Answers
Answers
estimates should be preferred if time to estimate is available, estimating cost is reasonable, and
accuracy is important.
4. What are the major types of costs? Which costs are controllable by the project
manager?
the major types of costs:
1. Direct
2. direct overhead
3. general and administrative costs.
Direct overhead and general and administrative costs are only controllable in the sense that if the
resource or project is finished early or late the costs will continue for the duration of the project.
Ch 6
1. How does the WBS differ from the project network?
a. The WBS is hierarchical while the project network is sequential.
b. The network provides a project schedule by identifying sequential dependencies and timing
of project activities. The network sets all project work, resource needs, and budgets into a
sequential time frame; the WBS does not provide this information.
c. The WBS is used to identify each project deliverable and the organization unit responsible for
its accomplishment within budget and within a time duration.
d. The WBS provides a framework for tracking costs to deliverables and organization units
responsible.
2. How are WBS and project networks linked?
The network uses the time estimates found in the work packages of the WBS to develop the
network. Remember, the time estimates, budgets, and resources required for a work package in
the WBS are set in time frames, butwithout dates. The dates are computed after the network is
developed.
3. Why bother creating a WBS? Why not go straight to a project network and forget the
WBS?
The WBS is designed to provide different information for decision making.
For example, this database provides information for the following types of decisions:
a. Link deliverables, organization units, and customer
b. Provide for control
c. Isolate problems to source
d. Track schedule and cost variance. Network doesnt.
e. Assign responsibility and budgets
f.
Many companies engaged in contracted work refer to scope statements asstatement of work
(SOW)
Project Charter: document that authorizes the PM to initiate & lead the project.
Scope creep
: the tendency for the project scope to expand over time (usually by changing
requirements, specifications, and priorities).
2. What questions does a project objective answer? What would be an example of a good
project objective?
The project objectives answers what, when, and how much. To replace the Willamette bridge by
August 3rd at a cost not to exceed $1.5 million.
3. What does it mean if the priorities of a project include: Timeconstrain, Scope-accept,
and Costenhance?
The project must be completed on a specific date, the scope can be scaled back in order to meet
cost and time objectives, and when possible seek opportunities to reduce costs.
Causes of Project Trade-offs
Shifts in the relative importance of criterions related
to cost, time, and performance parameters
BudgetCost
ScheduleTime
PerformanceScope
One technique found in practice that is useful for this purpose is completing a
priority matrix for the project to identify which criterion is constrained, which
should be enhanced and can be accepted.
2.
3.
4.
5.
6.
7.
1. Mrs. Tolstoy and her husband, Serge, are planning their dream house. The lot for the
house sits high on a hill with a beautiful view of the Appalachian Mountains. The plans
for the house show the size of the house to be 2,900 square feet. The average price for a
lot and house similar to this one has been $120 per square foot. Fortunately, Serge is a
retired plumber and feels he can save money by installing the plumbing himself. Mrs.
Tolstoy feels she can take care of the interior decorating.
The following average cost information is available from a local bank that makes loans to
local contractors and disperses progress payments to contractors when specific tasks are
verified as complete.
24 %
8%
3%
6%
5%
17 %
9%
4%
10 %
6%
4%
4%
Siding on
Windows, insulation, walks, plaster, and garage complete
Furnace installed
Plumbing fixtures installed
Exterior paint, light fixtures installed, finish hardware installed
Carpet and trim installed
Interior decorating
Floors laid and finished
a. What is the estimated cost for the Tolstoys house if they use contractors to complete
all of the house?
Estimated total cost for the house is $348,000 (2,900 sq. ft. x $120 per foot).
b. Estimate what the cost of the house would be if the Tolstoys use their talents to do
some of the work themselves.
Estimated savings of Serges plumbing work and Mrs. Tolstoys interior decorating:
Plumbing roughed in
Plumbing fixtures installed
Interior decorating
6% x $348,000
4% x $348,000
4% x $348,000
Total saving
Estimated total cost for the completed house using their talents is $299,280 ($348,000 $48,720).
Chapter 6: Exercise 19
=
=
=
=
$20,880
$13,920
$13,920
$48,720
CH 4:
1.You are in charge of organizing a dinner-dance concert for a local charity. You have reserved a
hall that will seat 30 couples and have hired a jazz combo.
Project Objective: Organize a dinner dance for 30 couples by March xx at a cost not greater than
yy to raise money for a local charity.
Deliverables: 60 catered dinners Jazz combo Rented hall Tickets
Milestones: Rent hall by x Sell 30 tickets by y Arrange caterer by z
Technical Requirements: Hall has sufficient space for tables and dance floor Convenient
parking available Hall has infrastructure to support catered dinner and jazz combo Meals
include vegetarian option
Limits and Exclusions: Caterer responsible for preparing, serving, and clean-up Ticket price
set to generate at least $50 profit per couple Jazz combo responsible for sound system Event
transpires between 7 12 a.m
Customer Review: Charity official