Viewport Inspect
Viewport Inspect
Viewport Inspect
Window User: the party who owns, maintains and / or operates the Pressure Vessel for
Human Occupancy (PVHO).
Window User Responsibilities
Provide window designer with service conditions.
Protect the window from damage.
Ensure window is used as designed.
Determine the windows safe service life.
Keep records on all windows.
Establish and maintain an inspection program.
Establish and maintain an inspector qualification procedure.
Ensure that inspectors, both internal and 3rd party, meet the qualifications stated in
PVHO-2-2012.
Under ASME PVHO-2-2012 there are two types of required inspections to insure occupant
safety:
Operational viewport inspection (OVI).
Maintenance viewport inspection (MVI).
The operational viewport inspection is done prior to each pressurization of the PVHO. If
the PVHO is pressurized more than once per day, the viewports need only be inspected
prior to the first pressurization of that day. The objective of the operational viewport
inspection is to examine each viewport component and document signs of damage or
deterioration. The Inspection shall include the following:
(a) Windows. Inspect for signs of crazing, discoloration, cracks, chips, scratches,
gouges, burns, or pits. If flaws are detected, their size, location, and population
shall be recorded and compared to the allowable limits listed in Tables 2-4.1-1
through 2-4.1-4 of PVHO-2-2012. Windows with defects exceeding these allowable
limits shall be taken out of service.
(b) Flanges, Retaining Rings, and Bolts. Inspect for mechanical damage, corrosion,
and deformation. If flaws are detected, their type, size, and location shall be
recorded and compared to the allowable limits listed in the facilitys inspection
program. If any flaw exceeds the facilitys stated limits or as directed by the
facilitys safety director the PVHO shall be taken out of service.
(c) Seats and Seals. Inspect for mechanical damage, corrosion, extrusion, and
irregularities. If flaws are detected, their type, size, and location shall be recorded
and compared to the allowable limits listed in the facilitys inspection program. If
any flaw exceeds the facilitys stated limits or as directed by the facilitys safety
director the PVHO shall be taken out of service.
Paraphrased from PVHO-2-2012 section 2-4.1
The maintenance viewport inspection is done on a schedule specific to your PVHO. The
requirements are laid out in PVHO-2-2012. The inspection itself has the same objectives
as the OVI and covers the same components as the OVI, but is more comprehensive and
is done by an inspector with the next level of qualification from that of the operational
viewport inspector. Special optical and measuring devices are often used during this
inspection. At the discretion of the inspector, components of a viewport may need to be
removed for a more detailed inspection. PVHO-2 Form VP-1, Viewport Inspection is
completed and signed by the inspector.
We will assume that the decision has been made that the Maintenance Viewport
Inspection will be outsourced.
Window fabricator.
3rd party organization.
Representative of your management company.
The window user is responsible for selecting a competent contractor to provide these
services.
The window user is also responsible for establishing a policy and schedule for meeting the
requirements of the Maintenance Viewport Inspection.
If your facility does choose to do this inspection, much more education and resources will
need to be acquired.
Staff Training Module (OVI specific)
This can be a self learning packet or lecture.
The training needs to be facility specific.
The training also needs to include how the facility policy and inspection schedule
was established.
The validation method should include a test and observation by the hyperbaric safety
director.
Facility Policy and Inspection Schedule
It needs to meet the minimum requirements set forth in ASME PVHO-2-2012 based
on your facilitys unique circumstances.
Service environment
Service life of the window(s). ( < or > design life)
Window type(s).
2
July 2013
3
July 2013
4
July 2013
B cyl.
0.03"
0.01"
0.01"
Key:
* Data taken from ASME PVHO-2-2012, Table 2-4.1-2 Limits for Blemishes or Flaws on Window Surfaces
Document findings
If the limits are not exceeded: Use the facility generated form for recording and
tracking damage and deterioration to the viewports.
Record: Date, location, flaw type, depth, width and length.
If the limits are exceeded: That lock needs to be taken out of service until the
specific viewport component in question has been repaired or replaced.
Depth/Width Perspective
21 lb. copy paper is 0.004"
A typical business card is about 0.01"
1/64" < 0.016"
A cereal box is about 0.02"
Window Flaws Can Be Caused By:
External mechanical damage.
Heat.
Solvents and solvent-vapors.
Age.
Ultraviolet light (wave length < 320 nm).
X-rays.
Pressure (amount, comp. rate, duration, previous loads, # of cycles).
Pressure (combined with- heat, solvents & vapors, age and UV).
Damage To Other Components Of The Viewport Can Be Caused By:
External mechanical damage.
Deterioration of protective coatings leading to corrosion of unprotected material.
Uneven or leaking pressure leading to extrusion of seats and seals.
5
July 2013