Disputes Review Board
Disputes Review Board
Disputes Review Board
disputes between
parties,
including
negotiation,
mediation,
arbitration,
Furthermore:
. . . contractors are less likely to present exaggerated claims for the sake of
increasing pressure on the owner/employer, and owners/employers are less likely to
reject meritorious claims. Stated differently, both sides have a vested interest in
preserving their credibility, which may suffer if they misbehave while the teacher is
in the room.
The City of Toronto's Yonge Street subway line, the first of its kind in Canada, opened
in 1954. And on January 1 of that year, the Toronto Transit Commission (the TTC), an
agency of the City of Toronto, became the sole provider of public transportation services in
the city. Over the years, new subway extensions, branches and lines extended the reach of
the city to the growing suburban populations.
The Sheppard Subway line, which took 8 years to build, and which cost almost $1
billion, opened on November 22, 2002. It was the first subway line in Canada whose two
separate subway tunnels (the Twin Tunnels) were built entirely by two tunnel boring
machines (TBMs). The TBMs (nicknamed Rock and Roll) not only dug through the
earth, but also installed reinforced concrete liner rings as they passed. The Twin Tunnels
were approximately 2.7 miles in total length, were to run side by side, approximately 40 feet
apart, and were generally located from approximately 15 to 85 feet below the surface of
Sheppard Avenue East.
TTC had entered into a CDN $93 million tunnelling contract with MPF, a joint
venture consisting McNally International Inc., PCL Constructors Eastern Inc., and The
Foundation Company Inc. (subsequently known as Aecon Construction Group Inc.). The
Twin Tunnels contract established, and set out the procedure, function and key features of, a
Dispute Review Board. The DRBs stated purpose was to assist in the resolution of claims
and other disputes arising out of the performance of the work on the Twin Tunnels project, in
an independent, fair and impartial manner, in order to avoid construction delay and litigation.
The DRB member selected by the two appointed members of the DRB as Chair of the
DRB, and approved by both TTC and MPF, was an engineering consultant with substantial
9
Shortly thereafter, the DRB released its detailed and comprehensive 41-page written
Recommendation. The three members of the panel, in unanimously rejecting MPFs claim,
10
12
13
REFERENCES
14
B. G. Corgan, T. J. Kelleher and E. Dorris, Construction Disputes: Practice Guide with Forms
2nd edition. New York: Aspen Publisher, 2002
D. F. Turner and A. Turner, Building Contract Claims and Disputes 2nd Edition. Singapore:
Longman, 1999
DRRF,
DRBF
Practices
and
Procedures,
2007.
Retrieved
from
http://www.drb.org/manual_access.htm
K. M. J. Harmon, K., Dispute Review Board: Elements of a Convincing Recommendation,
Professional Issues in Engineering Education and Practice, Vol. 130, 2004, pp. 289 295.
S. Rajoo. Sundra Rajoo Trade Disputes Solving Mechanisms, 2009. Retrieved from http://
www.sundrarajoo.com/2009/10/trade-disputes-solvingmechanisms-poram-coursejuly-2009/
The institutes of Arbitrators & Mediators
https://www.iama.org.au/sites/default/files/resources/rules-guidelines/disputereview.pdf
DRBF Practices and Procedures Manual, Chapter 1, Section 3 (revised April 2007), pages 23 (at http://www.drb.org/manual/1.3_final_4-07.doc)
Z.M. Matyas, A.A. Mathews, R.J. Smith, P.E. Sperry, Construction Dispute Review Board
Manual (N.Y.: McGraw Hill, 1995) at 30.
C. Chern, Chern on Dispute Review Boards (Oxford: Blackwell Publishing, 2008) at ps. 5964.
John W. Hinchey and Troy L. Harris, International Construction Arbitration Handbook
(Thomson/West, 2008), at para 1:10
Harvey
J.
Kirsh,
The
Ins
and
Outs
of
Dispute
Review
Boards,
http://www.glaholt.com/files/the_ins_and_outs_of_dispute_review_boards__paper_.pdf
16