Pre Engineered Building
Pre Engineered Building
INTRODUCTION
1.1 GENERAL
Buildings & houses are one of the oldest construction activities of human beings the
construction technology has the beginning from primitive construction technology to
the present concept of modern house building. The present construction methodology
for buildings calls for the best aesthetic look, high quality & fast construction, cost
effective & innovative touch.
1.2 PEB IN INDIA
India has the second fastest growing economy in the world and a lot of it, is attributed
to its construction industry which figures just next to agriculture in its economic
contribution to the nation. In its steadfast development, the construction industry has
discovered, invented and developed a number of technologies, systems and products,
one of them being the concept of Pre-engineered Buildings (PEB s). As opposed to
being on-site fabricated, PEB s are delivered as a complete finished product to the site
from a single supplier with a basic structural steel framework with attached factory
finished cladding and roofing components. The structure is erected on the site by bolting
the various building components together as per specifications. PEB s are developed
using potential design software. The onset of technological advancement enabling 3d
modelling and detailing of the proposed structure and coordination has revolutionized
Conventional building construction. Pre-Engineered
PEB has boon to Multi storey Buildings in India. Decking sheets with concrete over can
be used as roofing and raised to any extent above 40 meters. These have a tracking rate
of 80% in western countries. PEB Buildings is the future for India. Most of the Indian
1
business community is just started to realize the benefits of PEB .Where you have been
building with concrete for as long as anyone can remember, it is difficult to change.
However Indias most progressive companies are seeing the benefits of PEB
Although PEB systems are extensively used in industrial and many other non
residential constructions worldwide it is relatively a new concept in India .these concept
were introduced to the Indian markets lately in the late 1990s with the opening up of
the economy and a number of multi nationals setting up their projects .the market
potential of PEB is 1.2 million tonnes per annum .the current pre engineered steel
building manufacturing capacity is 0.35 tonnes per annum. The industry is growing at
the compound rate of 25 to 35 % [16]
40% faster than masonry construction. PEB buildings provide good insulation effect
and would be highly suitable for a tropical country like India.
The pre-engineered building calls for very fast construction of buildings and with good
aesthetic looks and quality construction.
CHAPTER 2
LITERATURE REVIEW
2.1 GENERAL
In this chapter the literature review of pre-engineered building is carried out from
various books, reference, journals, and from several websites .the brief discussion of
the pre-engineered building is presented below in this project
2.1.1 Syed Firoz, Sarath,Chandra Kumar et.al (2012) observed that, The preengineered steel building system construction has great advantages to the single storey
buildings, practical and efficient alternative to conventional buildings, the System
representing one central model within multiple disciplines. Pre- engineered building
creates and maintains in real time multidimensional, data rich views through a project
support is currently being implemented by STAAD pro software packages for design
and engineering [16]. Choosing steel to design a Pre-engineered steel structures
building is to choose a material which offers low cost, strength, durability, design
flexibility, adaptability and recyclability. Steel is the basic material that is used in the
Materials that are used for Pre- engineered steel building. It negates from regional
sources. It also means choosing reliable industrial products which come in a huge range
of shapes and colours; it means rapid site installation and less energy consumption. It
means choosing to commit to the principles of sustainability. Infinitely recyclable, steel
is the material that reflects the imperatives of sustainable development.
A tall steel building is not more in the total number of tall steel structures that are built
around the world. A large steel structures being built are only single storey buildings
for industrial purpose. Secondary structural members span the distance between the
primary building frames of metal building systems. They play a complex role that
extends beyond supporting roof and wall covering and carrying exterior loads to main
4
frames. Secondary structural, as these members are sometimes called, may serve as
flange bracing for primary framing and may function as a part of the buildings lateral
loadresisting system. Roof secondary members, known as purlins, often form an
essential part of horizontal roof diaphragms; wall secondary members, known as girts,
are frequently found in wall bracing assemblies. The majority of steel structures being
built are only low-rise buildings, which are generally of one storey only. Industrial
buildings, a sub- set of low-rise buildings are normally used for steel plants, automobile
industries, light, utility and process industries, thermal power stations, warehouses,
assembly plants, storage, garages, small scale industries, etc. These buildings require
large column free areas. Hence interior columns, walls and partitions are often
eliminated or kept to a minimum. Most of these buildings may require adequate
headroom for use of an overhead traveling crane. A third type of secondary
framing,[16]] known by the names of eave strut, eave purlin, or eave girt, acts as part
purlin and part girtits top flange supports roof panels, its web, wall siding. Girts,
purlins, and eave struts exhibit similar structural behaviour. Since most secondary
members normally encountered in metal building systems are made of cold- formed
steel, our discussion starts with some relevant issues in design of cold-formed steel
structures.
2.1.2 Aijaz Ahmad Zende 1, Prof. A. V. Kulkarni, et.al (Jan. - Feb. 2013) observes
that even though PEB
Conventional Buildings. Infinitely recyclable, steel is the material that reflects the
imperatives of sustainable development. For longer span structures, Conventional
buildings are not suitable with clear spans. Pre-engineered building are the best solution
for longer span structures without any interior column in between as seen in this present
work, an industrial structure has been designed for 88m. With the advent of
computerization, the design possibilities became almost limitless. Saving of material on
low stress area of the primary framing members makes Pre- engineered buildings more
economical than Conventional steel buildings especially for low rise buildings spanning
5
up to 90.0 meters with eave heights up to 30.0 meters. PEB structures are found to be
costly as compared to Conventional structures in case of smaller span structures. To
Conclude Pre-Engineered Building Construction gives the end users a much more
economical and better solution for long span structures where large column free areas
are needed [6].
2.1.3 C. M. Meera (June 2013) observes that Pre-Engineered Building (PEB) concept
is a new conception of single storey industrial building construction. This methodology
is versatile not only due to its quality pre-designing and prefabrication, but also due to
its light weight and economical construction. The concept includes the technique of
providing the best possible section according to the optimum requirement. This concept
has many advantages over the Conventional Steel Building (CSB) concept of buildings
with roof truss. This paper is a comparative study of PEB concept and CSB concept.
Pre-Engineered Building concept have wide applications including warehouses,
factories, offices, workshops, gas stations, showrooms, vehicle parking sheds, aircraft
hangars, metro stations, schools, recreational buildings, indoor stadium roofs, outdoor
stadium canopies, railway platform shelters, bridges, auditoriums, etc, explicitly as in.
PEB structures can also be designed as re-locatable structures. Steel is a material which
has high strength per unit mass. Hence it is used in construction of structures with large
column-free space. Most of the Industrial Structures require this criterion. An Industrial
Warehouse is a storage building and is usually characterized as single storey steel
structures with or without mezzanine floors. The enclosures of these structures may be
brick masonry, concrete walls or GI sheet coverings. The walls are generally nonbearing but sufficiently strong enough to withstand lateral forces caused by wind or
earthquake. The designing of industrial warehouse includes designing of the structural
elements including principal rafter or roof truss, column and column base, purlins, sag
rods, t gantry girder, bracings, etc. A combination of standard hot-rolled sections, coldformed sections, profiled sheets, steel rods, etc. are used for the construction of
industrial steel structures. Industrial buildings can be categorized as Pre-Engineered
6
Buildings (PEB) and Conventional Steel Buildings (CSB), according to the design
concepts. The paper starts with the discussion of methods adopted in the study.
Introduction to PEB systems and CSB systems are then described followed by the
details of case study. Loads and the load combinations adopted for carrying out the
analysis of the structure is well defined in the further portions. A section depicting the
importance of the software used and the software procedure followed is included. Final
portion explains the results obtained from the software analysis of the case study and
the inferences from the literature studies. The paper aims at developing a perception of
The design concepts of PEB structures and its advantages over CSB structures.
2.1.4 Jatin D. Thaka r, 2 Prof. P.G. Patel observes that Pre-engineered building are
steel building wherein the framing members and other components are fully fabricated
in the factory after designing and brought to the site for assembly, mainly by nut-bolts,
thereby resulting into a steel structure of high quality and precision. In conventional
steel construction, we have site welding involved, which is not the case in P.E.B using
nut-bolt mechanism. These structures use hot rolled tapered sections for primary
framing and cold rolled sections for secondary framing as per the internal stress
requirements, thus reducing wastage of steel and the self- weight of the structure and
hence lighter foundations. International codes are referred in their design as per the
MBMA (Metal Building Manufacture Association) Standards which are more flexible
Allowing the use of built - up sections of minimum 3.5 mm thickness against 6 mm as
minimum criteria in conventional steel sections .There is use of steel of high strength
(345MPa) which prominently speaks about greater strength with judicious use of steel
as a result of tapered profile. The tapered section concept was first adopted in U.S.A
keeping in mind the bending moment diagram. At locations of high bending moment
values, greater depth is used while less moment encouraged the use of lesser depths.
Further unlike the conventional steel sections, where Moment of inertia (I) remains
constant, it is not so in case of P.E.B due to varying depths.
2.1.5 G. Sai Kiran, A. Kailasa Rao, R. Pradeep Kumar (Aug 2014) observes that, in
recent years, the introduction of Pre Engineered Building (PEB) concept in the design
of structures has helped in optimizing design. The adoptability of PEB in the place of
Conventional Steel Building (CSB) design concept resulted in many advantages,
including economy and easier fabrication. In this study, an industrial structure (Ware
House) is analysed and designed according to the Indian standards, IS 8001984, IS 8002007 and also by referring MBMA-96 and AISC-89. In this study, a structure with
length 187m,width 40m,with clear height 8m and having Slope 1:10,isconsidered to
carry out analysis& design for 2D frames (End frame, frame without crane and frame
with 3 module cranes). The economy of the structure is discussed in terms of its weight
comparison, between Indian codes (IS800-1984, IS800-2007) & American code
(MBMA-96), & between Indian codes (IS800-1984, IS800-2007).
2.1.6 S.D. Charkha and Latesh S (June 2014) observes that, Using of PEB instead of
CSB may be reducing the steel quantity. Reduction in the steel quantity definitely
reducing the dead load. Reduction in the dead load reducing the size of Foundation.
Using of PEB increase the Aesthetic view of structure.
concrete floor, which required extra 22.70% of direct cost and 14.96% of net cost.
However, study is restricted to structural frame only. If other items are also considered
in the study like excavation work, finishing items, services, cladding etc.
elastic properties of the members. Based on this, the data is stored and member section
properties are computed.
Unless otherwise specified, the deflections will go to MBMA, AISC criteria and
standard industry practices.
Using IS 875 Part 3 design wind loads are calculated and Using IS 1893- 2002
seismic loadings are calculated.
11
Pre-engineered
buildings
Structural
weight
Pre-engineered
design?
tapered
constant
cross
section
regardless
of
varying
depths
built
up
in areas
of
higher stress.
the
have
Secondary
Members
members
are
formed z or c shaped
members
Design
sections
Specialized
computer
analysis
programs
design
to
Delivery
Average 6 to 8 weeks
Foundation
Simple
design,
Average 20 to 26 weeks
easy
Erection
Since
the
connection
to Extensive, heavy
foundation
required.
of The
connections
are
normally
conventional
steel
upon
13
experience
with
buildings.
estimated accurately.
Erection
The erection process is faster
process
is
slow
and
requirement
equipment.
The
Seismic
low
weight
Resistance
Over
Price per square meter may be Higher price per square meter.
All Price
as
Low as by 30 % than the
conventional building.
Architecture
Outstanding
using
architectural
interfaces.
Sourcing And Building is supplied complete Many sources of supply are there so
Coordination
14
Cost of
Charge order
by
mills
is
Building
Accessories
mass
produced
for
Future
Expansion
Safety
more costly.
source
the entire job is being done by the components do not fit in properly,
insufficient material is supplied or
one supplier.
parts fail to perform particularly at
the supplier/contractor interface.
and
Performance
for
In pre-engineered building concept the complete designing is done at the factory and
the building components are brought to the site in CKD (Completely knock down
condition). These components are then fixed / jointed at the site and raised with the
help of cranes. The pre-engineered building calls for very fast construction of buildings
and with good aesthetic looks and quality construction. Pre-engineered Buildings can
be used extensively for construction of industrial and residential buildings. The
buildings can be multi storied (4-6 floors). These buildings are suitable to various
environmental hazards. Pre-engineered buildings can be adapted to suit a wide variety
of structural applications; the greatest economy will be realized when utilizing standard
details. An efficiently designed pre-engineered building can be lighter than the
conventional steel buildings by up to 30%. Lighter weight equates to less steel and a
potential price savings in structural framework.
with a choice of single skin sheeting with added insulation or insulated sandwich panels
for roofing and wall cladding. The concept is designed to provide a complete building
envelope system which is air tight, energy efficient, optimum in weight and cost and,
above all, designed to fit user requirement like a well fitted glove. [6]
The most common and economical type of low rise buildings is a building with ground
floor and two intermediate floor plus roof. The roof of low rise buildings may be flat
or sloped. Intermediate floors of low rise buildings are made of mezzanine systems.
Single storied houses for living take minimum time for construction and can be built
in any type of geographical location like extreme cold hilly areas, high rain prone areas,
plain land obviously and extreme hot climatic zones as well.
Advantages:
Reduction in Construction Time: Buildings are typically delivered in just a few weeks
after approval of drawings. Foundation and anchor bolts are cast parallel with finished,
18
ready for the site bolting. In India the use of PEB will reduce total construction time of
the project by at least 50%. This also allows faster occupancy and earlier realization of
revenue.
Lower Cost: Due to the systems approach, there is a significant saving in design,
manufacturing and on site erection cost. The secondary members and cladding nest
together reducing transportation cost.
Flexibility of Expansion: Buildings can be easily expanded in length by adding
additional bays.
Also expansion in width and height is possible by pre designing for future expansion.
Larger Spans: Buildings can be supplied to around 80M clear spans.
Quality Control: As buildings are manufactured completely in the factory under
controlled conditions the quality is assured.
Low Maintenance: Buildings are supplied with high quality paint systems for
cladding and steel to suit ambient conditions at the site, which results in long durability
and low maintenance costs. Energy Efficient Roofing and Wall Systems: Buildings can
be supplied with polyurethane insulated panels or fiberglass blankets insulation to
achieve required U values [16]].
Architectural Versatility: Building can be supplied with various types of fascias,
canopies, and curved eaves and are designed to receive pre-cast concrete wall panels,
curtain walls, block walls and other wall systems.
Single Source Availability: As the complete building package is supplied by a single
vendor, compatibility of all the building components and accessories is assured. This
is one of the major benefits of the pre-engineered building systems.
right at the drawing preparation stage. Systems engineering and fabrication methods
help reduce interim financing costs through faster construction and minimized field
erection expense. An added benefit is earlier occupancy of the facility and a head start
on day-to-day operations by the client.
Apart from costs, there is an assurance of factory-built quality and uniformity in design
and fabrication. These systems are also energy efficient; incorporate watertight roofing
systems; enable easy disassembly or future expansion and have the lowest life cycle
maintenance costs.
Adding to these; there is no mess of sand and cement; power savings; walkable
ceilings; progressive and non-progressive panel systems for walls. A poor man can be
provided with a home created under strict quality control and having a longer life span,
with greater safety against natural disasters like earthquakes and cyclones.
Moreover, it is possible to create the building in required form and shape. And the
'system approach' renders a holistic way of thinking at one platform for consultants,
designers, architects, and builders. Thus it tends to achieve a perfect harmony among
various stringent specifications and aesthetic requirements in a most economical way.
In nutshell, the benefits may be summarized as under
in any type of geographic location like extreme cold hilly areas, high rain prone areas,
plain land, extreme hot climatic zones etc.
Applications of Pre-engineered steel buildings include
Factories
Warehouses
Aircraft Hangers
Supermarkets
Workshops
Office Buildings
Labour Camps
Schools
Community centres
Railway Stations
Equipment housing/shelters.
There is a great possibility of improving the aesthetic quality with a choice of roofing
elements, exterior finishes, weather-sheds, colour system and variations in planning as
well as massing.
compatible to modern demands viz. speed, quality and value for money. Preengineered buildings find many pre-engineered construction applications, which could
be intrinsic and high-end.
PEB concept has been very successful and well established in North America, Australia
and is presently expanding in U.K and European countries. PEB construction is 30 to
40% faster than masonry construction. PEB buildings provide good insulation effect
and would be highly suitable for a tropical country like India.
construction in remote & hilly areas. [16]. A recent survey by the Metal Building
Associations (MBMA) shows that about 60% of the non- residential low rises building
in USA are pre-engineered buildings.
MARKET POTENTIAL
PEB systems are extensively used in industrial and many other non- residential
constructions worldwide, it is relatively a new concept in India. These concepts were
introduced to the Indian markets lately in the late 1990 s with the opening up of the
economy and a number of multi nationals setting up their projects. The market potential
of PEB is 12 lakh Metric tonnes per annum. The current pre-engineered steel building
manufacturing capacity is 0.35 million tonnes per annum. The industry is growing at
the compound rate of 25 to 30 %. [16]
23
FUTURE OF PEB
The steel structures (SS) market in India is in excess of 4.5 Mn.MT, growing at a rapid
pace of more than 10% p.a. over the past few years. This market has experienced a
higher growth compared to both Indian steel industry as well as Indian construction
GDP. Overall construction sector accounts for majority (greater than 80%) of the steel
structures market (volume terms) in India.
The current pre-engineered steel building manufacturing capacity is 0.35
million tonnes per annum. The industry is growing at the compound rate of 25 to 30%.
2.4.1 PRODUCTION
Pre-engineered Steel Buildings are tailor made buildings which are those fully
manufactured in the factory after designing. This fabrication is done in a controlled
environment with latest technology. The production is done under standard conditions.
The Raw material required is imported from major companies like Tata BlueScope to
all the companies in India.
Historically, the primary framing structure of a pre-engineered building is an
assembly of I shaped members, often referred as I beam. In pre-engineered buildings,
I beams used are usually formed by welding web and flange plates together to form I
section. I beams are then field assembled (e.g. bolted connections) to form the entire
frame of the pre-engineered building. Some manufacturers taper the framing members
(varying in web depth) according to the local loading effects. Larger plate dimensions
are used in areas of higher load effects.
Cold formed Z and C-shaped members may be used as secondary structural
elements to fasten and support the external cladding. Roll-formed profiled steel sheet,
wood, tensioned fabric, precast concrete, masonry block, glass curtain wall or other
materials may be used for the external cladding of the building.
24
Profiling
for
Roof
and
Wall
Bracings
like
sheeting
4.
Accessories
&
process
3. Fabrication for fitments like end plates, stiffeners and connections cleats.
4. Cleaning the surface for painting
5. Slitting HR coils for cold forming operations to make Z and C sections with
punching
25
Primary framing
All rigid frames shall be welded built-up "I" sections or hot-rolled sections. The
columns and the rafters may be either uniform depth or tapered. Flanges shall be
connected to webs by means of a continuous fillet weld on one side. All end wall roof
beams and end wall columns are in cold formed "C" sections, mill-rolled sections, or
built-up "I" sections depending on design requirements. All base plates, splice and
flanges shall be shop fabricated to include bolt connection holes. Webs are shop
fabricated to include bracing holes. [16]
Secondary Framing
Purlins and girts shall be cold-formed "Z" sections with stiffened flanges. Flange
stiffeners shall be sized to comply with the requirements of the latest edition of AISI.
Purlin and girt flanges shall be unequal in width to allow for easier nesting during
26
erection. They shall be pre punched at the factory to provide for field bolting to the
rigid frames. They shall be simple or continuous span as required by design.
Connection bolts will install through the webs, not flanges. [16]
Bracing
Diagonal bracing in the roof and sidewalls shall be used to remove longitudinal loads
(wind, crane, etc.) from the structure. This bracing will be furnished to length and
equipped with bevel washers and nuts at each end. It may consist of rods threaded each
end or galvanized cable with suitable threaded end anchors. If load requirements so
dictate, bracing may be of structural angle and/or pipe, bolted in place. [16]
Welding
Welding is a fabrication or sculptural process that joins materials, usually metals. In
Pre-engineered Steel Buildings the hot rolled steel sections are subjected to submerged
arc welding. Shielding gas is used in order to protect the welding region. Welding is
Done by passing the Steel plates into the welding machine, which welds along the
joints. In PEB the Tapered sections are welded, but at some locations manual welding
is done. Double side welding is preferred according to Indian Code but Single side
Welding is much beneficent because it increases the Quality of steel sections. Single
side welding is more economical, all manufactures follow the American code which
states Single side welding.
Base plates are welded to base of columns for the structural strength. These base plates
are provided with bolt holes. Anchor bolt dimensions are taken into account for Base
plate preparation. [16]
Anchor Bolts:
Anchor bolts are manufactured with circular steel rods having threading portion at the
top for bolting and bent up at the bottom for Foundation. These are bent at 90 degrees
27
for embedding into the soil. The dimensions for Anchor bolts are taken from support
reactions of the columns.
Surface Preparation:
The surface of columns and rafters are prepared in order to protect it from rusting.
Abrasive paper is used to scrub the top layers of columns and rafters in order to remove
accumulated rust on the top of the sections. This is old method, it is done manually.
Advancement technologies avoided manual procedure and brought Sand blasting and
short blasting into existence.
Sand blasting: Sand Blasting is a method in which sand is blown with high velocities
to the members. This is blown with sand particularly with 2 to 4 mm thick sand and
surface is cleared.
Short Blasting: Short blasting is a latest process in which members are sent into the
machine and hit with iron balls of 3mm thick under a huge velocity. Periodical removal
of rust is done in case of short blasting. Short blasting is observed as more efficient
surface cleaning process
Varnishing or Painting: Normally the primary and secondary steel are coated with
one coat (35 microns) of red oxide paint without any special treatment to steel.
However, if some special paint has to be applied to steel in order to give better anticorrosion properties etc. then the steel members have to be shot-blasted and then coated
with the special paints.
2.4.5 ERECTION
Steel construction is considered as a process that involves many related activities. Preengineered buildings (PEB) steel parts are required to be installed in a specific order
due to structural safety requirements and to the logical sequence of erection. However,
28
shipping, transportation, unloading and on-site storage does not take into account the
erection order of the assembly. As a result, considerable time is consumed locating,
sorting, and identifying steel Components.
Integrating promising information technologies such as radio frequency identification
(RFID), mobile computing devices and wireless technology can be useful in improving
the effectiveness and convenience of information flow in construction projects. Preengineered buildings require repetitive operations and assembly of many structural
elements.
Pre-engineered buildings (PEB) steel parts are required to be installed in a specific order
due to structural safety requirements and to the logical sequence of erection.
Erection Drawings:
Erection drawings provide the field erection crew (raising gang) with the roadmap of
how to erect (put together) the steel assemblies after they are delivered to the field.
Essentially, they are a set of instructions on how to put the puzzle pieces together.
Every assembly shipped to the field is given a shipping piece number to identify it.
This number is noted on the drawing and is also stenciled onto the actual assembly of
steel. Erection drawings illustrate how the connections will be fabricated in the field.
C. Construct the foundation using the materials recommended as per design parameters.
Transiting on all corners the foundation locations are determined and trenches are made
for foundation. In foundation trenches the Anchor bolts are set along with the concrete.
for drying. Puddles of water should not be allowed to collect and remain on columns
or rafters for the same reason.
31
most satisfactory to erect the columns first, tie them together with the girt and tighten
the anchor bolts. On small spans and short eave heights, columns can often be set in
place by hand without the use of hoisting equipment. Temporary bracing should always
be installed as soon as sections are lifted in place.
Installation of Bracing:
Diagonal bracing in metal buildings is critical. They provide support for wind loads or
other longitudinal loads, such as those created by an overhead crane in the completed
structure. Many times additional temporary bracing is needed to stabilize the structure
during erection. On some smaller buildings, diagonal bracing is not needed for the
building design, so the erector must furnish any erection bracing needed.
33
Assemble the next brace cable the same way and connect to the next column to form
an X with the other cable. To square the building, measure the length of the diagonal
cables and tighten or loosen the turnbuckle/eye-bolt until the cable lengths are the
same. Brace each sidewall frame the same way so that you have an x-brace on each
side. Tighten the column anchor nuts after insuring that the building is square.
The diagonal bracing is cable. It should always be installed as shown on the erection
drawing and should be tensioned so that the building will not sway or rock when the
wind blows. Care should be taken, however, not to over tighten and bend the structural
members. The workman should watch the structural members carefully as he tightens
the bracing. Occasionally the bracing in the wall of a building cannot be installed in
the specified bay because of doors or other complications. Usually these can be moved
to other bays without affecting the structural integrity of the building.
Bolts shall be inserted through the holes after alignment from such a direction that the
nut has easiest access for tightening.
Wall Insulation
Fiberglass blanket insulation is the most common type used, and these instructions
pertain to this type only. One side of the blanket insulation should have a vapour barrier
that must face the inside of the building regardless of whether the insulation is for
heating or cooling.
Cut the insulation to length allowing an additional 6 or more to facilitate handling. The
wall panel can be used as a guide. The first run of wall insulation should be installed
so that its forward edge is just ahead of the leading edge of the wall panel. This keeps
the forward edge of the insulation ahead of the wall panel for joining the next blanket.
Roof Insulation:
Pre-cut roof insulation to reach from eave to eave allowing approximately 2 feet of
additional length to facilitate handling. Hold insulation at one sidewall and roll out
insulation across the purlins, vapour barrier to the inside of the building. Stretch the
35
insulation to provide a tight and smooth inside surface. Double sided tape or contact
adhesives can be used to hold insulation in place while the roof sheets are being
installed. Trim excess insulation to the edge of the eave trim and cut fiberglass
approximately 4 inches from end leaving only facing. Fold facing over end of blanket
insulation to seal the end.
Screw alignment:
Good alignment of the screws, especially on the wall panels, will give a professional
appearance to the wall panel installation. One way this can be accomplished is by predrilling holes in the panels at identical locations. Up to 15 panels can be stacked
together and drilled using a template panel. 1/8 or 5/32 diameter drill bit is used for
panel to structural fasteners and a 1/4 diameter bit for the side lap clearance holes.
36
Fastener Installation:
Correct fastener installation is one of the most critical steps when installing roof panels.
Drive the fastener in until it is tight and the washer is firmly seated. Do not overdrive
fasteners: A slight extrusion of neoprene around the washer is a good visual tightness
check.
Always use the proper tool to install fasteners. A fastener driver (screw gun) with and
rpm of 1700-2500 is used for self-drilling screws.
Align the centre of the major rib of the panel edge with the edge of the end wall
roofline. With the panel properly placed, secure the panel to the structure with
appropriate fasteners.
37
Final Installation:
While back lapping the last roof panel (to match panel coverage with the building
length) is routinely done, this installation method can compromise the integrity of the
roof by trapping moisture between the panels. This moisture could, in time, create an
environment conducive to rust and metal failure. Manufacturer recommends field
cutting the final panel lengthwise to create the desired panel width necessary to finish
off the building. The cut edge of the panel should always be installed on the outside
edge, not the lap edge. The narrow panel should be handled with care, and foot traffic
avoided until the final panel is completely installed.
Skylight Installation:
Skylight panels are installed using the same procedures as a steel panel. Care should
be taken when installing fasteners in the skylights to avoid cracking the material. Install
roof panels, leaving the light-transmitting panel run open, except for lower light
transmitting panel run panel. Install tape sealer to panel side laps and across panel
width as normal. Lay light transmitting panel in place overlapping lower metal panel
[6]. Apply double run of tape sealer across light transmitting panel width at lower and
middle purlins.
38
Strength Building:
With the country's five year plan catering for infrastructure addition in the form of
airports, metros and bridges sector differentiation is expected to separate industrial
buildings and building systems. These include Design & Engineering, Manufacture
and Construction & Erection. This pattern of restructuring indicates an industry that
39
sees PEB s coming into its own with experiencing exponential growth with
diversification into various sectors and segments.
Add to that the reduced time to completion with the benefit of quality, and there is recipe
for success.
"PEB is getting its due credit as a favourable alternative construction methodology in
India today. More sectors are realizing the benefits of metal over brick and mortar.
The scope of metal/steel buildings is very vast for the Indian market. PEB proves to
be relevant and beneficial to several construction verticals including warehousing,
infrastructure, oil & gas refineries as well as group housing,"(Kirby). "The advantages
of having a steel structure or building over traditional concrete are far too many.
Primarily, speed and quality of construction are the top two benefits. Steel buildings
are fire, quake and cyclone resistant hence from a safety and longevity perspective,
these buildings are timeless".
40
Almost 100% of PEB s world-wide are insulated for the following reasons.
Minimize energy loss, cooling load and operating cost for air conditioned
buildings
41
CHAPTER 3
METHODOLOGY
3.1 GENERAL:
Pre-engineered Buildings are custom designed to meet client s requirements. PEB are
defined for definite measurements. The produced members fit to the designed
dimensions. Measurements are taken accurately for the requirements. The basic
parameters that can define a PEB are as follows.
42
Dead Load:
The structure first of all carries the dead load, which includes its own weight, the weight
of any permanent non-structural partitions, built-in cupboards, floor surfacing
materials and other finishes. It can be worked out precisely from the known weights of
the materials and the dimensions on the working drawings.
43
Live Load:
All the movable objects in a building such as people, desks, cupboards and filing
cabinets produce an imposed load on the structure. This loading may come and go with
the result that its intensity will vary considerably. At one moment a room may be
empty, yet at another packed with people. Imagine the `extra' live load at a lively party.
Wind loads:
Wind has become a very important load in recent years due to the extensive use of
lighter materials and more efficient building techniques. A building built with heavy
masonry, timber tiled roof may not be affected by the wind load, but on the other hand
the structural design of a modern light gauge steel framed building is dominated by the
wind load, which will affect its strength, stability and serviceability. The wind acts both
on the main structure and on the individual cladding units. The structure has to be
braced to resist the horizontal load and anchored to the ground to prevent the whole
building from being blown away, if the dead weight of the building is not sufficient to
hold it down. The cladding has to be securely fixed to prevent the wind from ripping it
away from the structure.
Roof load:
Live loads produced by maintenance activities, rain, erection activities, and other
movable or moving loads by not including wind, snow, seismic, crane, or dead loads.
Roof snow load:
Gravity load induced by the forces of wind blowing from any horizontal direction.
Collateral loads:
The weight of any non-moving equipment or material such ceilings, electrical or
mechanical equipment, sprinkler system, or plumbing.
Auxiliary loads:
44
45
46
3.1.9 SUBSYSTEMS
Major companies use standard components and designs to manufacture a wide range
of structural subsystems according to customers' requirements. These structural
subsystems fulfil the requirements of two types viz. Aesthetic and Functional. They
produce a large number of structural subsystems according to exact specifications as
the strength of the pre-engineered building system depends largely on various
incorporated structural subsystems. Subsystems are available for following structures
End wall Roof Extension:
panel, Gable trim, soffit panel, and end wall rafter. The end wall is extended to an
extent under end wall panel support.
Sidewall Roof Extension: The sidewall roof extension has the same assembly but the
soffit panels are above the Roof Extension Rafter.
Centre Curved Fascia: The centre curved fascia consist Backup panel, soffit panel. It
is an assembly of Cap flashing, Fascia panel with valley gutter or eave gutter on the
rafter with rigid frame support.
Bottom Curved Fascia: The entire assembly of Centre curved fascia contains for the
Bottom curved Fascia a slight change in Connection of wall panel to Frame.
Top and Bottom Curved Fascia: In this the assembly is a combination of Top Curved
Fascia which has curvature at top and bottom curved Fascia having bottom Fascia. [6]
Roof Platform: The roof platform has Grating on above and roof panels on the sides.
47
1. Primary components
2. Secondary components
3. Sheeting (or) cladding
4. Accessories
48
Columns:
The main purpose of the columns is to transfer the vertical loads to the foundations.
However a part of the horizontal actions (wind action) is also transferred through the
columns.
Basically in pre-engineered buildings columns are made up of I sections which are
most economical than others. The width and breadth will go on increasing from bottom
to top of the column. I section consists of flanges and web which are made from plates
by welding.
49
Rafter
Rafter:
A rafter is one of a series of sloped structural members (beams) that extend from the
ridge or hip to the wall-plate, down slope perimeter or eave, and that are designed to
support the roof deck and its associated loads.
50
51
Eave Struts
Eave Struts shall be unequal flange cold-formed "C" sections. Eave struts are 200 mm
deep with a 104 mm wide top flange, a 118 mm wide bottom flange, both are formed
parallel to the roof slope. Each flange has a 24 mm stiffener lip.
52
Bracings:
The Cable bracing is a primary member that ensures the stability of the building against
forces in the longitudinal direction such as wind, cranes, and earthquakes.
Diagonal bracing in the roof and sidewalls shall be used to remove longitudinal loads
(wind, crane, etc.) from the structure. This bracing will be furnished to length and
equipped with bevel washers and nuts at each end. It may consist of rods threaded each
end or galvanized cable with suitable threaded end anchors [6]
Base metal of either Galvalume coated steel .Galvalume coating is 55% Aluminium
and about 45% Zinc by weight. An exterior surface coating on painted sheets of 25
microns of epoxy primer with a highly durable polyester finish.
3.2.4 ACCESSORIES
Anchor bolts:
Bolts used to anchor the structural members to the concrete floor, foundation or other
support. This usually refers to the bolts at the bottom of all columns. Anchor bolts are
Anchor bolts are manufactured with circular steel rods having threading portion at the
top for bolting and bent up at the bottom for Foundation.
Turbo ventilators
A Turbo Ventilator is a free spinning roof ventilator that works on free wind energy.
When there is a difference in thermal or wind pressure between the inside and outside
of the building, the air is forced to move through the opening of the Turbo Ventilator
in order to maintain an equilibrium condition. The benefits of using turbo ventilators
Are that it improves air circulation and cuts off the suffocation. Eco friendly turbo
ventilator involves no operating cost, are free from maintenance and are has trouble
free operations.
54
Louvers:
Standard Louvers shall have a 26 gauge galvanized steel frame, painted, with 26 gauge
blades. Heavy Duty Louver frames shall be 18 gauge galvanized steel frame, painted,
with 20 gauge blades They shall be equipped with adjustable or fixed blades as
specified. Nominal sizes shall be 2 -0" x 2 0" x 2'0", 3'-0" x 3'-0" 4'-0" x 3'-0", and 3'0" x 4'-0
Walking doors:
Walk doors are generally 915 mm or 1830 mm wide x 2134 mm high made of 20 gauge
electro galvanised steel with a core of polyurethane insulation. Door fixture is provided.
[6]
Aluminium windows:
Designed for installation with wall panel, double slide, self -flashing with pre-glazed
clear glass and removable half insect screen. Standard size is 1 m x 1 m. multiple
windows can be formed by joining the jamb fins together
Fasteners:
Standard fasteners shall be self -drilling screws with metal and neoprene washers. All
screws shall have hex heads and are zinc plated.
57
Design of Rafter
`
Design of Column
Structural Analysis
Design of Purlin
Design of Connection
Foundation
On Violating Initial
assumptions
On satisfying
Initial assumptions
Final design
58
CHAPTER 4
DESIGN OF PRE-ENGINEERED STEEL BUILDING
4.1 GENERAL
Pre-engineering of metal buildings can be optimized to meet specific design criteria.
Largely Indian and American practice of design is followed by most of the consultants
and PEB vendors in India these days. A brief of design codes used in each of these is
attached herewith:
The main framing of PEB systems is analysed by the stiffness matrix method. The
design is based on allowable stress design (ASD) as per the American institute of Steel
Construction specification or the IS 800. the design program provides an economic and
efficient design of the main frames and allows the user to utilize the program in
different modes to produce the frame design geometry and loading and the desired load
combinations as specified by the building code opted by the user. The program operates
through the maximum number of cycles specified to arrive at an acceptable design.
The program uses the stiffness matrix method to arrive at an acceptable design. The
program uses the stiffness matrix method to arrive at the solution of displacements and
forces. The strain energy method is adopted to calculate the fixed end moments,
stiffness and carry over factors. Numerical integration is used.
4.1.1 DESIGN CYCLE
The design cycle consists of the following steps:
1. Set up section sizes and brace locations based on the geometry and loading specified
combination.
59
actual and allowable stresses and calculate the combined stress ratios.
5. Design the optimum splice location and check to see whether the predicted sizes
[16]
Frame Geometry:
The program has the capability to handle different types of frame geometry as follows
Frames of different types viz. rigid frames, frames with multiple internal columns,
single slope frames, lean to frames etc; Frames with varying spans, varying heights and
varying slopes etc. Frames with different types of supports viz. pinned supports, fixed
supports, sinking supports, supports with some degrees of freedom released.
Unsymmetrical frames with off centric, unequal modules, varying slopes etc. User
specified purlin and girt spacing and flange brace location.
Frame Loading:
Frame design can handle different types of loadings as described below:
All the building dead loads due to sheeting, purlins, etc. and the self- weight of the frame
and Imposed live load on the frame with tributary reductions as well.
Wind loads input such as basic wind speed or basic wind pressure that will be converted
to deign wind pressure as per the building code specified by the user and shall be
applied to the different members of the building according to the coefficients
mentioned in the codes prescribed by the user. The standard building codes like
60
MBMA, UBC, ANSI, IS: 875 parts 3 etc. are used for this purpose. Crane and noncrane loading can be specified by the user and the program has the capability to handle
these special loads and combine them with the other loads as required.
Seismic loads corresponding to the different zone categories of various international
codes can also be defined and combined with other load cases as required. Temperature
loads can also be specified in the form of different differential temperature value on
centigrade and specifying the appropriate coefficient for the thermal expansion. Load
combinations with appropriate load factors can be specified by the user as desired.
Structure with Span larger than 40 m can be regarded as long span structures and need
to be carefully designed keeping a balance of all the aspects like its weight, deflections
(sway) and foundation forces. There are many combinations of designing large spans,
like conventional truss & RCC column combination, truss & steel columns, Preengineered building (PEB) etc.
These days with the concept of PEB, the major advantage we get is the use of high
strength steel plates (usually Fe 350), lighter but high strength cold form purlins, and
550 Map Galvalume profiled sheets. The use of PEB not only reduces the weight of
the structure because high tensile steel grades are used but also ensures quality control
of the structure. In the following study, we have designed a warehouse using this
modern concept of PEB. [16]
61
Dead load:
Dead loads shall cover unit weight/mass of materials, and parts or components in a
building that apply to the determination of the dead loads in the design of buildings
and shall be considered as per IS: 875 (Part 1) - 1987 according to the densities of the
possible components. This includes main frames, purlins, girt, cladding, bracing and
connections etc.
Live Load:
Imposed loads shall be considered as per IS: 875 (Part 2) 1987. Live load shall be
considered as 2.675 KN/m for the analysis and design.
Wind Load:
The basic wind speed and design velocity which shall be modified shall be taken
As per IS: 875 (Part 3) 1987.
As though this warehouse building is located within the area surrounded by high rise
apartments and buildings action of wind load is neglected as even the eave height is
limited only to 6m wind load is not considered.
62
Width
= 60 meters
Length
= 15 Meters
Eave Height
= 6 Meters
Bay Spacing
= 6 Meters
Brick work
= 2 Meters
Rise
= 2m
Slope
= 14.93 degree
63
65
= 15 m
Span
(l) = 15m
Rise
(h) = 2m
60 m
2
)
7.5
= 14.930
= 14.930
Lr =
(6)2 + (2)2
Lr = 7.76m
Actual length of the sheeting is likely more than this to cover eave girder
7762
1400
= 5.54 nos
Place 6 number of purlin on each rafter @ 1290mm c/c
Spacing of purlins = 1.29 m
66
= 150 + 100
= 250 N/m2
= 0.250 KN/m2
= 750 -20
= 651 N/m2
2
3
rd.
Load =
2
3
651 KN/m2
= 434.2 KN/m2
Live load on the plan area
= 434.2 6
= 0.4342 103
= 2.605 KN/m
67
68
= 14 m
= 1290 mm
= 14.93
The purlin is subjected to biaxial bending moment and as to design for different load
combinations and here as we exclude wind load only under live load and dead load
combination is designed
The following are the loads;
Wd = 1 KN
WL = 1.62 KN
And the components along the principal axes of the purlin are:
cos (14.93)
= 1.566 KN
Wlx = wl sin
= 0.417 KN
The load combinations considered is D.L + L.L
The design bending moments are computed assuming that the purlins are continuous
and the maximum (absolute) bending moment occurs at the support.
69
0.966 1.566
] 6
10
9
= (0.9066 + 0.174) 6
Mx1 = 1.6236 KNm
My1 = [ WlY B + WlxB ]
10
= [ 0.966 0.414 ] 6
10
= (0.9066 + 0.046) 6
My1 = 0.8576 KNm
Here
MX 1 MY 1
Zx
Zy
1.62 0.85
20.3 4.7
KN/m2
= 180.85 N/m2
MX 1 MY 1
Zx
Zy
70
1.62 0.85
103.9
9
Here = 110.23
KN/mm2
160 N/mm2
Thus the value is lesser than the permissible value 160 n/mm2
Hence it is safe.
Thus provide 6 nos of ISMC 150 at 1.29m c/c
71
= 100 N/m2
= 250 N/m2
Spacing of purlins
= 1.29 m
1.29
= 0.3225 KN/m
Live load
= 2.6052 KN/m
= 1.5
= 1.5 6 = 9 KN/m
= 1.5
9 = 13.5 KN/m
M=
Wl 2
8
M = 1.6875
7.762
M = 101.67 KNm
Design shear
V=
Wl
2
V = 6.75 7.76
V = 52.38 KN
Section modulus required =
Zp
101.67
= 250
M
Fy
ym0
1.1 10 6
Zp = 447.348
10 3 mm3
10 3 mm3.
h = 400 mm
b = 140mm
Section area
a = 7845.58mm2
tf = 16mm
tw = 8.9 mm
Depth of web
9.5
84
73
fy
VD
1
3
1.1
fy
VD
area
h TW
1
3
1.1
250
VD
400 8.9
1
3
1.1
VD 467728 N
VD 467.128
27.37
Hence It Is Safe
4.6.5 Check for Moment Capacity
D/TW = 38.2 WHICH IS LESS THAN 67 , SINCE =1
Hence,
fy
1
3
1.1
fy
area
h TW
1
3
1.1
250
Md =
400 8.9
1
3
1.1
467728 N
467.128
27.37
Md = 1.0 1176.163 103 250 /1.1 1.2 1022.7 103 250 /1.1
= 267 .310 10 6 278 .918 106
Md = 267.310 106 N-mm
Check for deflection, total working load = 12.8
74
5 wl 4
384 EI
5 17.3(8300)4
27.127mm
Hence it is Safe
Provide ISMB 400
TOTAL WORKING LOAD = L.L + D.L
= 12.8 4.5
= 17.3 N/mm
6.9037.434
5
MINIMUM DEFLECTION = =
220458.4105104 584
20.127mm
Le/300 = 27.76 ,6
20.127
27.67
Hence it is safe
75
N
mm 2
N
m
= 7846 mm 2
.
Width of the Flange = 140 mm
Area Provided
2b =
b; 200 mm
Thus provide 20mm 200mm plates
Check for Over Hang :
Over Hang = 200 -
140
= 3 p 12 t
20
76
N
m
Izz = 2045.4 104 mm 4
For ISMB 400 @ 604.3
Iyy = 15846 mm 2
77
78
79
80
81
82
83
84
CHAPTER 5
ANALYSIS USING STAAD PRO
87
88
89
CHAPTER 6
CONCLUSION
6.1 GENERAL:
Using of PEB instead of CSB may be reducing the steel quantity and thus reducing
the construction cost and Reduction in the steel quantity definitely reducing the dead
load. Reduction in the dead load reducing the size of Foundation. And reduction is all
but not the performance and life span is the unique property of pre- Engineered and
using PEB increase the Aesthetic view of structure
All the result values obtained on analyzing in this project proves to be economical and
the performance delivered by the pre engineered building is higher than that of
conventional steel building and the results are as follows
6.2 Results:
Thus for the under taken project on pre-engineered building the results of the
components that were designed are as follows:
1. Roof Design : For The Area Of The Roof (A = 900mm2) Provide 6 Nos of
Purlin @ 1290mm C/C [4.4]
2. Purlin Design : Provide 6 Nos of ISMC 150 @ 1290 mm C/C [4.5]
3. Rafter Design : Provide ISMB 400 604.3 N/M [4.6]
4. Column Design : Provide ISMB 400
200 mm Plates
[4.7]
5. Design Of Connections : Provide 12 Nos Of 20mm Diameter Bolts With The
Pitch Of 40 mm In Four Rows [4.8]
6. Design Of Gusset Plate : Provide ISA 125
90
95 [4.9]
100
8 mm Connecting Angles
91
REFERENCE:
[1]. Aijaz Ahmad Zende, Prof. A. V. Kulkarni, Aslam Hutagi (Feb 2013).
Comparative Study of Analysis and Design of Pre-Engineered- Buildings and
Conventional Frames. IOSR Journal of Mechanical and Civil Engineering,
Volume 5, Issue.
[2]. C. M. Meera (June 2013). Pre-engineered building design of an industrial
warehouse. International journal of engineering sciences & emerging technologies.
Volume 5 Issue 2, pp: 75-82 Dr. Ramachandra & Virendra Gehlot Design of Steel
Structures
[3]. Design Concept of Pre-engineered Building by Syed Firoz1, Sarath Chandra
Kumar B1, and Design concept of pre-engineered building. International journal of
engineering research & applications, volume 2, issue 2, pp: 267-272
[4]. Design of Long span structures and Hangars by Amit Bharana ERA buildings
ltd.
[5] G. Sai Kiran, A. Kailasa Rao, R. Pradeep Kumar (Aug 2014). Comparison of
Design Procedures for Pre Engineering Buildings (PEB): A Case Study.
International Journal of Civil, Architectural, Structural & Contruction Engineering,
Volume 8, No. 4
[6]. http://www.engineeringcivil.com/pre-engineered-buildings.html
[7]. http://nbmcw.com/articles/PEB -roofing/PEB -prefab-steel-structures/18161preengineered-building-systems-a-promising-future.html
[8]. http://nbmcw.com/articles/PEB -roofing/PEB -prefab-steel-structures/18161preengineered-building-systems-a-promising-future.html
92
http://www.engineeringcivil.com/preengineered-buildings.html
[10]. IS: 800-2007: General Construction in Steel - Code of practice
[11]. IS: 875 (Part 1): - 1987 Code of Practice for Design Loads
[12]. IS: 875 (Part 2): - 1987 Code of Practice for Design Loads
[13]. IS: 875 (Part 3): - 1987 Code of Practice for Design Loads
[14]. Jatin D. Thakar, 2 Prof. P.G. Patel. Comparative study of pre- engineered
steel structure by varying width of structure. International journal of advanced
engineering technology, volume 4, issue3
[15]. N. Subramanian (2010) Design of Steel Structures
[16]. P. Dayaratnam Design of Steel Structures
[17]. Pre-engineered Metal Buildings < The Latest Trend in Building
Construction. By.K. Mitra Llyods Insulations Limited.12.
[18]. PEB VS Conventional the Zamil Steel Limited
[19]. S.S. Bhavikatti Design of Steel Structures
[20]. S. Ramamrutham Design of Steel Structures
93