o r i z o n t a l l y
oriented block of water having length L h i t s a r i g i d wall with
v e l o c i t y V. Continuing the analogy to water hammer in r i g i d
pipelines,
(15.03)
where: c i s the v e l o c i t y of sound i n sea water (about 1543 m/s Sverdrup et al (1942)),
L is the length of the water mass, and
At is the t o t a l duration of the impact pressure.
This water mass causes a pressure maximum given approximately by:
p = p Ve
(15.04)
when t h i s strikes a r i g i d surface and is contained in a r i g i d pipe see Heerema (1974). The r i g i d surface assumption is not too bad, but
the oncoming water mass is c e r t a i n l y not r i g i d l y contained in the
directions normal to the flow. Further, no allowance has been made
f o r the e f f e c t s of a i r which may either be entrained i n the breaking
wave or trapped between i t and the v e r t i c a l w a l l . Fhrbter (1969) and
summarized by Heerema (1974) attempted to correct f o r these d e f i c i e n cies in an experimental study. He found that the e f f e c t i v e length,
L, of the approaching water mass was of the same order as the hydraul i c radius, R, of the impact area. This was explained by the f a c t
95
(15.05)
(15.06)
At = >
(15.07)
with
(15.08)
,t = ^
(15.09)
and
=
0.3 ms.
96
here.
wave impact
dynamic foroe
ipressures
on a large
97
98
16.
16.1.
E.W.
Bijker
W.W. Massie
consolidation
Types of Foundations
Some Indication of foundation types has already been given i n chap-
breakwater.
The foundation j u s t proposed is adaptable only when the surface
of the underlying ground s t i l l
99
^ ' - a d d e d later\
7^
F i g u r e 16.2
different
filter
fine
Figure
layers
sand
16.3
F I L T E R LAYER U N D E R M O N O L I T H I C
BREAKWATER
100
drainage
reasonably
straightforward.
Wave impact loads described i n the previous chapter can, however,
cause s i g n i f i c a n t analysis problems. Since the duration o f an impact
force is not long (a few tenths of a second) r e l a t i v e to the natural
period of v i b r a t i o n of the structure, these loads can no longer be
treated as s t a t i c .
be included.
The combination o f the breakwater, surrounding water, subsoil and
foundation may be schematized as a mass-spring system. The spring is
formed by the s o i l . Although t h i s may not be a nice l i n e a r spring, l i nearity is assumed in the f u r t h e r analysis. The mass consists of the
breakwater mass plus an e f f e c t i v e ( v i r t u a l ) water mass f o r those motions which excite water movements (waves). A d d i t i o n a l l y , t h e ' S o i l
forming the spring also has a mass which must be included. A v i r t u a l
Figure 16.4
SCHEMATIC R E P R E S E N T A T I O N O F
S I G N I F I C A N C E OF EQUATION 16.01
In equation form:
101
00
oo
p
-00
a ( x , y , z ) d x l d y dz
(16.01)
l_-oo
where:
a(x,y,z)
ag i s
is
the a c c e l e r a t i o n
of the soil
nig i s
the v i r t u a l
Pg i s
t h e mass d e n s i t y o f
soil
at point
(x,y,z),
breakwater,
mass, and
soil.
11152)2+
(16.02)
(mg + m^^ + m ) X + c ^
(16.03)
My(t) =
(IB
+ Isy + Iwy)* +
(16.04)
where:
m^ is a v i r t u a l water mass,
I
is a v i r t u a l i n e r t i a ,
not serious wh^n only the short term behavior is important and the
damping is not too great.
Equations of the form of
(16.03)
and
(16.04)
(1976)
t r e a t the problem thoroughly. Such dynamic systems have a natural f r e quency given by:
(16.05)
102
nx
(16.06)
+ ""s + w
Further properties of the response are dependent upon the char a c t e r i s t i c s of the applied f o r c e , F ( t ) . For example i f F ( t ) is a
block f u n c t i o n :
for t 0
F(t) = 0
(16.07)
F ( t ) = F = constant
(16.08)
for t ^ t j
F(t) = 0
(16.09)
contact force
here
[cos[
(t - t ^ ) ] -
cos(.^^t)]
(16.10)
F (t)
F
for t ^ t^
Responses to other types of loads are also given by Bouma and Esveld
mw
(1976).
Our primary i n t e r e s t , however, is in the contact force between
Figure
15.5a
PROBLEM
the breakwater and ground. This can be better visualized using the
SCHEMATIZATION
c(t)
F(t)
S ( t ) = F,(t)
(16.11)
FORCE
c,(t)
mn +
+ m.
F [ cos ^^^t
cos [ M ^ ^ ( t - t ^ ) ] ]
(16.13)
This is a nice neat r e s u l t , but why are we spending so much e f f o r t on a block function response? Even though most dynamic loads on
breakwaters are not block f u n c t i o n s , any loading function can be approximated by the sum of several of these block f u n c t i o n s . Since the system
has been assumed to be l i n e a r , the response (contact f o r c e , i n t h i s case)
w i l l be the sum of the contact forces caused by each of the block funct i o n s . This w i l l be i l l u s t r a t e d with an example i n the next section.
Before proceeding to that example, however, i t is useful to examine
Note: Even though F ( t ) = 0 f o r t >^ t^ - equation 16.09, F ^ 0;
i t comes from the derivative of equation 16.10.
103
period, the two cosine terms i n equation 16.13 cancel out and C(t)
= 0 f o r a l l t 21 t p Another extreme example occurs when t^ i s one
h a l f o f the natural period. The maximum value of the term i n brackets i n equation 16.13 i s then two, and C(t) undergoes i t s maximum
v a r i a t i o n . In general, the force duration f o r impact forces on breakwaters w i l l be shorter than the natural period of the construction.
16.4. Example of Impact Response
Consider a single caisson o f a monolithic breakwater having d i mensions o f 15 X 10 x 30 m and a mass o f 9 x 10^ kg. A wave impact
pressure having a maximum value of 5 x 10^ N/m^ acts over an area
1.5 m high and 8 m wide f o r a t o t a l time of 20 ms. The r e s u l t i n g
actual and schematized force diagrams are shown i n f i g u r e 16.6. The
s o i l spring constant i s 3 x lO^'^'^ N/m and the v i r t u a l s o i l mass is
equal to the mass of the breakwater. The v i r t u a l water mass is 11
percent o f the breakwater mass.
Using (16.06) and the above data:
3
10
= 125.69
rad/sec.
(16.14)
( 1 . + 1. + 0.11)(9 X 10^)
or
1^ = 50 ms
(16.15)
also.
1. + 0.11
= T: + 1 . + 0 . 1 1
= 0.526
(16.16)
104
ACTUAL
FORCE
SCHEMATIZED
FORCE
UJ
u
cc
e
10
Time
Figure
20
15
in m i l l i s e c o n d s
16.6
ACTUAL A N D SCHEMATIZED
FORCE
DIAGRAM
Middle Block
Upper Block
t^ = 15 ms
t l = 9 ms
t ^ = 5 ms
Absolute
time
(ms)
Total
Relative
Contact
Relative
Contact
Relati ve
Contact
Contai
Time
Force
Ti me
Force
Time
Force
Force
(ms)
(lO^N)
(ms)
(lO^N)
(ms)
(lO^N)
(lO^N
n
U
3
6
3.
6.
5.
0.20
9.
0.60
8.
0.41
0.91
11.
0.57
2.86
4.
9.
15
12.
1.
18
15.
1.38
12.
20
17.
1.58
14.
1.05
13.
0.63
3.26
25
22.
1.65
19.
1.09
18.
0.60
3.34
30
27.
1.08
24.
0.72
23.
0.35
2.15
35
32.
0.11
29.
0.07
28.
-0.04
0.14
33.
-0.41
-1.92
40
37.
-0.91
34.
-0.60
45
42.
-1.58
39.
-1.05
38.
-0.63
-3.26
50
47.
-1.65
44.
-1.09
43.
-0.60
-3.34
60
57.
-0.10
54.
-0.07
53.
0.04
-0.13
70
67.
1.58
64.
1.05
63.
0.63
3.26
80
0.35
2.15
77.
1.08
74.
0.72
73.
90
87.
-0.92
84.
-0.61
83.
-0.42
-1.95
100
97.
-1.65
94.
-1.09
93.
-0.60
-3.34
105
F i g u r e 16.7
R E S P O N S E TO E X A M P L E
LOADINGS
( A L L TIMES IN M I L L I S E C O N D S )
4-
schematic
applied
20
40
60
"io"
time
looTrns) Load
lower
block
response
middle
block
response
-4
106
F^ sin Mt
where:
F^ is the dynamic force amplitude,
t
is time, and
This load frequency is less than that o f impact forces treated earl i e r . I t is also much lower than the natural frequency o f the structure so that the forces may be considered to be s t a t i c ; the massspring analogy used e a r l i e r i n t h i s chapter can be neglected.
Vi/aves
,W
^
B
k ^-=
N
F
N
F i g u r e 16.8
FORCES ON B R E A K W A T E R
N = W - B - N'
where:
B is the bouyant force with (assumed) s t i l l
water,
107
(15.19)
thus,
N' = E F^^ = e
s i n ut
(16.20)
in which e i s a constant.
The horizontal f r i c t i o n f o r c e , Fp, i s related to the normal f o r c e ,
N, by the Coulomb f r i c t i o n c o e f f i c i e n t as f o l l o w s :
Fp u N
(16.21)
where u i s the f r i c t i o n c o e f f i c i e n t .
This f r i c t i o n c o e f f i c i e n t is related to the underlying soil properties by:
li = tan 4
(16.22)
= Fp < u N
(16.23)
(16.24)
mg = W/g
(16.25)
K ^ ( ~ i - )
- F
1 + pe J
(16.26)
Cal 1 t h i s root u t p
For computational ease, equation 16.25 can be rewritten as:
mg
(16.27)
or:
^
(1
s, . t -
(16.38)
108
> tp
Doing t h i s :
^2
= I
v|
F
^
~- (I + ve)
m
(1 + us) sin . t dt -
^2
f
dt
'
(16.29)
(tg - t ^ )
(16.30)
= 0, thus:
cos Mt^ - cos loti + ( t g - t | ) sin wt^ = 0
(16.31)
=
'
v ( t ) dt
(16.32)
^1
^2
F
^
^2
(1 + ye) [cos ut -
COS
m t J dt -
( t - t l ) dt
(16.33)
(*2 - ^ l ) '
(16.34)
2
mg 10
1 2
2
- -2- 10 (tg - t^)
sin u t ^ ]
(16.35)
This is the o b j e c t i v e l Now, there remains only a problem of evaluat i n g equation 16.35 i n view of the f a c t that neither t-^ nor tg is
exactly known. ( I n a given physical problem, a l l of the other coeff i c i e n t s are known.) Luckily, t^ can be solved easily using known
parameters in equation 16.26; indeed, t h i s is simply an inverse sine
f u n c t i o n . Then, given a value f o r w t p iot2 can be solved using equat i o n 16.31. The solution of t h i s non l i n e a r equation must be done by
t r i a l . A v a l i d but t r i v i a l solution i s :
109
utg = oit^
(16.36)
From the physical problem statement and equation 16.17 we can conclude
that
0 < lot^ < J
(16.37)
utg > ^
(16.38)
and
(16.39)
Table 16.2
Breakwater s l i d i n g parameters
%
(rid)
f()t.)
(-)^
0.2
4.7822
3.6014
0.3
4.4407
2.6812
0.4
4.1451
1.9513
0.5
3.8771
1.3802
(rad)
0.5236
3.8168
1.2658
0.6
3.6276
0.9427
0.7
3.3913
0.6167
0.7854
3.1974
0.4115
0.8
3.1648
0.3823
0.9
2.9458
0.2212
1.00
2.7324
0.1169
1.0472
2.6332
0.0830
1.1
2.5233
0.0545 '
1.2
2.3176
0.0211
1.3
2.1144
6.0202
x 10
1.4
1.9129
9.5548
x 10
1.5
1.7124
2.8252
x 10
1.5708
1.5708
0.0000
110
Ill
closure
TT
Thus, e becomes a function of b, namely:
b _ b
e = 7F" ~
(16.40)
(16.41)
112
F (1 + us)
1.25 X 1 0 ^ 1 + 0.5 x - ^ ) ( l 2
rUg )''
F^^ 1 + us
. . . .
1.25 X lo''
0.5
1 + (0.5)(^)
= 6.48 X lO'^ ( ^ - )
1 + R
(16.43)
(16.44)
im,
(16.45)
(16.46)
(16.47)
= 1.08. This, combined with b = 10 m and
equation 16.39 y i e l d s ;
(16.48)
This is too small, since the allowable movement is 0.20 m; b must be reduced.
Table 16.3 shows the computation. As shown in the t a b l e , a width of 8.8 m
is s u f f i c i e n t .
Another i n t e r e s t i n g question i s "How f a r w i l l t h i s caisson be moved by
an 8 second clapotis caused by an individual wave having a 10% chance of
exceedance i n t h i s design storm?"
The actual oncoming wave height must f i r s t be found from the Rayleigh
d i s t r i b u t i o n - see volume I chapter 10. Using table 10.1 from that book y i e l d s ,
f o r 10% exceedance:
Tri = 1.07
sig
(16.49)
H = (1.07)(5.2) = 5.56 m
(16.50)
Thus,
= 100 m
(ig_5j^
113
Table 16.3
S l i d i n g computation
lOt^
f(u,ti)
(m)
{-)
{-)
^|t=tp
(m)
10.
0.566
1.08
0.14
0.407
1.90
0.342
0.513
1.30
0.189
8.9
0.508
1.33
0.195
8.8
0.503
1.35
0.200
(16.52)
= 0.99
P 9. 1^,
COSTTW
wl
cosh k(z + h) dz
(16.53)
-12
0
= P g H
K
sinh k(z + h)
cosh kli"'
(16.54)
12
(16.55)
5.16
(16.56)
10-" N/m
Fw2 = 7
(16.57)
9 H ^c
(16.58)
10^
0.5
1 +
( 0 . 5 ) ( | ^ ) J
= 1.04
Since t h i s is greater than 1.00 no motion can be i n i t i a t e d ; the
is stable.
(16.59)
structure
114
F i g u r e 16.10
FORCES
(Fw?)
I M P O R T A N T TO ROTATION
f^) + ( B | )
= W|
(16.60)
where i t has been assumed that the wave force, F^^, acts at an elevation
2 above the bottom. By assuming that the horizontal and vertical dynamic
wave pressures are the same at the lower exposed corner of the breakwater,
N' can be evaluated in terms of F^^, b, and h:
N' = ^
(16.61)
also:
p g b h
(16.62)
and
W = Pg (h + z^)(b) g
(16.63)
(i6_64)
115
In most problems, the water depth, h, and the wave f o r c e , F^, are known
Unknowns are band z^, both d i r e c t l y related to the breakwater dimensions.
The simplest handy s o l u t i o n , then, is to solve f o r z^ i n terms of b:
^ TIT "
P)
(16.65)
9'^
2
PB
(16.66)
\
p) gh
Obviously the positive root of (16,66) w i l l be the one of i n t e r e s t . Depending upon the problem, e i t h e r o f equations 16,65 or 16.66 may be u s e f u l .
16,8. Example o f Rotation
Let us check the breakwater used i n the sample calculation of section
16,6 against r o t a t i o n . In other words, f i n d the minimum width required to
prevent the breakwater from t i p p i n g over. Putting values from that section
in equation 16,65 y i e l d s :
(1.25
b=
10 )(12)
(16
10^ - 6.94
10'
(16.68)
= (163)2 = 12.8 m
(16.69)
116
17.
E.W. B i j k e r
17.1. Introduction
In the previous two chapters the e f f e c t s of waves on monolithic
breakwaters and t h e i r foundations have been discussed i n d e t a i l . Here,
we shall examine the influence which the breakwater has on the nearby
wave patterns and bottom morphology. In p r i n c i p l e each phenomenon d i s cussed i n the following sections occurs f o r both monolithic and rubble
mound breakwaters. Usually, since the phenomena depend upon wave r e f l e c t i o n they are most pronounced near v e r t i c a l monolithic breakwaters.
17.2. Standing Waves
One may remember from short wave theory that the resultant o f an
incident and d i r e c t l y r e f l e c t e d t r a v e l l i n g wave is a standing wave. Since
the r e f l e c t i o n i s greatest from v e r t i c a l smooth monolithic breakwaters,
standing wave problems are most often found near these structures. What
are the standing wave problems?
Since the wave height o f the standing wave is twice as much as that
of the incident wave, these waves can make f o r p r e t t y choppy going f o r
smaller ships approaching a harbor entrance or navigating w i t h i n the
harbor near a r e f l e c t i n g breakwater exposed to sea waves. For t h i s reason,
i t is often rewarding to avoid the construction o f v e r t i c a l r e f l e c t i n g
walls (breakwaters or quays) where sea waves penetrate i n t o the harbor.
- Standing cross waves can form i n narrow canals and harbor basins
having r e f l e c t i n g surfaces on both sides. The e f f e c t can be appreciable
when the width and depth of the basin enhances a reasonance - see volume
I chapter 19.
When longer v/aves such as swell and t i d a l components are involved,
both rubble mound and monolithic structures are e f f e c t i v e r e f l e c t o r s . The
resulting seiches can cause problems f o r both cargo handling and ship
moorings. These topics are discussed more f u l l y i n volume I I .
17.3. Local Morphological Changes
In areas where short standing waves are found (near v e r t i c a l breakwaters) the water motions are e s s e n t i a l l y d i f f e r e n t from those under a
t r a v e l l i n g wave. Therefore, morphological changes i n an erodable bottom
can be expected. Figure 17.1 shows the mass transport under a standing
wave as well as the expected bottom changes. These results were obtained
in a model study carried out by de Best (1971) and Wichers (1972), and
are also reported i n de Best, B i j k e r , Wichers (1971).
As is shown i n f i g u r e 17.1a, coarse material moves as bedload; the
resultant of forces on the grains tends to move them toward the nodes
r e s u l t i n g i n deposition there. Since there i s l i t t l e water motion near
the antinodes, the bottom remains stable there. Erosion i s most severe
midway between the nodes and antinodes.
A d i f f e r e n t pattern develops with f i n e sand which i s transported
largely i n suspension. Erosion takes place at the nodes where bottom
v e l o c i t i e s are high and material is deposited near the antinodes where
117
WAVE LENGTH X
ANTINODE
NODE
/ / / = 1 ' / A = y 7 7
/ / ^ / / = ^ / 7
DEVELOPED PROFILE
DEVELOPED PROFILE
Figure 17.1
STANDING
BOTTOM CHANGES
/ / J l = f / / ^
118
18.1
18.1.
Iiitroduction
Just as with rubble mound breakwaters, the method of construc-
t i o n can influence the design of a monolithic breakwater. The cons t r u c t i o n methods described i n the f o l l o w i n g sections w i l l apply to
the construction of only the massive monolithic part of the s t r u c t u r e .
Construction methods f o r bottom preparation - laying f i l t e r s - are
essentially the same as f o r rubble mound breakwaters; one is referred
to chapter 10. The only exception to t h i s remark would be the use o f a
separate p i l e foundation f o r a monolithic top construction. This is no
longer common p r a c t i c e , however, and w i l l not be discussed here except
i n c i d e n t a l l y i n section 18.4.
18.2 Construction Over Crest
One o f the principal methods o f placing the large elements o f a
monolithic breakwater is to set them i n place using a special
crane
119
Since the keying j o i n t s of these units s l i d e along each other during placement, special precautions must be taken to prevent damage
to the keys. The usual method is to face the contact surfaces with
hardwood - greenhart i s e x c e l l e n t . This is shown i n cross-section c-c
of f i g u r e 18.2.
120
CONSTRUCTION C O N S I S T I N G
OF C Y L I N D R I C A L C A I S S O N S
121
In the north polar sea icebergs are sometimes towed near shore and
sunk by adding ice on top of them in order to form a breakwater.
122
123
19.
OPTIMUM DESIGN
W.W. Massie
A. Paape
19.1.
Introduction
The objective of t h i s chapter i s to use the information presented
Design Data
While a l l of the data presented i n chapter 11 remains v a l i d f o r
Storm Data
sig^
Interval
Period
No. o f Waves
h'
(-)
(m)
(yrs)
(m)
0.1
4.5
7.4
3000
0.5
5.5
2500
1.0
6.0
10
2000
(s)
7.0
11
1000
20
8.0
12
1000
100
9.0
13
800
Water level
3.2
4.6
Cost of materials
The cost data provided i n table 11.2 must be augmented. Further,
since the monolith w i l l be fabricated from concrete elements, costs
of armor stone are no longer relevant. Table 19.2 gives the r e l a t i v e
cost figures necessary f o r t h i s design.
A l l other data remains as presented i n chapter 11 section 3.
124
125
Unit
Use
Sand
caisson
fill
Gravel
f i l t e r layer
Caissons
Concrete
(p = 2400
kg/\)
Placement Method
barge
Over
dumped
Crest
6*
10
40
50
350
400
Large Elements
150
cap Const.
19.3. Preliminary Computations
Since the face o f t h i s breakwater i s to be v e r t i c a l , we can expect a standing wave to form before i t . Also, since the breaking c r i t e r i a f o r standing waves d i f f e r from those f o r t r a v e l l i n g waves, the
vrave breaking computations of section 11.4 must be revised.
From Wiegel (1964), the appropriate breaking c r i t e r i u m f o r standing waves i s :
= 0.109 X tanh kh
(19.01)
where:
H is the maximum progressive wave component,
k
follow
from equation 19.01. We see that the standing wave breaking criterium
is never a governing f a c t o r f o r the s i g n i f i c a n t wave, since the higher
of these break from shoaling long before reaching the breakwater. As
can be seen by comparison of the two tables mentioned, the results f o r
'^sig
TABLE 19.3
Wave Computations
Recurrence
h'
^0
Interval
Wave
Total
length
depth
h
^0
h/x^
h/x
^sig
Note
P(Hsig)
Waves
N
11
(yrs)
(m)
(sec)
(m)
(m)
(m)
0.1
4.5
7.4
2.8
85.
0.5
5.5
3.0
No. of
, storms^
year '
(-)
(-)
(-)
(m)
(m)
12.8
0,.1506
0.,1838
70.
6.2
0,9133
4.1
(1)
10
3000
126.
13.0
0 .1028
0..1434
91.
7.0
0.9308
5.1
(1)
2500
(m)
6.0
10
3.2
156.
13.2
0 .0845
0..1273 104.
7.5
0.9487
5.7
2000
7.0
11
3.7
189.
13.7
0 .0725
0..1163 l i s
8.0
0.9667
6.7
(1)
(2)
0.2
1000
10
7.5
11.5
3.9
207.
13.9
0 .0673
0,.1114 125.
8.2
0.9766
6.8
(2)
0.1
1000
20
8.0
12
4.2
225.
14.2
0 .0631
0,.1074 132.
8.5
0.9858
7.0
(2)
0.05
1000
50
8.5
12.5
4.4
244.
14.4
0 .0590
0,.1033 139.
8.7
0.9958
7.1
(2)
0.02
900
100
9.0
13
4.6
264.
14.6
0 .0553
0,.0996 147.
8.9
1.006
7.2
(2)
0.01
800
500
10.0
14
5.1
306.
15.1
0 .0493
0..0934 162.
9.3
1.025
7.4
(2)
0.002
600
1000
10.5
15
5.3
351.
15.3
0 .0436
0..0873 175.
9.5
1.048
7.5
(2)
0.001
500
5000
11.5
16
5.8
399.
15.8
0 .0396
0,.0827 191.
9.9
1.066
7.7
(2)
0.0002
500
Notes:
(1)
(2)
127
TABLE 19.4
S t a t i s t i c a l Calculation f o r
= 8.0 m
Char.
H
exceedance P(H,. ) H
N
HxVHsig
sig
s i g ' sig
, .
,storm. /Storm, - , ,waves, / x
/ N
P(%)
/ \
^2i
^1
(-)
10
4.1
4.5
3000
6.8
0.0
0.0
0.0
1.
5.4
2000
7.3
0.0
0.0
0.0
0.8
6.1
1500
7.7
0.0
0.0
0.0
0.15
6.8
1000
8.2
1.18
6.28x10'^
1.00
1.50x10. - 1
0.04
7.1
900
8.7
1.13
7.89x10'
1.00
4.00x10
0.008
7.3
700
9.1
1.10
9.05xlO"^
1.00
8.00x10
0.0018
7.5
500
9.5
1.07
LOSxlO'^
1.00
1.80xl0"^
5.1
5.7
6.7
0.2
7.0
0.05
7.2
0.01
7.4
-3
0.002
7.7
0.0002
P(H > Hg) = 1.92
10
-1
brea-
P(Hjj) = 0 when Hp > H^ (table 19.3) corresponding to the other cond i t i o n s i n the row.
128
P(Hj) =e
- 2(|r^)2
^ig
(19.02)
H ,
Since the ratios - p j are never extremely large, the chance that
oc-
(19.03)
[ , n ^ ( l - E2i)]
(l^-""^)
= 0.192
f o r the data i n table 19.4. This value is the same as ( w i t h i n reas-onable computational accuracy) the chance of exceedance o f the lowest Hg.g i n which
this
problem
with
breaking
waves,
speoial
this
19.4.
F i g u r e 19.2
D E S I G N W A V E H E I G H T A S FUNCTION
OF A N N U A L F R E Q U E N C Y
OF
EXCEEDANCE
11
n
11.U
i1 nun. u
H>ir~
Q
y. u
O n
8.0
7 0
f,
D. U
10"^
2x10 ^
5x10"^
10 ^
2x10 ^
5x10"^
10 ^
2x10"^
5x10"^
P(H>Hd)
1.0
130
A thickness i n the order of 1.5 m should be s u f f i c i e n t . This e l i m i nates one source of possible damage.
Since the short period dynamic forces can cause e i t h e r a s l i d i n g
or t i p p i n g f a i l u r e of the breakwater, these forces must be used i n
both c r i t e r i a . For a given design, however, f a i l u r e w i l l occur e i t h e r
by s l i d i n g or t i p p i n g and not, i n general, by both forms simultaneousl y . The condition ( s l i d i n g or tipping) which happens to be important
i n a given design w i l l be that which occurs with the lower applied
f o r c e , F^^.
Failure w i l l be considered to have occurred when any o f the f o l l o wing occur:
a.
b.
c.
19.5.
waves of the i r r e g u l a r
131
Figure 19.3
ELEMENT DETAILS
LT
SECTION A-A
b
concrete cap 1 nn thick
bottonn 1 m thick
132
(19.05)
155011401 = 4000/m
(19.06)
x (5h* + bh* + 4b - 4)
(19.07)
Sand f i l l :
(4b - 4)
(19.09)
= 109.09b - 109.09
(19.10)
(19.11)
(-4h* + 4bh* - 8b + 8)
(19.12)
(19.13)
133
TABLE 19.5
Element Quantities
Item
dimensions
(-)
(m)
number
volume
(-)
(m^)
3
3
Concrete: p = 2400 kg/m ; costing 400/m
Ribs
0-5 X 0.5 X h*
h*
Side Walls
0.5 x 4 x h*
4h*
End Walls
0.5 x h* x b
h*b
Bottom
4 X (b-l) X 1
4b;:4
5h* + bh* + 4b - 4
(b-l)
costing 150/m'
1
4b-4
3
3
Sand F i l l , wet: p = 2400 kg/m ; costing 6/m
(h*-2)(b-l)4
-4h* + 4bh* - 8b +
= 17.5 and
(19.14)
Determination o f Damage
Since two optimization variables are involved, they w i l l be varied
independently with one, the crest elevation being held constant while
the width i s varied. This process w i l l be repeated with various ( f i x e d )
crest elevations. The steps below are numbered f o r easier reference.
The order shown i s not the only one possible; other sequences of the
f i r s t steps, especially, are conceivable.
1.
be:
h* = 9 + 10 - 1.5 = 17.5 m
This establishes the f i r s t of our optimization variables.
(19.15)
134
= 8.7 m with a
SWL 4.4 m above MSL. This wave has a period of 12.5 sec. and a length,
X, of 139 m. Other values w i l l be chosen l a t e r when a new condition
is needed.
3. Compute the clapotis f o r c e . The clapotis force is computed using
the methods described i n section 15.2. The i n t e g r a t i o n of the dynamic part of equation 15.01 extends from the SWL (MSL + 4.4 m) to the
bottom o f the monolith (MSL - 8.5 m). Thus:
0
wl
cosh k(z + h) dz
cosh kh
(19.16)
-h.
where:
g is the acceleration of g r a v i t y ,
H is the approaching wave height,
h is the water depth to SWL.
h^ is the depth above the structure toe,
k is the wave number =
2T7/A,
z is the v e r t i c a l coordinate,
P is the mass density of water, and
A is the wave length.
0
''wi = F c o f h kh
(19.17)
^^"h k(z + h)
z = -h.
-MrW
[sinh(kh) - sinh(1.5k)]
(19.18)
(19.19)
(19.20)
(2)(Tr)(cosh kh)
'TofAh
"
'w2 = 2 P9 ^d ^c
where z^ is the crest height above SWL.
and
(19.21)
135
= i
pg
(19.22)
Rec.Int.
h'
(yrs)
(m)
(m)
(m)
10
8.2
3.9
125.
20
8.5
4.2
132.
5
10
9.586 X 10^
50
8.7
4.4
139.
1.005
Fwl
(N/m;)
8.959 X
X
10^
100
8.9
4.6
147.
1.053
10^
500
9.3
5.1
162.
1.157
10^
1000
9.5
5.3
175.
1.212
10^
5000
9.9
5.8
191.
1.321
10^
(19.23)
(19.24)
^ = ^ 1
4.
+ ^2
(19-25)
(19.26)
> 1.00
(16.26) (19.27)
where:
B is the bouyant force on the breakwater
section,
PR
(19.28)
136
y i e l d s , when u = 0.5:
(b){h*)pe g - b(h^) pg
(19.29)
> 1
1 + 0.5
or, since
= h
2 h.
- h, :
(19.30)
Tpri
- 2 g h^[pg
Substituting numerical
+"(pg - P) h^]
b
,
1.207 X 10^
(4)(12.9) + b - (2)"(9.81)"(T2".9) [(2400)(4.6) + (2400" - 1030)12.9]
(19.31)
b + 51.6
(19.32)
> 0.166
-
or:
(19.33)
The r o t a t i o n check follows from equation 16.69:
(16.66)(19.34)
b>
2 F.
Again s u b s t i t u t i n g values y i e l d s :
(1 .207 x l O )(12.9)
b>
10'
(19.36)
>_ 8.42 m
Choose b = 10.3 m; t h i s s a t i s f i e s both conditions.
5.
ding displacement.
K (1 +
f{ti)
(15.39)
(19.37)
Again using (16.40) and assuming that the dynamic force has a period of
one second:
137
PQIJ-)
bh
Thus:
4 / bh*
Pp,
Fw f c ^ i ) = r ^ ^ | t = t ,
1 +
2
(19-39)
(19.40)
where J i s a constant.
A second r e l a t i o n involving F^^ which must be s a t i s f i e d results from
equation 16.26:
sin(t^) = ^ S ^ i - ^ )
(19.41)
''w
o r , using previously introduced relations such as were used i n (19.29):
F^ s i n ( t ^ ) =
bg(h* Pg - p h j
5
^
2(1 + R ^ )
(19.42)
(19,43)
where K i s a constant.
Dividing (19.40) by (19.43) y i e l d s :
(19.44)
sin(t^)
f(cot,)
I f we know the r a t i o ^.!/ -ir-r as a function of toti .then uti can be
sin((i)ti)
i'
- i
evaluated from known parameters. Once ut-^ i s known, then F^ follows
d i r e c t l y from, f o r example, (19.43). The r a t i o ^ ( " ^ ' l )
sin(Mt-j^)
i s independent
df the breakwater properties and can be evaluated from the data i n t a ble 16,2. This has been done; the results are l i s t e d i n table 19,7 and
shown i n f i g u r e 19.4.
For the problem at hand,
f(t^)
4^2 i^h* Pg
2(1+^)
sin(cotiy " ^ b \ ^ t = t , ,
"7
1
(1 + W^'
2 bg(h Pg - h^
which with the known constants y i e l d s :
T
p)
(19.45)
138
139
TABLE 19.7
wt-|^
sin((i>t^]
(rad)
0.2
18.1276
0.3
9.0728
0.4
5.0108
0.5
2.8789
0.5236
2.5316
0.6
1.6696
0.7
0.9573
0.7854
0.5819
0.8
0.5329
0.9
0.2824
1.00
0.1389
1.0472
0.0958
1.1
0.0612
1.2
0.0226
1.3
6.2479 X 10"3
1.4
9.6959 X 10"*
1.5
2.8323 X 10'5
1.5708
0.0000
^"^"M^
(2400)(17.5)-(1030)(12.9)
= 1.177
(19.49)
which y i e l d s :
wtj^ = 0.66
(19.50)
(2)(1 + ^ ) s i n ( w t i )
(19.51)
yielding:
F
- (9.81)(10.3)[(2400|(17.5) - (1030)(12.9)]
"
2(1 + - ^ ^ 1 ^ )
= 1.973
10^ N/m
sin(0.66)
(19.53)
140
6.
(19.54)
7.
^^ggg^
(19.56)
is done because the lower force has the greatest frequency of exceedance. In t h i s c a l c u l a t i o n , the lower force is 1.626 x 10^ N/m and
is determined by a r o t a t i o n c r i t e r i u m . This means that s l i d i n g w i l l
not be a problem; a short period force w i l l cause f a i l u r e by t i p p i n g
before s l i d i n g becomes c r i t i c a l . Thus, the p r o b a b i l i t y of f a i l u r e by
s l i d i n g is t o t a l l y i r r e l e v a n t .
From f i g u r e 1 9 . 1 , with L
P(F^^) = 1/34
per year
(19.57)
9.
= P(F) + P(Hj)
(19.58)
(19.59)
(19.60)
(19.61)
141
10.
(19.62)
(11.31)
(19.63)
y i e l d s a c a p i t a l i z e d damage cost o f :
cap.dam. = (12.2335)(2)(C)(P(f))
11.
(19.64)
c a p i t a l i z e d damage cost:
t o t a l cost = [ ( 1 2 . 2 3 3 5 ) ( 2 ) ( P ( f ) ) + 1 ] C
= [24.467 P ( f ) + 1 ] C
(19.65)
(19.66)
or i n t h i s case:
t o t a l cost = [(24.467)(4.941 x l O ' ^ ) + 1]
= 6.305 X 10*/m
142
parameter
value ( t o t a l cost, here) as a function of the two optimization paramet e r s , height and width. This is shown i n f i g u r e 19.7. The previous f i gures can, o f course, be related to f i g u r e 19.7. The curves i n f i g u r e
19.5 are p r o f i l e s made by intersecting the optimization surface with
At
planes h
c.
143
Eq. No.
h'
.'11*
(m)
(-)
(m)
(m)
(m)
(m)
3
tab.19.6
(19.21/22)
"wl
(N/m)
''w2
(N/m)
(19.25)
(N/m)
(19.34)
SLIP
TIP
chosen
sin ojtj
*t.|^
(m)
(m)
(m)
(19.30)
(19.47)
f i g . 19.4
f()tj^)
(19.51)
(19.54)
sliding
tipping
critical
(N/m)
(N/m)
f i g . 19.1
K
(N/m)
(-)
11
(19.58)
(19.13)
(19.65)
P(f)
{-)
(-/m)
' t o t a l cost
(-/m)
17.5
1/50
8.7
4.4
4.6
12.9
1.005x10^
2.022x10^
1.207x10^
10.27
8.42
10.3
1.177
0.66
1.973x10^
1.626x10^
1.626x10^
1/34
4 .941x10"^
2.854x10^
6.305x10*
17.5
1/100
8.9
4.6
4.4
13.1
1.053x10^
1.979x10^
1.251x10^
10.79
8.71
10.8
1.185
0.66
2.043x10^
1.714x10^
1.714x10^
1/41
3.439x10''^
2.945x10^
5.423x10*
0.65
2.216x10^
1.994x10^
1.894x10^
1/62
4.538x10*
2.296x10^
1.996x10^
1.996x10^
1/80
1 .813x10 ^
U350xl0"^
3.144x10^
0.65
3.253x10'^
4.327x10*
17.5
1/500
9.3
5.1
3.9
13.6
1.157x10^
1.833x10^
1.340x10^
11.89
9.34
11.9
1.207
17.5
1/1000
9.5
5.3
3.7
13.8
1.212x10^
1.776x10^
1.390x10^
12.51
9.66
12.5
1.216
17.5
1/5000
9.9
5.8
3.2
14.3
1.321x10^
1.601x10^
1.481x10^
13.72
10.33
13.8
1.239
17.5
17.5
0.65
2.458x10^
2.199x10^
2.199x10^
1/140
7 .343x10"'^
3.488x10'^
4.115x10*
14.3
14.5
0.65
2.558x10^
2.334x10^
2.334x10^
1/205
4 .878x10"-^
3.615x10^
4.046x10*
14.3
16.0
0.65
2.764x10^
2.611x10^
2.611x10^
1/450
2 .222x10"-^
3.886x10^
4.097x10*
19
1/50 '
8.7
4.4
6.1
12.9
1.005x10^
2.682x10^
1.273x10^
9.51
8.08
9.5
1.135
0.67
2.048x10^
1.629x10^
1.629x10^
1/34
4 .941x10"^
2.879x10^
6.359x10*
19
1/100
8.9
4.6
5.9
13.1
1.053x10^
2.654x10^
1.318x10^
9.96
8.34
10.0
1.143
0.67
2.130x10^
1.732x10^
1.732x10^
1/43
3 .326x10"^
2.975x10^
5.397x10*
0.66
2.313x10^
1.921x10^
1.921x10^
1/67
1 .693x10"^
3.169x10^
4.481x10*
0.66
2.390x10^
2.018x10^
2.018x10^
1/86
1 .263x10'^
3.265x10^
4.274x10*
3.458x10^
4.093x10*
19
1/500
9.3
5.1
5.4
13.6
1.157x10^
2.238x10^
1.411x10^
10.93
8.93
11.0
1.161
19
1/1000
9.5
5.3
5.2
13.8
1.212x10^
2.496x10^
1.462x10^
11.47
9.22
11.5
1.169
19
1/5000
9.9
5.8
4.7
14.3
1.321x10^
2.351x10^
1.556x10^
12.52
9.83
12.5
1.189
19
14.3
14.0
19
14.3
15.0
21
1/500
9.3
5.1
7.4
13.6
1.157x10^
3.478x10^
1.505x10^
21
1/1000
9.5
5.3
7.2
13.8
1.212x10^
3.457x10^
1.558x10^
9.97
0.66
2.534x10^
2.193x10^
2.193x10^
1/137
7 .499x10"'^
0.56
2.779x10^
2.533x10^
2.533x10^
1/360
2 .778xlO"'^
3.748x10^
4.003x10*
0.66
2.936x10^
2.750x10^
2.750x10^
1/650
1 .538x10''^
3.941x10^
4.090x10*
8.50
10.0
1.114
0.67
2.429x10^
1.930x10^
1.930x10^
1/69
1 .549x10"^
3.210x10^
4.505x10*
8.77
10.5
1.121
0.67
2.522x10^
2.047x10^
2.047x10^
1/93
1 .175x10"'^
3.314x10^
4.267x10*
11.5
1.137
0.67
2.699x10^
21
1/5000
2.262x10^
2.262x10^
1/170
6 .082x10"^
3.524x10*
4.048x10*
21
14.3
12.5
0.57
2.891x10^
2.534x10^
2.534x10^
1/360
2,,778x10"'^
3.733x10*
3.987x10*
21
14.3
13.5
0.67
3.078x10^
2.798x10^
2.798x10^
1/750
1 .333x10"'^
3.942x10*
4.071x10*
23
1/5000
0.67
2.252x10^
2.837x10^
2.252x10^
1/200
5,.200x10''^
3.556x10*
4.009x10*
23
14.3
12.0
0.67
2.722x10^
3.172x10^
2.722x10^
1/600
1,,667x10"-^
3.895x10*
4.054x10*
23
14.3
12.5
23
1/1000
9.5
5.3
9.2
13.8
1.212x10^
4.417x10^'
1.654x10^
20
1/1000
9.5
5.3
6.2
13.8
1.212x10^
2.977x10^
20
1/5000
9.9
5.8
5.7
14.3
1.321x10^
2.852x10^
20
14.3
20
14.3
22
1/1000
9.5
5.3
8.2
13.8
1.212x10^
3.937x10^
1.606x10^
8.58
10.0
22
1/5000
9.9
5.8
7.7
14.3
1.321x10^
3.852x10^
1.706x10^
9.11
10.9
22
14.3
22
14.3
9.9
9.9
5.8
5.8
6.7
8.7
14.3
14.3
3.352x10^
1.321x10^
1.321x10^
4.355x10^
1.659x10^
9.33
1.756x10^
8.92
10.5
1.097
0.67
2.875x10^
3.280x10^
2.875x10^
1/910
1.,099x10"^
4.008x10*
4.115x10*
8.42
9.7
1.084
0.68
2.063x10^
2.639x10^
2.063x10^
1/97
1,,131x10"^
3.376x10*
4.310x10*
1.510x10^
8.98
11.0
1.143
0,66
2.042x10^
2.480x10^
2.042x10^
1/92
1.,187xl0"^
3.294x10*
4.250x10*
1.606x10^
9.55
11.9
1.161
0.66
2.212x10^
2.623x10^
2.212x10^
1/145
7.097x10"^
3.475x10*
4.078x10*
13.0
0.66
2.488x10^
2.820x10^
2.488x10^
1/320
3..125x10'^
3.696x10*
3.979x10*
14.0
0.66
2.730x10^
2.995x10^
2.730x10^
1/620
1. 613x10"^
3.898x10*
4.052x10*
1.101
0.67
2.032x10^
2.581x10^
2.032x10^
1/89
1. 224x10"^
3.327x10*
4.322x10*
1.116
0.67
2.237x10^
2.754x10^
2.237x10^
1/155
6.652x10"'^
3.522x10*
4.096x10*
2.984x10^
2.560x10^
1/390
2.564x10"^
3.762x10*
3.998x10*
2.847x10^
1/825
1. 212x10"^
3.979x10*
4.097x10*
9.67
12.0 -
0.67
2.560x10^
13.0
0.67
2.847x10^
-3,
3.186x10^
145
F i g u r e 19.5 a
COST C U R V E S
CREST
FOR V A R I O U S
ELEVATIONS
70
10
04
10
11
12
13
15
16
WIDTH ( m )
146
F i g u r e 19.5 b
COST CURVES
CREST
FOR
VARIOUS
ELEVATIONS
70
60
50
c]
H
40
'
30
20
10
WIDTH
(m)
h ' * = 2 D.Or
h'^ = 2 I.Or
147
F i g u r e 19.5 c
COST CURVES FOR VARIOUS
CREST E L E V A T I O N S
70
60
50
40
'
20
h'*=2 3.0
h''= 2 ?.0 m
10
10
11
12
13
V^IDTH
(m)
15
16
Figure
19.6
T O T A L COST V E R S U S
HEIGHT
T O T A L COST V E R S U S
WIDTH
FOR B E S T S O L U T I O N S
c
O
39-
37-
35-
10
12
width
b (m)
16
18
height
20
h (m)
22
17
10
12
13
w i d t h , b, (m)
15
15
13
etev. 11.7
110.0, s l o p e
1:100
20
70
F i g u r e 19.8
S K E T C H OF M O N O L I T H I C
ORIGINAL
S C A L E : 1 :500
BREAKWATER
fig
11.3
151
b.
c.
will
(19.69)
not occur i n the l i f e of the structure i s :
[1 - P ( f ) ] ^
(19.70)
(19.71)
(19.72)
152
20.
J.F. Agema
E.W.
20.1. Introduction
Bijker
W.W. Massie
The purpose of t h i s chapter w i l l be to b r i e f l y summarize the a p p l i cation of breakwater design principles i n a s p e c i f i c case. In order to
put the breakwater design i n proper perspective, general harbor layout
considerations w i l l f i r s t be discussed. Later the discussion becomes
more s p e c i f i c r e s u l t i n g i n construction details o f the northern breakwater of the entrance.
A special feature of t h i s p a r t i c u l a r design study was that both
monolithic and rubble mound structures were considered. More important,
the economically least expensive solution was not chosen.
The reasons f o r t h i s appear in section 20.4.
20.2. Harbor Layout Considerations
This design problem involves the expansion o f an e x i s t i n g , busy
harbor complex. Ship t r a f f i c destined f o r the e x i s t i n g harbor f a c i l i t i e s
must be taking i n t o consideration when planning the expansion.
One way to avoid c o n f l i c t s between construction operations and exist i n g shipping i s to develop a second, new, separate harbor entrance. While
such a plan has advantages during construction, i t results i n a more complex (dangerous) t r a f f i c pattern i n the immediately adjacent sea a f t e r
completion. Many more crossings occur i n ship's paths entering and leaving from two adjacent harbor entrances than from a single entrance. A l so, t i d a l current patterns become more complex as the number o f entrances
increases. Navigation becomes more d i f f i c u l t ; wider dredged channels are
needed.
All o f these factors led to an early decision to use only a single
main harbor entrance. The consequences - that an accident i n the single
harbor entrance could shut down the e n t i r e port and that construction
a c t i v i t i e s could not be allowed to s i g n i f i c a n t l y hinder shipping - were
accepted.
Four possible main purposes of breakwaters are l i s t e d i n chapter 2:
wave reduction, reduce dredging, provide quay f a c i l i t i e s , and guide currents. Which of these are important f o r Europoort? L i t t o r a l transport
of sand was e f f e c t i v e l y stopped by other features - the seaward indust r i a l expansion to the south and the e x i s t i n g breakwater and groins to
the north. The entrance width would not be varied appreciably - harbor
currents and erosion or deposition would not be m a t e r i a l l y influenced;
dredging would not be increased by the breakwater extensions. Adequate
quay f a c i l i t i e s were planned elsewhere f u r t h e r i n l a n d . Since ships would
be entering with a reasonable speed, even tugboat assistance could be
postponed u n t i l ships were well inside the harbor entrance.
The combination o f longshore and harbor t i d a l currents d i d , however, present harbor layout problems. The layout o f the harbor entrance
breakwaters was to a great extent determined by the predicted current
patterns. The r e s u l t of the chosen layout on the current pattern has a l ready been shown - f i g u r e 2.4. Concluding, the primary .purpose o f the
153
breakwater i s to guide t i d a l currents. How does t h i s functional need ref l e c t on the breakwater design?
Since wave action i n the entrance is not detrimental to the harbor
operation i n this case, the breakwater crest need not be high; overtopping is o f no consequence. Other navigational aids, buoys and f i x e d
l i g h t s would guarantee v i s i b i l i t y ; the crest elevation could be low, only
mass overtopping which could lead to substantial currents i n the entrance
must be prevented. Thus, the minimum crest elevation r e s u l t i n g from the
harbor layout was a b i t higher than the normal high t i d e l e v e l . *
Breakwater porosity was not a design f a c t o r since sand transport and
wave transmission were not important. Low porosity was not considered det r i m e n t a l , but i t was not required. A l l of these design layout aspects
are dealt with i n more d e t a i l i n an anonymous Dutch r e p o r t . Ret Ontwerp
van
de Nieuwe
Havenmond bij
which s a t i s f y these harbor layout requirements are discussed i n the f o l l o wing section. There, and f o r the rest of t h i s chapter, the discussion w i l l
be r e s t r i c t e d to the extension of the northern breakwater - see f i g u r e
20.1.
20.3. Proposed Designs
Many types o f breakwater structures were considered, a l l of which met
the harbor layout requirements expressed i n the previous section. Rubble
mound, monolithic and composite constructions were considered, twelve d i f ferent concepts i n a l l . These are each i l l u s t r a t e d via sketches i n f i g u r e
20.2.
154
simplified.
The f i n a l choice f o r the breakwater form was a rubble mound struct u r e , constructed using concrete cubes f o r primary armor. More details
of the design and construction are given i n the following section.
20.5. Construction Details
Two cross sections of the northern breakwater are shown i n f i g u r e
20.4.
As i s shown i n figure 20.4, a broad portion of the sea bed was raised
using a sand and gravel f i l l . A large quantity of inexpensive, easily
placed material was used i n order to reduce the size of the breakwater
proper. In t h i s way, a maximum portion of the structure could be b u i l t
from moving ships; the hinderance to other shipping t r a f f i c was m i n i mized. Further details of the construction phases are shown i n f i g u r e
20.5.
TABLE 20.1
Type
90 Caisson
25200
1300
26500
1/1000
60 Caisson
13500
500
14000
1/1000
Hanstholm
Caisson
11400
100
11500
1/5000
Hanstholm
Caisson
with Cubes
12700
300
13000
1/3000
Hanstholm
block Wall
14300
200
14500
1/5000
Concrete
f
Cube Rubble
Mound
154U0
600
16000
1/1500
Stone As- g
f a i t Rubble
Mound
19000
Concrete
Cubes Retaining
Wall
15000
Caisson
with cubes
17000
Retaining
Wall on
top of
Rubble
Mound
17000
Wall d i f f i c u l t to place
Rock asphalt top used
Retaining
Wall on
top of
Rubble
Mound
17000
Concrete
Cubes with
Crest
Struct.
15500
155
156
Figure
20.2
NORTH BREAKWATER
a 90 CAISSON
NAP=0
15K.
NAP =0
-1,8 ( - ^ 3 0 ^
/ sand
mineston
a ravel
b= 11,8m
ft
157
NAP = 0
^^V22Dtn<g/m
300-1000
IU-1UUU kkg I
10-60M
///(///??<m:
b = 12m
gravel
NAP:=0
-12
158
J. R E T A I N I N G
W A L L ON R U B B L E
MOUND
NAP=0
RETAINING
W A L L ON R U B B L E
MOUND
+ ^ stone a s p h a l t
NAP = 0
-11
-12
I. CONCRETE
CUBES WITH
CREST
STRUCTURE
J ^ s t o n e asphalt
NAP =0
159
- _ T O W _ C ;OST
CON
6.1
3 T R U C T l O b\
6.2
5.3
COST
6.4
6.5
-m> D E S I G N LOAD
Figure
20.3Q
OPTIMIZATION
HANSTHOLM"
CURVE
CAISSON
21000
Hsigd (m)
Figure 20.3b
OPTIMIZATION C U R V E FOR
C U B E RUBBLE MOUND
FOR
6.6
(10^N/m^)
CROSS
SECTION
Fiqure
D-Q
IN
FIGURE
20.4
C R O S S S E C T I O N S OF
NORTH BREAKWATER
20.1
161
t r a i l i n g dredger
( sailing )
fed
;=?;\WA?^W-<^^'^^^ original bottomv//
t h e n a t u r a l b o t t o m raising phase 3
f i n e gravel and coarse sand
t r a i l i n g dredger
{sailing )
barge w i t h s i d e unloading
{ cross s a i l i n g )
r u b b l e dumping
0.3 - 1,0 T
barge w i t h s i d e unloading
(cross sailing )
1
Vr-irw.-v
c o m p l e t i n g berms
r u b b l e d u m p i n g 1-6T
Figure
20.5
(CONSTRUCTION ) PHASES
OF N O R T H
BREAKWATER
162
W.W. Massie
Roman Letters
Sym-
Definition
bol
Equa-
dimensions
Units
,2
2
m
tion
coefficient
ag
acceleration
16.01
LT-2
m/s^
bouyant force
16.18
MLT"2
7.02
coefficient
breakwater width
C^
contact force
16.11
MLT"2
c^
spring constant
16.02
ML2T-2
Nm/rad
MT'2
MT"2
N/m
7.08
16.40
7.22
L-2
. u n i t surface area
c^
spring constant
16.03
c^
spring constant
16.02
block "diameter"
7.01
F^
force in z d i r e c t i o n
16.03
16.02
MLT'2
-2
MLT
N/m
N
N
163
Sym-
Equa-
Definition
bol
dimensions
Units
tion
F^^
wave force
16.17
MLT ^
Fp
f r i c t i o n force
16.21
MLT'2
7.04
MLT'2
LT'2
m/s^
f r i c t i o n force
failure in P(f)
ACCELERATION OF GRAVITY
WAVE HEIGHT
19.58
7.01
19.02
H.j
15.01
Hg^jg
s i g n i f i c a n t wave height
11.03
s i g n i f i c a n t wave height at
11.04
5.04
f i g . 5.02
7.19
Lj
sig^
deep water
H^
Hy
WATERDEPTH
component
tab.11.3
hg
h'
waterlevel
11.05
t o t a l height o f breakwater
19.07
Ig
virtual inertia
16.04
ML^
kgm^/rad
^wy
virtual inertia
16.04
ML^
kgm^/rad
Igy
virtual inertia
16.04
ML^
kgm^/rad
subscript index
16.04
ML^
kgm^/rad
constant
19.40
15.01
L"1
1/m
tab.11.1
constant
WAVE NUMBER
19.43
15.03
mass
16.05
16.04
MLV^
2TI/X
m
kg
Nm
My
moment
m'
mg
breakwater mass
16.02
kg
m^
v i r t u a l s o i l mass
16.01
kg
m^
v i r t u a l water mass
16.03
kg
normal force
MLT"2
number of waves
7.21
7.23
7.03
tab.19.3
164
Sym-
Definition
bol
Equa-
dimensions
Units
tion
N'
slope porosity
P( )
p r o b a b i l i t y of ( )
19,02
pressure
15.01
run up
16.18
MLT"2
5,01
ML"1T"2
N/m^
5,01
hydraulic radius
15.05
slope roughness
5,01
PERIOD (wave)
5.01
TIME
15.01
s;hr
Layer thickness
7,21
COMPONENT VELOCITY IN X
LT"1
m/s
DIRECTION
V
TOTAL VELOCITY
15.02
LT"1
m/s
COMPONENT VELOCITY IN Y
16.24
LT"1
m/s
16,18
MLT'2
7,03
MLT"2
LT"1
m/s
DIRECTION
W
breakwater weight
^sub
block weight
COMPONENT VELOCITY IN Z
DIRECTION
COORDINATE DIRECTION
COORDINATE DIRECTION
16.01
horizontal displacement
16,32
16.01
15,01
5.02
COORDINATE DIRECTION
COORDINATE DIRECTION
COORDINATE DIRECTION
COORDINATE DIRECTION
crest elevation above SWL
165
GREEK LETTERS
Sym-
Definition
Equa-
dimensions
Units
tion
bol
breakwater slope
5.01
rad.
foreshore slope
5.01
rad.
breaker index
RELATIVE DENSITY
11.02
7.11
time interval
15.03
dynamic pressure c o e f f i c i e n t
16.20
slope angle
7.03
WAVE LENGTH
fig.5.2
friction coefficient
rad.
7.04
3.1415926536
DENSITY OF WATER
7.01
Pa
density of armor
7.08
PB
Pc
-3
ML
ML'
ML'
ML"
kg/m^
kg/m^
density of breakwater
16.63
density of s o i l
16.01
angular r o t a t i o n
16.04
rad.
angle of internal f r i c t i o n
16.22
rad.
c i r c u l a r frequency
15.01
natural frequency
16.05
r-l
.-1
kg/m'^
kg/m^
rad/s
rad/s
Special symbols
pwf
structure l i f e
11.30
i n t e r e s t rate
11.29
11.02
15.03
amplitude of
16.17
present worth f a c t o r
11.29
years
LT
-1
m/s
166
Subscript
Sym-
Definition
Equa-
bol
tion
armor
7.08
breakwater
crest
5.02
incident H^j
5.01
natural (frequency)
deep water
soil
sub
submerged
7.03
toe of construction
5.01
transmitted
5.03
water
16.17
X component
16.03
y component
16.04
z component
16.02
16.02
16.05
fig.5.2
16.01
Functions used
Trigonometric functions
s1n( )
sine o f ( )
cos( )
cosine of ( )
tan( )
tangent of ( )
-1
sin
j!
( )
cos-l( )
tan"'l( )
167
hyperbolic functions
sinh( )
hyperbolic sine of { )
cosh( )
hyperbolic cosine of { )
tanh( )
hyperbolic tangent of ( )
sinh 1( )
cosh 1( )
tanh '( )
logarithmic functions
log( )
logarithm to base 10 of { )
ln( )
logarithm to base e of { )
exp( )
P{ )
p r o b a b i l i t y of exceedance of ( )
f( )
general function of ( )
n( )
product of { )
T,{ )
sum of ( )
168
Definition
bol
Op
degree Celsius
cm
centimeter = 1 0
ft
foot
GRAM
hour
hr
hour
kg
KILOGRAM
km
kilometer = 10^ m
kt
LENGTH DIMENSION
lb
pound force
-2
m
MASS DIMENSION
METER
mg
milligram = 10 ^ g
mm
m i l l i m e t e r = lO"^ m
um
micrometer = 10 ^ m
NEWTON
rad
radians
SECOND
TIME DIMENSION
yr
year
degree temperature
degree angle
169
REFERENCES
The f o l l o w i n g l i s t includes bibliographic data on a l l of the
references used i n the previous chapters.
Works are l i s t e d in alphabetical order by f i r s t author and in
sequence of p u b l i c a t i o n .
Ahrens, J.P.
title:
Zee.
T?rooeeding8
12^^ Coastal
Engineering
Washington,
Conference:
D.C.
Anonymous (before 1964): Ooourrenoe
Haringvliet
Sluice
Gates:
Frequencies
of Wave Forces
on the
t i t l e : Jaarfrequenties
van de
van de Golfbelasting
op de
Schuiven
Haringvlietsluis.
Entrance
at Hook of
Holland:
van Nieuwe
Havenmond bij
Hoek van
Holland.
t i t l e : Golfoploop
en Golfoverslag.
An English version is
also available.
(1973): Shore Protection
(1974): Computation
and Overtopping
of Set-up,
due to Wind-generated
Longshore
Waves:
Currents,
Doctorate Thesis,
D e l f t University of Technology, D e l f t .
Benassai, E. (1975): The S t a b i l i t y Against Sliding of Breakwaters
Under the Action o f Breaking Waves: Bulletin
Intemational
Association
of Navigation
of the Permanent
Congresses,
volume
in Standing
Waves:
Thesis,
in- Staande
Golven.
Run-^p,
170
Part 1.
deel 1.
Civil
of Civil
Division,
Engineevs,
Jouvnal
of Amevioon
of Watevways
and
Harbors
Permanent
Congresses,
Intemational
Association
of
of
Navigation
of 11^^ Coastal
Engineering
Conference,
London.
Fhrbter, A. (1969): Laboratory Investigation of Impact Forces:
P r e p r i n t s , Symposium
on Research
on Wave Action,
D e l f t , 24-28
March.
G r i f f i n , O.M. (1972): Recent Designs f o r Transportable Wave
Barriers and Breakwaters: Marine
Technology
Society
Journal,
of Engineers,
Beach Erosion
Board,
Thesis,
May.
coastal
op
title:
Golf-
Palen.
Society
of Civil
Engineers,
of
volume 11 B, p.
653.
Hudson, R.Y.
(1974): Concrete
Wave Attack:
Armor
Units
for
Proteotion
Against
171
of
the
of Civil
pp. 51-63.
J a r l a n , G.L.E. (1961): A Perforated Vertical Wall Breakwater: The
Book and Harbour Authority,
pp.
394-398.
Johnson, J.W. ; Fuchs, R.A.; Morison, J.R.,(1951): The Damping Action
of Submerged Breakwaters: Transaction
of American
Geophysical
and
Properties
t i t l e : Bodembescherming:
deel A,
Ontwikkeling
Eigenschappen.
Reef,
- Association
of Asphalt
Paving
Technologists,
volume
34.
Kowalski, T.
(1974); e d i t o r : Floating
Breakwaters
Conference
Papers
v.d.
Resulting
Dynamic Reactions:
on the
Front
of Caissons
and
the
Waterloopkundige A f d e l i n g , Deltadienst,
Golfbelasting
Dynamische
Reacties
op het
Voorvlak
tengevolge
van Havenhoofdoaissons
en
de
daarvan.
Breakwater
Structures;
A Cost
Comparison: Report by Ministry of Public Works and D e l f t Hydraul i c s Laboratory: W 732 M 748; in Dutch, o r i g i n a l
Constructies
HaVendammen
title:
Europoort.
Authority,
172
Conference,
11^^ Coastal
Engineering
pp. 367-396.
Blanche,
Breakwaters
The Permeability
Periodic'Gravity
in FRENCH, o r i g i n a l
aux ondes
of Dikes
and Breakwaters
to
de gravit
des diques
en enrouohementa
priodiques.
N i j b o e r , M. (1972): Literature
and Model
Study
of the Stability
of
of 11^^ Coastal
Engineering
Unit
for
Cover
Layers
D e l f t Hydraulics Laboratory,
of Civil
Division,
Engineers,
Journal
of Waterways
American
and
Harbors
of S*^ Coastal
Engineering
Conference,
Ingenieur,
t i t l e : Het vernietigen
Their
Physics
Chemistry
and General
Biology:
, Proceedings
ofthe
Prentice H a l l , Inc.
Taylor, G . I . (1955):
Royal Society,
Valembois, J.
(1953): Investigation
on Wave Propagation:
of the Effect
of Resonant
Structures
173
of a Rubble Mound in
Dam voor
in Standing
Niet
title:
permanente
DoordringStroming.
and Sandtransport
Direction
Onderzoek
richting
naar
in Staande
de Neerwerking
en de landtransport
Golven.
Authority,
Engineering:
150.
Prentce -
Unpublished r e p o r t . University of C a l i f o r n i a .