CPM Made Easy
CPM Made Easy
1.0
GETTING STARTED
2.0
2.1
2.2
TABLE COLUMNS
2.3
Move to the month that work will not be performed. Once on the month, click and hold on the first day
which work cannot be performed, then drag to the last day of the month. This will highlight all the days in
the month and then click the Nonworking check box on the right. Now click once on any day in the month
and you will see that all the days are gray and have no hours assigned to them. Continue the same
process for the remaining months work will not be performed. Once you are done, press OK.
3.0
3.1
ENTERING TASKS
Enter the information highlighted below in the first 6 rows, first 3 columns. Notice that once you enter a
task name, the start date defaults to whatever you have setup and the duration defaults to 1 day.
For milestone activities, such as Notice to Proceed, interim completion dates, and the Fixed Completion
Date, enter the duration as 0 (zero) days.
One major pitfall in entering data is that the delete key actually deletes the entire task, as opposed to
simply clearing that cell. To clear the contents of a cell choose Edit, Clear All from the menus.
3.2
LINKING TASKS
Tasks are linked simply by highlighting the tasks and pressing the link button as shown below. To link
tasks 2 through 4 together, highlight 2-4 and press the link button (or choose from the menus, Edit, Link
Tasks).
This will make tasks 3 through 4s dates change to reflect the activities being completed sequentially,
based on the working days available on the standard calendar. Project assigns the number of the activity
as a predecessor to the activity shown, i.e. Clearing has activity 2 as its
predecessor. To see the predecessors, if they are not already shown on your screen, widen the left side
of the screen by clicking and holding on the vertical bar between the table and the Gantt chart. The
linked tasks with predecessor numbers are shown below.
3.3
SUMMARY TASKS
Summary tasks are groupings of tasks that relate to one item. For instance, a bridge might have
substructure and superstructure activities. Summary tasks are created in Project a lot like an outline,
simply by indenting or outdenting the activities. We entered activities 5 and 6, so lets make task 5 a
summary activity. Click once on activity 6, the one we want to indent, and press the indent button as
shown below. This will move the activity name for 6 in, bold activity 5 and create a summary bar for
activity 5.
Now you could double click on activity 5 and roll up the summary tasks so that sub structure does not
show. This is helpful when you have a complicated schedule, tasks can be rolled that do not need to be
shown all the time.
3.4
If you would like to link tasks that are not immediately adjacent to each other, you can simply click on one
of the tasks (say task 2) and then while holding the control key click on the other tasks (say task 6).
When both tasks are highlighted, press the link button.
3.5
Enter tasks 7 through 12 as shown below. Note that when you enter task 12, at first it is indented like
task 11. Press the Outdent key as shown to move task 12 back to the left. You do not have to enter the
dates, we will link the activities to create the start and finish dates.
3.6
Highlight tasks 6 through 11 and press the link button to link those together.
4.0
Most of the time there are some restrictions on when a certain activity can take place. Common
restrictions are working below the high water mark in certain types of streams or when a road closure can
take place. In our example project we have two restrictions currently, an in-stream work restriction and a
road closure restriction.
We specifically broke the substructure and superstructure into 3 activities each because of the in-stream
work restriction. This way we could assign a time restriction to the activities involving rip rap. When you
are developing your schedule, consider what activities might include a restriction. The proposed
schedules do not have to be detailed to the nth degree, but some minor level of detail might be required
to deal with time restrictions.
4.1
5.0
5.1
Enter the following (this is the last time of entering data) information for tasks 13 through 15:
5.2
Links tasks 12 and 2, 13 and 1, and 14 and 4. Now link tasks 14, 12, 13, and 5 all to task 15 pavement.
To do this you can click on sets of two and press the link button or type the task numbers separated by
commas in the predecessor box for pavement.
6.0
SPECIAL RELATIONSHIPS
All the links we have created so far have been Finish-Start relationships, the link is from the finish of one
activity to the start of another. This is normally the case with most activities, however sometimes a
different relationship is more appropriate. Notice that currently there is not a link between crushing and
placing base. If we linked these activities with a finish-start relationship, that would overstate the time to
complete the project because all crushing would have to be finished before placing base could begin,
which is not true. Click on activities 13 and 14 and press the link button to create a finish-start link.
Now double click anywhere on activity 14 and the following dialog box will appear. Press the
Predecessors tab to view which activities number 14 is linked to. Click once on the crushing activity and
then change the relationship to Start-Start as shown below.
Now we can assign a lag time for the start-start relationship. This would be the time it takes to crush
enough base to make hauling and placing the material reasonable. Lets assume 15 days would be
enough. Enter 15 in the lag column as shown below.
7.0
7.1
7.2
To format the individual bars for a task, and the text that is displayed with each task, just double click on
the time bar, on the Gantt chart, for the specific activity. Double click on activity 12 and the following
dialog box will appear. Press on the Bar Text table to see what text is currently being displayed. You
can customize the text to whatever you need.
8.0
Printing with Projects what you see is what you get versus what fits on a page. It becomes an iterative
process. The columns that are visible to the left of the vertical bar between the table and Gantt chart will
determine columns that will print. The time scale of the Gantt chart (days, weeks, quarters, months) will
determine the width of the printout. Usually the goal is to have a printout that is one page wide with a
time scale that is still readable. Lets use the zoom in/zoom out function to make our schedule appear in
quarters as shown below.
Now from the File menu choose print preview. If the triangular arrows are black that means there are
more sheets to the right or down. Preview and adjust the settings as necessary to get the desired
printout.