Cutoff-Grade Analysis at Fazenda Brasile PDF
Cutoff-Grade Analysis at Fazenda Brasile PDF
Cutoff-Grade Analysis at Fazenda Brasile PDF
Synopsis
Underground working at the Fazenda Brasileiro gold
mine started in 1988. Initially, surface declines served
both access and production needs, but as the mine
deepened the development of a central ore-hoisting
shaft became necessary. The effects of increased mining
costs in recent years have been made worse by falls in
the gold price. Steps that have been taken in response
to improve the long-term economic future of the mine
include the development of a declining cutoff-grade
strategy. The main objective of this strategy, for implementation over the life of the mine, is to increase its net
present value. Incorporation of an opportunity cost element in cutoff-grade calculations has led to higher
cutoff grades than were previously adopted. The application of a declining cutoff-grade methodology also
assists in short-term decision-making with respect to
major variations in the gold price. Additonally, operational cutoff grades have been calculated, for both
mine-limited and mill-limited situations, to aid the
evaluation of different situations. Finally, the overall
long-term planning model developed for the cutoffgrade study provides a means to analyse the sensitivity
of other mining parameters.
The Fazenda Brasileiro gold mine is in Teofilndia, Bahia,
Brazil, some 210 km northwest of the city of Salvador
(Fig. 1). Its development is summarized by the following
noteworthy dates:
1972
1974
1976
1984
1985
1988
1992
1999
Fig. 1
CIP + Heap-leach
5000
4000
Heap-leach only
3000
2000
1000
0
Fig. 2
Geology
The Itapicuri Greenstone Belt trends northsouth, extending
for 100 km with a width of approximately 40 km, in the
northwest of Bahia State, Brazil. This belt is composed of
three major lithological domains: mafic, felsicintermediate
and sedimentary. Granitic bodies intrude all of the sequence.
The Fazenda Brasileiro deposit is located in the southern part
of this structure, hosted within a sheared mafic unit of the
eastwest-trending Weber Belt. The deposit is mesothermal
and extends for some 13 km.
The Weber Belt is composed of a basal mafic unit and an
upper volcano-sedimentary unit. It is set locally between
basaltic rocks, with carbonatic sedimentary lenses of the
A35
Fig. 3
Metasediments
Volcaniclastics
Metagabbro
Pyroclastics
Gneiss
Metabasalts
Volcano-sedimentsCanto Sequence
Riacho do Inco Sequence on the footwall and felsic volcanosedimentary rocks of the Canto Sequence in the hangingwall. The Weber Belt is also characterized by the presence of
intrusive rocks of gabbroic to felsic composition. These intrusions are associated with large structures where hydrothermal
alteration can be observed. Fig. 3 shows a plan of the south
part of the Itapicuru Greenstone Belt.
The main host rock for the mineralization is a magnetic
schist (quartzchloritemagnetite schist), which occurs in two
horizons to the south and north of the gabbroic unit. The
mineralization dips 4050 southwards. The mineralized ore
shoots also tend to have a plunge of approximately 10 eastwards. Six main ore shoots have been mined so far and
various minor satellite orebodies are known. These ore shoots
occur in a portion of the Weber Belt approximately 8 km in
strike length. The ore shoots are 200800 m long and 230 m
wide. At present, the underground workings are 500 m deep
and mineralization has been intercepted down to a depth of
800 m.
Initial exploration was generally based on surface diamond
drilling, employing a section spacing of 400 m along strike.
Definition of the most promising areas is accomplished by
systematic reduction in the interval between geological drill
sections from 400 to 100 m. In addition, the section spacing
of 100 m provides information with which to undertake the
design of primary access and infrastructure. More recently,
exploration drifts have been excavated to provide access to
the mineralization found at depth. Currently about 6000 m of
A36
trucks at loading points 100150 m apart. Modern techniques and state-of-the-art equipment are used, enabling high
productivity and standards of safety to be achieved. Getman
and Nitronobel auxiliary service vehicles are employed.
The sulphide ore is fed to a CIP plant, where it is crushed
in three stages and subsequently fed to one of two ball-mills.
The milled pulp is cycloned and fed to Knelson or Falcon
concentrators. The concentrate is cleaned on vibrating tables,
producing 50% of the final gold. Afterwards the concentrate
pulp is passed to a thickener, where process water is recovered. Thereafter, thickened pulp is transferred to two
cyanidation lines where dissolution of the gold takes place.
Gold is adsorbed on to activated carbon, which is screened in
elution columns, and the gold is released. The pregnant solution is pumped to an electrowinning section to recover gold
on cathodes. Gold bullion at 90% Au is subsequently produced in the form of 12-kg bars.
Fig. 4
The original mine layout was influenced by the surface outcrop of the deposit. Thus, development of the underground
mine started with a ramp system for access, services and
haulage. This configuration contained the capital expenditure
on underground access and infrastructure, thereby increasing
cash flows during the early years of production. However, as
the shallower orebodies were exhausted, deepening of the
mine workings led inevitably to extended haulage distances
and increased costs for development, extraction, ventilation
and general infrastructure. At the same time, exploration
from surface became increasingly difficult and more costly.
All these factors led to the development of the recently completed ore extraction shaft.
In addition to these challenges mining costs have been
continuously increasing and the gold price has been declining. These pressures have created the need to focus on key
aspects of mine planning. In particular, with the long strike
length of the deposit, the selection of ore blocks to be stoped
has a critical effect on the amount of developmentfor
required infill drilling access as well as for stope preparation
and subsequent mining. These problems have been further
compounded by the large proportion of inferred resources at
the mine and how these are best considered with respect to
long-term mine-planning decisions.
It was realized that a key element in addressing many of the
mine-planning issues was the cutoff grade. Accordingly, an
initial cutoff-grade study was completed at the mine towards
the end of 1996. This enabled an assessment of the potential
impact of cutoff grade and was followed up by further work
on cutoff grades, the results of which are described here.
Another initiative was started to gain a better understanding
of, and engineering control of, ore dilution. This, in turn, has
led to some of the results of the cutoff-grade study being
analysed with respect to variations in dilution.
The most significant aspects of this cutoff-grade project
were: (i) establishing maximization of the mine net present
value (NPV) as the principal objective in the calculation of
cutoff grades; (ii) use of an opportunity cost in cutoff-grade
calculation; (iii) consideration of a declining cutoff-grade
strategy as part of the life-of-mine plan; and (iv) ensuring that
cutoff grades were applied and tested against approximately
stope-size units of potential ore.
The way in which this cutoff-grade analyis was considered,
with respect to long-term mine planning, is presented
schematically in Fig. 5. The geological tonnage and grade
data were prepared so as to form an available reserve base.
A cutoff-grade analysis was then applied to determine which
parts of the deposit would be included in the long-term
A37
Fig. 5
VULCAN
EXCEL
Fig. 6
VULCAN
EXCEL
Table 1
Measured
Indicated
Total
12
101
12
32
19
51
44
19
63
101
104
172
276
205
172
377
Cutoff-grade analysismethodology
Optimum cutoff grades
Fig. 7
A40
Principal component
Operations
Access
Mineralized material
Shaft sinking,
primary development
Treatment
and stoping
Ore
Stoping, tramming,
hoisting
Crushing, grinding,
separating
Marketing
Metal
Smelting, refining,
selling
V +
f +F
A
NSR r
V+
In situ Gtend =
f
A
NSR r
(1 + d)
(3)
Optimization methodology
Under normal conditions the opportunity cost is given by
F = c PV
(4)
(1)
(2)
Fig. 8
A41
Gt1 =
V +
f+ F
A
NSR r
(1 + d )
(6)
V2 +
f+ F
A
NSR r
(1 + d )
(7)
V3 +
f+ F
A
NSR r
(1 + d )
(8)
V4 +
f+ F
A
NSR r
(1 + d )
(9)
Fig. 9
Tonnagegrade curves
V3
(1 + d)
NSR r
V4
(1 + d)
NSR r
(11)
Fig. 10
(10)
A43
A44
Fig. 11
Fig. 12
Table 3
33% Dilution
NPV Au, g/t
26% Dilution
NPV Au, g/t
43
68
56
82
4.7
5.5
5.0
5.8
A set of operational cutoff grades, which applied to the current economic and operational conditions at the mine, was
calculated in accordance with the theory presented above
(Table 4). The opportunity cost used was that which
reflected the low gold price of $285/oz. When the current
Table 4
Type
Description
Initial stope
selection
Application of all
relevant stope
preparation costs
After stope
Stope development
development costs removed from
complete
variable costs/t
In-stope caved Drilling and blasting
muck
costs also removed
Development Only treatment costs
muck
in variable cost
n.a.
3.6
n.a.
3.4
1.3
1.2
0.9
Surface
Shaft
Development muck
1.2 g/t
Variable costs,
treatment only
Fig. 13
Further work
An inferred resource was also used in the project, being based
on the assumptions of (a) a fairly uniform incidence of ore
occurrences with depth and (b) a distribution of minable
blocks similar to that of the existing measured and indicated
blocks.
It is known by geologists on site that initial exploration
drilling may well have missed occurrences of ore within the
CLX horizon. Mining and geological experience at the mine
supports the occurrence of many potential ore blocks at a
spatial frequency similar to that found in the upper regions of
the mine. To improve assessment of this inferred resource
base and its potential effects on the mines future the geological department intends to apply conditional simulation
techniques. Besides assisting in the development of cutoffgrade strategies it is intended that this will enable testing of
the primary development layout and schedule with reference
A45
A46