Equipment Cost Estimating - Otuonye - 2000
Equipment Cost Estimating - Otuonye - 2000
Equipment Cost Estimating - Otuonye - 2000
I of42
CEAPTER
lPsrt2
Name
Address
Operation
Req'd
Production
Location
Unit Model
Yds.
Heaped Cap
lbs.
Material
Bank
Yd.
Yd.
lbs. Swell
Capacity
Factor
Loose
lbs.
Cu.Yds
Yds.
Bank
lbs.
Bucket Size
Loading Conditions
Bank Cu. Yds.{.
No. OfPasses to
Loading Production
Tons or
A. LOADING
TIME
Mn.
Loaded Haul-Total
o
Length
Ft. Elevation
Rolling
Resist.
Section
Per Cent
Grade
Road
Gear
Time
Min.
Speed
Ft.
Rolling
Resist.
Section
Hauling
Speed
Min.
-Total
Length
Max.
Factor
in Ft.
Trans.
Ft.
Per Cent
Grade
Trans.
Gear
Max.
Speed
Average
Speed
Factor
Speed
Return
Time
in Ft.
6.
htm
5120100
Page2 o142
Min.
Time
Spotting
Mn.
H. Hour Production
Yds. Per Hour
Hour: :,Yh.,Pr=od.,tr:_
(F) Total Cycle Time
Tons or Bank
Production Req'd
:
- : _!ur!L
(H) Bank Yds. or Tons per Unit per Hour
Units
Fleet Production per Hour
Jx
H:
Bank Yds.
Units@_
orKReq'd
each:
each:
Total
TON:
Fleet Production
Production
ESTIMATING COSTS
Types of Costs
http ://www. mg. mtu. edu/-frotuony/mg33 6/2m9336. htm
sl20l00
Page3 of 42
Ownership Costs
Those costs which are incidental to the purchase and possession of a piece of equipment before any
use or income may be derived from that unit.
A fixed cost
Operating Costs
Those costs which are incurred in using the unit to perform its designated tasks.
Ownership Costs
Depreciation
A reserve established to offset the effects of wear and obsolescence on a piece of equipment so that,
theoreticall sufficient funds will be available to replace the existing unit when it has lost its value. An
alternate definition is that depreciation is the loss in value of equipment resulting from use or age. The
owner of equipment must recover the loss in value of equipment during its useful life or he will sustain
an equipment loss on those projects where the equipment is used.
In estimates, the straight line method of depreciation is generally used and it is assumed that the
equipment possesses no scrap value at the end of the period.
Total Cost of Equipment: Purchase Price + Cost of Transportation + Cost of Unloading &
Erecting '
Normal Depreciation Schedules:
a. Scrapers - 5 yrs at2,000
hrs/yr: 10,000
hrs
It is convenient to
express costs in an hourly basis. To obtain hourly depreciation rates, divide the
delivered price less tires by the total hourly depreciation schedule.
www.
mg. mtu.
sl20l00
Page 4
o42
(Where
n:
n+1
2"
Ddived Price
The formula is derived by taking the average value remaining in the unit at the beginning of each
succeeding year of its useful life (refer to example I and 2).
Operating Costs
Fuel cost per
hour:
Lubrication costs per hour are estimated from required service intervals as listed in vehicle
manufacturers service manuals.
Maintenance and repair costs per hour can be estimated by taking a constant times the fuel
consumption.
Tire costs are based on an average discounted price available to most fleet owners divided by tire life.
Operator's hour wage varies locally, and current labor rates should be consulted.
Supervision and overhead costs should be scheduled in this estimate.
Other figures of importance are:
a) Scrapers, cost per yard
6I
2mg3
3 6.
htm
5120/00
Page 5 o142
qlrating cmts
prudwtion,tonsperlnur
hourlJr ownlp +
Each manufacturer has detailed guides for calculating ownership and operating costs.
EXAMPLE
Original cost of equipment: $25,000
life:5
Estimated useful
years
$0 $25,000
2 5,000 20,000
3 10,000 15,000
4 15,000 10,000
5 20,000 5,000
6 25,000 0
Averagevalue:
!$$ffi
ry
1l'999 -
fOO
Er7o
25,000
o/o
of purchase price
$$,ooo
It
o/o
EXAMPLE
Original cost of equipment: $12,000
Estimated useful
life:4
years
36I
2mg3 3 6 .htm
5120100
Page 6 of 42
2 3,000 9,000
3 6,000 6,000
4 9,000 3,000
5 12,000 0
$?Foo
cost:
Average
value:
ryqq
ffi.
tOO
= 625to/o
o+l
o/o
of purchase price
x looo/o
1*roo =
= 4+l
88 =
frL.ilol
COST ESTIMATION
Haulage Unit (Truck)
A. Ownership Costs
1. Depreciation
a) Purchase Price: estimate as $7650/ton of truck capacity (live load).
5120100
Page 7 of 42
f) Delivered price: u_rchase price) + (freight) + (unloading and moving cost) - (salvage value) (tire
-
cost)[a+c+d-b-e].
shifl/day of operation.
* taxes f
other.
rate.
+I
2n
where
n:
B. Operating Costs
1.
61
2mg336. htm
5120/00
Page 8 of 42
unfavorable lTYo
3. Repairs
& maintennce
: (depreciation)(repair
cost
unfavorable 60Yo
4. Fuel or power
cost, $/gal)
unfavorable 0.026
6I
2m9336. htm
sl20l00
Page 9 of 42
5.
Lubrication
: (fuel, cost/hn)(lubrication
factor)
favorable l/5
average
l/3
unfavorable %
6. Labor = (wage rate) + (35%wage rate)
Assume one (1) operator per truck and35yo of wage rate as benefits.
7. Total operating costs
+2
+3 + 4 + 5 + 6
D. Unit Cost
1. (Cost of owning and operating)(Units in-run)
Dl
Dl
: (x truck unit$(C)
D2:
(y truckunitsxA3)
3. Total cost of owning and operating x units in-run and owning y spare units
D3:Dl +D2
4. Unit
cost:
Hourly production:
=$ton
bN*
shift
shift
# of hosofqeration
values with known varues
if possible.
5120100
Pg i of42
EXAMPLE
Determine the total hourly and unit cost of owning and operating five 85-ton trucks and one spare 85ton truck ifthe trucks operate on an 8-hour shift and the following information is provided.
Operating conditions: average
l4%o,
taxes:
2Yo,
other:2Yo
61
2mg336. htm
5120100
Page 17 of42
A. Ownership Costs
1.
DEPRECIATION
a. Purchase
price:
b. - Salvage value
c.
$650.250
(UZ:
- 97.538
4.760
cost:476
:557.948;
say $525.000
less
tire cost)
: $_3j.0q /hr
U*88q hr
2. INTEREST, TAXES, INSURANCE AND STORAGE
a. Rate
rate:
6I
x 56.7Yo:
$Difi
2mg336. htm
n*l
n
S.5
l5
56,79t
5/20/OO
Page 72 of 42
charge: $5_3J82
2000 hr/yr
: S 26.79 lhr
: $ 61.79 /hr
B. Operating Costs
set of tires
W212
V2_I2
& MAINTENA{CE:
45Yo
$35-QQ
: $ 2.2L {hr
x 15/10 deprec.
: $ 23.63 lht
5.
/lr
operator @$ 12,90
/lr:
$ 12.00 lhr
@lhr: lfu
helper @
lhr:
lhr
lfu: $ t6.20 lh
: $ 77.71 III
http
II
sl20l00
Page 13 of 42
(Own)
standby
5759.29/hr
price:
hr:
Depreciation:
tires
yr (n)
tire cost)
: $_/hr
hr
2. INTEREST, TAXES, INSURA}ICE A}{D STORAGE
a. Rate
%o
r+l
b. Average annual investment
rate:
2n
oZ: $
hrlyr:
charge:
$_/hr
5/20100
ase
i4 of 42
: $ /hr
B. Operating Costs
1. TIRE
REPLACEMENT COST
tires:
Tire life hr
Tire
cost:
hr: $ /tr
2, TIRE REPAIR COST:
3. REPAIRS
o/o
$_tire
& MAINTENAIICE:
cost:
o/o
$_/hr
x $_x_deprec. : $_/hr
: $_/hr
5.
6.
AIIXLIARY FUEL:
7. LABOR: operator
oiler @
llv:
helper @
$_/hr
@$_/ltr:
$_/hr
llv
ltv: llr
Total $ /h
+ 35yo benefits $
/lr:
$ /hr
: $ /hf
: $ /hr
(Own)standby@$:$_/hr
5120100
Page 15 of 42
:$/hr
E. The discussion on trucks would also apply to:
1. Shuttle cars:
Selpropelled rubber-tired haulage vehicle designed for underground mining, primarily in coal mines.
Drive mechanism is located on the sides of the vehicle and the load is carried in the center.
A chain and flight conveyor distributes the load when the car is being loaded by a loading machine or
continuous miner and also discharges the load onto a conveyor belt or into a mine car.
As the name implies, shuttle car shuttles back and forth between the working face and the unloading
point and is not required to turn round.
Cost Estimation
Haulage Unit (Truck)
A. OWNERSHIP COSTS
1. Depreciation
a. Purchase Price: estimate as $7650/ton of
(cwt:
loadO
1001b)
f. Delivered price: a
* c*
d-b-e
5120100
Page 16
of42
shift/day
Rate: interest *
t<es
* insurance
f other
rate: n+l/2n
B. OPERATING COSTS
1. Tire replacement cost
6. Labor: assume
7. Total operating
cost: Bl + B2 + ... + B6
s/20100
Page 17 of 42
: (*) (c)
2. Cost of owning y spare
3. Total hour cost of owning and operating x units-in-run and owning y spare
units: Dl + D2
4. Unit
EXAMPLE:
Determinethe total hourly and unit cost of owning and operating five 85-ton trucks and one spare 85ton truck if the trucks operate on an 8-hour shift and the following information is provided.
Operating conditions: average
12.00/hr
l4%o, taxes
2Yo, other
:2Yo
A. Ownership Costs
I. DEPRECIATION
a. Purchase
price:
$650,250
4.760
cost:476
s/20/00
Page
e. Delivered
price:557.948
f. Operating period
20OA
ir
of+z
say $525.000
hr:7.:L yr(n)
15.000 hr
2. INTEREST, TAXES,INSURA}ICE, A}ID STORAGE
a. Rate
rate: (n+l)/2n:
8.5/15
:$
56.7 yo
x 56.7yo: $297.5g2
Purchase price
set of tires
: $ 32.512
$ 32.512:$13.0_O
/lr
2500 hr
/tr
:$
17.00 /hr
6. AIDLIARY FUEL:
:$ - /hr
33 6 I 2mg336.
htm
5/20100
Page 19 of 42
7.
/hr:
$ IZ.OO lItI
oiler@$/hr:$/tr
helper
@g_ltu:
Total $ 12.00
$ /hr
lly
/lr:$
16.20 lhr
S 759.29
ltv +
1250
tonftr
(Own)
:$
139.50 /h
: $ 0.61 /ton
697.501tr
standvy @561.79:61.79
S759.2glltr
desired.
,.,,2.
,,'Determin
'.'.loader
,,.,CyCle
, time
http ://www. mg.mtu.
5120100
Page 20 of 42
lxo%efficiency
fl min
total clule time min'
iii. Correction in cycles per hour has to be made using efficiency factors for the loader
3. Determine payload per cycle in tons, pounds, and loose cubic yards.
_ hourly pruduction
a) Required production per
# of cycles/hr
cycle
rcquird uaylnad/cwle
b) volume or loose cubic yards per
4. Determine bucket
cycle
size
5. Make machine selection using bucket size and payload as criteria to meet production
http //www. mg. mtu. edu/-frotuony/mg33
:
61
2m9336. htm
sl20l00
Page2l of 42
requirements.
6. Compare the cycle times of the loader, used in calculations, to the cycle time of the selected
If there is a difference, rework the process beginning at step 2.
machine.
fill factor)
8. Loader
p, =
'
Where: P,
C,
Fr:
F.
60
can be determined as
xClxFfxFt
tar"
T,l":
return
maneuver + delays
9. I)ozer production assuming l00yo efficiency and/or availability can be calculated as:
5/20100
Page 22 of 42
Where:
Po:
Lu:
blade loading,
F.:
t,u:
Lyd,
Dozer production is in bank volume of material excavated, but the blade loading and volume
material spread, dumped or piled, is in loose volume.
10.
of
as
.' _ 60xLx'!VxP
'
tt,
Where:
Pr:
,, = oI:r,=
Where: P,
L.:
t,,
ry
5120100
Page23 of42
Lr=CrxF,
Where:
Lr:
material swell
A.Introduction
The major types of excavators used in earthmoving operations include:
1. Members
2. Struck Capacity - Bucket capacity when the load is struck offflush with the bucket sides.
3. Water Line Capacity - Assumes a level of material flush with the lowest edge of the bucket (i.e. the
material level corresponds to the water level that would result if the bucket were filled with water.
4. Heaped Volume, expressed in Lcy - maximum volume that can be placed in the bucket without
spillage based one specified angle of repose for the material in the bucket.
6.
htm
sl20l00
Page24 of42
EXAMPLE
Estimate the actual bucket load in bcy for a loader bucket with heaped capacity of 5 yd3.
Soils bucket
:3.
bcy
at2:l
angle of repose
6.
htm
s/20100
Page25 of42
Speeds are
too low.
b) Truck mounting
capable of higher speeds of 30 mph
to 50 mph.
c) Wheel mounting
Speed is intermediate between crawler and truck mounting.
Truck and wheel mountings provide greater mobility between job sites, but are less stable than crawler
mountings and require better surfaces over which to operate.
2. Revolving Deck or Turntable
D. Shovels
(The figure shows members of the crane-shovel family according to the US Dept. of the Army).
Whelher dbsigned primarily for stripping or loading, has its greatest application in handling tight or
poorly fractured overburden because of its crowding action, which allows a higher breakout force to
be applied.
Can handle loose material as well as rock and block-like material and
Cycle times are lower because most of the material loaded is confined to an area directly
in front ofthe unit and dumped within a relatively short radius of the loading point.
Ordinarily a shovel works from a position directly on top of a coal deposit, eliminating the need for
preparation of a working bench.
Relatively thin overburden, which permits low stripping ratio.
Combinations of shovel and truck move the overburden quickly and farther than any stripping capacity
dragline.
5120100
Page 26 of 42
a) Stripping shovels
Strip overburden to expose minerals such as coal, phosphate, bauxite, gJsum, iron, stone, etc.
Remove overburden and waste by a dry excavation process.
Remove overburden in long nanow cuts from the pay material and deposit it by a simple overcasting
process in an adjoining mined out pit.
Simple overcasting.
Tandem operations with other machines to remove overburden. Tandem operations can note the use
of two or more machines, each removing and spoiling overburden with one machine following
another.
Shovel-pull-back, a shovel in connection with a dragline operating "pull back".
Generally offers lower overall operating costs than draglines or bucket wheel excavators
comparable size. This is a consequence of a number of factors including:
a.
of
to 180 yd3 with boom lengths of up to 235 ft.and can handle lengths of up to 43 m
(140 ft) of available stripping.
Price of a stripping shovel with 100 yd3 dipper and200ft boom including shipment and erection costs
12.0 x 106.
sl20l00
Page27 of42
2. Shovel Size:
The size of the shovel is indicated by the size of the dipper, expressed in yd3.
The earth is struck even with the contour of the dipper. This is referred to as struck volume,
distinguished from heaped volume which the dipper may pick up in loose soil.
Due to the swelling of a soil when it is loosened, the bank measure volume of a dipper will be less than
its loose volume. It is possible that a dipper may be heaped sufficiently to give a bank measure volume
equal to the rated size of the d ipper. This condition will not occur except for in easy digging soils.
forced out (crowded) or pulled back (retracted) by the turning of the dipper shaft. Dumping is
accomplished by releasing the dipper door latch, a llowing the dipper door to swing open.
In the digging action, if the depth of the face is just right, considering the type of soil and the size of
the dipper, the dipper will be filled as it reaches the top of the face.
In selecting the size of a shovel, the two primary factors which should be considered are the cost per
cubic yard of material excavated and the job conditions under which the shovel will operate. A
crawler-mounted shovel usually is less expensive than the rubber tired mounted unit and can operate
on ground surfaces which are not firm enough to support the latter type unit.
Thc follswing onditions should be considered in selecting the size of a shovel;
a. High lifts
a basement or trench
6I
2mg336. htm
5120100
Page 28 of 42
b. If blasted rock is to be excavated, the large size dipper will handle bigger rocks.
c. Ifthe material to be excavated is hard and tough, the dipper of the large shovel which exerts higher
digging pressures will handle the material more easily.
d. If the time allotted to the completion of the job requires a high hourly output, alarge shovel must
be used.
e. The size of available hauling units must be considered in selecting the size of the shovel.
Weight limitations imposed by most states for hauling on highways may restrict the size of a shovel
if it is to be hauled over state highways.
4. Optimum Depth of Cut
The optimum depth of cut is that depth which produces the greatest output and atwhich the dipper
comes up with a full load without undue crowding, The depth varies with the class of soil and the size
of the dipper.
5. Output of Power Shovels - Depends on:
a.) Class of material
b.) Depth of Cut
If the depth of the face from which a shovel is working is too shallow, it vvill be difficult or impossible
to fill the dipper in one pass up the face.
If the depth of the face is greater than the minimum required to fill the dipper, the operator may do
one of three things:
i. Reduce the depth of penetration of the dipper into the face in order to fill the dipper in one full
stroke - results in an increase in cycle time.
ii. Dig above the base and remove the lower portion for the face later. iii. Run dipper up the full height
of the face and let the excess earth spill,
c.) Angle of Swing
Angle of swing of a power shovel is the horizontal angle expressed in degrees between the position
the dipper when it is excavating and the position when it is discharging the load.
of
sl20/00
Page29 of 42
If
angle of swing increases, time for a cycle increases and vice versa.
No two excavating jobs are alike. There are certain conditions at every job over which the owner of
the shovel has no control. These conditions are considered in estimating the probable output of a
shovel. Consequently job conditions may be classified as excellent, goo, faii, and poor.
Ajob having
i. A shovel operates in a large, open pit with a firm well drained floor, where trucks can be spotted on
either side ofthe shovel to eliminate lost time. ii. Terrain of the natural ground is uniformly level so
that the depth of cut is always an o ptimum.
iii. Haul road is not affected by climatic conditions such as rain or snow.
hauling units.
ii. The sides of the cut must be carefully sloped. The sides ofthe cut may be so narrow that a loaded
truck must move out before an empty truck can back onto loading positions. As the truck must be
spotted behind the shovel, the angle of swing will approximate 180o.
iii. The floor of the cutmay be muddy which will delay the movement of trucks. Light rains may delay
operations for several days.
e) Management Conditions
The attitude of the owner of a shovel will also affect productivity. While the owner may not improve
job conditions, he or she can improve management conditions. The following are just u f.* goa
things he or she can do:
a. Provide a competent supervisor.
5120100
Page3} of 42
g) Ph)sical conditions of the shovel
EXAMPLE
Consider a3/4 cu-yd shovel excavating earth with 90 swing and with a 2l
sec. cycle time.
Assume dipper & truck are operated at their heaped capacities.
Assume that the number of dippers required to
fill a truck:
capacity
Assume that the travel cycle which includes traveling to the dump, dumping
and returning to
6 minutes.
shovel:
+
3t{
2l seconds
: 2l x 4 :
4 rlpers
g4 seconds
1.4 minutes
1.4:
5.3
Thus, 6 trucks will be necessary to keep the shovel busy or else permit the
shovel to idle between
trucks.
Time to load six
trucks:6 x
1.4
: 8.4 min.
ff6
6 - 8.
3t4
16g
seconds:2.g minutes
: g.g seconds
36.
htm
:3.15
s/20100
age
trucks:
3 x 2.8
3t
o+2
: 8.4 minutes
: 8.4 + 8.8 :
.95
:95yotruck time,
or a loss of (11.2-8.8)/11.2:2tYo
Assume shovel is operating80%o efliciency.
# of cycles per minute
# of cycles per
hour:
60/21:2.86
60 x
171.6
2.86:
128 x 0.80
truck:
:102
cu-yd
6 minutes
x 102:97 cv-ydper
hour.
cu-ydper hour.
driver: $14.70
: $44.10
14.70)/60 = $0.66
Haulingcostpercu-yd:
:97
: $0.11
ffi
$.4s6
sl20l00
Page32 of 42
EXAMPLE
in-run:4
:4/.8:5
Number purchased:
Acceptable availability
Capital Utilization
units
415
80Yo
: 3.3/5 : 66Yo
Check shovel capacity per hour and compare to truck capacity per hour.
Check body size.
p.lJL4 =
,
.
" volume:demsity
(bcy)
Body
2:I heq
ffi=2sesr=26y:
Actual Payload
2gg Jd 3
EXAMPLE
Consider a I cu-yd power shovel for excavating hard clay with a depth of cut of 7.5 ft. An analysis of
the project indicates an average angle of swing of 75, job conditions will be fair, management will be
good. Determine the probably output in cubic yards per hour bank measure.
Solution
From Table: ideal output
:145 cu-yd/hr
6I
2mg336. htm
5/20100
Page33 of42
cut:7.5
factor:
: 7.5/9 :
83.3Yo
0.69
145
1.04
For a 50 minute hour @fficiency: 50 min), the probable output:0.83 x 104 : 86 yd3
6. Production
100% efficiency
90% (90 degree) angle of swing
Power shovels are rated by their ideal output (yd3llv or -3/hr. The output is a function of:
bucket size
type ofmaterial
6I
2m9336. htm
5/20/00
Page 34 of 42
working time
difficulty in digging
type of haulage unit
b) Calculation:
Cycle
time:
+ dumping
factor:
+lcr ir
yd
t Oanlc mmrurc)
EXAMPLE
Based on the following information determine the expected shovel production in
bank cubic yards per
hour.
Shovel size:2yd3
Swing angle:120
s/20100
Page35 of42
Average depth of
cut:8.2 ft
Solution
Ideal output
: 300 bcy/hr
:10.2ft
cut:8.2 ft
A.Ettrl dqtJr/optimrmr
rl+th
8.2 x t0t
t0.2
= 80o/o
: 0.86
193.5 bcy/hr
E. Draglines
Draglines are used to excavate earth and load it into hauling units, such as trucks or tractor-pulled
wagons, or to deposit it in levees, dams, and spoil banks near the pits from which is excavated. In
general, a power shovel up to a capacity of 2.5 yd3 can be converted into a dragline by replacing the
boom of the shovel with a crane boom and substituting a dragline bucket for the shovel dper.
For some projects either a pou/er shovel or a dragline may be used to excavate materials, but for
others the dragline will have a distinct advantageiompard with a shovel. A dragline usually does not
have to go into a pit or hole in order to excavate. It may operate on natural ground while excavating
material from a pit with its bucket. This will be very advantageous when earth is removed from a
ditch, canal, or pit containing water. If the earth is hauled with trucks, they do not have to go into the
pit and contend with mud. If the earth can be deposited along a canal or ditch or near a pit, it
frequently is possible to use a dragline with a boom long enough to dispose ofthe earth in one
operation, eliminating the need for hauling units, which will reduce the cost of handling the earth.
Draglines are excellent units for excavating trenches when the sides are permitted to establish their
angles of repose, without shoring.
One disadvantage in using a dragline compared with a power shovel is the reduced output of the
dragline. A comparison ofthe ideal output of various sizes of draglines with the output of power
shovels shows that a dragline will excavate approximately 75 to 80 percent as much earth as a shovel
ofthe
same size.
6.
htm
5120100
Page 36 of 42
a. Does not have the positive digging action or lateral control of the shovel.
b. Ease of maneuverability.
c. Since the dragline operates on top of the overburden, certain problems such
runoffand seepage are reduced or eliminated.
as bank slides,
water
d. Compensation for pitches and rolls in the mineral deposit can be made and if necessary, the dragline
to chop down a small portion of the overburden to prepare it a working bench.
may be used
Pressure exerted on the ground range from 19 psi for large machines to bearing pressures of 9.5 psi
for smaller machines making them extremely suitable for soft or wet formations.
g. Can operate on the tops of spoil either as a primary stripping tool or for reclamation purposes.
h. Ideal for producing the initial or box cut in a stripping operation, a procedure that is almost
impossible for a shovel.
i. Can be effective in operations such as building roads and ditches in addition to being able to clean
rough coal seam for direct loading into transportation vehicles.
to
150 yd3.
5120100
Page37 of 42
1. Types of Draglines
crawler mounted
truck mounted
wheel mounted (wagon mounted & walking draglines)
2. Size of Draglines
Size is indicated by the size of the bucket expressed in yd3 which in general is the same size as the
dipper of the shovel into which it may be converted.
3. Operation
Excavating is started by swinging the empty bucket to the digging position, at the same time stacking
offthe drag and hoist cables.
Excavating is accomplished by pulling the bucket toward the machine while regulating the digging
depth by means of the tension maintained in the hoist cable.
The cycle is made up
of
a. Digging
b. Hoisting
c. Swinging
d. Dumping
It
is more difficult to control the accuracy of dumping from a dragline as compared with a power
shovel; it is desirable to use larger hauling units for dragline loading in order t reduce the spillage.
the
Depth of cut
6.
htm
5120/00
Page 38
of42
angle of swing
size and type of bucket
length of boon
job conditions
managemeil conditions
rnethod
ffud,
si
dllanig
skM
dqer-aor
ws
LiU[ duty buckets - used for excavating materials which are easily dug such as sand, or sand clay.
Medium duty buckets - used for general excavating service
gravel.
Heavy duty buckets - used for mine stripping, handling blasted rock, excavating hardpan and highly
abrasive materials.
Buckets are sometimes perforated to permit excess water to drain from the loads. In selecting the
most suitable size of bucket to use for use with a given dragline, it is desirable to know the w:eight of
the loosened material to be handled, expressed in lb/ft3. Combined weight of the bucket and load
should not exceed the safe load recommended by the dragline.
The production of a dragline can be estimated using the tables based on PCSA data or by calculation.
The procedure using the PCSA data to determine the production of a dragline is similar io that for a
power shovel. The table for a dragline with short booms is given on the next page. The procedure for
calculation production for a dragline is similar to that for a power shovel.
EXAMPLE
Determine the expected dragline production in bank cubic yards
informaton.
ed
ul
(gr3)
5/20/00
Page39 of42
Dragline bucket
size:2
yd3
Swing angle:720
Average depth of cut
:7.9 ft.
Solution
Ideal output
230 bcylhr
Optimum depth of
cut:9.9 ft.
Efficiency
:7.919.9:
0.80
factor:0.9
factor:
50/60
Estimated production
: 0.833
Remove very effectively unconsolidated overburden such as earth glacial till, clay and soft shale that
does not require blasting.
Will excavate material from a highwall on one side of a mine and deposit it
to 2000 yd3lfu up to 426'away on the opposite side of the pit.
of 1500
Largest unit in the world produces 12,000 yd3lhr, operates in a German brown coal seam.
Long stacker allows a much greater discharge radius to be achieved while consuming less powerd3
of materials removed compared to other equipment.
Advantages
a.
a given output.
5/20100
Page 40 of 42
d. Larger discharge radius and can be designed to operate above or below the active mine level.
e. Can load mined material efficiently onto a variety of haulage modes, including truc haulage, or
belt conveyor.
fl
tkough
mining of interbedded coal and mall partings such as high and low sulfur
k. There is little or now dead weight structure required as counterweight because the stacker and drive
are used.
Disadvantages
a. Machinery is highly complicated and therefore has reduced
availabil.
Unit restricted to mining thick coal seams only. Thickness of coal seam would at least be 0.7 times
the wheel diameter. This is because bucket configuration and wheel diameter can cause problems in
tryrng to follow the bottom of the coal seam.
e.
Wheels are designed with either celled or cell-less construction. Most modern wheels are cell-less. In
the cellJess type, the buckets in the digging position can continuously empty into an annular ring.
EXAMPLE
A wheel loader must produce (230m3lhr) :00 yd3ltr in a truck loading application. Estimated cycle
http ://www. mg. mtu. edu/-frotuony/mg33
2mg336. htm
5/20/00
Pase 41 o 42
time is 0.6 min. and job efficiency is75% (or working 45min/hr). Bucket fill factor is95Yo and
material density is (1780 kglrn3) 3000 lb/yd3.
Determine bucket size and machine model:
Solution
#ofcycteslhr=
fffi
o.?s
= 75 cycles/hr
Let bucket size be x yd3
Volume of material
Production/hr
: 0.95x
: (75 cycles/hr)(0.
95 x yd3lcycle)
:7l.25xyd3/nr.
Required production
7
x:4.2
Useg66fwith 4yd3bucket dependent on material dens and bucket capacity. Refer to pg.
Caterpillaf.
EXAMPLE
12-40 in
A wheel loader is required to produce 496 tons/lr for 3/8" gravel in 20 ft high stockpile. The density
of material is 28001b/yd3. Cycle time is 0.5 min. with actual working time of 50 midhr. The bucket fill
factor is 0.95. Trucker are in 8-12 yd3 . Determine the required rated bucket capacity.
Solution
#ofcycles/hr=
.5=.0.!s..
0.5mircpb
Volume ofmaterial
required:
looclrles/lu.
ffiffi
l.4ton/yd3
6I
2mg336.htm
5/20/00
Page 42 of 42
Required
production:
Volumepercycle:
Rated bucket
ffi
3s4 yd3ihr
ss4yd3/cycb
==l54slll0 culeeiluur =
capacity:
354 yd3/cfle
fill fator
0.95
:3.75
yd x 2800 lb/yd3
10,500lbs.
336I
sl20l00