Guidelines Project Schedule
Guidelines Project Schedule
Process
The project Schedule outlines the tasks and activities of the project; the duration; start and end dates for
each individual task and the project as a whole; and the resources and effort required. Developing a
project Schedule involves a number of defined steps.
For most projects there will be at least two separate Schedules developed. One will be for the Initiation
Phase (Initial Schedule) and the other for the Planning, Execution and Closure phases. All schedules are
added to Eclipse for tracking and updating.
The Initial Schedule is developed in the Initiation Phase of the project to help produce the Project Charter.
At this point, the Schedule is not expected to be very accurate or contain firm dates; rather it gives the
Project Manager (PM) a rough idea of the project timeline and the assignment of resources. When the
Charter is approved, a second Schedule is developed, with the approval date as the Project start date.
In the Planning Phase, a Project Management Plan is created (from the Charter), and the second Schedule
is updated with a more accurate and realistic timeline. In effect, the start and end dates of the first
Schedule will be replaced by the start and end dates of the second Schedule. Eclipse allows for the
development and saving of multiple schedules. This feature can help in creating what if schedules
without disturbing the active schedule.
A process flow diagram outlining detailed steps in completing a Schedule is contained in Appendix A.
Work Packages
Work packages are the lowest level in a WBS decomposition where an activity duration can be reliably
estimated and managed. A Work Package can be created where a Project Manager (PM) deems it
necessary to help develop the project Schedule.
A work package details a level of work to be completed. It would contain a description of the work,
details of constraints, and agreement between the PM and the team or individual doing the work, that the
work can be done within the constraints. Assumptions would be defined in the work package depending
on the needs of the project.
Work packages are particularly useful where contractors or other departments are involved in the project.
A work package should define durations of 4 to 6 weeks. The PM would assign the work package and
authorize the work to be completed according to the project Schedule. The PM would monitor and control
the project at the work package level and not necessarily at the task level.
An example of a Work Package is included in Appendix B.
Page 2 of 7
performing the work, and even the data logs of a resource like a machine (to find out how fast the
equipment can get the job done).
PERT analysis requires three numbers:
1. Most Likely Time The activity time which will likely occur most often
2. Most Pessimistic Time The activity duration under the least favourable conditions
3. Most Optimistic Time The minimum activity duration under the most favourable conditions
The formula to calculate the estimated effort or duration is:
Estimated Duration = Optimistic + (4 x Most Likely) + Pessimistic /6
Once this estimated duration is determined, a personal fatigue factor (PFD) should be applied. This is
typically 20% of the estimate, and will allow for factors such as; experience level and issues which could
impact the person not spending full time on the task.
Schedule
Once the tasks and activities are developed, the Schedule is produced. The schedule is a living document
and needs to be monitored and kept up to date. It may be created directly in Eclipse or developed in MS
Project and imported into Eclipse. Once complete, project milestones should be identified and
incorporated into the Schedule. A milestone is a point in time in the project which identifies the end of
a significant set of related activities indicating the completion of a major deliverable. A milestone has no
duration or effort.
A final step in the development of the Schedule is to determine a contingency factor to be applied to the
schedule. Typically, a contingency of 10% is applied at the overall schedule level and not at the task
level. On a large project contingency can be applied at a phase, sub-phase or activity level.
Once initial and subsequent schedules are developed, they should be baselined. In most cases, this is
done at the completion of the Project Management Plan. A baseline establishes a point of reference from
which a comparison can be made against the plan.
During the development of the Schedule it is important for the PM to keep in mind any Assumptions
and Constraints identified in the Project Charter and/or Plan, and how they may impact the timeline.
As well, risks and issues should be taken into consideration when creating the project schedule.
Page 3 of 7
Appendix A
Process Flow
Project Scope
Develop Work
Breakdown
Structure
WBS
A1
Define Work
Packages
Work Packages
A2
Distribute Work
Packages
Work Packages
A3
Define Activities
and Tasks
A4
Task List
Define Task
Dependencies
A5
Determine
Resource(s) for
each Task
A6
Develop Effort
Estimates
A7
Define Calendar
Dates
A9
Schedule
Apply Contingency
Factors
Updated Schedule
A10
Review Schedule
with Team
Members
A11
Schedule
Update Eclipse
with Schedule
A12
Updated Eclipse
Execute Schedule
and Project Details
A13
NODE:
TITLE:
Page 4 of 7
NO.:
Sample WBS
Page 5 of 7
Appendix B
Sample Work Package
The purpose of the Work Package is to agree and record clearly to a sufficient level of detail such that the
person or team required to carry out the work knows what needs to be delivered, to what detail and
quality standard and within what timeframe.
January 8, 2013
Requirements
Document the processes involved in Auto Entrance.
Define and document the business rules, checks and validations associated with Auto Entrance.
Define the information (data) required of the process and detail its origins and end point.
Page 6 of 7
Sample
Activity/ Task
Days
Effort
15
Elapsed Time
(Duration)
20 days
March 1 to March 31, 2014
10
20 days
March 1 to March 31, 2014
7 days
March 17 to March 22, 2014
Reverse engineering code may not allow the definition of all business rules
Current system code was written by an outside developer in 2003 and may not be easily read
Current documentation may not be available
Page 7 of 7