Volume 04

Download as pdf or txt
Download as pdf or txt
You are on page 1of 83

Section A - Contents

Schools Complex & Staff Housing at Al Khiysa Umm Salal Doha Qatar

Schools Complex & Staff Housing


For
Al Andalus Schools
At
At Al Khiysa Umm Salal - Doha Qatar

Volume 4
Parcel 2 Secondary School BOQ

December 2014
2014
Contents/(2)

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF HOUSING
at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

RATE
QR

AMOUNT
QR

SUBSTRUCTUR WORKS
A.EXCVATION WORKS AND EARTH
WORKS
Note:-Excavation and earthworks quantites
have been based upon an average existing site
level of 0.00 the contractor is deemed to have
visited the site and made aware of the
conditions and charcter of the site, nature of
the ground, existing levels etc and satisfied
himself with the ground, existing levels etc
and satisfied himself with extent of the works
evisaged in this section
A

strip surface of site mm deep and remove


stripped material from site

m2

9,702

Excavate to receive foundations level

m3

14,555

Disposal
C

Removing surplus excavated materials from


site

m3

7,130

Backfill selected excavated material


compacted in layers arround foundations

m3

7,425

m3

4,749

item

item

Filling
E

Filling to make up levels with imported fill


material or selected excavated material
compacted in layes to Engineer's approval
Protection

all for protecting all work in this section


ANTI-TERMITE TREATMENT

allow for carrying out termite control


treatment as specified

To summary Q.R
SUB - STRUCTURE

S.B/Page1/5

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF HOUSING
at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

m2

2770

RATE
QR

AMOUNT
QR

Concrete Works
The Contractor is referred to the Specifications
and Drawings for all details related to this
Section of the works and he is to include for
complying with all the requirements contained
therein
For tanks all details and sizes are according to
the drawings and the electro-mechanics work
specifications and the consultant approval.
Structural Drawings shall be read in
conjunction with all relevant architectural,
civil and services drawings and specifications.
Discrepancies shall be brought to the notice of
the Engineer.
The Contractor shall be responsible for the
proper setting out of the works , correctness of
line, levels and for quality control of materials.
The approval of the Consultants Engineer
(The Engineer) shall not in any way relieve
the Contractor of his responsibility and any
errors rectified by the Contractor to the
approval of the Engineer at no cost to the
contract.
All materials shall be as per Engineers
satisfaction and approval. All material
submittals shall be approved by the Engineer
in writing.
All testing shall be at Contractors expenses
and shall be carried out at independent testing
laboratory approved by the Engineer
All drainage lines or sleeves and any other
services shall be laid before casting of the raft
foundation and/or the ground floor slab.
The contractor must refer to service engineers
drawings for positions of all cast in items and
also provide details of how the items are cast
in.
SUBSTRUCTRUE WORKS
plain in- situ concrete Grade 20 SRC
A

100 mm Blinding

To summary Q.R

SUB - STRUCTURE

S.B/Page2/5

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF HOUSING
at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

Item

RATE
QR

AMOUNT
QR

plain in- situ concrete Grade 20 SRC


(Cont'd)
A

50mm Blinding laid to slope exceeding 15


degree from horizontal including any
nessecary work
Reinforced In-situ SRC + 8 % micro silica
concrete Grade 40

Isolated foundation

m3

1,641

Ground beams

m3

528

Beds,Sloping(Ramps) exceeding 15 degree


from horizontal

Item

Slab on grade

m3

1,100

Reinforced In-situ SRC + 8 % micro silica


concrete Grade 50
F

columns

m3

32

walls

m3

13

Kg

189,048

m2

11,000

Reinforcement
high yield steel reinforcing bas of minimum
strenth 460 N/mm2 as specified
H

Reinforcing Bars In various diameters


Fabric reinforcment mesh to Bs 4483

Ref.A393

To summary Q.R
SUB - STRUCTURE

S.B/Page3/5

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF HOUSING
at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

RATE
QR

AMOUNT
QR

Formwork
A

to vertical side of foundations,ground beams


and the like

m2

6,687

to edges of beds.

m2

369

to vertical side of Coulmns

m2

312

to vertical sides of walls

m2

65

m2

7,106

m2

9,486

L.M

457

m2

880

SUNDRIES
1000 Gauge polyethene sheets
E

to vertical surfaces and horizontal surfaces of


concrete
Prepare and apply two coats bituminous
paint,
to horizontal & Vertical surfaces of concrete

Expantion Joints
G

Allow for all expansion joints and


construcation joint as specified
BLOCKWORK
Hollow concrete block to BS 6073 part 1 made
with sulphate resisting cement : bedding and
jointing in class M6 mortar with sulphate
resisting cement as specified

200 mm thick walls

To summary Q.R
SUB - STRUCTURE

S.B/Page4/5

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF HOUSING
at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

RATE
QR

AMOUNT
QR

COLLECTION

Page S.B/1/5
Page S.B/2/5
Page S.B/3/5
Page S.B/4/5

TOTAL CARRIED TO DIVISION


SUMMARY
SUB - STRUCTURE

S.B/Page5/5

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF HOUSING
at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

RATE
QR

AMOUNT
QR

SUPERSTRUCTURE
Concrete Works
The Contractor is referred to the
Specifications and Drawings for all details
related to this Section of the works and he is
to include for complying with all the
requirements contained therein
For tanks all details and sizes are according to
the drawings and the electro-mechanics work
specifications and the consultant approval.
Structural Drawings shall be read in
conjunction with all relevant architectural,
civil and services drawings and
specifications. Discrepancies shall be brought
to the notice of the Engineer.
The Contractor shall be responsible for the
proper setting out of the works , correctness
of line, levels and for quality control of
materials. The approval of the Consultants
Engineer (The Engineer) shall not in any way
relieve the Contractor of his responsibility
and any errors rectified by the Contractor to
the approval of the Engineer at no cost to the
contract.
All materials shall be as per Engineers
satisfaction and approval. All material
submittals shall be approved by the Engineer
in writing.
All testing shall be at Contractors expenses
and shall be carried out at independent testing
laboratory approved by the Engineer
All drainage lines or sleeves and any other
services shall be laid before casting of the raft
foundation and/or the ground floor slab.
The contractor must refer to service
engineers drawings for positions of all cast in
items and also provide details of how the
items are cast in.
Reinforced In-situ OPC concrete Grade 40
A

Parapet

SUPER-STRUCTURE

m3
90
To summary Q.R

S.T/Page 1/4

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF HOUSING
at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

RATE
QR

AMOUNT
QR

SUPERSTRUCTURE (Cont'd)
Reinforced In-situ OPC concrete Grade 50
A

Staircases

m3

164

Suspended slab,horizontal and not exceedin


15 degrees from horizonntal include overhang

m3

63

sawtooth slab

m3

223

Beams

m3

361

sawtooth beams

m3

286

Lift Shaft

m3

46

Coulmns

m3

1,280

kg

445,997

Reinforcement
high yield steel reinforcing bas of
minimum strenth 460 N/mm2 as specified
H

Reinforcing Bars In various diameters


Formwork

to vertical side of Lift Shaft

m2

235

to vertical side of Coulmns

m2

10,832

sides and soffites of staircase,risers and


landing

Item

horizonatl of slab

m2

365

Sawtooth slab

m2

1,277

sides and soffit of beams

m2

2,219

sides and soffit of sawtooth beams

m2

1,718

To summary Q.R

SUPER-STRUCTURE

S.T/Page 2/4

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF HOUSING
at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

m2

12871

Item

RATE
QR

AMOUNT
QR

SUPERSTRUCTURE (Cont'd)
Post tention concrete in superstructure
Supply and casting in-place of post tention
concrete in superstructure including in super
structure including hydrophopic additives
such as PUDLO or similar
approved,necessary preparation works
,protection works, reinforcement and steel
decking " where necessary " , cables , pushing
strands, tensioning and grouting, adequate PT
equipment to comply with the site
requirements, stressing jacks including
pumps, mixer/ grout set, strand dispensers,
formwork, scaffolding, reinforced steel,
expansion and construction joints, joint filler,
sealant, transporting, mixing, pouring,
leveling, finishing, curing of concrete and
testing all in accordance with drawings and
specification. including all of the approval for
the design drawings and shopdrawings from
certified posttension design consultant

Supply and casting in-place of reinforced


concrete with ordinary Portland cement
Grade OPC-40 for Slabs

Decorative design at elevations

Concrete wall as mentioned at the two sided


elevation as per specification and details
mentioned in the drawings

To summary Q.R
SUPER-STRUCTURE

S.T/Page 3/4

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF HOUSING
at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

RATE
QR

AMOUNT
QR

COLLECTION

Page ST/1/4
Page ST/2/4
Page ST/3/4

TOTAL CARRIED TO DIVISION


SUMMARY
SUPER-STRUCTURE

S.T/Page 4/4

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF HOUSING
at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

m2

4,816

RATE
QR

AMOUNT
QR

ROOFING
Supply and apply a water proofing for
Upper Roof and all roofs , with a 10 years
warranty from the supplier supported by a
letter by the main contractor as following :
Slopping concrete with average thick of 8cm
of plain concrete, area not more than 4m2 (1
unit) and mastic in between to be used ,
accordance with drawings.
Cement & sand plaster to form a
rectangular sector at the angle linking the
slab with the parapet or bases on the roof
(slope skirting)
Layer of Cold Primer.
2 Layers of insulating rubber "Membrane"
4 mm thick to be fixed by ISOFLEX-200HP
laid as specified Covering on leveling screed ,
in accordance with constructional details.
Layer of insulating rubber (MEMBRANE) 4
mm thick to be fixed by heat in linking
points between the slab and the parapet
according to details illustrated in the
drawings to the end of skirting, inside wall,
and filling openings with mastic.
Layer of heat-insulating 5 cm thick boards ISOFOAM or ROOFMAT- enduring high
pressure not less than 40 in order to be heat
and water resistant and proof.
1000 gage a polythine sheet to be fixed above.
10cm Screed. as a top layer.
The contractor should do a water test for 48
hours for all insulated places and to be
checked by the consultant before continuing
to the following item, the system is according
to an approved shop drawing.
BUILT UP ROOFING
lightweight screed as specified
A

Minimum 50 mm screed bed laid to fall

To summary Q.R
ROOFING

ROF/Page 1/3

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF HOUSING
at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

m2

4,816

m2

4,816

m2

4,816

m2

4,816

m2

4,816

l.m

904

Item

RATE
QR

AMOUNT
QR

ROOFING (Cont'd)
prepare and apply bituthene primer B1 as
specified to cement and sand screed base
(measured separetley)
A

roof covering laid to falls, cross - falls or slope


not eexeeding 10 degree from horizonatal
prepare and apply 4mm thick approved
membrane in strict accordance with the
manufacture's instruction including all fillets

roof covering laid to falls, cross - falls or slope


not eexeeding 10 degree from horizonatal
separation layer as spcecified

laid to falls,cross falls or slopes not exceeding


10 degree from horizontal on polstrene based
(measured separetley)roof covering laid to falls,
cross - falls or slope not eexeeding 10 degree
from horizonatal
polystyrene insulation boards as specified

50 mm thick fire rated insulation board, loose


laid on roof membrane(measured elsewhere)
Cement and sand lightweight screed as
specified

50 mm(minimum) thick layer laid to falls, crossfalls or slopes not exceeding 10 degree from
horizontal on filter membrane (measured else
where)
Aluminum sheets as specified

300 mm grith flashing


SUNDRIES

allow for additional roofing membrane,solar


protection,etc roof plinth

To summary Q.R

ROOFING

ROF/Page 2/3

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF HOUSING
at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

RATE
QR

AMOUNT
QR

COLLECTION

Page ROF/1/3
Page ROF/2/3

TOTAL CARRIED TO DIVISION


SUMMARY
ROOFING

ROF/Page 3/3

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF
HOUSING at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

RATE
QR

AMOUNT
QR

BLOCK WORKS
Hollow concrete blocks to BS 6073,Part1
bedded and jointinted in class M6/M8 mortar
as specified
A

100 mm walls

m2

1170

200 mm walls

m2

6892

300 mm walls

m2

2354

350 mm walls

m2

956

400 mm walls

m2

4444

500 mm walls

m2

241

600 mm walls

m2

2628

800 mm walls

m2

86

To summary Q.R

BLOCK WORKS

B/Page1/2

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF
HOUSING at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

RATE
QR

AMOUNT
QR

COLLECTION

PageB/1/2

TOTAL CARRIED TO DIVISION


SUMMARY

BLOCK WORKS

B/Page2/2

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF
HOUSING at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

RATE

AMOUNT

QR

QR

QTY

CARPENTRY AND JOINERY

THE CONTRACTOR SHOULD CHECK


THE FIRE SAFETY PLAN FOR THE
FIRE RATED DOORS AND ALL
ACCESSORIES SHOULD BE AS PER
CIVIL DEFENSE REQUIREMENT

12 mm thick platform fininished in approved vinyl


fixed to and including 20 mm thick vertical support
framework and like as indicated on drawings

No.

Double leave door 1700 x 2000 mm as specificed at


the drawings

No.

L.M

57

Wood skirting
C

100mm skirting for prayer Area

To summary Q.R

CARPENTARY

CAR/Page1/2

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF
HOUSING at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

RATE

AMOUNT

QR

QR

QTY

COLLECTION

Page CAR/1/2

TOTAL CARRIED TO DIVISION


SUMMARY
CARPENTARY

CAR/Page2/2

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF
HOUSING at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

NO

NO

NO

NO

NO

NO

NO

47

RATE
QR

AMOUNT
QR

METAL WORK
DOORS
THE CONTRACTOR SHOULD CHECK
THE FIRE SAFETY PLAN FOR THE
FIRE RATED DOORS AND ALL
ACCESSORIES SHOULD BE AS PER
CIVIL DEFENSE REQUIREMENT
45mm thick core flush door comprising
two skins of 1.2 mm thick galvanised sheet
steel painted as specified in filled with
polyurethene insulationfixing to steel
frames(measured elsewhere) complete
with glazing panel (as required).
Aluminum louvered grill (as reequired ).
fire rated as required building in
lintels,cills weather sealing etc. and
assoiciated builders work as specified and
indicated
A

2000x2200 Double leaf steel door with vision


glass type D2 as per drawing number P2-A-601

1600x2200 Double leaf steel door with vision


glass type D3 as per drawing number P2-A-601

1600x2200 Double leaf steel door with vision


C
glass type D3* as per drawing number P2-A-601

1700x2200 Double leaf steel door with vision


glass type D4 as per drawing number P2-A-601

1700x2200 Double leaf steel door with vision


glass type D4* as per drawing number P2-A-601

1600x2200 Double leaf steel swing door


F

with vision glass type D6 as per drawing number P2A-601

1200x2200 Single leaf steel door with vision


glass type D8 as per drawing number P2-A-601

To summary Q.R
METAL WORKS

MET/Page 1/10

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF
HOUSING at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

NO

NO

22

NO

NO

NO

NO

11

NO

14

NO

NO

75

NO

NO

NO

11

NO

RATE
QR

AMOUNT
QR

METAL WORK (Cont'd)


DOORS (Cont'd)
A

1200x2200 Single leaf steel door with vision


glass type D8* as per drawing number P2-A-601

1000x2200 Single leaf steel door with vision


glass type D9 as per drawing number P2-A-601

1000x2200 Single leaf steel door with vision


glass type D9* as per drawing number P2-A-601

F
G

1000x2200 Single leaf steel door type D10 as


per drawing number P2-A-601

1000x2200 Single leaf steel door type D11 as


per drawing number P2-A-601

1000x2200 Single leaf steel door type D11*


as per drawing number P2-A-601

1000x2200 Single leaf steel door type D12 as


per drawing number P2-A-601

1000x2200 Single leaf steel door type D12*


as per drawing number P2-A-601

1000x2200 Single leaf steel door type D13 as


per drawing number P2-A-601

1000x2200 Single leaf steel door type D14 as


per drawing number P2-A-601

1000x2200 Single leaf steel door type D15 as


per drawing number P2-A-601

1000x2200 Single leaf steel door type D15*


as per drawing number P2-A-601

1000x2200 Single leaf steel door type D16 as


per drawing number P2-A-601

To summary Q.R
METAL WORKS

MET/Page 2/10

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF
HOUSING at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

NO

NO

NO

RATE
QR

AMOUNT
QR

METAL WORK (Cont'd)


DOORS (Cont'd)
A

1000x2200 Single leaf steel door type D16*


as per drawing number P2-A-601

1000x2200 Single leaf steel door with vision


glass type D17 as per drawing number P2-A-601

1000x2200 Single leaf steel door with vision


glass type D19as per drawing number P2-A-601

To summary Q.R
METAL WORKS

MET/Page 3/10

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF
HOUSING at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

NO

18

RATE
QR

AMOUNT
QR

METAL WORK (Cont'd)


DOORS (Cont'd)
Decorative Powder coated Cast
Aluminium Screens manufactured by
approved range, comprising with suitable
section cast aluminium Fixing with
stainless steel fixing accessories as
specifiedas detailed on drawings ;include
polycarbonate sheet covers 2cm for the
door wholes ,all acessories ,iron mongeries
and painting as specified
A

Double leaf type D1 as per the drawings.

To summary Q.R
METAL WORKS

MET/Page 4/10

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF
HOUSING at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

NO

193

NO

NO

42

NO

NO

10

NO

NO

18

NO

RATE
QR

AMOUNT
QR

METAL WORK (Cont'd)


WINDOWS
Aluminium Powder Coated section glazed
windows system by approved manufacure
; complete with 24 mm thick hermetically
sealed double glazing consisting of 6.0 mm
thick tinned solar reflective glass to
exterior panel, 12 mm thick hermaticaly
sealed air space and 6 mm thick
hermaticaly sealed clear toughned glass to
interior pane including ironmongery as
specified ; fixing frames to concrete or
blockwork and sealing all around with
approved sealant (final color to be
accordig to the approval of the Engineer).
A

1700 x 1800 fixed and sliding window type


W1 as per drawing number P2-A-603

1700 x 1800 fixed and sliding window type


W2 as per drawing number P2-A-603

2200 X 2800 fixed window type W3 as per


drawing number P2-A-603

2200 X 2800 fixed and sliding window


type W4 as per drawing number P3-A-603
1700 X 1600 fixed and sliding window type
W6 as per drawing number P2-A-603

2200 X 3200 fixed and sliding window type


W7 as per drawing number P2-A-603

3800 X 2200 fixed and sliding window type


W9 as per drawing number P2-A-603

7200 X 2200 fixed and sliding window


type W10 as per drawing number P2-A-603

To summary Q.R

METAL WORKS

MET/Page 5/10

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF
HOUSING at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

RATE
QR

AMOUNT
QR

METAL WORK (Cont'd)


WINDOWS (Cont'd)
A

600 X 2200 fixed window type W11 as per


drawing number P2-A-603

NO

600 X 1200 fixed window type W12 as per


drawing number P2-A-603

NO

119

NO

283

NO

NO

600 X 600 window type W13 as per


C
drawing number P2-A-603
D

3200 X 2200 fixed and Sliding window


type W17 as per drawing number P2-A-603
1350 X 1700 fixed and Sliding window type W18
as per drawing number P2-A-603

Type W23 as per drawing number P2-A-603

NO

1400 X 1200 fixed and Sliding window


type W24 as per drawing number P2-A-603

NO

97

NO

14

NO

600 X 6200 fixed and Sliding window type


W25 as per drawing number P2-A-603
3200 X 2200 fixed and Sliding window

I
type W33 as per drawing number P2-A-603

To summary Q.R
METAL WORKS

MET/Page 6/10

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF
HOUSING at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

RATE
QR

AMOUNT
QR

METAL WORK (Cont'd)


Cast aluminum
Powder coated Cast Aluminium Screens
manufactured by approved range,
comprising with suitable section cast
aluminium Fixing with stainless steel
fixing accessories as specified; fixing to
concrete or block work in accordance with
the manufacturer's recommendations.
A

1700 x1800 mm for screen type SCR1 as


per drawing number P2-A-603

NO

26

1700 x 6600 mm for main screen type


SCR4 as per drawing number P2-A-603

NO

50

750 x 2000 mm for screen type SCR3 as


per drawing number P2-A-603

NO

72

2200 x 3200 mm for screen type SCR6 as


per drawing number P2-A-603

NO

3800 x 2200 mm for screen type SCR7 as


per drawing number P2-A-603

NO

To summary Q.R

METAL WORKS

MET/Page 7/10

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF
HOUSING at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

RATE
QR

AMOUNT
QR

METAL WORK (Cont'd)


IRON MONGERY
Ironmongery, supply and fixed as
specified and indicated on drawing P2-A602
A

Ref.Set 1 for D1

NO

18

Ref.Set 2 for D2

NO

Ref.Set 3 for D3&D3*

NO

Ref.Set 4 for D4&D4*

NO

Ref.Set 5 for D5

NO

Ref.Set 6 for D6*

NO

Ref.Set 7 for D8&D8*

NO

53

Ref.Set 8 for D9&D9*

NO

26

Ref.Set 9 for D10

NO

Ref.Set 10 for D11&D11*

NO

18

Ref.Set 11 for D12&D12*

NO

15

Ref.Set 12 for D13

NO

75

Ref.Set 13 for D14

NO

Ref.Set 14 for D15&D15*

NO

20

Ref.Set 15 for D16&D16*

NO

16

Ref.Set 15 for D17

NO

Ref.Set 16 for D19

NO

To summary Q.R

METAL WORKS

MET/Page 8/10

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF
HOUSING at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

900 mm high

351

Handrails fixed to staircase walls as per the


drawings

194

balustrade as per drawing ref P1-A-305

49

NO

42

m2

223

RATE
QR

AMOUNT
QR

METAL WORK (Cont'd)


HANDRAILS
50 mm diameter polished stainless steel
queuing line barrier complete as detailed
on drawing P2- A-502
A

Steel ladder

supply and fix steel ladder all material to the


approval of engineer: protection of materials
from damage will responsibility of the
contractor
LADDERS
Built in 100 x 250 mm aluminum poder
coated box section pergola as per drawings

ALUMIUN BERGOLAA
For the emergency entrance including
artificail columns
Aluminum pergola
Aluminum pergola as mention at AR-08

To summary Q.R
METAL WORKS

MET/Page 9/10

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF
HOUSING at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

RATE
QR

AMOUNT
QR

COLLECTION

PageMET/1/10
PageMET/2/10
PageMET/3/10
PageMET/4/10
PageMET/5/10
PageMET/6/10
PageMET/7/10
PageMET/8/10
PageMET/9/10

TOTAL CARRIED TO DIVISION


SUMMARY
METAL WORKS

MET/Page 10/10

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF
HOUSING at Al KHIYSA- UMM SALAL - DOHA QATAR
ITEM

DESCRIPTION

UNIT

QTY

Item

Item

Item

Item

Item

Item

RATE

AMOUNT

QR

QR

STRUCTURAL STEEL WORK


Framed steel work Grade 43 relevant
British
Standards with welded and bolted site
connections.

B
C

the contractor is responsible for the following:


make complete design for whole system as
per shown at drawings and gain all the
approval required for the steel structure
system from an authorithed third party
consultant (third party consultant is
responsible for the design approval and site
inspection at the site
the scope will be :-concrete area (arround the
walls) and steel structure system with
1polycarbonate acrylic sheet 4 cm thickness
(6layers) at the external side and
1polycarbonate acrylic sheet 2 cm thickness (
2 layers ) in the internal side as per shown in
the drawings (steel system will be paint in a
diffrent color).as per architect approvals
Surface preparation and protective system to
structural steelwork
Rainwater installation (gutters and down
pipes).
Drawings.

Allow for preparation, submission and


obtaining the Engineers from authorised third
fabrication and erection drawings as required
by QCS.
Certificate testing.

C Allow for provision of certificates, samples


and tests as required by QCS.
Guarantee.

Allow for providing guarantees for the


structural steel work as required by the
Specification.

To summary Q.R
SSS/Page 1/3
STEEL STRUCTURE SYSTEM

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF
HOUSING at Al KHIYSA- UMM SALAL - DOHA QATAR
ITEM

DESCRIPTION

UNIT

QTY

RATE

AMOUNT

QR

QR

STRUCTURAL STEEL WORK (Cont'd)


Sundries
A

Allow for all anchor bolts inserts and steel


embedded parts

Item

Allow for all welding, cutting and notching


out
etc.

Item

Allow for protective coating system in the


section as specified.

Item

Item

Protection
D

Allow for projecting the work in this section

To summary Q.R
SSS/Page 2/3
STEEL STRUCTURE SYSTEM

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF
HOUSING at Al KHIYSA- UMM SALAL - DOHA QATAR
ITEM

DESCRIPTION

UNIT

QTY

RATE

AMOUNT

QR

QR

COLLECTION

PageSSS/1/3
PageSSS/2/3

TOTAL CARRIED TO DIVISION


SUMMARY
SSS/Page 3/3
STEEL STRUCTURE SYSTEM

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF HOUSING
at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

RATE
QR

AMOUNT
QR

PLUNMBING AND DRAINGE


Supplying, erection, testing, commissioning,
and guarantee the following works as per
the project drawings, specifications and
standard codes complete with all
requirements for the proper of the systems
up to the satisfaction of the consultant
engineer and finish the works as conformity
with regulations
NOTES:
All sanitary fixtures shall be selected from
attached approved prime production.
All drainage pipes risers shall be UPVC
All drainage pipes inside toilets shall be UPVC
6 bar.
All drainage pipes under ground shall be
UPVC pipes 6 bar
All pressurized drainage pipes shall be UPVC
pipes 16 bar
All cold and hot water pipes inside buildings
from
PP-R-80
25 (more
(up to than
size 100mm)
All cold
waterPN
pipes
100mm size)
shall be high denisity polyethylene pipes
HDPE) All exposed water supply pipes shall
be insulated.
Sanitary Fixtures and Ancillaries:
Supplying, installing, erecting, testing and
commissioning
all sanitary wares with all accessories and
fittings as per (architecture) specifications
complete with cold and hot water supply
pipes,fittings ,valves, drainage soil, waste, and
vent pipes inside toilets, bathrooms and
kitchens- which serve sanitary fixtures up to
nearest riser, complete with all needed fittings,
etc all as per Specification and, as shown on
the drawings and finish the work as conformity
with regulations
To summary Q.R

PLUMBING DRAINGE

PL/Page 1/9

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF HOUSING
at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

RATE
QR

AMOUNT
QR

PLUNMBING AND DRAINGE (Cont'd)


A

Wash hand basin (counter top type).

No

156

Shower stall

No

10

Toilet

No

75

PBH

No

75

MobSink

No

50

ablution

No

Floor Drain Gully,Balacony Drain and


Tranch with all accessories and fittings as
per specifications
Supplying installing erecting, testing and
commissioning the following items as per
Specification, and as shown on the drawing,
C/W all requirements, and finish the work
as conformity with regulations.
H

Floor Gully with stainless steel cover 150 mm


X 150 mm.

No.

13

Floor Gully 50mm

No.

45

Floor Gully 100mm

No.

113

Clean Out 160mm

No.

18

Floor clean outs FCO. Size 110 mm

No.

11

Floor clean outs FCO. Size 150 mm

No.

38

Floor clean outs FCO. Size 160 mm

No.

To summary Q.R

PLUMBING DRAINGE

PL/Page 2/9

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF HOUSING
at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

RATE
QR

AMOUNT
QR

PLUNMBING AND DRAINGE (Cont'd)


A

Roof vent cowl diameter 50 mm

No.

Roof vent cowl diameter 75 mm

No.

Rain water Spout

No.

11

Water Tap

No.

Glope valve 15mm

No.

Glope valve 20mm

No.

10

Glope valve 25mm

No.

24

Glope valve 32mm

No.

10

Glope valve 50mm

No.

16

Glope valve 100mm

No.

Gully Trap

No.

12

No.

18

No.

11

Manhole

Concrete manhole with sizes as per the


drawings C/W manhole heavy duty cast iron
cover, benching, connections, insulationsetc
and finalize the work as conformity with
regulations.
Rain water soakaway

Supplying installing , erecting, testing and


commissioning soakaways 1800mm DIA.
complete with all pipes fittings, vent, covers,
laders, excavation etc as per specifications
and as shown on the drawings and finish the
work as conformity with regulations.

To summary Q.R
PLUMBING DRAINGE

PL/Page 3/9

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF HOUSING
at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

No.

Set

No.

RATE
QR

AMOUNT
QR

PLUNMBING AND DRAINGE (Cont'd)


Polyethylene Tanks
Supplying installing , erecting, testing and
commissioning roof storage water tanks
complete with all pipes fittings, valves, vent
etc as per specifications and as shown on the
drawings and finish the work as conformity
A

roof water tanks


Roof pressure boster Pump set
Supplying , installing , erecting, testing and
commissioning automatic factory packaged ,
prefabricated , tested ,certified and guaranteed
multi-stage domestic water pumping system
set complete with all valves, fittings, gauges,
suction and discharge headers , control panel
and hydropenumatic tanks all as per drawings
and specifications and finalize the work as
conformity with regulation

Roof pressure booster pump set


Water filters
Supplying installing, testing and
commissioning high pressure multi media

water filter , C/W all needed valves,


interconnecting pipe worksetc, and finalize
the work as conformity with regulations.

To summary Q.R

PLUMBING DRAINGE

PL/Page 4/9

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF HOUSING
at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

RATE
QR

AMOUNT
QR

PLUNMBING AND DRAINGE (Cont'd)


PP-R Domestic Water Pipes
Supplying, installing, erecting, testing and
commissioning PP-R 80 PN25 pipe system for
domestic cold water supply outside toilets,
bathrooms, and kitchens, complete with all
needed fittings, valves, supports, expansion
joints, insulations for exposed pipes, etc
all as per Specification, regulation, and as
shown on the drawings & Finish the works as
conformity with regulations
( all pipe size shown to be internal diameter)
A

Pipe diameter 15 mm

No.

520

Pipe diameter 22 mm

No.

472

Pipe diameter 28 mm

No.

418

Pipe diameter 35 mm

No.

260

Pipe diameter 42 mm

No.

63

Pipe diameter 54 mm

No.

226

Pipe diameter 67 mm

No.

108

Pipe diameter 76 mm

No.

136

Pipe diameter 100 mm


UPVC Sewar System Pipes

No.

15

55

Supplying, installing, erecting, testing and


commissioning UPVC Soil, Waste, Rainwater
and Vent pipes complete with all needed
standard fittings using rubber ring type, clean
outs, , supportsetc and all accessories
required to finalizing the works as per
specification and as shown on the drawings,
and finish the work as conformity with
regulations.
J

Pipe diameter 32 mm

To summary Q.R
PLUMBING DRAINGE

PL/Page 5/9

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF HOUSING
at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

RATE
QR

AMOUNT
QR

PLUNMBING AND DRAINGE (Cont'd)


UPVC Sewar System Pipes (cont'd)
A

Pipe diameter 40 mm

210

Pipe diameter 50 mm

15

Pipe diameter 75 mm

80

Pipe diameter 100 mm

600

Pipe diameter 160 mm

10

Under Ground UPVC Sewar System Pipes


Supplying, installing, erecting, testing and
commissioning under ground UPVC surface
drainage pipes in basement floor plan complete
with all needed standard fittings using rubber
ring type, and finalize the works as per
specification and as shown on the drawings,
and finish the work as conformity with
regulations.
F

Pipe diameter 110 mm

300

Pipe diameter 200 mm

385

To summary Q.R
PLUMBING DRAINGE

PL/Page 6/9

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF HOUSING
at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

Supplying, installing all electrical works in


connection with plumbing and drainage work
as per specifications.

Item

Supplying, installing all builders works in


connection with plumbing and drainage work
as per specifications.

Item

Allow for testing and commissioning all the


foregoing installation to the complete
satisfaction of the engineer

Item

Allow for sterilization and cleaning out of all


Pipe work system (Contractor shall submit
complete set of sterilization methods and
specifications from specialist contractor for
revision and approval).

Item

Allow for providing all painting and plates,


discs, labels etc for identification of systems
equipments, appliances, pipes, valves,
pumps,etc.

Item

RATE
QR

AMOUNT
QR

PLUNMBING AND DRAINGE (Cont'd)

Sundries

To summary Q.R

PLUMBING DRAINGE

PL/Page 7/9

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF HOUSING
at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

Item

Allow for providing all operating and


maintenance instruction manuals, catalogues,
warranties, guarantees certificates of all
mechanical equipments and list of suppliers of
all items used in the project.

Item

Allow for any other necessary items required


for the completion of the work as described in
the relevant sections of the drawings and/or
specifications and not mentioned herein or
suggested from the contractor and approved
from consultant office.

Item

RATE
QR

AMOUNT
QR

PLUNMBING AND DRAINGE (Cont'd)


Sundries
A

Allow for preparing shop and record drawings


of the
installations "as fitted"

To summary Q.R

PLUMBING DRAINGE

PL/Page 8/9

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF HOUSING
at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

RATE
QR

AMOUNT
QR

COLLECTION

Page PL/1/9
Page PL/2/9
Page PL/3/9
Page PL/4/9
Page PL/5/9
Page PL/6/9
Page PL/7/9
Page PL/8/9

TOTAL CARRIED TO DIVISION


SUMMARY
PLUMBING DRAINGE

PL/Page 9/9

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF
HOUSING at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

RATE
QR

AMOUNT
QR

H.V.A.C
FAN COIL UNIT
Supply install , testing, balancing and
commissioning of fan coil units as per
drawings and specifications the price
include.Service and balance
valves,Flexible connections ,Connection
piping, Connections thermal
insulation,Three speed wall mounted
switch , Wiring and power cable and
earthling ,Supports , hangers and
vibration isolators ,Drainage and piping to
the nearest drain point,Identifications and
tags , Any other items are mentioned on
the drawings and specification
A

F.C.U - 01

No

F.C.U - 02

No

10

AIR HANDLING UNIT


Supply install , testing , balancing and
commissioning of air handling units as per
drawings and specifications, price
include.Service and balance
valves,Flexible connections (duct & piping)
,Piping thermal insulation ,Cables and
wiring and earthling,Base and supports
and vibration isolation ,Drainage and
piping to the nearest drain
point,Identifications tags and cladding
,Temperature and pressure gauges on
piping ,Any other items are mentioned on
the drawings and specifications and
Arraangemet
Arraangemet 2 :
C

AHU-06 ( 10,420 cmh)

No

AHU-08 ( 19,900 cmh)

No

To summary Q.R
H.V.A.C SYSTEM

H.V.A.C/Page 1/9

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF
HOUSING at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

No

11

RATE
QR

AMOUNT
QR

H.V.A.C (Cont'd)
AIR HANDLING UNIT (Cont'd)
Arraangemet 3 :
A

AHU-10 (13,345 cmh)


Arraangemet 1 :

AHU-12 ( 8,500 cmh)

No

AHU-14 ( 28,280 cmh)

No

VAV Unit
F

VAV 01

No

VAV 02

No

VAV 03

No

VAV 04

No

VAV 05

No

43

VAV 06

No

30

To summary Q.R
H.V.A.C SYSTEM

H.V.A.C/Page 2/9

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF
HOUSING at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

RATE
QR

AMOUNT
QR

H.V.A.C (Cont'd)
FANS
Supply install , testing , balancing and
commissioning supply or exhaust fan
complete with all accessories as per the
drawings and specifications, price include.
drawings.Roof curb , base , support and
mountings Out door disconnecting switch IP55 , cables , wiring and earthling Gravity
shutter , wire mesh on the discharge Duct
connections , identifications and tages Any
other items are mentioned on the drawings
and specifications for fans
A

Centrifugal Fan - Inline -

No

Centrifugal Fan - Inline -

No

Roof Ventilator

No

19

PIPES
Supply and install , testing , balance and
commissioning of chilled water piping
complete as per drawings and
specifications , the price per meter length
include - concrete trench with
cover,Supports , fittings and pipes.Vents at
the top of risers Drains at bottom of risers
Paints , and surface treatment Penetration
curbs at roofs Provisions of penetration
details at walls Any other items are
mentioned on the drawings and
specification
D

- Size 15 mm

56

- Size 20 mm

152

- Size 25 mm

111

- Size 32 mm

H.V.A.C SYSTEM

m
25
To summary Q.R
H.V.A.C/Page 3/9

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF
HOUSING at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

RATE
QR

AMOUNT
QR

H.V.A.C (Cont'd)
PIPES (Cont'd)
A

- Size 40 mm

217

- Size 50 mm

119

- Size 65 mm

236

- Size 75 mm

97

- Size 100 mm

136

- Size 150 mm

380

- Size 200 mm

50

DUCTS
Supply and install , testing , balance and
commissioning of air duct complete as per
drawings and specification the price
include Supports , sealers and fittings
Volume dampers and fire damper Any of
sound attenuators to reach the sound level
of 46 DBA inside the conditioned space
(HVAC Impact) Duct curb at duct
penetration of the roof.Provision of duct
penetration details at walls Any other
items are mentioned on the drawings and
specifications
H

- Galvanized Steel

kg

56600

- Flexible connection

25

Item

Smoke Dampers

Supply install connection, testing and


commissioning of fire smoke dampers
complete with all accessoreis as shown on
drawings and specifications

To summary Q.R

H.V.A.C SYSTEM

H.V.A.C/Page 4/9

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF
HOUSING at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

RATE
QR

AMOUNT
QR

H.V.A.C (Cont'd)
AIR OUTLETS
Supply install of air outlet (grilles or diffuser
) as per specification and drawings price
include
- Inlet guide & damper
- Supporting and fixation
- Paint and colours
- Mesh screen on back
Supply Ceiling Diffusers
A

Size 300x300

No

51

Size 600x600

No

432

Supply Air Grille


D

Size 200 x 150

No

Size 1000 x 300

No

10

Size 1200 x 400

No

16

Return Air Grille


G

Size 300 x 300

No

77

Size 150 x 150

No

10

Size 225 x 225

No

Exhaust Ceiling grilles


J

Size 150 x 150

No

45

Size 225 x 225

No

Size 300x150

No

19

Size 300x300

No

To summary Q.R

H.V.A.C SYSTEM

H.V.A.C/Page 5/9

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF
HOUSING at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

No

RATE
QR

AMOUNT
QR

H.V.A.C (Cont'd)
Exhaust Ceiling Diffuser
A

Size 300x150
Supply Jet Diffuser

Size 450mm

No

16

Size 600 mm

No

Return Jet Diffuser

Size 600 mm

No

28

PIPING INSULATION
Supply and installation and commissioning
of thermal insulation (internal insulation)
for chilled water piping as per drawings
and specifications the price of the item
include.Over Laping , closing up the vapor
barriers gaps Identification of the flow
direction and fluids type on the surface
Insulation of valves and fittings , flanges
and accessories Insulation of pumps and
drainage lines, vent lines Aluminum
clading for all duct pipe work in machine
rooms and outside work Any other items
are mentioned on the drawings or
specifications
F

- Size 15 mm

56

- Size 20 mm

152

To summary Q.R

H.V.A.C SYSTEM

H.V.A.C/Page 6/9

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF
HOUSING at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

RATE
QR

AMOUNT
QR

H.V.A.C (Cont'd)
PIPING INSULATION (Cont'd)
A

Size 25 mm

111

Size 32 mm

25

Size 40 mm

217

Size 50 mm

119

Size 65 mm

236

Size 75 mm

97

Size 100 mm

136

Size 150 mm

380

Size 200 mm

50

DUCT INSULATION
Supply and installation and commissioning
of thermal insulation for air duct as per
the drawings and specification the price
include Insulation overlapping , closing up
of vapor barrier gaps Insulation support
wires or belts Identification of flow and
flow direction Aluminum clading for
external duct Insulation of the dampers
and fitings and accessories .Any other
items are mentioned on the drawings , and
specifications for duct

- Duct of AHU & FCU

m2

9000

- Duct of Kitchen Hood (calcium silicate)

m2

1000

Duct of smoke extraction (calcium silicate)

m2

600

To summary Q.R
H.V.A.C SYSTEM

H.V.A.C/Page 7/9

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF
HOUSING at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

Item

Item

Item

Item

RATE
QR

AMOUNT
QR

H.V.A.C (Cont'd)
SYSTEM FLUSHING

System flushing , chemical cleaning and


filling of water and balancing of water
quantities (Do not use system pumps in
flushing)
STARTING UP

Start up testing and handling over include


training of the owner staff and
documentation
BUILDERS WORK FOR ENGINEERING
SERVICES

Builders Works & sleeves for proper


installation of equipments & services in this
section
MAINTENANCE

Service and maintenance change of


consumable materials (refragerant, oil, AHU,
filters, sealers, gaskets ..ect) for one year
include any spare part and gurantee

To summary Q.R

H.V.A.C SYSTEM

H.V.A.C/Page 8/9

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF
HOUSING at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

RATE
QR

AMOUNT
QR

Page H.V.A.C 1/9


Page H.V.A.C 2/9
Page H.V.A.C 3/9
Page H.V.A.C 4/9
Page H.V.A.C 5/9
Page H.V.A.C 6/9
Page H.V.A.C 7/9
Page H.V.A.C 8/9

TOTAL CARRIED TO DIVISION


SUMMARY
H.V.A.C SYSTEM

H.V.A.C/Page 9/9

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF
HOUSING at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

No.

19

RATE
QR

AMOUNT
QR

Fire Fighting System


SUPPLY, INSTALLATION, TESTING,
COMMISSIONING AND GUARANTEE
THE FOLLOWING WORK AS PER
DRAWINGS, SPECIFICATIONS, QCDD
& NFPA REQUIRMENT AND
FINALIZING THE WORKS AS
CONFORMITY WITH REGULATIONS.
FIRE HOSE REEL SINGLE CABINET

Supplying, installing, testing, and


commissioning, fire hose reel single cabinet
complete with all valves,hoses, extinguishers,
landing valve, hose as per specifications and
as shown on the details drawings and finalize
the work as conformity with regulations.
PIPING NETWORK
Supplying, installing, erecting, testing and
commissioning all fire fighting seem lees
black steel pipes schedule 40 complete with
all needed standard fittings, supports...etc
as shown on the drawings and as per
specifications, and finish the work as
conformity with regulations.

Diameter 150 mm (6 Inch)

812

Diameter 100 mm (4 Inch)

118

Diameter 75 mm (3 Inch)

20

Diameter 65 mm (2.5 Inch)

703

Diameter 50 mm (2 Inch)

514

Diameter 40 mm (1.5 Inch)

663

Diameter 32 mm (1.25 Inch)

918

Diameter 25 mm (1 Inch)

2,377

Diameter 20 mm

FIRE FIGHTING SYSTEM

m
12
To summary Q.R
F.F/Page 1/6

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF
HOUSING at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

Supplying, installing, testing, and


commissioning, firefighting sprinklers
complete with fixation to pipe works and all
accessories according to the specifications
and as shown on the drawings and finalize
the work as conformity with
regulations.Sprinkler head pendent recessed
center , 680C 15 mm ( Inch) diameter,
quick response, small thermosentive glass
bulb , spray sprinkler, UL/FM approved.

No.

1292

Sprinkler head side wall , 680C 15 mm (


Inch) diameter, quick response pendent
sprinkler are small thermosentive glass bulb ,
spray sprinkler UL/FM approved.

No.

48

Sprinkler head upright , 790C 15 mm (


Inch) diameter, quick rsponse upright
sprinkler are small thermosentive glass bulb
, spray sprinkler UL/FM approved.

No.

1304

No.

12

RATE
QR

AMOUNT
QR

Fire Fighting System (Cont'd)


SPRINKLER HEAD

AUTOMATIC AIR VENT

Supplying, installing, testing and


commissioning 25 mm diameter automatic
air vent valve at the highest point of the fire
risers, complete with gate valve, pressure
gauge connections, and finalize the work as
conformity with regulations

To summary Q.R

FIRE FIGHTING SYSTEM

F.F/Page 2/6

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF
HOUSING at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

No.

No.

21

RATE
QR

AMOUNT
QR

Fire Fighting System (Cont'd)


ZONE CONTROL VALVE
Supplying, installing, testing, and
commissioning, pressure gauge, flow
switches, connections with firefighting
zoon control valve complete with all
valves,pressure gauge, flow switches,
connections with fire alarm system, etc,
and all accessories according to the
specifications and as shown on the
drawings and finalize the work as
conformity with regulations.
A

100 mm
FLUSHING VALVE

Supplying, installing, testing and


commissioning At end of each horizontal
main pipes c/w ball valve 50 mm, and
finalize the work as conformity with
regulations
FIRE EXTINGUSHIERS
Supplying, installing, all types of fire
extinguisher with all it is accessories
hanger,. Ect. and finalize the work as
conformity with regulations

dry powder fire extingushiers

No.

49

CO2 Fire extinguisher

No.

12

Fam1

No.

No.

12

FIRE BLANKET
F

Supplying, installing,fire balanket (1.2X1.2)


and finalize the work as conformity with
regulations

FIRE FIGHTING SYSTEM

To summary Q.R

F.F/Page 3/6

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF
HOUSING at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

No.

No.

RATE
QR

AMOUNT
QR

Fire Fighting System (Cont'd)


SIAMESE CONNECTION

Supplying, installing, testing, and


commissioning,4 way fire siamese
connection complete with all valves, check
valve, enclousers, and all accessories
according to the specifications and as shown
on the drawings and finalize the work as
conformity with regulations.
ALARM CHECK VALVE

Supplying, installing, testing, and


commissioning, Alarm check valve 150 mm
(6 Inch) diameter with variable pressure trim
retarding chamber, mechanical alarm gong,
pressure switch complete including tamper
switch, as per drawings

To summary Q.R

FIRE FIGHTING SYSTEM

F.F/Page 4/6

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF
HOUSING at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

Item

Allow for producing all shop and as built


drawings for approval and as required by the
engineer

Item

Allow for sterilization and cleaning out of all


Pipe work system (Contractor shall submit
complete set of sterilization methods and
specifications from specialist contractor for
revision and approval).

Item

Allow for providing all painting and plates,


discs, labels etc. for identification of systems
equipments,

Item

Allow for any other necessary items required


for the completion of the work as described
in the relevant sections of the drawings
and/or specifications and not mentioned
herein or suggested from the contractor and
approved from the consultant office.

Item

RATE
QR

AMOUNT
QR

Fire Fighting System (Cont'd)


BUILDER WORK

Builder's works include all openings through


wall and floors also, include sleeves, and all
sub-bases of fire fighting equipments, and
closing surrounding all opennings by fire
rated sealantsetc.

GENERAL REQUIREMENTS

To summary Q.R
FIRE FIGHTING SYSTEM

F.F/Page 5/6

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF
HOUSING at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

RATE
QR

AMOUNT
QR

COLLECTION

Page FF 1/6
Page FF 2/6
Page FF 3/6
Page FF 4/6
Page FF 5/6

TOTAL CARRIED TO DIVISION


SUMMARY
FIRE FIGHTING SYSTEM

F.F/Page 6/6

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF
HOUSING at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

RATE
QR

AMOUNT
QR

Electrical Equipment Schedule


all of the following items and fitting, the
item include the wirings ,
conduting,cabletray,installation details
builder works,excavations and backfilling
if any .and feeders cables if applicable
A

Automatic Bell Controller: antenna

No

Control Panel: CONTROL MODULE

No

Control Panel: CP

No

Lighting switching station: LCP

No

MDB-UPS-ATS-MCC: UPS

No

motor factory control panel: EMCP

No

motor factory control panel: MOTOR


FACTORY PANEL

No

25

motor factory control panel: SET MOTOR


FACTORY PANEL 2

No

PP Panel Board: DB

No

26

PP Panel Board: DP

No

public adress system rack: antenna

No

Wireless Access Point: antenna

No

75

To summary Q.R

ELECTRICAL SYSTEM

EL/Page 1/11

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF
HOUSING at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

No

No

No

16

Exit Ceiling with two directions: C-XT - 1


AROW
Exit Ceiling with two directions: C-XT - 1
AROW2
Exit Ceiling with two directions: C-XT - 1
AROW
Exit Ceiling with two directions: EX

No

44

Exit Ceiling with two directions: EX1

No

15

Exit Ceiling with two directions: EX2

No

Exit Ceiling with two directions: EXIT (EX1)

No

33

Exit_Ceiling with one direction1: EX

No

17

Exit_Ceiling with one direction: C-XT - 1


AROW

No

15

FLOOD LIGHT FOR SCHOOL: FL1

No

20

Surface_Mounted_600x600_Origin_Centered
: F3

No

160

Surface_Mounted_600x600_Origin_Centered
: F3E

No

37

Surface_Mounted_600x600_Origin_Centered
: F4

No

316

Surface_Mounted_600x600_Origin_Centered
: F4E

No

55

Surface_Mounted_600x600_Origin_Centered
: F5

No

70

RATE
QR

AMOUNT
QR

Lighting Fixture Schedule


all of the following items and fitting, the
item include the wirings ,
conduting,cabletray,installation details
builder works,excavations and backfilling
if any .and feeders cables if applicable
A
B
C

To summary Q.R
ELECTRICAL SYSTEM

EL/Page 2/11

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF
HOUSING at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

RATE
QR

AMOUNT
QR

Lighting Fixture Schedule (Cont'd)


A

Surface_Mounted_600x600_Origin_Centered
: F5E

No

12

Surface_Mounted_600x600_Origin_Centered
: F8

No

Surface_Mounted_1200x150_Centered: F6

No

12

Surface_Mounted_1200x300_Origin_Centere
d: F1

No

312

Surface_Mounted_1200x300_Origin_Centere
d: F1E

No

78

Surface_Mounted_1200x300_Origin_Centere
d: F2

No

22

Surface_Mounted_1200x300_Origin_Centere
d: F2E

No

62

Surface_Mounted_Big_Spot_Origin_Centere
d: C1

No

648

Surface_Mounted_Big_Spot_Origin_Centere
d: C1E

No

229

Surface_Mounted_Big_Spot_Origin_Centere
d: C2

No

167

Surface_Mounted_Big_Spot_Origin_Centere
d: C2E

No

35

Surface_Mounted_Big_Spot_Origin_Centere
d: C3

No

78

Surface_Mounted_Big_Spot_Origin_Centere
d: C4

No

10

Surface_Mounted_Big_Spot_Origin_Centere
d: C5

No

28
To summary Q.R

ELECTRICAL SYSTEM

EL/Page 3/11

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF
HOUSING at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

RATE
QR

AMOUNT
QR

Lighting Fixture Schedule (Cont'd)

Surface_Mounted_Big_Spot_Origin_Centere
d: C5E

No

Surface_Mounted_Big_Spot_Origin_Centere
d: C6

No

14

Surface_Mounted_Big_Spot_Origin_Centere
d: C6E

No

Surface_Mounted_Big_Spot_Origin_Centere
d: C7

No

41

Surface_Mounted_Big_Spot_Origin_Centere
d: C7E

No

14

Surface_Mounted_Big_Spot_Origin_Centere
d: C8

No

10

Surface_Mounted_Big_Spot_Origin_Centere
d: C8E

No

Surface_Mounted_Big_Spot_Origin_Centere
d: H1

No

15

Surface_Mounted_Big_Spot_Origin_Centere
d: H1E

No

15

Surface_Mounted_Small_Spot_Origin_Center
ed: D3

No

20

Surface_Mounted_Small_Spot_Origin_Center
ed: D3E

No

Wall Bulk head: B1

No

28

Wall Bulk head: B2

No

63

Wall Bulk head: L06

No

ELECTRICAL SYSTEM

EL/Page 4/11

2
To summary Q.R
Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF
HOUSING at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

RATE
QR

AMOUNT
QR

Lighting Device Schedule


all of the following items and fitting, the
item include the wirings ,
conduting,cabletray,installation details
builder works,excavations and backfilling
if any .and feeders cables if applicable
A

Lighting Switch_One_Way-One_Gang: D

No

176

No

Lighting Switch_One_Way-Two_Gang.0001:
D
Lighting Switch_Two_Way_One_Gang: SW1

No

34

Up: LE01

No

26

Electrical Fixture Schedule


all of the following items and fitting, the
item include the wirings ,
conduting,cabletray,installation details
builder works,excavations and backfilling
if any .and feeders cables if applicable
E

3 phase power socket: SO6

No

12

ceiling EO: EO

No

48

Disconnect_Switch: 20A, 2P

No

126

Disconnect_Switch: 20A, 3P (W.P)

No

Disconnect_Switch: 20A, 4P (W.P)-WH-2

No

10

Disconnect_Switch: 32A, 6P (W.P)-SMEF


12.5

No

Disconnect_Switch: 40A, 4P (W.P)-WH-1

No

12

Disconnect_Switch: 40A, 6P (W.P)-SMEF


16.5

No

Disconnect_Switch: 250A, 4P W.P EWH

No

EO_Switched FCU: AC

No

ELECTRICAL SYSTEM

EL/Page 5/11

16
To summary Q.R
Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF
HOUSING at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

RATE
QR

AMOUNT
QR

Electrical Fixture Schedule (Cont'd)


A

EO_Switched FCU: EWH

No

EO_Switched FCU: HD

No

Hand Dryer_EO_20 AOP Switch

No

58

Power Socket_Wall: SO4

No

12

SO_Floor: FB-2

No

Socket_Wall_Duplex: RO1

No

203

Socket_Wall_Single: shaver outlet

No

Socket_Wall_Single: SO1

No

424

UPS socket Duplex: SO1

No

31

EL_Conduit Schedule

Conduit without Fittings: Rigid Nonmetallic


Conduit (RNC Sch 40) size 50 mm

Item

Conduit without Fittings: Rigid Nonmetallic


Conduit (RNC Sch 40) size 100m

Item

Conduit without Fittings: Rigid Nonmetallic


Conduit (RNC Sch 40) size 150 mm

Item

To summary Q.R

ELECTRICAL SYSTEM

EL/Page 6/11

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF
HOUSING at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

RATE
QR

AMOUNT
QR

Cable Tray Schedule

Cable Tray with Fittings: Channel Cable


covered Tray (150 x 100) mm

Item

Cable Tray with Fittings: Channel Cable


covered Tray (300x100) mm

Item

Cable Tray with Fittings: Channel Cable


covered Tray (450x100) mm

Item

Cable Tray with Fittings: Channel Cable


covered Tray (600x100) mm

Item

Cable Tray with Fittings: Channel Cable


covered Tray (900x100) mm

Item

Cable Tray with Fittings: Channel Cable


LADDER (300x100) mm

Item

Cable Tray with Fittings: Channel Cable


LADDER (900x100) mm

Item

Cable Tray with Fittings: Channel Cable Tray


(150 x 100) mm

Item

Cable Tray with Fittings: Channel Cable Tray


(300x100) mm

Item

Cable Tray with Fittings: Channel Cable Tray


(450x100) mm

Item

Cable Tray with Fittings: Channel Cable Tray


(600x100) mm

Item

Cable Tray with Fittings: Channel Cable


Trensh (1000 x 800) mm

Item

Cable Tray with Fittings: Solid Bottom Cable


Tray (300x100) mm

Item

To summary Q.R
ELECTRICAL SYSTEM

EL/Page 7/11

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF
HOUSING at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

RATE
QR

AMOUNT
QR

Security Device Schedule


Item include all wiring according to
drawings, junction boxes distribution
boxes prc conduting , Rgs Conduites,cable
truncking,builder works,installation details

ACCESS CARD READER: CR

No

12

ACCESS_DOOR CONTACT: DC

No

12

Display Bell: Door_Bell_ButtonPress_14195


(1)

No

ELECRICAL LOCK: E.L

No

12

PUSH BOTTOM: PB

No

12

VGA: C.R

No

48

11

Fire Alarm Device Schedule


Item include all wiring according to
drawings, junction boxes distribution
boxes prc conduting , Rgs Conduites,cable
truncking,builder works,installation details
G

Evacuation Speaker - Ceiling Mounted: SP

No

153

Interface module : F31

No

Heat Detector Combination: H

No

11

Manual Alarm Control Point: M

No

36

Smoke Detectors: Optional Smoke Detector

No

333

Smoke Detectors: RF

No

Strobe Light (110 CD ): F31

No

104

Wall Mounted Speaker: WP

No

17
To summary Q.R

ELECTRICAL SYSTEM

EL/Page 8/11

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF
HOUSING at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

RATE
QR

AMOUNT
QR

Electrical Equipment Schedule


Item include all wiring according to
drawings, junction boxes distribution
boxes prc conduting , Rgs Conduites,cable
truncking,builder works,installation details

Automatic Bell Controller: antenna

No

Control Panel: CONTROL MODULE

No

Control Panel: CP

No

Lighting switching station: LCP

No

MDB-UPS-ATS-MCC: UPS

No

motor factory control panel: EMCP

No

motor factory control panel: MOTOR


FACTORY PANEL

No

25

motor factory control panel: SET MOTOR


FACTORY PANEL 2

No

PP Panel Board: DB

No

26

PP Panel Board: DP

No

Public adress system rack:antenna

No

Wireless Access Point: antenna

No

75

To summary Q.R
ELECTRICAL SYSTEM

EL/Page 9/11

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF
HOUSING at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

RATE
QR

AMOUNT
QR

Telephone Device Schedule


Item include all wiring according to
drawings, junction boxes distribution
boxes prc conduting , Rgs Conduites,cable
truncking,builder works,installation details

Telephone Outlet (H-120 CM): Telephone


Outlet (H-120 CM)

No

27

Telephone Outlet New: Telephone Outlet


New

No

91

Phone plate socket

Item

Data Device Schedule


Item include all wiring according to
drawings, junction boxes distribution
boxes prc conduting , Rgs Conduites,cable
truncking,builder works,installation details

Public Adress Ceiling Speaker1: 6 W

No

177

Public Adress Ceiling Speaker: 6 W

No

10

Wall_Data Outlet New: DA1

No

251

Wireless Access Point_R145: LC09

No

74

To summary Q.R

ELECTRICAL SYSTEM

EL/Page 10/11

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF
HOUSING at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

RATE
QR

AMOUNT
QR

Page EL/1/11
Page EL/2/11
Page EL/3/11
Page EL/4/11
Page EL/5/11
Page EL/6/11
Page EL/7/11
Page EL/8/11
Page EL/9/11
Page EL/10/11

TOTAL CARRIED TO DIVISION


SUMMARY

ELECTRICAL SYSTEM

EL/Page 11/11

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF
HOUSING at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

m2

542

m2

14,919

m2

709

RATE
QR

AMOUNT
QR

PAINTING AND DECORATING


Prepare and apply acrylic emulsion paint
(Interior) and primer/compound as
specified to provide a matt finish
A

To ceilings
Prepare and apply acrylic eggshell
emulsion paint (Interior) and
primer/compound as specified to provide a
smooth finish

To rendered walls
Prepare and apply splatter texture with
acrylic anticarbonation paint and
primer/compound as specified to provide a
weather tough external quality finish

To rendered walls & fair face concrete soffits


Prepare and apply semi-gloss enamel paint
(Interior) and primer/compound as
specified to provide a smooth finish

To rendered walls

m2

765

External paint as the texture mentioned at


drawing no A-201,A-202,A-203 AND A204 As per the client/architect approval

m2

7,217

To summary Q.R

Painting and Decoration

PA/Page 1/3

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF
HOUSING at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

m2

357

542

57

RATE
QR

AMOUNT
QR

PAINTING AND DECORATING (Cont'd)


4mm thick epoxy paint floor fosroc/jotun
or approved equal over 80 mm thick
cement + sand screed (measured elsewhere)
A

To screeded floors.

To roof deck
Prepare and apply semi-glass finish paint
system consisting of two coats of primer /
undercoat and two coats of semi-glass
enamel paint as specified and the colour to
match with floor finishings.

To wooden skirting

To summary Q.R

Painting and Decoration

PA/Page 2/3

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF
HOUSING at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

RATE
QR

AMOUNT
QR

COLLECTION

Page PA/1/3
Page PA/2/3

TOTAL CARRIED TO DIVISION


SUMMARY

Painting and Decoration

PA/Page 3/3

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF
HOUSING at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

m2

542

m2

14,919

m2

709

RATE
QR

AMOUNT
QR

PAINTING AND DECORATING


Prepare and apply acrylic emulsion paint
(Interior) and primer/compound as
specified to provide a matt finish
A

To ceilings
Prepare and apply acrylic eggshell
emulsion paint (Interior) and
primer/compound as specified to provide a
smooth finish

To rendered walls
Prepare and apply splatter texture with
acrylic anticarbonation paint and
primer/compound as specified to provide a
weather tough external quality finish

To rendered walls & fair face concrete soffits


Prepare and apply semi-gloss enamel paint
(Interior) and primer/compound as
specified to provide a smooth finish

To rendered walls

m2

765

External paint as the texture mentioned at


drawing no A-201,A-202,A-203 AND A204 As per the client/architect approval

m2

7,217

To summary Q.R

Painting and Decoration

PA/Page 1/3

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF
HOUSING at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

m2

357

542

57

RATE
QR

AMOUNT
QR

PAINTING AND DECORATING (Cont'd)


4mm thick epoxy paint floor fosroc/jotun
or approved equal over 80 mm thick
cement + sand screed (measured elsewhere)
A

To screeded floors.

To roof deck
Prepare and apply semi-glass finish paint
system consisting of two coats of primer /
undercoat and two coats of semi-glass
enamel paint as specified and the colour to
match with floor finishings.

To wooden skirting

To summary Q.R

Painting and Decoration

PA/Page 2/3

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF
HOUSING at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

RATE
QR

AMOUNT
QR

COLLECTION

Page PA/1/3
Page PA/2/3

TOTAL CARRIED TO DIVISION


SUMMARY

Painting and Decoration

PA/Page 3/3

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF
HOUSING at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

No

1131

No

1131

No

47

No

47

RATE
QR

AMOUNT
QR

Provisional Sum
number of items have been included as
provisional sums. The Alandalus schools
reserves the right to either tender them
separately and delegate them to the
contractor or procure them at his end and
supply them to the Contractor for
installation at this (Employers) sole
discretion. These sub-contractors/suppliers
shall be treated as domestic subcontractors/suppliers of the Contractor
and not as nominated subcontractors/suppliers unless designated as
Nominated sub-contractors as per clause
58 from general condtion of contract
AT CLASSES
A

Students' tables for classes as per drawings


and specifiactions
Students' chair for classes as per drawings
and specifiactions
Teacher's table for classes as per drawings
and specifiactions
Teacher's chair for classes as per drawings
and specifiactions

CUPBOARD 600X1400 mm for calsses as


per drawings and specifiactions

No

47

WHITEBOARD for classes as per drawings


and specifications

No

47

To summary Q.R
PROVISIONAL SUM

P.S/Page 1/9

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF
HOUSING at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

RATE
QR

AMOUNT
QR

Provisional Sum (cont'd)

AT SUPERVISOR'S ROOM
A

Supervisior chair as per drawings

No

22

Supervisior table 600 x 1600 mm

No

Sofa

No

Supervisior table 400 X 900 mm

No

At Teachers' Room
E

Teachers' Table 700 X 1400 mm

No

116

Chair

No

232

Office
G

Office's table 800 x 1500 mm

No.

16

Office's Chair

No.

34

Canteen
I

Table Size 1100 x 1800 mm

No.

47

Waiting Path 1300 x 4400 mm

No.

Chair

No.

282

To summary Q.R

PROVISIONAL SUM

P.S/Page 2/9

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF
HOUSING at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

RATE
QR

AMOUNT
QR

Provisional Sum (cont'd)


H-Master Deputy
A

H-Master Deputy Table 800 X 1500 mm

No.

Chair

No.

Sofa

No.

Head Master
D

H-Master Table 800 X 1500 mm

No.

Chair

No.

Sofa

No.

Clinic
G

Doctor's Table 800 x 1500 mm

No.

Chair

No.

Sofa

No.

Patient's Bed

No.

Secrtary
K

Socialist's table 800 x 1600 mm

No.

Chair

No.

Sofa

No.

To summary Q.R

PROVISIONAL SUM

P.S/Page 3/9

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF
HOUSING at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

RATE
QR

AMOUNT
QR

Provisional Sum (cont'd)


Art Room
A

Teacher Table 1200 x 2200

No.

Student Table 700 x 1800

No.

30

Teacher Chair

No.

Cupboard 500 X 1200 mm

No.

14

Sink

No.

Sink Holder 600 X 5100

No.

Chemistry Lab
G

Teacher Bench 1400 x 2500 mm

No.

Student Table 1700 x 4400 mm

No.

Lab stool

No.

60

Cupboard

No.

Sink

No.

14

Wall Bench with Sink 600 x 3400 mm

No.

Wall Bench 750 x 2000 mm

No.

Heater

No.

Eye Wash

No.

To summary Q.R

PROVISIONAL SUM

P.S/Page 4/9

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF
HOUSING at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

RATE
QR

AMOUNT
QR

Provisional Sum (cont'd)


Biology Lab
A

Teacher Bench 1400 x 2500 mm

No.

Student Table 1700 x 4400 mm

No.

Lab stool

No.

62

Cupboard

No.

Sink

No.

14

Wall Bench with Sink 600 x 3400 mm

No.

Wall Bench 750 x 2000 mm

No.

Heater

No.

Cupboard 900 x 1200

No.

Eye Wash

No.

Phiscs Lab
K

Teacher Bench 1400 x 2500 mm

No.

Student Table 1700 x 4400 mm

No.

Lab stool

No.

30

Cupboard

No.

Sink

No.

Heater

No.

To summary Q.R

PROVISIONAL SUM

P.S/Page 5/9

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF
HOUSING at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

RATE
QR

AMOUNT
QR

Provisional Sum (cont'd)


Phiscs Lab (Cont'd)
A

Wall Bench with Sink 600 x 3400 mm

No.

Wall Bench 750 x 2000 mm

No.

Eye Wash

No.

Computer Lab
D

Computer Table 800 x 900 mm

No.

21

Computer Chair

No.

21

Teacher Table 800 x 1500

No.

Teacher Chair

No.

Library
H

Counter 1200 x 5000 mm

No.

counter chair

No.

student Table 700 X 1400 mm

No.

22

student chair

No.

22

Shelves 300 x 200 mm

No.

16

To summary Q.R

PROVISIONAL SUM

P.S/Page 6/9

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF
HOUSING at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

RATE
QR

AMOUNT
QR

Provisional Sum (cont'd)


Language Lab
A

Computer Table 800 x 2700 mm

No.

10

Computer Chair

No.

30

Teacher Table 800 x 1500

No.

Teacher Chair

No.

WC
E

Toilets

No.

61

Toilet Paper Dispenser

No.

60

Vanity Unit on Counter Top

No.

84

Vanity Wall Unit

No.

18

Handy Cap Unit

No.

Basin

No.

Showers
K

Toilet Paper Dispenser

No.

Vanity Unit On counter Top

No.

15

Handy Cap unit

No.

To summary Q.R

PROVISIONAL SUM

P.S/Page 7/9

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF
HOUSING at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

No.

12

RATE
QR

AMOUNT
QR

Provisional Sum (cont'd)


Hand Wash
A

Vanity Unit On counter Top


Abloution

Vanity Wall Unit

No.

10

Toilet Paper Dispenser

No.

Loacker 600 x 600 mm

No.

282

Sofa

No.

Drinking Water Fountain

No.

No.

30

Cooridor
D

Changing
G

Loacker 300 x 500 mm

To summary Q.R

PROVISIONAL SUM

P.S/Page 8/9

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF
HOUSING at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

RATE
QR

AMOUNT
QR

COLLECTION

Page P.S/1/9
Page P.S/2/9
Page P.S/3/9
Page P.S/4/9
Page P.S/5/9
Page P.S/6/9
Page P.S/7/9
Page P.S/8/9

TOTAL CARRIED TO DIVISION


SUMMARY

PROVISIONAL SUM

P.S/Page 9/9

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF
HOUSING at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

RATE
QR

AMOUNT
QR

Tenderer's Adjustment

the contractor shall describe the enter


below,the quantity of addition for any bill
of the quantity item(s) and or any omited
items that in his opinion are necessary
for the full and proper completion of the
work as described in the specifications or
shown on the drawings and for which
either expressed or implied provision is
required and which are not covered by
items or the rates in the bill of quantities

To summary Q.R

Tenderer's Adjustment

T.A/Page 1/2

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF
HOUSING at Al KHIYSA- UMM SALAL - DOHA QATAR

ITEM

DESCRIPTION

UNIT

QTY

RATE
QR

AMOUNT
QR

COLLECTION

PageTA/1/2

TOTAL CARRIED TO DIVISION


SUMMARY
Tenderer's Adjustment

T.A/Page 2/2

Parcel 2
Secondary School

PROJECT:
CONSTRUCTION OF SCHOOLS COMPLEX AND STAFF
HOUSING at Al KHIYSA- UMM SALAL - DOHA QATAR
Division No.

DESCRIPTION

PAGE/NO

Division1

SUB-STRUCTURE

SB/5/5

Division2

SUPER - STRUCTURE

ST/4/4

Division3

ROOFING

Division4

BLOCKWORK

Division5

CARPENTARY AND JOINERY

Division6

METALWORK

Division7

STEEL STRUCTURE SYSTEM

SSS 3/3

Division8

PLUMBING AND DRAINGE

P.L/9/9

Division9

H.V.A.C

Division10

FIRE FIGHTING

Division11

ELECTRICAL INSTALLATION

Division12

FINISHING

FIN/9/9

Division13

PAINTING AND DECORATION

PAI/3/3

Division14

PROVISONAL SUM

P.S/9/9

Division15

TENDER'S ADJUSTMENT

TA/2/2

Total Amount

ROF/3/3
B/2/2
CAR/2/2
MET/10/10

H.V.A.C/9/9
FF/6/6
ELC/11/11

TOTAL VOLUME 4 SUMMARY

Page 1

Parcel 2
Secondary School

You might also like