Report On Mega Projects (Rs.1000 Crores and Above) February, 2010

Download as pdf or txt
Download as pdf or txt
You are on page 1of 21

9th REPORT ON MEGA PROJECTS

(Rs.1000 Crores and above)


February, 2010

expressway

Government of India
Ministry of Statistics and Programme Implementation
Infrastructure and Project Monitoring Division
Sardar Patel Bhavan, Sansad Marg
New Delhi-110001
Website: www.cspm.gov.in

Contents

Executive Summary

1-7

Summary of Projects

8-12

Sector wise analysis of projects

13-20

EXECUTIVE SUMMARY

The 9th report on mega projects contains information on the status of


127 projects in the Central Sector, each costing Rs. 1000 Crores and above.
During February 2010, no project reported completion. Sector-wise number
of ongoing projects is given below:

Sl no.

Sector

Projects on monitor

1.

POWER

38

2.

PETROLEUM

39

3.

RAILWAYS

16

4.

COAL

6.

STEEL

7.

SHIPPING & PORTS

9.

ATOMIC ENERGY

5.

TELECOMMUNICATION

8.

CIVIL AVIATION

10.

URBAN DEVELOPMENT

11.

MINES

12.

WATER RESOURCES

Total

2.

127

Twenty two (22) projects have reported additional delays compared to the

position in the previous month. There have been slippages in the range of 1-60 months
in respect of projects relating to Atomic Energy, Civil Aviation, Coal, Steel, Petroleum,
Power and Railway sectors.

3.

Out of 127 projects, 4 projects are ahead of schedule, 37 projects are on

schedule and 74 projects are delayed. Of the balance 7 projects do not have fixed
date of commissioning.

4.

The original cost of implementation of 127 projects of Rs 442727 Crores, is

anticipated to cost Rs 479369 Crores, implying a cost overrun of around 7%. The
expenditure incurred on these projects 2009 is Rs 183878 Crores which is 38% of the
anticipated Completion cost of the projects.

5.2 In the Coal sector, 2 projects have reported additional delays in the range of 1-48

months while Tuticorin Thermal Power Project, have reported considerable improvement
over the completion schedule by 1 month respectively. Expansion of Mine-II (10.5 MIPA
to 15.0 MTPA) project of National Lignite Corporation, (NLC) has reported additional
delay of 1 month due to acquisition of private land, delay in supply of indigenous
equipment by private sector and delay in equipment erection. DIPKA Expansion OCP, 20
MTY of SECL has reported additional delays of 48 months due to finalization of tender
and award of work for construction of workshop.

5.3 In the Power Sector, 9 projects have reported additional delays in the range of
1- 21 months. Parbati Hydro Electric Project Stage-III 4x130 MW (NHPC) has
reported additional delay of 7 months due to delay in land acquisition for Sainj bypass
and delay in award of E&M contract. Chamera, Hydro Electric Project Stage III
(NHPC) has reported additional delays of 4 months due to violence among contractors
laborers and court stay on crushing Plant leading to huge shortage of aggregate for
concrete work.

Bongaigaon Thermal Power Project (NTPC) has reported additional

delay of 3 months due to delay in slow progress by civil agency. Korba STPP StageIII, 500 MW (NTPC) has reported additional delay of 6 months due to delay in civil
and structural work by M/s SPML.

Farakka STPP Stage-III (NTPC) has reported

additional delay of 3 months due to delay in finalization of erection by M/s BHEL.


Kaiga 3 & 4 Transmission System (PGCIL) has reported additional delay of 3 months
due to revision of works in 50 km Karnataka portion. Kunadankulam Atomic Power
Project HEP Transmission Line 1838 CKM (PGCIL)

has reported additional delay of

one month, to match with the commissioning of linked Generation Projects.


Vishnugad-Pipalkoti Hydro Electric Project (THDCL) has reported additional delays of
21 months due to delay in acquisition of forest land.

5.3

In the Petroleum Sector, 2 projects have reported additional delays in the

range of 1-24 months. Panipat Naphta Cracker Project has reported additional delay
of 1 month due to delay in completion of Captive Power Plant by L&T.

Development of

B-46 Cluster Field has reported additional delay of 24 months, due to revision of
works.

5.4

In the Railway Sector, 2 projects have shown additional delays in the range of

3-60 months. Udhampur-Srinagar-Baramulla (NL), NR has reported additional delay


of 60 months due to delay in land acquisition of Army Land. Tollyganj-Garia (MTP)
project, has reported additional delay of 3 months, however, no specific reason has
been reported by the concerned project authorities.

5.5 In the Steel Sector, 3 projects have reported additional delays in the range of
2-12 months. Expansion of Bokaro Steel Plant, Expansion of Bhilai Steel Plant and
Rourkela Steel Plant have reported additional of 2 months,6 months and 12 months
respectively due to inadequate mobilization of resources by the contractor.

Status as on 01.03.2010 in respect of completion of projects costing Rs.1000


Crores and above in different sectors during 2009-10 is indicated in the following
tables.

(Pankaj Jain)
Additional Secretary to the Government of India
Ministry of Statistics & Programme Implementation

EXECUTIVE SUMMARY

Sl. No.
1
2
3
4
5
6
7
8
9
10
11
12

Sector

Projects on Monitor
39
38
16
8
6
6
5
3
2
2
1
1
127

Petroleum
Power
Railways
Coal
Steel
Shipping & Ports
Atomic Energy
Civil Aviation
Telecommunications
Urban Development
Mines
Water Resources
Total

Projects Additional
Delayed
2
9
2
3
3
0
2
1
0
0
0
0
22

ANNEXURE-I

Month wise List of Completed Project Costing Rs.

1000 Crore and above during

2009-2010
Sl. No.

Project
Name

Original Cost
(Rs. Crore)

Original Date
Of
Commissioning

Cumulative
Expenditure
(Rs. Crore)

June,2009
Petroleum
1

GREEN FUELS & EMISSION CONTROL (HPCL) MUMBAI


REF.(HINDUSTAN PETROLEUM CORPORATION LIMITED) [160100236]

1,152.00

06/2009

1,551.79

5,868.31

05/2007

4,881.17

1,008.00

03/2009

337.50

1,136.08

09/2009

1,196.24

985.17

03/2006

1,568.46

July,2009
Power
2

KAHAL GAON STPP STAGE - II (NTPC)(NATIONAL THERMAL


POWER CORPORATION) - [180100230]
Telecommunications

PROJECT NIB-II BROADBAND MULTIPLY(BHARAT SANCHAR


NIGAM LIMITED) - [N26000047]
September,2009
Shipping & Ports

ACQUISION OF 2-300,000 DWT VERY LARGE CRUDE


CARRIERS(SHIPPING) - [250100174]
October,2009
Petroleum

DEVELOPMENT OF BASSEIN EAST (ONGCL)(OIL & NATURAL


GAS CORPORATION LIMITED) - [160100232]

ANNEXURE-I
Month wise List of Deleted Project Costing Rs. 1000 Crore and above during
2009-2010
Sl. No.

Project
Name

Original Cost
(Rs. Crore)

Original Date
Of
Commissioning

Cumulative
Expenditure
(Rs. Crore)

Summary of projects on the Flash Report


for the month of February, 2010
I.

Project Implementation Current Status:


Number of Projects Previous Month

127

Number of Projects Completed/Dropped/Frozen in Previous Month

Number of Projects Completed/Dropped/Frozen in Current month

Number of Projects Added in Current month

0
127

Number of Projects in Current Month

II.

Brief Analysis

Without ODC
but DOC
Without
DOC (7)

available (5)

Delayed
(74)
On
schedule
(37)
Ahead (4)

III.

a) Project Status w.r.t


Original Schedule: Out of 127
projects, 4 projects are ahead of
schedule, 37 projects are on
schedule and 74 projects are
delayed.
Of the balance, 7
projects do not have fixed dates
of commissioning while 5
projects were sanctioned without
any commissioning date but
subsequently dates of completion
were finalised.

Investment Scenario
Figures are in Rs. Crore

The total cost of implementation of


127 projects when sanctioned, was
of the order of Rs. 442727.32
Crores but this was subsequently
revised to Rs. 479368.52 Crores
implying a cost overrun of 6.90%.
The expenditure incurred on these
projects till February, 2010 is Rs.
183877.74 Crores, which is
38.36% of the revised cost of the
projects.
8

700000
600000
500000
400000
300000
200000
100000
0

442,727.32

479,368.52

183,877.74

Sanctioned Anticipated Expenditure


cost
cost

I. Project Added / Completed / Dropped / Frozen


No of Projects in Previous Month
No of Projects Completed/Dropped/Frozen in Previous Month
No of Projects Completed/Dropped/Frozen in Current Month
No of Projects added in Current Month
No of Projects in Current Month

127
0
0
0
127

II. Project status


Number of Projects

With Respect To

Delayed

Original
Latest Approved

On
schedule

Ahead

74
75

4
5

Without ODC
but DOC
available

37
40

Without
D.O.C

5
4

Total

7
3

127
127

Delay
(%)
58.27
59.06

III. (A) Project cost


(Cost/ Expenditure in Rs. crore )

Cost
With
Respect to

No. of
Projects

Sanctioned

Cost overrun
Anticipated

Expenditure

(Rs. Crore)

Original
Latest Approved

103
24

376,564.00
66,163.32

402,380.61
76,987.91

145,057.05
38,820.69

36.00
50.40

25,816.61
10,824.59

6.90
16.40

Total

127

442,727.32

479,368.52

183,877.74

38.36

36641.2

8.28

III. (B) Delayed Project cost


(Cost/ Expenditure in Rs. crore )

Cost
With
Respect to
Original
Latest Approved
Total

No. of
Projects

Sanctioned

Cost overrun
Anticipated

Expenditure

(Rs. Crore)

74
75

255,533.99
53,308.00

308,614.74
313,678.14

150,824.03
154,095.42

48.90
49.10

53,080.75
260,370.14

20.80
488.40

149

308,841.99

622,292.88

304,919.45

49.00

313450.89

101.49

IV. Additional Delayed Project cost


(Cost/ Expenditure in Rs. crore )

Cost
With
Respect to
Latest Approved
Total

Cost overrun

No. of
Projects
22

Sanctioned
72,370.79

Anticipated
87,147.66

Expenditure
40,806.94

%
46.80

(Rs. Crore)
14,776.87

%
20.40

22

72,370.79

87,147.66

40,806.94

46.83

14776.87

20.42

V. List of projects completed/dropped current month

(Cost /Expenditure in Rs. crore )

Now anticipated

Original
Project

DOA

Cost

Cost

DOC

DOC

VI. List of projects added

Expenditure

(Cost in Rs. crore )

Original
Project

Final

DOA

Cost

DOC

VII. Milestones (Cumulative due & achieved)


Total

1595

Achieved up to month

658

10

Anticipated
Cost

DOC

VIII. List of projects reporting additional delays


Cost ( Rs. Crore)
Project name
Atomic Energy
RAJASTHAN ATOMIC
POWER PROJECT 5 and 6
(NPCIL)
KAIGA 3 and 4 UNITS (NPCIL)
Civil Aviation
C/O INTEGRATED
PASSENGER TER. BULD.
NSCBI AIRPORT
Coal
TUTICORIN THERMAL
POWER PROJECT
EXPANSION OF MINE-II
(10.5 MTPA TO 15.0 MTPA)
(NLC)
DIPKA EXPANSION OCP
(SECL) (20 MTY)
Steel
EXPANSION OF BOKARO
STEEL PLANT
EXPANSION OF BHILAI
STEEL PLANT
EXPENSION OF ROURKELA
STEEL PLANT
Petroleum
PANIPAT NAPHTA CRACKER
PROJECT
DEVELOPMENT OF B-46
CLUSTER FIELD
Power
KUNADANKULAM-APP
TRANS. SYSTEM (PGCIL)
KAIGA 3&4 TRANSMISSION
SYSTEM (PGCIL)
Farakka STPP Stage-III
BONGAIGAON THERMAL
POWER PROJECT
CHAMERA,STAGE-III (NHPC)

Original

DOC reported

Anticipated

Delay

Original

Last month

This month

(in months)

3,072.00

3,072.00

02/2008

02/2010

03/2010

4,213.00

3,282.00

10/2009

03/2010

05/2010

1,942.51

1,942.51

05/2011

05/2011

08/2011

4,904.54

4,904.54

08/2012

09/2012

08/2012

-1

2,161.28

2,295.93

06/2009

02/2010

03/2010

1,268.53

1,943.66

03/2010

03/2010

03/2014

48

3,316.00

3,534.00

12/2010

10/2011

12/2011

5,185.00

6,146.00

05/2011

09/2012

03/2013

6,133.00

8,128.00

02/2011

03/2012

03/2013

12

12,138.00

14,439.00

09/2009

02/2010

03/2010

1,436.21

1,436.21

07/2010

05/2010

05/2012

24

1,779.29

1,896.65

11/2008

02/2010

03/2010

596.45

1,007.16

12/2007

03/2010

06/2010

2,570.44
4,375.35

2,570.44
4,375.35

08/2010
07/2011

08/2010
11/2011

11/2010
02/2012

3
3

1,405.63

1,405.63

08/2010

08/2010

12/2010

11

VIII. List of projects reporting additional delays


Cost ( Rs. Crore)
Project name
WESTERN REGION
STRENGTHENING SCHEMEII
KORBA STPP STAGE-III
PARBATI H.E.P. STAGE -III
(NHPC)
VISHNUGAD PIPALKOTI
HYDRO ELECTRIC PROJECT
Railways
TOLLYGANJ-GARIA(MTP)
UDHAMPUR-SRINAGARBARAMULLA (NL),NR

DOC reported

Delay

Original
5,221.23

Anticipated
5,221.23

Original
07/2010

Last month
07/2010

This month
12/2010

2,448.50
2,304.56

2,448.49
2,304.52

02/2010
10/2010

02/2010
11/2010

08/2010
06/2011

6
7

2,491.58

2,491.58

06/2013

06/2013

03/2015

21

907.69
2,500.00

1,032.76
11,270.00

12/2006
03/2001

03/2010
12/2012

06/2010
12/2017

3
60

Number of projects reporting additional delay =

22

12

(in months)
5

Sectorwise analysis of projects


Number of
Sector
Atomic Energy
Civil Aviation
Coal
Mines
Steel
Petroleum
Power
Railways
Shipping & Ports
Telecommunications
Urban Development
Water Resources
Grand total

projects

Cost (Rs. Crore)

5
3
8
1
6
39
38
16
6
2
2
1

Original
25,054.29
5,023.51
15,236.55
4,091.51
39,671.00
133,986.06
147,515.35
20,018.55
11,934.87
2,974.69
14,513.00
542.90

Latest
25,054.29
4,962.51
16,305.90
4,091.51
39,671.00
143,666.19
149,329.43
27,430.67
11,934.87
2,974.69
16,763.36
542.90

Anticipated
26,308.29
5,023.51
17,431.69
4,091.51
46,381.00
154,858.59
151,241.71
42,804.26
11,995.27
2,974.69
15,071.00
1,187.00

127

420,562.28

442,727.32

479,368.52

13

(Feb,2010)

Date of
Commissioning

S.No Project
1

Date of
Approval

Original /
Revised
Cost

Anticipated
Cost

Delay
w.r.t.
Original Milestones
Cumm.
Achieved/
(in
Expendi- Original / AnticiTotal
ture
Revised pated months)
6

10

Atomic Energy
1 RAJASTHAN ATOMIC POWER
PROJECT 5 and 6 (NPCIL) [020100042]

04/2002

3,072.00
-

3,072.00

2,133.00

02/2008
-

03/2010

25(O)

73/75

2 KAIGA 3 and 4 UNITS (NPCIL) [020100041]

05/2001

4,213.00
-

3,282.00

2,515.00

10/2009
09/2007

05/2010

32(R1)

71/75

3 KUDANKULAM APP (NPCIL) [020100040]

12/2001

13,171.00
-

13,171.00

12,614.00

12/2008
-

03/2011

27(O)

61/119

4 URANIUM ORE MINE & PROCESSING


PLANT AT TUMMALAPALL [N02000007]

09/2007

1,106.29
-

1,106.29

486.37

04/2011
-

04/2011

0(O)

0/0

5 PROTOTYPE FAST BREEDER


REACTOR (BHAVINI, 500 MWE) [020100044]

09/2003

3,492.00
-

5,677.00

2,288.38

09/2010
-

09/2011

12(O)

8/80

25,054.29
-

26,308.29

20,036.75

Total

213/349

Civil Aviation
6 D/O KAMARAJ DOMESTIC TER-PH-II &
EXP. ANNA INT. TE - [N04000038]

08/2008

1,273.00
1,212.00

1,273.00

255.24

01/2011
-

01/2011

0(O)

0/0

7 DEV. OF KAMRAJ DOMESTIC


CHENNAI AIRPORT - [N04000056]

08/2008

1,808.00
-

1,808.00

523.27

01/2011
-

01/2011

0(O)

0/0

8 C/O INTEGRATED PASSENGER TER.


BULD. NSCBI AIRPORT - [N04000037]

08/2008

1,942.51
-

1,942.51

539.43

05/2011
-

08/2011

3(O)

0/0

5,023.51
-

5,023.51

1,317.94

Total

0/0

Coal
9 EXPANSION OF MINE-II (10.5 MTPA
TO 15.0 MTPA) (NLC) - [060100088]

10/2004

2,161.28
2,295.93

2,295.93

1,789.91

06/2009
-

03/2010

9(O)

29/23

10 GEVRA EXPANSION OCP (SECL) (25


MTY) - [060100093]

07/2005

1,667.55
-

1,667.55

961.42

03/2010
-

03/2010

0(O)

3/7

11 BARSINGSAR TPS (2X125MW) (NLC) [060100089]

12/2004

1,114.18
1,626.09

1,626.09

1,385.97

06/2009
-

09/2010

15(O)

32/26

12 TPS-II EXPANSION (1470MW TO


1970MW) (NLC) - [060100087]

10/2004

2,030.78
2,453.57

2,453.57

1,919.29

06/2009
-

06/2011

24(O)

23/24

13 TUTICORIN THERMAL POWER


PROJECT - [N06000047]

05/2008

4,904.54
-

4,904.54

572.16

08/2012
-

08/2012

0(O)

0/0

14 KUSMUNDA
EXPN.OCP(SECL)(10MTY) [N06000008]

06/2006

737.65
-

1,188.31

582.38

03/2011
03/2013

03/2013

0(R3)

0/4

15 DIPKA EXPANSION OCP (SECL) (20


MTY) - [060100094]

07/2005

1,268.53
-

1,943.66

765.78

03/2010
-

03/2014

48(O)

2/6

16 AMLOHRI EPR (NCL) (6 MTY) [N06000010]

05/2006

1,352.04
-

1,352.04

26.99

03/2014
-

03/2014

0(O)

1/1

15,236.55
-

17,431.69

8,003.90

Total

Mines

14

90/91

(Feb,2010)

Date of
Commissioning

Date of
Approval

S.No Project
1

2
17 SECOND PHASE EXPANSION OF
CAPTIVE ALUMINIUM,SMELTER AND
POWE - [100100054]

3
10/2004

Total

Original /
Revised
Cost
4

Anticipated
Cost
5

Delay
w.r.t.
Original Milestones
Cumm.
Achieved/
Expendi- Original / Antici(in
Total
ture
Revised pated months)
6

4,091.51
-

4,091.51

3,316.00

4,091.51
-

4,091.51

3,316.00

12/2008
-

11/2009

9
11(O)

10
18/111

18/111

Steel
18 EXPANSION OF SALEM STEEL PLANT
- [N12000050]

01/2008

1,902.00
-

1,902.00

1,358.80

03/2010
-

06/2010

3(O)

0/0

19 EXPANSION OF RINL/VSP FROM 3


MTPY-6.3 MTPY OF LIQUID STEEL [120100067]

10/2005

8,692.00
-

12,228.00

5,523.00

10/2009
-

06/2011

20(O)

0/126

20 EXPANSION OF IISCO STEEL PLANT [N12000051]

02/2008

14,443.00
-

14,443.00

6,545.80

07/2010
-

06/2011

11(O)

0/0

21 EXPANSION OF BOKARO STEEL


PLANT - [N12000055]

01/2008

3,316.00
-

3,534.00

932.87

12/2010
-

12/2011

12(O)

0/0

22 EXPENSION OF ROURKELA STEEL


PLANT - [N12000056]

09/2008

6,133.00
-

8,128.00

1,253.17

02/2011
-

03/2013

25(O)

0/0

23 EXPANSION OF BHILAI STEEL PLANT


- [N12000057]

09/2008

5,185.00
-

6,146.00

1,474.84

05/2011
-

03/2013

22(O)

0/0

39,671.00
-

46,381.00

17,088.48

Total

0/126

Petroleum
24 CLEAN FUELS PROJECT AT VISAKH
REFINERY(HPCL) - [160100281]

04/2003

1,635.00
-

2,147.79

2,095.36

05/2006
-

12/2009

43(O)

29/45

25 CRUDE OIL RECEIPT


FACILITIES,KOCHI REFINERY [N16000028]

04/2006

2,591.80
-

3,941.41

1,793.00

09/2009
-

12/2009

3(O)

0/0

26 MSQ UPGRADATION PROJECT AT


PANIPAT REFINERY - [N16000035]

01/2008

1,131.00
-

1,131.00

750.71

12/2009
-

01/2010

1(O)

0/0

27 INST. OF FACILITIES FOR


IMPROVEMENT IN DIESEL QUALITY
(IOCL) - [160100289]

11/2005

1,876.00
2,869.00

2,869.00

2,550.34

04/2009
12/2009

02/2010

2(R1)

31/36

28 CAPACITY EXP. CUM


MODERNISATION PH-II - [N16000080]

09/2009

2,591.80
3,941.41

3,941.41

2,176.19

12/2009
-

02/2010

2(O)

0/0

29 PANIPAT NAPHTA CRACKER


PROJECT - [160100292]

04/2006

12,138.00
-

14,439.00

11,284.00

09/2009
11/2009

03/2010

4(R1)

61/101

30 VIJAPUR DADRI-BAWANA PIPE LINE


PROJECT - [N16000048]

11/2007

5,595.31
-

3,860.00

3,114.04

11/2009
04/2010

04/2010

0(R3)

0/0

31 DEVELOPMENT OF C-SERIES FIELDS


- [N16000023]

08/2006

3,195.16
-

2,800.00

1,557.81

12/2008
-

05/2010

17(O)

0/0

32 LUBDE OIL BASE STOCK QUALITY


UPGRADATION AT MUMBAI [N16000026]

10/2006

638.90
-

1,030.00

576.32

04/2009
-

05/2010

13(O)

0/0

33 DIESEL HYDRO TREATMENT


PROJECT,BRPL DHALIGAON [N16000009]

06/2006

1,431.91
-

1,675.72

1,218.02

09/2009
-

06/2010

9(O)

0/0

34 RESIDUE UPGRADATION AND


MS/HSD QUALITY IMPROVEMENT [N16000021]

01/2007

5,693.00
-

6,898.00

5,086.94

01/2010
-

06/2010

5(O)

0/0

15

(Feb,2010)

Date of
Commissioning

Date of
Approval

S.No Project
1

Original /
Revised
Cost
4

Anticipated
Cost

35 HEERA AND SOUTH HEERA REDEVELOPMENT PROJECT [N16000024]

09/2006

2,305.30
-

2,305.30

1,144.34

06/2010
06/2010

06/2010

0(R1)

0/0

36 MSQ UPGRADATION PROJECT AT


BARAUNI REFINERY - [N16000038]

04/2008

1,492.00
-

1,492.00

795.50

04/2010
-

06/2010

2(O)

0/0

37 C2-C3 AND LPG RECOVERY FROM


LNG, DAHEJ (ONGC) - [160100168]

12/2003

900.92
-

1,493.49

595.34

06/2006
05/2008

07/2010

26(R1)

0/2

38 EXPANSION OF PANIPAT REFINERY


FROM 12 TO 15 MMTPA - [N16000017]

06/2005

806.00
1,007.83

1,007.83

593.33

03/2008
12/2009

08/2010

8(R1)

18/48

39 BAWANA NANGAL PIPE LINE


PROJECT - [N16000050]

10/2010

1,816.07
-

1,816.07

10/2010
-

10/2010

0(O)

0/0

40 DAHEJ-VIJAYPUR PIPE LINE


PROJECT - [N16000052]

11/2007

4,429.38
-

3,000.00

10/2010
-

10/2010

0(O)

0/0

41 COMPRESSOR STATIONS (VIJAYPUR


AND JHABUA) PHASE-I - [N16000053]

11/2007

1,512.00
-

1,212.85

10/2011
-

10/2010

-12(O)

0/0

42 IOR GELEKI (ONGCL) - [160100216]

09/2001

390.09
834.90

1,200.00

987.26

03/2007
03/2011

03/2011

0(R3)

6/6

43 MUMBAI HIGH SOUTH


REDEVELOPMENT PH-2 - [N16000039]

06/2007

1,252.75
-

8,061.42

3,818.71

06/2009
-

04/2011

22(O)

0/0

44 COMPRESSOR STATIONS (KAILARAS


&CHAINSA) - [N16000054]

11/2007

1,061.93
-

1,061.78

11/2011
-

04/2011

-7(O)

0/0

45 INTEGRATED DEV OF G1 and GS-15


(ONGCL) - [160100231]

04/2003

429.82
1,262.93

1,262.93

1,231.40

03/2005
-

05/2011

74(O)

0/0

46 DIESEL HYDROTREATOR PROJECT


AT VISAKH REFINERY - [N16000068]

03/2009

3,597.00
-

3,597.00

49.88

09/2011
-

09/2011

0(O)

0/0

47 DIESEL HYDROTREATOR PROJECT


AT MUMBAI REFINERY - [N16000069]

03/2009

3,284.00
-

3,284.00

54.39

09/2011
-

09/2011

0(O)

0/0

48 ADDITIONAL GAS PROCESSING


UNITS AT URAN - [N16000064]

10/2008

1,797.35
-

1,797.35

12/2011
-

12/2011

0(O)

0/0

49 ADDITIONAL DEV. OF D-1 FIELD [N16000086]

01/2010

2,163.64
-

2,163.64

12/2011
-

12/2011

0(O)

0/0

50 DEVELOPMENT OF B-193 CLUSTER


FIELDS - [N16000033]

06/2007

3,248.78
5,633.44

5,633.44

0.61

03/2010
08/2010

03/2012

19(R1)

0/0

51 Integrated crude Oil handling facilities at


Paradip - [N16000090]

12/2009

1,492.33
-

1,492.33

18.70

06/2012
-

03/2012

-3(O)

0/0

52 DEVELOPMENT OF B-22 CLUSTER


FIELDS - [N16000032]

01/2007

1,552.63
-

2,920.82

5.24

02/2009
09/2010

04/2012

19(R1)

0/0

53 CONSTRUCTION OF NEW PROCESS


COMPLEX MHN - [N16000030]

01/2007

2,853.29
6,326.40

6,326.40

188.14

05/2010
-

05/2012

24(O)

0/0

54 DEVELOPMENT OF B-46 CLUSTER


FIELD - [N16000046]

06/2007

1,436.21
-

1,436.21

07/2010
-

05/2012

22(O)

0/0

55 MUMBAI HIGH NORTH


DEVELOPMENT PHASE-II [N16000060]

01/2009

6,855.93
-

6,855.93

478.71

09/2012
-

09/2012

0(O)

0/0

56 Paradip-Sambalpur-Raipur-Ranchi
Pipeline - [N16000088]

08/2009

1,793.00
-

1,793.00

5.76

09/2012
-

09/2012

0(O)

0/0

57 PARADIP REFINERY PROJECT [N16000058]

02/2009

29,777.00
-

29,777.00

3,212.29

03/2012
-

11/2012

8(O)

0/0

58 KOCHI-KANJIRKOD BANGALOREMANGALORE PIPELINE PROJE [N16000071]

06/2009

3,032.00
-

3,032.00

12/2012
-

12/2012

0(O)

0/0

16

Delay
w.r.t.
Original Milestones
Cumm.
Achieved/
Expendi- Original / Antici(in
Total
ture
Revised pated months)
6

10

(Feb,2010)

Date of
Commissioning

Date of
Approval

S.No Project
1

Original /
Revised
Cost
4

Anticipated
Cost
5

Delay
w.r.t.
Original Milestones
Cumm.
Achieved/
Expendi- Original / Antici(in
Total
ture
Revised pated months)
6

12/2012
-

12/2012

0(O)

0/0

12/2012

0/0

01/2013
-

01/2013

0(O)

0/0

2,378.86

36.27

03/2013
-

03/2013

0(O)

0/0

133,986.06
-

154,858.59

45,420.11

59 DHABOL-BANGALORE PIPELINE
PROJECT - [N16000073]

06/2009

4,543.43
-

4,543.43

60 De-bottlenecking of SMPL [N16000089]

12/2009

1,584.00
-

1,584.00

1.51

61 JAGDISHPUR-HALDIA PIPELINE
PROJECT - [N16000072]

07/2009

7,596.18
-

7,596.18

62 ASSAM RENEWAL PROJECT FOR


GROUP A - [N16000061]

03/2009

2,465.15
-

Total

10

145/238

Power
63 SEWA- II H.E.P (NHPC) - [180100220]

09/2003

665.46
-

1,016.74

950.76

09/2007
-

03/2010

30(O)

8/36

64 KUNADANKULAM-APP TRANS.
SYSTEM (PGCIL) - [180100258]

05/2005

1,779.29
-

1,896.65

1,511.39

11/2008
-

03/2010

16(O)

20/38

65 TRANSMISSION SY. ASSOCIATED


WITH BARH GENER. PROJECT(P.GR.)
- [180100260]

12/2005

3,779.46
-

3,779.46

3,257.17

09/2009
-

03/2010

6(O)

11/30

66 KAIGA 3&4 TRANSMISSION SYSTEM


(PGCIL) - [180100246]

03/2005

596.45
1,007.16

1,007.16

725.60

12/2007
-

06/2010

30(O)

7/18

67 KORBA STPP STAGE-III - [N18000011]

08/2006

2,448.50
-

2,448.49

1,805.10

02/2010
-

08/2010

6(O)

3/24

68 National Capital Thermal Power Project


Stage-II - [N18000013]

10/2006

5,135.33
-

5,135.33

3,676.30

10/2010
-

10/2010

0(O)

9/40

69 Farakka STPP Stage-III - [N18000016]

07/2006

2,570.44
-

2,570.44

1,529.40

08/2010
-

11/2010

3(O)

11/26

70 KOTESHWAR HEP(THDC) [180100184]

04/2000

1,301.56
-

1,301.56

1,667.43

04/2005
-

12/2010

68(O)

0/0

71 CHAMERA,STAGE-III (NHPC) [180100241]

08/2005

1,405.63
-

1,405.63

1,112.84

08/2010
-

12/2010

4(O)

0/0

72 WESTERN REGION STRENGTHENING


SCHEME-II - [N18000022]

07/2006

5,221.23
-

5,221.23

2,027.32

07/2010
-

12/2010

5(O)

2/20

73 TESSTA LOW DAM STAGE - II, III


(NHPC) - [180100222]

10/2003

768.92
-

1,279.40

1,064.60

03/2007
-

02/2011

47(O)

1/25

74 URI H.E.P STAGE -II (NHPC) [180100251]

08/2005

1,729.29
-

1,724.79

1,021.16

11/2009
-

02/2011

15(O)

0/0

75 SIMHADRI STPP STAGE -II [N18000032]

08/2007

5,103.39
-

5,038.53

2,529.30

05/2011
-

05/2011

0(O)

0/0

76 PARBATI H.E.P. STAGE -III (NHPC) [180100250]

10/2005

2,304.56
-

2,304.52

942.29

10/2010
-

06/2011

8(O)

0/0

77 TEESTA LOW DAM HEP, STAGE-IV


(NHPC) - [180100243]

09/2005

1,061.38
-

1,307.03

670.98

09/2009
-

08/2011

23(O)

0/0

78 SIPAT STPP STAGE - I (NTPC) [180100229]

12/2003

8,323.39
-

8,323.39

6,571.00

12/2009
-

10/2011

22(O)

33/56

79 KOLDAM HEP (NTPC) - [180100211]

10/2002

4,527.15
-

4,527.15

3,008.50

04/2009
-

12/2011

32(O)

19/41

80 BONGAIGAON THERMAL POWER


PROJECT - [N18000041]

01/2008

4,375.35
-

4,375.35

831.30

07/2011
-

02/2012

7(O)

0/0

81 765 KV SYSTEM FOR CENTRAL PART


OF NORTHERN GRID PA [N18000068]

02/2009

1,347.32
-

1,347.32

163.56

02/2012
-

02/2012

0(O)

0/0

17

(Feb,2010)

Date of
Commissioning

Date of
Approval

S.No Project
1

Original /
Revised
Cost

82 RAMPUR HEP(412 MW) - [N18000024]

01/2007

2,047.03
-

2,047.03

771.30

01/2012
-

03/2012

2(O)

2/10

83 MOUDA STPP - [N18000048]

11/2007

5,459.28
-

5,459.28

764.60

02/2012
-

08/2012

6(O)

0/0

84 SUPPLIMENTARY TRANSMISSION
ASSOCIATED WITH DVC AND [N18000065]

08/2008

2,360.95
-

2,360.95

765.72

08/2012
-

08/2012

0(O)

0/0

85 765 KV POOLING STATION &


NETWORK WITH DVC AND MAIT [N18000069]

08/2008

7,075.33
-

7,075.33

1,526.62

08/2012
-

08/2012

0(O)

0/0

86 TR. SYSTEM ASSOCIATED WITH


MUNDRA ULTRA MEGA POWER [N18000061]

10/2008

4,824.12
-

4,824.12

304.68

10/2012
-

10/2012

0(O)

0/0

87 VINDHYACHAL STTP STAGE-IV [N18000072]

01/2009

5,915.00
-

5,915.00

484.80

11/2012
-

11/2012

0(O)

0/0

88 RIHAND STTP STAGE-III (2X500MW) [N18000073]

01/2009

6,230.81
-

6,230.81

425.23

11/2012
-

11/2012

0(O)

0/0

89 LOWER SUBANSIRI H.E.P (NHPC) [180100221]

09/2003

6,285.33
-

6,285.33

3,751.11

09/2010
-

12/2012

27(O)

2/11

90 LOHARINAG-PAL HEP(4X150MW) [N18000005]

06/2006

2,895.10
-

2,895.10

552.33

11/2011
-

12/2012

13(O)

6/34

91 TRANSMISSION SYSTEM
ASSOCIATED WITH SASAN ULTRA
ME - [N18000046]

12/2008

7,031.88
-

7,031.88

440.03

12/2012
-

12/2012

0(O)

0/0

92 PARBATI HEP (NHPC) II - [180100210]

09/2002

3,919.59
-

3,919.59

2,710.83

09/2009
-

03/2013

42(O)

1/20

93 Tapovan-Vishnugad HEP (4x130MW) [N18000014]

11/2006

2,978.48
-

2,978.48

733.50

03/2013
-

03/2013

0(O)

5/31

94 TEHRI PUMPED STORAGE


PLANT(1000MW) - [N18000010]

07/2006

1,657.00
-

1,657.60

243.51

07/2010
-

04/2013

33(O)

0/0

95 KAMENG HYDROELECTRIC PROJECT


(NEEPCO) - [180100239]

12/2004

2,496.90
-

3,253.22

1,077.81

05/2013
-

05/2013

0(O)

37/161

96 BARH STPP STAGE -II - [N18000047]

02/2008

7,341.04
-

7,341.04

658.40

08/2013
-

08/2013

0(O)

0/0

97 NORTH- EAST NORTH WESTERN


INTERCONNECTOR I PROJECT [N18000066]

02/2009

11,130.19
-

11,130.19

482.60

08/2013
-

08/2013

0(O)

0/0

98 BARH STPP(3X660MW) NTPC [180100242]

12/2003

8,692.97
-

8,692.97

4,626.50

11/2010
-

10/2013

35(O)

15/51

99 VISHNUGAD PIPALKOTI HYDRO


ELECTRIC PROJECT - [N18000042]

08/2008

2,491.58
-

2,491.58

98.10

06/2013
-

03/2015

21(O)

0/0

100 KISHANGANGA HEP - [N18000031]

07/2007

2,238.67
3,642.04

3,642.04

245.85

07/2014
-

01/2016

18(O)

0/0

147,515.35
-

151,241.71

55,729.52

Total

Anticipated
Cost
5

Delay
w.r.t.
Original Milestones
Cumm.
Achieved/
Expendi- Original / Antici(in
Total
ture
Revised pated months)
6

10

192/672

Railways
101 CONV.OF 1500V DC TRACTION TO 25
KV AC,WR - [220100233]

07/1996

273.67
654.51

1,160.52

434.32

102 TOLLYGANJ-GARIA(MTP) [220100268]

03/2000

907.69
-

1,032.76

1,006.89

18

06/2010

12/2006
-

06/2010

42(O)

0/0
0/0

(Feb,2010)

Date of
Commissioning

Date of
Approval

S.No Project
1

Original /
Revised
Cost
4

Anticipated
Cost
5

Delay
w.r.t.
Original Milestones
Cumm.
Achieved/
Expendi- Original / Antici(in
Total
ture
Revised pated months)
6

12/2010
-

12/2010

0(O)

0/0

02/2011

0/0

1,965.78

03/2009
-

03/2012

36(O)

0/0

1,480.71

445.84

10/2007
-

12/2012

62(O)

0/0

912.70
915.70

1,556.23

158.87

03/2013

04/1996

1,000.00
1,500.00

3,087.44

1,682.94

04/2008
12/2011

03/2014

27(R1)

0/0

109 MAYNAGURI TO JOGIGHOPA VIA


CHANGRA (NL),NEFR - [220100266]

02/2000

733.00
733.00

1,502.29

424.34

12/2008
-

03/2014

63(O)

0/0

110 MUMBAI URBAN TRANSPORT


PROJECT PHASE-II - [N22000092]

04/2008

5,300.00
-

5,300.00

120.00

03/2014
-

03/2014

0(O)

0/0

111 SEVOK RANGPO - [N22000102]

04/2008

1,339.48
-

1,339.48

12/2015
-

12/2015

0(O)

0/0

112 JIRIBAM TO IMPHAL


(TUPUI)(NL)(NEFR) - [220100288]

04/2003

727.56
727.53

2,492.53

129.76

03/2011
-

03/2016

60(O)

0/0

113 UDHAMPUR-SRINAGAR-BARAMULLA
(NL),NR - [220100133]

03/1995

2,500.00
8,000.00

11,270.00

5,956.55

03/2001
-

12/2017

201(O)

0/0

114 KODERMA-RANCHI VIA


BARKAKHANA (NL),ECR - [220100222]

03/1999

491.19
-

1,099.20

540.09

07/2005
-

0/0

115 RAMGANJMUNDI-BHOPAL (NL),WCR [220100314]

04/2001

727.13
727.13

1,225.00

109.16

0/0

116 AHMEDNAGAR-PARLI VAIJNATH(NL)


CR - [220100181]

02/1997

353.08
353.08

1,010.00

45.16

12/2012

12/2012

20,018.55
-

42,804.26

16,281.35

103 MUMBAI URBAN TRANSPORT


PROJECT PHASE-I - [N22000093]

04/2003

3,125.20
-

4,174.00

3,182.58

104 KHURDA ROAD-BOLANGIR(NL)ECOR


- [220100284]

04/1994

355.38
-

1,000.00

79.07

105 LUMDING-SILCHAR(GC),NEFR [220100170]

04/1996

648.00
1,676.31

4,074.10

106 PATNA GANGA BRIDGE (NL), ECR [220100308]

04/2001

624.47
-

107 RANGIA-MURKONGSELEK, (GC)


NEFR - [220100315]

01/2004

108 BRAHAMAPUTRA BRIDGE AT


BOGIBIL & LINK LINES,NEFR [220100201]

Total

10

0(R3)

0/0

0/0
0/0

Shipping & Ports


117 ACQUISITION OF 6 NOS. 60470 DWT
LR-I PRODUCT TANKE - [N25000029]

10/2006

1,658.59
-

1,658.59

318.24

07/2010
-

07/2010

0(O)

0/0

118 SETHUSAMUDRAM SHIP CHANNEL


PROJECT - [250100175]

06/2005

2,427.40
-

2,427.40

813.75

10/2008
-

11/2010

25(O)

0/0

119 Acquisition of two nos. of 120 B.P [N25000042]

04/2009

2,908.48
-

2,908.48

58.18

03/2011
-

06/2011

3(O)

0/0

120 ACQUISITION OF 4 NOS. OF 115000


DWT CRUDE OIL CARR - [N25000032]

08/2008

1,108.12
-

1,168.42

374.36

04/2011
-

12/2011

8(O)

0/0

121 Acquisition of Two nos. of 3060 DWT [N25000043]

04/2009

2,770.32
-

2,770.42

554.06

09/2011
-

12/2011

3(O)

0/0

122 ACQUISITION OF 6 NOS. OF 57000


DWT HANDYMAX BULK C [N25000033]

11/2007

1,061.96
-

1,061.96

219.98

03/2012
-

01/2012

-2(O)

0/0

11,934.87
-

11,995.27

2,338.57

Total

Telecommunications

19

0/0

(Feb,2010)

Date of
Commissioning

Date of
Approval

S.No Project
1

Original /
Revised
Cost

123 GSM EQUIPMENT OF 3125K


LINES(2G) AND 625K LINES(3 [N26000043]

09/2008

1,799.94
-

1,799.94

73.54

09/2009
-

06/2010

124 GSM EXPANSION PH.IV (B) (BSNL)


MAHARASHTRA - [260100095]

07/2005

1,174.75
-

1,174.75

371.41

03/2006
-

2,974.69
-

2,974.69

444.95

Total

Anticipated
Cost
5

Delay
w.r.t.
Original Milestones
Cumm.
Achieved/
Expendi- Original / Antici(in
Total
ture
Revised pated months)
6

10

9(O)

0/0

0/0
0/0

Urban Development
125 DELHI MRTS PHASE-II PROJECT [280100002]

08/2005

8,118.00
8,605.36

8,676.00

12,228.48

06/2010
-

10/2010

4(O)

0/7

126 BANGALORE METRO RAIL PROJECT


- [N28000008]

05/2006

6,395.00
8,158.00

6,395.00

1,636.20

12/2011
09/2012

12/2011

-9(R3)

0/1

14,513.00
-

15,071.00

13,864.68

542.90
-

1,187.00

35.49

542.90
-

1,187.00

35.49

0/0

420,562.28

479,368.52

183,877.74

658/1595

Total

0/8

Water Resources
127 PAGLADIYA DAM PROJECT [300100001]
Total

Grand Total

01/2001

20

12/2007
-

12/2012

60(O)

0/0

You might also like