Jun 10 QA-2
Jun 10 QA-2
Jun 10 QA-2
com]
Sent: Tuesday, August 24, 2010 5:16 PM
To: [email protected]
Subject: Questions and Answers
Dear Professor,
Thanks for the mails you have sent me regarding above subject matter and today, I have
few questions and I hope you will comment on same.
Note for the Adjustment Items as follow,
The Adjustment item, if any in the Tender Summary, shall apply to all items of Works,
excluding Provisional Sum unless clearly indicated otherwise. The Adjustment Item shall
not be a lump-Sum, but a percentage of the total tendered sum excluding Provisional
Sum or a percentage of the totals for the items indicated. The Adjustment Item shall be
applied to all applicable item rates and sums including any addenda. The Contract shall
be signed with the inclusion of the adjusted rates and sums. The adjusted rates and
sums shall be applied during measure and valuation of variations.
1) My question is, Adjustment Item is applicable only for the BOQ Rates? If not is it
applicable for the BOQ Rates and New Rates, please clarify. According to the above
wording, if a new rate is built-up using the exiting BOQ rates, then the Adjustment would
proportionately apply to such new rate. If however, the new rate is built-up from first
principles (i.e. without using the existing BOQ rates), then the Adjustment would not
apply.
2) Within the Contract Period or Time Extension Period if Contractor is doing any
Variations, as a Consultants we have to pay any additional amount for the Builders Work
( Electricity, Water, Shop Drawings etc.). But we have lump Sum amount in the prelims,
please clarify. Either the lump sum should be broken-down to its components and they
could be used to value those related to the variations or the Contractor could be
instructed to maintain separate records of additional elec/water/shop drawings used for
variations.
Regards,
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Surveyor, Chartered QS, Chartered Manager, Chartered Builder
T. Ariyaratna.
----- Original Message ----From: Chen Xin
To: [email protected]
Date: Tue, 24 Aug 2010 11:00:56 +0400
Subject: RE: Q&A
Hi Prof. Sam,
Warm thanks for all Q&A which are being received via emails.
Could you please comment on my previous question in respect of weekly programme as delay
notice via email dated 01 August 2010 below. See email below.
Furthermore, could you please shed some light on following definitions:- (if wrong, please kindly
correct me)
Practical Completion - which the Works were completed in accordance with the Contract,
except for only minor outstanding work remain, MEP Testing and Commissioning completed.
Therefore, the practical completion certificate to be issued by completion of MEP Testing and
Commissioning. Yes.
Substantial Completion - which not substantially affect the use of Works or section for their
intended purpose. Yes. Therefore, Substantial Completion Date normally is earlier than Practical
Completion Date. No. And both dates are earlier than the date of Time for Completion. No.
Both mean the same thing. Where no specific definition is given for them in a Contract, they
should be read together with other Clauses such as Defects Liability clauses. If provisions similar
to 49.2(a) (FIDIC-4th) exist, then the taking-over of the Works and issuing Taking-Over Certificate
cannot be delayed whilst not only minor defects but also minor outstanding work are still pending
which would not prevent the Employer to put the project to its intended use. If however the
wording in a contract is specific to mean the Defects Liability Period to be only for latent defects,
then completion (or practical/substantial completion) is not achieved if there are any patent
defects or outstanding minor work.
Regards,
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Surveyor, Chartered QS, Chartered Manager, Chartered Builder
Prof. Sam,
Please accept my heartfelt thanks for your valuable continued service to the Industry
and to your Students, specially for your intention to extend your knowledge to us
through this Q & A.
Please could you comment whether a weekly program which identified delaying
events is adequate notice in accordance with Clause 44. It is unlikely that an
Arbitrator or the Courts would consider such a document to be a formal notice. As we
discussed during the 4th Session, a Notice is a specially written document with
specific contents and served in a specific manner. However, if the Clause is not
drafted in a manner to make the notice condition precedent, then there is no worry
because the Contractor does not lose his entitlement to EOT.
Regards,
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Surveyor, Chartered QS, Chartered Manager, Chartered Builder
Regards,
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Surveyor, Chartered QS, Chartered Manager, Chartered Builder
Regards,
If the appendix state Not applicable or Nil, would the clause 18.2.d be
deemed applicable or not? If it says Nil then the amount is zero and therefore
18.2.d. is applicable.
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Surveyor, Chartered QS, Chartered Manager, Chartered Builder
Regards,
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Surveyor, Chartered QS, Chartered Manager, Chartered Builder
1. Is it a correct practice? Noting that CESSM format is to be applied but the rule
will be overlook in this situation. You can depart from the rules provided that you
clearly state in the Preamble about such departure.
Considering a variation that might occur, in my opinion, the rate breakdown for
any certain item of works will be difficult to assess since rate is full inclusive of
work to be done. Yes. The whole purpose of using CESMM3 (as discussed
during the 8th Session) is lost as the rates would become inapplicable to value
variations.
2. In the event this scenario proceeds, during tender stage, can we request the
tenderers to substantiate their pricing methodology? Yes. Better to include
provisions for this in the Instructions to tenderers.
Regards,
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Surveyor, Chartered QS, Chartered Manager, Chartered Builder
Regards,
L. Robles
----- Original Message ----From: Roselma Martinez
To: "[email protected]" <[email protected]>
Date: Wed, 21 Jul 2010 15:36:49 +0400
Subject: RE: Q&A
Sir,
Im a bit confused regarding variation claims on a Lump Sum Contract.
There are items shown on Contract Drawing but there is no detail or specification. For example the Contract
Drawing (Elevation of the Whole Building) it was cut on the section showing canopy but there is no detail or
specification pertaining to canopy. The contractor issue RFI to consultant asking for the details of the
canopy. Can the contractor claim the canopy as a variation? Another example, there is a box type with door
showing in the floor plan (it is not clearly identified what is that item). The contractor again issue RFI to
consultant asking for the details of box type that looks like a lift. The consultant issued a response and
provided the specification for platform lift. Can the contractor claim the additional platform lift as a variation
since there is no specification and details provided during Tender Stage? Can the contractor use as a basis
of his claim the precedence of documents?
Since it is a Lump Sum Contract, the tenderer should have ideally ring-fenced the scope of work properly at
the time of tendering (raised the queries at that time not now !). If this was not done then he has to now
demonstrate with acceptable proof what he assumed that canopy/box to be, for the purpose of pricing the
tender and in no way an experienced contractor could have assumed them to be any other. If the contractor
can produce such proof, then anything other than that instructed by the Engineer would be a variation.
Regards,
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Surveyor, Chartered QS, Chartered Manager, Chartered Builder
Thanks,
From: jasim mohamed [mailto:[email protected]]
Sent: Tuesday, July 20, 2010 10:24 AM
To: [email protected]
Subject:
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Surveyor, Chartered QS, Chartered Manager, Chartered Builder
Prof. Sam,
Negative Variations in Lump Sum Contract
I take this opportunity to thank you for your fruitful classes as well as
valuable education given us with the form of Q. & A. which widened our
area of knowledge towards contract administration.
You have mentioned in most occasions that in a Lump sum Contract,
an omission cannot be instructed (as a negative Variation) for an item
which is not shown in the Contract drawings but appears only in the
B.O.Q.
How we can convince above (basic principle) to the Client/Consultant
where the Contract document doesn't say about it?
Is there any other standard documents for references or guidance?.
Please comment.
Ask from the Client/Consultant if there is no item in the BOQ for a
Chandelier shown in the drawing, whether they would agree to instruct
a variation to add that item to the BOQ.
Obviously they wont. Therefore a variation cannot be instructed to
omit an item for a Chandelier in the BOQ which is not shown in the
drawing.
It is not essential to refer to any documents for such standard practices
in the construction industry, however if your contract is FIDIC 4th,
then you can draw their attention to Sub-Clause 55.1 which states that
the BOQ quantities are not to be used for carrying out work. Therefore
it goes without saying that only the quantities that can be inferred from
the drawings should be executed by the contractor (and therefore his
Lump Sum Price is for those quantities obtainable from the drawings
and not for the quantities given in the BOQ) and therefore no
deduction can be made to a Lump Sum Contract Price unless an item
of work/quantity is omitted from the drawings.
Regards,
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Surveyor, Chartered QS, Chartered Manager, Chartered Builder
Regards,
Nayanasena
Quantity Surveyor
From: Yvette [mailto:[email protected]]
Sent: Tuesday, July 06, 2010 1:14 PM
To: [email protected]
Subject: variation question
Hi Prof Sam,
I thank you for sending us these Q & As , which really helpful with our
day to day Contracts Administration task. I hope to receive more from
you.
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Surveyor, Chartered QS, Chartered Manager, Chartered Builder
Regards,
Yvette T. Vivar
Contract Administrator