API 570 Course Model Test 9
API 570 Course Model Test 9
API 570 Course Model Test 9
API RP 578
A material manufacturer
A distributor
A fabricator
A owner/user
366
6. An organization that supplies materials furnished and certified by a material manufacturer, but does not
perform any operation intended to alter the material properties required by the applicable material
specification is a _______________.
A.
B.
C.
D.
distributor.
fabricator.
material supplier.
material manufacture.
7. Who has the responsibility to determine the extent of examination required and to verify the material
verification program is performed in accordance with RP 578?
A.
B.
C.
D.
engineer
owner/user or designee
Tim Schindler
material supplier
8. Review and approval of the material verification program and testing procedure of the fabricator or material
supplier should be done:
A.
B.
C.
D.
10. Which of the following is an example of a pressure-containing component that makes up a fabricated
piping system covered in the Material Verification Program?
A.
B.
C.
D.
Instruments
dummy legs
spring cans
none of the above
11. Verification of the alloy materials subsequently placed into service are as specified is a responsibility of:
A.
B.
C.
D.
Authorized inspector
Engineer
Owner/User or designee
None of the above
12. You have received a shipment of alloy electrodes and wire from your supplier. How much PMI testing
should you perform?
A.
B.
C.
D.
Positively identify two electrodes or wire samples from each lot or package.
Positively identify one electrode or wire sample from each lot or package.
As determined by the owner/user
No testing is required.
367
13. A new section of seamed (longitudinal) alloy pipe is to be used for repairs and requires PMI testing, where
should PMI testing be performed?
A. PMI the weld metal only.
B. PMI the base metal only.
C. PMI the base metal and weld metal
D. No testing is required. You only need to verify the correct ASTM markings are on the pipe.
14. The lead inspector (owner/user) has decided to prioritize existing piping systems in the crude unit for PMI
testing. Which is a consideration for prioritization?
A. How lucky he feels.
B. Likelihood of Failure
C. Consequence of failure
D. Both A and B
15. The greatest Number of material non conformities with serious consequence have involved carbon steel
components in ____________________________
A. non ferrous systems.
B. stainless steel systems.
C. low alloy systems.
D. non metallic systems.
16. ___________________ should be considered when determining the extent of PMI testing for existing units.
A.
B.
C.
D.
368
369
ANSWER SHEET
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
C, 1.1
C, 1.1
B, 1.1
C, 3
A, 3
C, 3
B, 4.2.1
A, 4.2.2
C, 4.2.4
A, 4.2.5
C, 4.2.1
B, 4.2.6
C, 4.2.6.1
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
24.
25.
26.
370
C, 4.3.2
C, 4.3.2.1
C, 4.3.4
D, 4.3.3
D, 5.3
A, 5.3
D, 5.5
C, 5.6
D, 6.1
C, 6.1
B, 6.3
D, 7.2
A, 7.4