PROPOSED TWO-STOREY JAIME HILARIO INTEGRATED SCHOOL - LA SALLE
PRE-BID AGREEMENT
Date
Project
:
:
Location
Owner
Architect
Bidder
:
:
:
:
28th of June 2013
PROPOSED TWO- STOREY JAIME HILARIO INTEGRATED
SCHOOL - LA SALLE
Banawang, Bagac, Bataan
DE LA SALLE PHILIPPINES
Vicente R. Benito, Jr.
_____________________________________________
The Architect and the Bidder Agree as follows:
P.A. 100
Ownership of Documents
Plans, Specifications and other related Contract Documents are
the properties of the Owner and therefore they shall be returned
complete and in proper order, upon submittal of Bids but not
later than 2 days after the award of the contract. Failure to do
so shall mean forfeiture of Bid Deposits.
P.A. 100
Clarification of MEANING and/or DISCREPANCIES of
Drawings, Specifications and Site Conditions.
Any discrepancies found between the Drawings & Specifications
and Site conditions or any error, changes, or omissions in the
Drawings or Specification shall be immediately reported to the
Architect who shall promptly correct such discrepancies, errors
or omissions after his recovery.
VRB Architectural Services, SHALL NOT BE RESPONSIBLE FOR NON-CONFORMITY OF
BID DUE TO THE MISINTERPRETATION OF DRAWINGS, SPECIFICATIONS & SITE
CONDITIONS. Any work involving such discrepancies shall be done at the Contractors
risk.
P.A. 300
Conference prior to date of Bidding
Bidders are enjoined to confer with the Architect prior to bidding
date thru the Pre-Bid Conference or queries addressed thru fax.
All questions and discrepancies shall be clarified and explained
by the Architect on such conference or thru fax. Should there be
no questions asked, the Architect assumes that the bidder
understand the plans. Inform the Architect for clarification of
discrepancies. His discussion shall be final.
P.A. 400
Date of Bidding
Sealed proposal in duplicate using the sample bid form, retyped on the Contractors letterhead legal size paper kept inside
4 x 9 envelop shall be received on:
Date: 12th of July 2013
PRE-BID AGREEMENT
Page 1 of 2
PROPOSED TWO-STOREY JAIME HILARIO INTEGRATED SCHOOL - LA SALLE
Time: 5:00 PM
Place: La Salle Greenhills,
343 Ortigas Avenue,
Mandaluyong City
Failure to do so shall mean rejection of bid proposal & forfeiture
of bid deposits.
P.A. 500
Conformity to Bid-procedures
Right to reserved to Arch. Vicente R. Benito, Jr. to reject any or
all bids without explanations on the basis of non-conformity of
bid documents to procedures of bidding.
The Architect and the Bidders to this Agreement hereby agree
to full performance of the covenants contained herein.
______________________
VICENTE R. BENITO, JR.
Architect
PRE-BID AGREEMENT
Page 2 of 2
UAP
_________________________
Bidder