Oil Containment For Major Substation

Download as pdf or txt
Download as pdf or txt
You are on page 1of 46

Network Standard

NETWORK

NW000-S0034

NW000-S0034

Document No
Amendment No
Approved By
Approval Date
Review Date

:
:
:
:
:

NW000-S0034
0
Chief Engineer
12/05/2015
26/11/2017

NS189 OIL CONTAINMENT FOR MAJOR SUBSTATIONS

UNCONTROLLED IF PRINTED

Page 1 of 46

NS189 Oil Containment for Major Substations

Amendment No 0

ISSUE
For issue to all Ausgrid and Accredited Service Providers staff involved with the design of oil containment systems at major
substations, and is for reference by field, technical and engineering staff.
Ausgrid maintains a copy of this and other Network Standards together with updates and amendments on www.ausgrid.com.au.
Where this standard is issued as a controlled document replacing an earlier edition, remove and destroy the superseded document
DISCLAIMER
As Ausgrids standards are subject to ongoing review, the information contained in this document may be amended by Ausgrid at
any time. It is possible that conflict may exist between standard documents. In this event, the most recent standard shall prevail.
This document has been developed using information available from field and other sources and is suitable for most situations
encountered in Ausgrid. Particular conditions, projects or localities may require special or different practices. It is the responsibility
of the local manager, supervisor, assured quality contractor and the individuals involved to make sure that a safe system of work is
employed and that statutory requirements are met.
Ausgrid disclaims any and all liability to any person or persons for any procedure, process or any other thing done or not done, as a
result of this Standard.
All design work, and the associated supply of materials and equipment, must be undertaken in accordance with and consideration
of relevant legislative and regulatory requirements, latest revision of Ausgrids Network Standards and specifications and Australian
Standards. Designs submitted shall be declared as fit for purpose. Where the designer wishes to include a variation to a network
standard or an alternative material or equipment to that currently approved the designer must obtain authorisation from the Network
Standard owner before incorporating a variation to a Network Standard in a design.
External designers including those authorised as Accredited Service Providers will seek approval through the approved process as
outlined in NS181 Approval of Materials and Equipment and Network Standard Variations. Seeking approval will ensure Network
Standards are appropriately updated and that a consistent interpretation of the legislative framework is employed.
Notes: 1. Compliance with this Network Standard does not automatically satisfy the requirements of a Designer Safety Report. The
designer must comply with the provisions of the Workplace Health and Safety Regulation 2011 (NSW - Part 6.2 Duties of designer
of structure and person who commissions construction work) which requires the designer to provide a written safety report to the
person who commissioned the design. This report must be provided to Ausgrid in all instances, including where the design was
commissioned by or on behalf of a person who proposes to connect premises to Ausgrids network, and will form part of the
Designer Safety Report which must also be presented to Ausgrid. Further information is provided in Network Standard (NS) 212
Integrated Support Requirements for Ausgrid Network Assets.
2. Where the procedural requirements of this document conflict with contestable project procedures, the contestable project
procedures shall take precedent for the whole project or part thereof which is classified as contestable. Any external contact with
Ausgrid for contestable works projects is to be made via the Ausgrid officer responsible for facilitating the contestable project. The
Contestable Ausgrid officer will liaise with Ausgrid internal departments and specialists as necessary to fulfil the requirements of this
standard. All other technical aspects of this document which are not procedural in nature shall apply to contestable works projects.
INTERPRETATION
In the event that any user of this Standard considers that any of its provisions is uncertain, ambiguous or otherwise in need of
interpretation, the user should request Ausgrid to clarify the provision. Ausgrids interpretation shall then apply as though it was
included in the Standard, and is final and binding. No correspondence will be entered into with any person disputing the meaning of
the provision published in the Standard or the accuracy of Ausgrids interpretation.
KEYPOINTS
This standard has a summary of content labelled KEYPOINTS FOR THIS STANDARD. The inclusion or omission of items in this
summary does not signify any specific importance or criticality to the items described. It is meant to simply provide the reader with a
quick assessment of some of the major issues addressed by the standard. To fully appreciate the content and the requirements of
the standard it must be read in its entirety.
AMENDMENTS TO THIS STANDARD
Where there are changes to this standard from the previously approved version, any previous shading is removed and the newly
affected paragraphs are shaded with a grey background. Where the document changes exceed 25% of the document content, any
grey background in the document is to be removed and the following words should be shown below the title block on the right hand
side of the page in bold and italic, for example, Supersedes document details (for example, Supersedes Document Type
(Category) Document No. Amendment No.).

NW000-S0034

UNCONTROLLED IF PRINTED

Page 2 of 46

KEY POINTS OF THIS STANDARD


Scope and Risks Addressed

This standard details general design


requirements for oil containment for major
substations with the limitations as listed below
and the associated risks as indicated:

Applies to new and existing major


substations with primary voltages of
33kV, 66kV and 132kV.
Controls apply to both normal operations
and during emergency situations
Maintenance and operation of oil
containment facilities is specified
separately in NS190 Oil Containment
Operational Requirements for Major
Substations
Consideration given to different types of
oil containment plant for various
situations found in major substations.
All materials and equipment used in
construction of Ausgrid assets must be
asbestos free.
Three main risks to be addressed:

Catastrophic failure causing


prolonged fire

Catastrophic failure large amounts


oil spreading off-site

Minimise oil pollution during normal


operation

Design Principles, Site and


Regulatory Requirements

This section lists the basic design assumptions


and principles used to design oil containment
systems within Ausgrid:

Basic design assumptions listed in Cl. 6.1


New and existing systems reviewed in Cl.
6.2
For existing major substations, all areas
with any oil-filled equipment containing
more than 1000 litres of oil will require oil
containment facilities
For equipment less than 1000 litres or in
areas designated low risk containment
may not be necessary.
For new substation sites all oil-filled
equipment will be bunded unless indicated
otherwise.
Due consideration to minimise
contamination of stormwater.
Principles for addressing three main risks
Selection criteria for oil containment
systems based on Life Cycle Cost.
Criteria for preferred designs indicated for
greenfield sites.
For brownfield retrofit sites the preferred
oil containment system is a closed
drainage PPS system.
Drainage design philosophy for closed
systems and gravity drainage reviewed.
Some existing and temporary sites may
adopt an alternative approach.
Designer Safety Report required.
Site selection criteria to limit impact of oil
loss.
Oil containment discharge to Stormwater
and Sewer may have Regulatory
requirements

Typical Layouts, Bunding and


Drainage

Specific design requirements are addressed as


listed:

Specific design requirements are addressed


as listed:

Typical oil containment layouts given for


CBD and suburban major substations
Bunding areas designed to minimise entry
of clean stormwater
For existing sites - transformers with more
than 1000 litres oil must be bunded unless
risk assessment indicates not required.
For new sites all oil-filled transformers
will be bunded
Bunding designed to prevent burning fuel
spreading fire to adjoining equipment.
Spray screens may be required if bund
unable to contain spray discharge.
Transformer roadways may have bunding
requirements
Bunding design requirements identified
Secondary containment requirements
determined by Ausgrid risk management
assessment.
Oil spill kits to be available for every major
substation
Section 12 identifies requirements for oil
water separators and oil containment
tanks
Section 13 identifies requirements for
drainage and associated structures
including pits, pipework, flame traps,
valves, and pumps

For CBD and other major indoor


substations fire-fighting water
containment capacity shall be made for
up to 90 minutes of expelled fire-fighting
water
For non-rural sites, the minimum
containment storage for non-fixed
firefighting is 20 minutes of one hose with
foam at 4l/s
For rural sites, the minimum containment
storage for firefighting is 20 minutes of
two hoses with water at 10l/s each.
The required minimum storage can be
inclusive of volume available in bunded
areas plus any secondary storage or
overflow areas.
Burn down rates can be included in
calculations for provisions of storage
where a full bund oil fire occurs.
Capacitors have specific containment
provisions.
After an emergency, oil containment and
containment tanks must be emptied and
remediation work undertaken.
Clean up should comply with
environmental guidelines and legislation
Requirements for decommissioning tanks
are provided.

Where to for more information?


Section 14, 15, 16, 17

Where to for more information?

Where to for more information?

Where to for more information?

Section 1, 2, 5, 7

Section 6, 7, 8, 9

Section 10, 11 12, 13

NW000-S0034

Fire Fighting & Cleanup

UNCONTROLLED IF PRINTED

Tools and Forms


Annexures A, B, C and D

Page 3 of 46

NS189 Oil Containment for Major Substations

Amendment No 0

Network Standard
NS189
Oil Containment for Major Substations
Contents
1.0

PURPOSE ............................................................................................................................................. 6

2.0

SCOPE .................................................................................................................................................. 6

3.0

REFERENCES ...................................................................................................................................... 6
3.1
Ausgrid Documents .................................................................................................................... 6
3.2
Other Standards and Documents .............................................................................................. 6
3.3
Acts and Regulations ................................................................................................................. 7
3.4
Literature .................................................................................................................................... 7

4.0

DEFINITIONS ........................................................................................................................................ 7

5.0

ASBESTOS ............................................................................................................................................ 9

6.0

INTRODUCTION ................................................................................................................................... 9
6.1
General ...................................................................................................................................... 9
6.2
Typical Oil Containment Systems ............................................................................................ 10

7.0

OIL CONTAINMENT PRINCIPLES ..................................................................................................... 11


7.1
Where is Oil Containment Required? ...................................................................................... 11
7.2
Selection Criteria for Oil Containment Systems ....................................................................... 12
7.3
Drainage Design Philosophy.................................................................................................... 13
7.4
Existing or Temporary Major Substations ................................................................................ 14
7.5
Structural and Other Design Considerations ........................................................................... 14
7.6
Designer Safety Reports .......................................................................................................... 14

8.0

SITE SELECTION CRITERIA .............................................................................................................. 15

9.0

REGULATORY REQUIREMENTS ...................................................................................................... 15


9.1
Sewer ....................................................................................................................................... 15
9.2
Stormwater ............................................................................................................................... 15
9.3
Local council requirements ...................................................................................................... 15

10.0

TYPICAL OIL CONTAINMENT LAYOUT FOR NEW SUBSTATIONS ............................................... 16


10.1 CBD Major Substation with High Velocity Water Spray ........................................................... 16
10.2 Suburban Major Substation ..................................................................................................... 17
10.2.1 Closed Drainage PPS System ..................................................................................... 17
10.2.2 Gravity Drainage System with Oil Containment Tank .................................................. 17

11.0

OIL CONTAINMENT BUNDING .......................................................................................................... 19


11.1 Transformer Bunding ............................................................................................................... 19
11.2 Spray Screens.......................................................................................................................... 19
11.3 Transformer Roadways ............................................................................................................ 19
11.4 Bunding Design Requirements ................................................................................................ 19
11.5 Secondary Containment .......................................................................................................... 20
11.5.1 Secondary Containment Area Requirements .............................................................. 20
11.5.2 Oil Spill Kits .................................................................................................................. 20
11.5.3 Secondary Containment Options ................................................................................. 20

12.0

OIL WATER SEPARATOR AND OIL CONTAINMENT TANKS .......................................................... 21

NW000-S0034

UNCONTROLLED IF PRINTED

Page 4 of 46

NS189 Oil Containment for Major Substations

12.1

12.2
12.3
12.4

Amendment No 0

Parallel Plate Separator (PPS) ................................................................................................ 21


12.1.1 PPS System Shut Down .............................................................................................. 21
12.1.2 PPS System Alarms ..................................................................................................... 21
12.1.3 Neat Oil Flow ................................................................................................................ 21
12.1.4 PPS Design and Installation......................................................................................... 22
Enhanced Gravity Oil Water Separator (EGOWS) .................................................................. 22
12.2.1 Emergency Operation of EGOWS ............................................................................... 22
Access to Tanks ....................................................................................................................... 22
12.3.1 Bolt Down Covers for Hydraulic Pressure ................................................................. 23
Inspection and Hold Points ...................................................................................................... 23

13.0

DRAINAGE AND ASSOCIATED STRUCTURES ............................................................................... 23


13.1 Pipework .................................................................................................................................. 23
13.1.1 Closed Drainage PPS System ..................................................................................... 23
13.1.2 Gravity Drainage with Oil Containment Tank ............................................................... 23
13.1.3 Pre-Commissioning Tests and Inspection ................................................................... 24
13.1.4 Design .......................................................................................................................... 24
13.2 Pits and Drainage Channels .................................................................................................... 24
13.2.1 Encasement and Finish ................................................................................................ 24
13.2.2 Flame Traps ................................................................................................................. 25
13.3 Valves ...................................................................................................................................... 25
13.3.1 Closed Drainage PPS Systems ................................................................................... 25
13.3.2 Gravity Drainage Systems ........................................................................................... 25
13.4 Pumps ...................................................................................................................................... 26
13.4.1 Pumps for Parallel Plate Separators ............................................................................ 26
13.5 Infiltration Trenches.................................................................................................................. 26

14.0

FIRE FIGHTING WATER CONTAINMENT CAPACITY ...................................................................... 26

15.0

CAPACITORS...................................................................................................................................... 26
15.1 Outdoor Capacitor Banks ......................................................................................................... 26
15.2 Capacitor Banks and Fire Sprinklers ....................................................................................... 27

16.0

POST EMERGENCY CLEAN UP ........................................................................................................ 27

17.0

DECOMMISSIONING OF OIL CONTAINMENT TANKS .................................................................... 27

18.0

RECORDKEEPING ............................................................................................................................. 28

19.0

AUTHORITIES AND RESPONSIBILITIES .......................................................................................... 28

20.0

DOCUMENT CONTROL...................................................................................................................... 28

ANNEXURE A SECONDARY CONTAINMENT OPTIONS.......................................................................... 29


ANNEXURE B OIL SEPARATOR DESIGN, INSTALLATION AND COMMISSIONING REQUIREMENTS 32
ANNEXURE C OIL SEPARATOR INSPECTION REQUIREMENTS AND HOLD POINTS ........................ 41
ANNEXURE D SAMPLE COMPLIANCE CHECKLIST ................................................................................ 43

NW000-S0034

UNCONTROLLED IF PRINTED

Page 5 of 46

NS189 Oil Containment for Major Substations

Amendment No 0

1.0 PURPOSE
Network Standard NS189 details the general requirements for oil containment for major
substations. The objective of this standard is to specify the design requirements for oil containment
on site during the day to day operation of major substations as well as in emergency situations.
This standard also aims to provide consistency of design and to minimise the spread of fire.

2.0 SCOPE
This Standard covers the design of oil containment systems for new and existing major substations
with primary voltages of 132, 66 and 33 kV.
This Standard also considers the different types of treatment plant for the various situations found
in major substations.
This Standard also defines the performance criteria of a containment system based on discussions
between the Environment Protection Authority (EPA) and Ausgrid.
Maintenance and operation of oil containment facilities is specified in NS190 Oil Containment
Operational Requirements for Major Substations.
This Standard does not include provisions for pole top transformers and capacitors, distribution and
customer substations, kiosks, regulators, tap changer auto transformer substations, reclosers or oil
filled cables and their associated pressure vessels.

3.0

REFERENCES

3.1

General
All work covered in this document shall conform to all relevant Legislation, Standards, Codes of
Practice and Network Standards. Current Network Standards are available on Ausgrids Internet
site at www.ausgrid.com.au.

3.2

Ausgrid documents

3.3

Company Form (Governance) - Network Document Endorsement and Approval


Company Procedure (Governance) - Network Document Endorsement and Approval
Company Procedure (Network) - Production / Review of Network Standards
Electrical Safety Rules
Electricity Network Safety Management System Manual
NS 171Firestopping in Substations.
NS 181 Approval of Materials and Equipment and Network Standard Variations
NS 187 Passive Fire Mitigation Design of Substations.
NS 190 Oil Containment Operational Requirements for Major Substations
NS 210 Documentation and Reference Design Guide for Major Substations
NS 211 Working with Asbestos Products
NS 212 Integrated Support Requirements for Ausgrid Network Assets
NS261 Requirement for Design Compliance Framework for Network Standards

Other standards and documents

Australian Rainfall and Runoff; The Institution of Engineers, Australia.


Austroads 92 Bridge Design Code.
AS 1170 Loading Code.
AS 1646 Elastomeric seals for waterworks purposes.
AS 1657 Fixed platforms, walkways, stairways and ladders - Design construction and
Installation.
AS 1940 The Storage and handling of flammable and combustible liquids.
AS 2067 Substations and high voltage installations exceeding 1kV a.c.
NW000-S0034

UNCONTROLLED IF PRINTED

Page 6 of 46

NS189 Oil Containment for Major Substations

3.4

AS 2865 Confined Spaces


AS 3500 National plumbing and drainage code Stormwater drainage.
AS 3600 Concrete structures.
AS 3610 Formwork for concrete.
AS 3735 Concrete structures retaining liquids.
AS 4100 Steel structures
ENA Doc 001-2008 National Electricity Network Safety Code

Acts and regulations

3.5

Amendment No 0

Building Code of Australia.


Electricity Supply (General) Regulation 2014 (NSW)
Electricity Supply (Safety and Network Management) Regulation 2014
Protection of the Environment and Operations Act 1997
Work Health and Safety Act 2011 and Regulation 2011

Literature
EMS 350: Environmental Management Strategy 350, Oil Filled Equipment.
Fire Safety Study Guideline, Hazardous Industry Planning Advisory Paper No. 2, Department of
Planning NSW Fire Brigades.
EG 100: Oil Handling and Spill Response Guideline.

4.0

DEFINITIONS
Accredited Service
Provider (ASP)

An individual or entity accredited by the NSW Government Trade & Investment in


accordance with the Electricity Supply (Safety and Network Management) Regulation
2014 (NSW).

Approved
Equivalent

Equipment or materials approved in writing by Ausgrid.

ARI

Average Recurrence Interval. This is the long-term number of years between the
occurrence of a flood as big as or larger than a selected event.

Bund

A wall/barrier of sufficient height constructed around fluid filled equipment to contain


spillage of liquids.

Business
Management
System (BMS)

An Ausgrid internal integrated policy and procedure framework that contains the
approved version of documents.

Butterfly valve

The valve used to close the outlet of an oil containment tank.

Closed Drainage

A drainage system designed to retain liquids within a bunded area for treatment or
disposal as required.

Document control

Ausgrid employees who work with printed copies of document must check the BMS
regularly to monitor version control. Documents are considered UNCONTROLLED IF
PRINTED, as indicated in the footer.

EGOWS

Enhanced Gravity Oil and Water Separator. An oil containment tank developed by the
UNSW. The tank contains stainless steel baffles and flow retarding devices.

Fire Sprinklers

Low flow rate water discharge nozzles not generally used on transformers.

First Flush

2
1 in 1 year ARI of 5 minutes duration plus 10mm/m of the catchment.

Flame trap

A pit with a down turned pipe used as a fire quenching mechanism.

FRC

Fibre reinforced concrete.

FSW

Fire Separation Wall.

NW000-S0034

UNCONTROLLED IF PRINTED

Page 7 of 46

NS189 Oil Containment for Major Substations

Amendment No 0

Gravity Drainage

A drainage system designed to remove liquids to a remote location, such as an oil


containment tank, for retention and/or treatment prior to discharge.

Gravity separation

Oil-water separation without the use of chemicals or mechanical means ie using


gravity only based on Stokes law. Single, double, triple stage separators and all PPSs
use gravity separation.

High Velocity
Water Spray

A high velocity fire water sprinkler with a typical flow rate of 50 to 90 L/s, usually
surrounding transformers.

Infiltration
trenches

Trench filled with gravel used to discharge stormwater into groundwater.

Major Substation

For the purpose of this document, major substation means zone and subtransmission substations with primary voltages of 132, 66 and 33 kV.

Neat Oil

Where the flow of liquid through the system is predominantly oil.

Network Standard

A document, including Network Planning Standards, that describes the Company's


minimum requirements for planning, design, construction, maintenance, technical
specification, environmental, property and metering activities on the distribution and
transmission network. These documents are stored in the Network Category of the
BMS repository..

Non Return Valve

Also called a flap valve, it is a one way valve that prevents flow back up into the pipe.

Normal operation

Day to day operation precluding major rainfall events.

Oil containment
system

The oil containment system refers to the transformer bunds, together with a suitable
combination of flame traps, pipes, oil containment tank and Parallel Plate Separator
as required. The oil containment system is not designed as an oil storage system. It is
designed for emergency situations and the treatment of minor oil contamination from
transformer bunds.

Passive system

A system that operates without automatic or manual intervention.

PCBs

Polychlorinated biphenyls.

Parallel Plate
Separator (PPS)

Parallel Plate Coalescing Separator also known as a PPS. PPSs are gravity
separation separators.

PPM

Parts per million. An oil-water concentration of 10ppm equals 10mg/l which is


equivalent to a mixture that is visibly free of oils and greases, i.e. no visible oil.

Review date

The review date displayed in the header of the document is the future date for review
of a document. The default period is three years from the date of approval. However a
review may be mandated at any time where a need is identified due to changes in
legislation, organisational changes, restructures, occurrence of an incident or
changes in technology or work practice.

Secondary
Containment

An overflow area used to capture firefighting water.

Sensitive
environment

Any parcel of land or waterway that has environmental attributes that contribute to the
retention and or creation of wildlife habitat, soils stability, or other vital ecological
functions. Examples of sensitive environment are national parks, wetlands and nature
reserves.

Surcharge

A condition where the hydraulic capacity of the drain system is temporarily exceeded
and the amount of liquid that enters the system exceeds the conveyance capacity

Tank

Refers to a vessel made from concrete or masonry that is usually wholly or partially
buried, that provides containment of lost oil and can also be an oil/water separator.

Surfactants

A substance which emulsifies, disperses, dissolves other substances eg a detergent.

Waste

Captured oil and sediment within the oil containment system.

Waterway

Any river, stream, lake, lagoon, swamp, wetlands, unconfined surface water, natural

NW000-S0034

UNCONTROLLED IF PRINTED

Page 8 of 46

NS189 Oil Containment for Major Substations

Amendment No 0

or artificial watercourse, dam or tidal waters (including the sea), or


Any water stored in artificial works, any water in water mains, water pipes or water
channels, or any underground or artesian water.

5.0

ASBESTOS
All materials and equipment used for construction of Ausgrids assets are to be free from Asbestos
and or Asbestos related products. Suppliers are expected to comply with the Work Health and
Safety Act 2011 (NSW) together with the Work Health and Safety Regulation 2011 (NSW) and
confirm in writing that all products supplied to Ausgrid contain no Asbestos related materials.
At existing substation sites, a site contamination and hazardous materials audit may be required
prior to work commencing on site.
Particular care shall be exercised when handling or working in the vicinity of existing asbestos
products. Items containing asbestos shall be disposed of properly. Ausgrids Asbestos Product /
Location Register shall be consulted prior to work commencing to identify relevant plant and
equipment. Asbestos related work shall only be carried out by suitably trained personnel and in
accordance with Ausgrid Network Universal Standard NS 211 Working with Asbestos Products.

6.0
6.1

INTRODUCTION
General
This document outlines Ausgrids minimum requirements for oil containment at major substations.
This Standard does not document sections from the relevant Australian Standard or requirements
of these standards unless a specific departure from the standard is required for major substation
specific purposes.
The provision of oil containment at major substations is based on the following basic assumptions:
Only one transformer will rupture at the one time releasing its entire contents into the oil
containment tank or into the bund where there is no gravity drainage.
No major rain event occurs simultaneously with an emergency situation.
The oil containment system is appropriately maintained and is free of excessive residual oil in
the tank i.e., less than 10% volume of the largest transformer.
Oil filled equipment is in good working order and does not continually leak significant amounts
of oil.
Oil containment tanks are designed for short term emergency oil retention only. The tanks do
not meet the design and legislative requirements for long term oil storage.
Replacement transformers and other oil filled equipment will not increase the volume of oil
requiring containment;
Major substations are generally not staffed, requiring the oil containment system to operate
automatically or to be a passive system wherever possible;
Oil-water concentration of 10ppm is equivalent to a mixture that is visibly free of oils and
greases, i.e. no visible oil.
The oil containment system is assumed to have a maintenance regime and operational
performance that is in accordance with NS 190.
Gravity separation will not separate oil and foam contaminated water. In such cases, secondary
containment will be used.
Gravity separation systems will not work with oil degreasers or surfactants.
The oil water separator does not retain any contaminants other than transformer oil, e.g. it will
not remove PCBs.
The use of a secondary containment area or emergency response process to manage the flow
of water when firefighting.

NW000-S0034

UNCONTROLLED IF PRINTED

Page 9 of 46

NS189 Oil Containment for Major Substations

Amendment No 0

For all sites except rural and CBD substations, a minimum of 20 minutes firefighting medium
containment is required by AS 1940. The flow rates shall be a minimum of 4 l/s (using foam) but
the overall volume shall be rounded up to 5,000 litres. Refer also to Section 14.
CBD sites shall have 90 minutes of firefighting water containment at the flow rate of the high
velocity water spray system. Refer also to Section 14.
For rural sites, containment shall be a minimum of 20 minutes firefighting medium. However, the
flow rate shall depend on the use/storage of foam. Where water only is available, a minimum of
two fire hoses at 10 l/s each (20 l/s) shall be assumed. Rural substations are covered by the
Rural Fire Service who may not utilise foam. Refer also to Section 14.
For all sites, a risk assessment shall be undertaken to determine if greater containment volumes
are needed and shall consider the cost/ease of providing the additional containment and the
benefit from a risk reduction perspective.
Overflow or surcharge into other bunds, or into secondary containment areas on the site, are
both acceptable under the application of firefighting medium. Refer also to Section 14 and
Annexure A.
Foam is corrosive and therefore potentially damaging to other assets where overflow or
surcharge is allowed to occur.

6.2

Typical oil containment systems


There are several different oil containment systems used in the Ausgrid franchise area as
summarised below:
1. Generally, older sites (pre 1990) have single, double or triple stage tank systems. Some exElectricity Commission of NSW sites use a PPS system.
2. A few older sites have early PPS systems installed and were purposely used as trial sites to
determine the most appropriate system to install.
3. For new substation sites, one type of oil containment system uses a closed drainage design
with bund storage and a PPS system.
4. An alternative EGOWS gravity drainage system and tank uses a delayed release principle to
separate the oil and water.
5. Retrofit substation sites normally use a closed drainage PPS system with bund storage.

NW000-S0034

UNCONTROLLED IF PRINTED

Page 10 of 46

NS189 Oil Containment for Major Substations

7.0

OIL CONTAINMENT PRINCIPLES

7.1

Where is oil containment required?

Amendment No 0

Oil containment systems shall be designed to meet the requirements of this Network Standard and
the relevant parts of AS 2067 and AS 1940. Where a conflict occurs, the requirements of this
Network Standard shall prevail.
For existing major substations, all areas with any piece of oil filled equipment containing more than
1000 litres of oil generally require oil containment facilities. If the piece of equipment has less than
1000 litres or if the location with this piece of equipment is designated low risk by Ausgrid, then
containment may not be necessary. In this case, the equipment should be located such that it is not
in a drainage path to a waterway, or that any oil lost will not create a hazardous situation to the
public, neighbouring buildings or equipment in accordance with AS 1940.
Due consideration must be made to minimise the potential for stormwater to become contaminated
with oil.
For new substation sites, all oil filled equipment shall be bunded, unless indicated otherwise by this
Standard.
High voltage capacitors generally do not require oil containment because they are sealed units that
contain minimal free oil. Refer also to Section 15 of this Standard.
The following principles shall be adopted to address the three main risks:
1. Catastrophic failure causing prolonged fire.
a.

Closed drainage PPS systems

In a catastrophic failure, the oil containment system shall reduce the risk of fire spread off site
by containing the oil in the bund.
The PPS shall be designed to shut down upon neat oil flow through the separator. This can be
achieved by diverting the neat oil directly to the waste oil tank, filling it, and triggering a shutdown of the equipment and the waste oil tank high level alarm.

b.

Gravity drainage systems

In a catastrophic failure, the oil containment system shall reduce the risk of prolonged fire
(hence fire spread) by containing oil spillage and/or providing a quick draining route for oil.
Oil containment bunds shall have a floor slope of 1% and pipes designed for the flow rate of
the firefighting water, which also facilitates the quick removal of oil from the bund. Each oil
containment bund is drained via a flame trap reducing the potential for fire to reach the oil
containment tank.
The oil containment tank provides an oil spill retention area away from the fire.

2. Catastrophic failure causing large amounts of oil spreading off site.


a. Closed drainage PPS systems

Bunds shall have capacity for the contents of the transformer plus approximately 5000 litres of
firefighting medium. Some sites may require more than 5000 litres of additional containment.
Oil shall be removed from the bund as soon as possible to avoid the risk of leakage to other
parts of the site.

b. Gravity drainage systems

NW000-S0034

Bunds shall contain oil in the area of loss thus preventing burning oil migrating off-site. The oil
containment bunds are designed to hold 100% of the oil volume to provide adequate drainage
time in the event that the pipes are partially blocked.

UNCONTROLLED IF PRINTED

Page 11 of 46

NS189 Oil Containment for Major Substations

Amendment No 0

The bund shall be drained to an oil containment tank. The tank is designed to retain 110%
volume of oil from one transformer.
EGOWS oil containment systems shall be fitted with a manual or automatic shut-off valve at
the outlet of the tank to facilitate the closing of the oil containment system to prevent discharge
of the firefighting medium. Overflow from the oil containment shall be managed by directing it
to a secondary containment area or by the emergency response process.

3. Minimise oil pollution during normal operation.


a.

b.

7.2

Closed drainage PPS systems


Providing oil filled equipment is maintained in good working order and is not continually
leaking, the system shall minimise the day to day loss of oil to the environment.
During normal operation a stormwater discharge less than 10ppm of oils and greases shall be
achieved in all storm events. Larger storm events will cause the water to rise inside the bunds
while treated discharge from the PPS will continue at a constant rate. Compliance of PPS
discharges is dependent on proper maintenance in accordance with NS 190.
Gravity drainage systems
Providing oil filled equipment is maintained in good working order and is not continually
leaking, the system shall minimise the day to day loss of oil to the environment.
During normal operation a stormwater discharge less than 10ppm of oils and greases shall be
achieved. In some higher rainfall events higher oil and water discharges may be experienced.

Selection criteria for oil containment systems


Selection of the preferred oil containment system shall be based on a Life Cycle Cost (LCC)
analysis together with an assessment of site constraints, site risks, environmental aspects and
impacts upon the project schedule.
The LCC analysis shall capture all site specific capital costs and include O&M costs that accurately
reflect the activities required to maintain the functional performance of the equipment.
For Greenfield sites the following criteria will typically determine the preferred oil containment
system when assessed in conjunction with a LCC analysis;
a.

b.

NW000-S0034

Closed drainage PPS systems may be preferred for Urban locations in the vicinity of Ausgrids Aqueous Waste Services depots where response
and travel times are low and operation and maintenance costs are reduced.
Locations where effective gravity drainage is difficult or costly to achieve.
Congested sites where a gravity system either cannot be readily accommodated, or would
constrain an efficient site layout for plant and equipment.
Sites where the EGOWS tank cannot be located adjacent to, or in close proximity (10m to
15m) of, the transformer bunds.
Sites where the EGOWS tank requires extra strengthening to support mobile crane outrigger
loadings (e.g. in the vicinity of TX bays).
Locations where difficult site conditions such as rock, low soil strength, high water table,
restricted access etc. adds significant costs to the civil works.
Locations where early civil works for gravity systems are an expected critical path item and a
significant project benefit can be realised through reduced program duration and site costs.
Environmentally sensitive areas where strict discharge limits cannot be satisfied by gravity
systems under all conditions (e.g. high flowrates).
Gravity drainage systems may be preferred for Rural locations where response and travel times are high and O&M costs are increased for
PPS systems.
Sites where sufficient space is available to locate the gravity system without significant impact
on the efficient site layout of plant and equipment.

UNCONTROLLED IF PRINTED

Page 12 of 46

NS189 Oil Containment for Major Substations

Amendment No 0

Sites where the EGOWS tank can be optimally located, namely;


a) adjacent to, or nearby (10m to 15m), the transformer bunds, and
b) with minimal gravity drainage pipework, and
c) without additional strengthening of the tank to support mobile crane outrigger loadings.

Locations with suitable geotechnical conditions and good site access that enable low cost civil
construction
Locations where the civil works for gravity systems will have minimal impact on the program
duration.
High hazard locations where the continuous removal of fuel by gravity drainage may provide a
reduced fire risk following a major oil spill.
CBD and other locations which require a high velocity water spray system for the transformer
area.
Sites where significant LCC benefits can be realised by combining the functions of an EGOWS
with required On-Site Stormwater Detention (OSD) into one tank unit.

For a generic Greenfield site, a closed drainage PPS system using bund storage can be
comparable, on a LCC basis, with a gravity drainage system using an EGOWS tank. Selection of
the preferred oil containment system should therefore be based on the site specific criteria
indicated above, together with a LCC analysis.
For existing Brownfield retrofit sites the preferred oil containment system is typically a closed
drainage PPS system. The alternative gravity drainage system is generally less favourable and can
incur significant additional costs and construction risk due to existing underground services,
together with increased site disturbance and site works duration.
For all oil containment systems, the design should be optimised for each site. This will generally
require;

7.3

Early incorporation into the substation site layout design to optimise all aspects of the
substation design and associated works.
A system design that is as compact as possible.
Innovation in design to take advantage of any multi-use functions (e.g. combined EGOWS and
OSD where possible).

Drainage design philosophy


Where a closed drainage system is adopted, using bund storage and a PPS, suitable pumps and
above ground pipework shall be provided as part of the oil containment system.
For gravity drainage systems, all drainage shall be accomplished by gravitational action where
possible. In cases where gravity systems are required but complete gravity drainage is not possible
(e.g. CBD substations), fixed pumps may be used at the outlet of an oil containment tank or
storage tank.

NW000-S0034

UNCONTROLLED IF PRINTED

Page 13 of 46

NS189 Oil Containment for Major Substations

7.4

Amendment No 0

Existing or temporary major substations


An alternative oil containment approach may be adopted for existing or temporary major
substations. At a minimum these sites will generally require a bund around each transformer.
However the bunds will need to be monitored and emptied after rain events. The bunds shall be
designed for 100% of the oil volume plus secondary containment as described in Section 11.5.
Allowance should be made for run-off from a significant rainfall event for the region. The retained
water may be contaminated and require disposal off-site.
The use of a PPS system on a temporary basis should be considered. The PPS can be reused at
another site upon decommissioning of the temporary installation.

7.5

Structural and other design considerations


All components of the oil containment system must be designed for the expected loading
conditions.
Effects of differential settlement shall be incorporated into the design.
The design of the oil containment system shall consider the relevant WHS requirements for
construction, operation and maintenance of the system.

7.6

Designer safety reports


For structures and plant, including equipment, pipelines and containers, the WHS Regulation 2011
(NSW) requires a written safety report to be provided by the designer of a structure or plant, or any
part of a structure or plant, to the person who commissioned the design.
The Designer Safety Report shall comply with the requirements of NS 210 and shall be prepared at
the completion of the design development process.

NW000-S0034

UNCONTROLLED IF PRINTED

Page 14 of 46

NS189 Oil Containment for Major Substations

8.0

Amendment No 0

SITE SELECTION CRITERIA


Consideration shall be given to the following requirements when evaluating a substation site to
assist in reducing the potential impact of oil loss from site:

Proximity of waterways and sensitive environments;


Ground conditions eg, sandy soils and/or high water table allow oil to be migrated easily.
Areas that have been filled or experience excessive heave can provide large differential
settlements which may damage watertight structures;
Sites with some slope are preferred to facilitate a gravity system; and
The level of the site should be higher than the 1 in 100 year flood level.

9.0

REGULATORY REQUIREMENTS

9.1

Sewer
For oil containment discharge to sewer:

A Trade Waste Agreement (TWA) is required and may have specific monitoring and discharge
requirements. Refer to relevant authorities for all TWA requirements and conditions.
Ausgrid currently adopts a discharge requirement of 10ppm for oils and greases. Refer to the
TWA for the relevant criteria.

Discharge of treated water to sewers is not preferred and shall only be done so when connection to
stormwater is not practical.

9.2

Stormwater
For oil containment discharge to stormwater:

9.3

Ausgrid currently adopts a discharge requirement of 10ppm for oils and greases.
No licence is required for connection to stormwater in accordance with the current
environmental management strategy, EMS 350.
Ensure appropriate Approvals are sought for new connections to Local Council, Sydney Water
or Hunter Water Corporation Stormwater Systems.

Local council requirements


Local council stormwater codes of practice or guidelines shall be reviewed and adopted where
practicable.

NW000-S0034

UNCONTROLLED IF PRINTED

Page 15 of 46

NS189 Oil Containment for Major Substations

Amendment No 0

10.0 TYPICAL OIL CONTAINMENT LAYOUT FOR NEW


SUBSTATIONS
10.1

CBD Major substation with high velocity water spray


A CBD major substation is fully contained within a building and no or limited stormwater enters the
substation during day to day operations. The transformers are typically protected by a high velocity
water spray fire protection system.
Each transformer has a bund which is drained to a storage tank or designated overflow area. The
tank is designed to take a minimum of 90 minutes of high velocity water spray from one of the
transformer bays and 110% of the oil volume of the largest transformer. The tank may overflow into
the cable basement or other area in the event of high velocity water spray operation greater than a
minimum of 90 minutes. The overflow is taken from the bottom of the tank.
Where stormwater can enter the system, the contents of the tank are pumped to a PPS and treated
prior to discharge to stormwater or sewer.
During emergency situations in existing CBD substations with PPS systems, the PPS is designed
to be shut down by the operation of the transformer protection system and activation of the high
velocity water spray system.
Refer to Section 12.1 for a description of PPS shut down modes under emergency operation.
CBD capacitor bays containing capacitors with oil shall also have bunds and may be fitted with
sprinklers. Where sprinklers are fitted, the bunded areas shall be connected to an independent
storage tank designed for 90 minutes of sprinkler discharge. The contents of this tank are not
treated. Any waste collected, is taken and disposed of off-site. A tank pump out point is provided
for tanker access.

Elevation
Figure 1 - Typical CBD substation with high velocity water spray

NW000-S0034

UNCONTROLLED IF PRINTED

Page 16 of 46

NS189 Oil Containment for Major Substations

10.2

Amendment No 0

Suburban major substation


A new suburban major substation generally consists of switching equipment (indoor or outdoor),
outdoor transformers and a control building. High volumes of stormwater run-off are expected from
these substations.
The management of stormwater, and of any potential oil contamination, will vary depending on
whether a closed or gravity drainage system is adopted for oil containment.

10.2.1

Closed drainage PPS system

The closed drainage PPS system, using bund storage and a PPS oil/water separator, can compare
favourably as a low cost option for oil containment. PPS systems shall be considered for all
suitable Ausgrid sites based on the selection criteria outlined in Section 7.2.
The transformers are individually bunded and any discharge points are kept normally closed.
Automatically operated pumps are provided within the bunds together with suitable bund sumps
and above ground pipes constructed to the requirements of Section 13.1.1. All liquids are pumped
to a PPS oil/water separator and treated prior to discharge to stormwater. Further details of the
PPS system are provided in Section 12.1.
The bund storage is sized to retain all oil spills, with a suitable margin for rainwater and/or firefighting medium. Any overflow from the bund area will be directed to a secondary containment
storage area or managed by the emergency response process. Secondary containment storage
areas shall be designed to the requirements of Section 11.5 or as specified by a risk management
approach, determined by Ausgrid.

Plan
Figure 2 - Typical Suburban Major Substation - Closed Drainage PPS System

10.2.2

Gravity drainage system with oil containment tank

The transformers are individually bunded and drained to an Enhanced Gravity Oil Water Separator
(EGOWS). The treated stormwater is discharged to stormwater.
The EGOWS is manually closed by a butterfly valve at the tank outlet upon application of
firefighting water. The overflow from the oil containment tank shall be directed to a secondary
containment area or managed by the emergency response process. Secondary containment areas

NW000-S0034

UNCONTROLLED IF PRINTED

Page 17 of 46

NS189 Oil Containment for Major Substations

Amendment No 0

shall be designed to the requirements of Section 11.5 or as specified by a risk management


approach, determined by Ausgrid.

Elevation
Figure 3 - Typical suburban major substation - Gravity drainage system

Elevation
Figure 4 - Typical cross-section for Figure 3

NW000-S0034

UNCONTROLLED IF PRINTED

Page 18 of 46

NS189 Oil Containment for Major Substations

Amendment No 0

11.0 OIL CONTAINMENT BUNDING


Oil containment bunded areas shall be designed to minimise the entry of clean stormwater. All subsoil drainage, yard run-off and roof drainage shall be excluded from the bunded areas. All bunds
are to be designed to AS 1940.

11.1

Transformer bunding
At existing sites where a retrofit system is being installed, each transformer containing greater than
1000 litres of oil shall be bunded unless a risk assessment indicates this is not required.
At new substation sites all oil filled transformers shall be bunded.
The extent of bunds shall be such that burning fuel can not propagate the spread of fire to adjoining
transformers, structures and adjacent premises and shall meet the requirements of AS 1940.

11.2

Spray screens
Bunding shall be designed to capture a 1:2 (Horizontal:Vertical) spray discharge to AS 1940
requirements. Where the bund cannot be placed to meet the spray discharge, then screens may
need to be installed.
Where the transformer radiators are positioned in very close proximity to the transformer roadway,
spray screens need only be placed to a maximum height of 1.5 m above the bund wall.
Spray screens near the transformer radiators shall be louvered to allow sufficient air flow around
the radiators. These spray screens are to be removable to allow access for maintenance.

11.3

Transformer roadways
For new sites, transformer roadways shall be bunded by the use of speed humps where required.
The drainage is to be to stormwater via an easily accessible and identifiable butterfly valve which is
to be left open except when oil filled equipment is parked on the roadway, or when operations are
underway that involve the transferring of oil.
At existing sites, this requirement also applies, but only where it is practicable without the need for
laying of new drainage pipes.
For sites of restricted size, it may be viable to use smaller transformer bay areas and drain the
transformer roadway within the 1:2 spray zone directly to an oil containment tank. The required
tank size may increase as a result due to higher stormwater inflows. A risk assessment and LCC
analysis shall be provided to evaluate the alternative oil containment arrangements and site
layouts.

11.4

Bunding design requirements


All bunded areas shall have a 1% floor slope. Where drainage from the bund is required for gravity
drainage systems it shall be via a flame trap. The use of gravel as a fire quenching medium is not
permitted for new sites.
All bunded areas shall be finished with a non-slip surface.
Permanent bunds shall be constructed from reinforced concrete. In instances where the bunds will
be temporary, earthen bunds are permitted.
All bunds shall be able to take loading from a spray screen. This allows flexibility for placing larger
transformers in bunds and maintaining AS 1940 requirements.
Removable bund walls may need to be provided at some locations as specified by Ausgrid.
Generally, these locations will be limited to sites with raised transformer plinths.

NW000-S0034

UNCONTROLLED IF PRINTED

Page 19 of 46

NS189 Oil Containment for Major Substations

Amendment No 0

Any openings in the bund floor shall be raised above the bund floor to avoid ponding and the lids to
the openings shall be gas tight. Where the cables pass through the opening, the opening shall be
raised using internal bunding to 50 mm above the bund wall height.
Access to the bund shall meet the requirements of AS 1657.

11.5

Secondary containment
The secondary containment for major substations shall be designed to the requirements specified
by a risk management approach determined by Ausgrid. The form of secondary containment can
vary depending on the site location and site constraints..

11.5.1

Secondary containment area requirements

Permeable or unpaved secondary containment areas shall not be located on areas with a high
water table or sandy soils or close to waterways or sensitive environments. Immediate localised
remediation would be required for the secondary containment area after use.

11.5.2

Oil spill kits

An oil spill kit shall be available for every major substation to assist with the provision of secondary
containment.

11.5.3

Secondary containment options

Annexure A provides details of the secondary containment options and the requirements for major
substations.

NW000-S0034

UNCONTROLLED IF PRINTED

Page 20 of 46

NS189 Oil Containment for Major Substations

Amendment No 0

12.0 OIL WATER SEPARATOR AND OIL CONTAINMENT TANKS


12.1

Parallel Plate Separator (PPS)


Parallel Plate Separators (PPS) shall be used with closed drainage oil containment systems that
rely on bund storage. A PPS can also be used in cases when it is not possible to drain entirely by
gravity, where a high velocity water spray system is installed (eg CBD substations), and for
retrofitting into existing major substations.
The Ausgrid currently accepted PPS unit is the Ovivo EnviroSEP OS 7500 supplied by Ovivo or
an approved equivalent. The PPS shall be correctly installed and fully commissioned on site with a
minimum 12 months defects liability period to ensure effective long term operation of the system.
Refer to Annexure C for the inspection requirements and hold points associated with PPS system
installation and commissioning.
The PPS control panel, and the motor-pump arrangement that supplies the PPS, shall be installed
above the bund high water level in order to prevent the equipment flooding in the event of bund
filling. The control panel shall also be installed in a location accessible from outside the bund
The PPS shall be fitted with waste oil tank that triggers the pump to stop when full. Testing and
maintenance specifications shall be supplied and verified by the manufacturer.

12.1.1

PPS system shut down

The PPS system shall be able to operate independently of the substation protection system. This
means the system shall independently shut down after an incident to avoid discharging oil off site.
The PPS power supply shall be dedicated and fitted with a Residual Current Device (RCD) unit at
the point of supply.

12.1.2

PPS system alarms

A communications system shall be installed using the Network Fibre Optic System where available.
This will enable local and remote monitoring and control of the PPS for the purposes of improved
efficiency and maintenance.
The PPS system shall provide alarm signals to the PPS control panel for the following conditions
as a minimum:
a)

Waste oil tank high level,

b)

Pump failure, and

c)

High bund level.

For Item c) the high level float switch shall be located in the sump just clear of the grate. The alarm
signal to SCADA is to be delayed by four hours.
Should any of these alarms activate, a flashing light mounted on top of the control panel is to
activate. In addition, suitable signals can be sent via the communications network identifying the
type of fault and any further data as required.
Only one alarm signal shall be sent to the control room via SCADA.

12.1.3

Neat oil flow

The PPS unit shall accept neat oil being pumped through the unit in the case of a bulk oil loss from
a catastrophic transformer failure. Under this condition the PPS unit shall:
a)

shut down when the waste oil tank high level is activated, and

b)

not discharge oil from the separator unit.

NW000-S0034

UNCONTROLLED IF PRINTED

Page 21 of 46

NS189 Oil Containment for Major Substations

12.1.4

Amendment No 0

PPS design and installation

Annexure B provides details of the main design features and installation requirements for PPS
systems to be installed at major substations.

12.2

Enhanced Gravity Oil Water Separator (EGOWS)


The EGOWS is an oil-water separation system developed by the University of New South Wales.
EGOWS are used with gravity drainage systems and generally provide stormwater discharges of
less than 10ppm of oil in water during normal storm events (refer to Section 13.1.4).
During higher intensity storm events the EGOWS could discharge oil/water of up to 100ppm or
greater. However, these events are rare and generally the discharge concentrations would be
much lower.
In environmentally sensitive areas the EGOWS tank may need to be increased in size where it is
necessary to achieve the required discharge limits for these higher intensity storm events.
Alternatively, where the site layout permits, a non-overflow tank design can be installed that
complies under all storm events. This system maintains a constant discharge and allows the inflow
to surcharge into the bund areas. The EGOWS tank will generally require access covers that are
raised to bund height.
EGOWS systems shall be installed in accordance with a site specific design to be provided by
Ausgrid for each substation. Refer to Annexure C for the inspection and hold points associated with
oil-water separator system installation and commissioning.

12.2.1

Emergency operation of EGOWS

A butterfly valve shall be located at the outlet of an oil containment tank in an easily accessible and
identifiable location. A butterfly valve may also be required at the secondary containment outlet.
Both valves shall be shut off with the application of firefighting medium in order to close off the
gravity drainage system.
Closure of the valves will allow the oil containment system to surcharge in such a way as to allow
overflow to be directed to a secondary containment area, whilst retaining bulk oil in the oil
containment tank. Alternatively, the flow can be surcharged into the transformer bund areas which
will provide a large secondary containment volume.
Where secondary containment is not viable an emergency plan response process will be required
to manage the surcharge overflow.

12.3

Access to tanks
All tanks shall be fitted with three 900 x 900 access covers to the appropriate class (Class B or D).
The covers shall be located one each on the inlet, middle and outlet chambers. Where surcharging
is possible, the tanks shall use bolt-down, gas tight covers in accordance with Section 12.3.1.
All tanks shall have 1.8m internal head clearance and shall contain internal vertical ladders or step
irons.
Enclosed tanks are confined spaces and will require signage and confined space entry procedures
in accordance with AS 2865 and WHS Regulation 2011. Refer to NS 190 for further details.
Tanks shall be provided with a 500 mm wide concrete slab at each end of the tank for the complete
width of the tank. This will allow erection of the fall arrest/confined space rescue supporting frame.
Where possible, allow 1 metre minimum access space around the access points of the tank for the
erection of fall arrest equipment.
All tanks are to be labelled with confined space signage located just inside the access covers on
the side edge of the roof slab.

NW000-S0034

UNCONTROLLED IF PRINTED

Page 22 of 46

NS189 Oil Containment for Major Substations

Amendment No 0

All tanks shall be suitably located to allow for removal of hatches and to enable ready access by
maintenance crews and cleanout tankers

12.3.1

Bolt down covers for hydraulic pressure

Bolt-down, gas tight covers shall be used where surcharge of the system is possible. The use of
bolt-down, gas tight covers will be site specific and dependent on the operation of the oil
containment system and hydraulic conditions.

12.4

Inspection and hold points


Annexure C provides details of the main inspection and hold points associated with the installation
of oil-water separators. Annexure C outlines the timing, responsibility and key inspection items
necessary to ensure that oil-water separation systems are properly installed and fully functional at
each site.
For closed drainage PPS systems a detailed commissioning procedure and checklist is provided in
NS190 Oil Containment Operational Requirements for Major Substations.

13.0 DRAINAGE AND ASSOCIATED STRUCTURES


13.1

Pipework
13.1.1

Closed drainage PPS system

Pipework installed between pumps and the PPS shall be located above ground and within the bund
storage area where possible.
Pipework shall be constructed using the following materials and designed to the appropriate
criteria;

Outdoor locations outside the bund area stainless steel pipes


Outdoor locations inside the bund area PVC pipes or other suitable material
Indoor locations where damaged pipework would discharge into stormwater stainless steel
pipes.
Indoor locations elsewhere PVC pipes or other suitable material
Temporary locations PVC pipes or other suitable material

Construction of above ground pipework is also preferred where a PPS system is being retrofitted to
an existing site or where buried pipework or gravity drainage is impractical. In such cases, the
appropriate pipework materials as indicated above shall be used.

13.1.2

Gravity drainage with oil containment tank

All pipes draining to an oil containment tank shall be designed to resist at least 1000C and be oil
resistant. In addition, any exposed pipes laid in open trenches shall also be fire resistant.
The preferred drainage system for gravity systems is:

Galvanised steel rolled grove system (Victaulic or approved equivalent), or


Stainless steel rolled grove system (Victaulic or approved equivalent), or
Cast iron pipes.

All pipe joints with rubber seals shall use Nitrile rubber or other oil resistant material.
Pipes are to be laid above ground on supports where possible or in trenches with removable
covers (similar to secondary cable trenches). Pipe trenches shall be drained to the stormwater
system.
For existing Brownfield sites, buried pipework using heavy-duty PVC, or cast iron can be direct laid
as a temporary measure to suit the phasing of construction works where required.

NW000-S0034

UNCONTROLLED IF PRINTED

Page 23 of 46

NS189 Oil Containment for Major Substations

Amendment No 0

For Brownfield sites, suitable exposed pipes that are laid on supports within existing cable trenches
can be considered where minimal ground disturbance is necessary. However, this approach will be
subject to achieving an acceptable design solution, and will require a site based risk assessment
and specific approval for each site.
A risk assessment shall be undertaken when adopting buried pipework to determine the risk of soil
contamination. The risk assessment shall consider issues such as site conditions, sensitive
environments, design life and ease of replacement.
Pipework in cable basements shall be subject to specific approval and will generally only be
acceptable in CBD major substations. Pipework in cable basements may also be considered at
sites where the transformers are adjacent to the substation building basement area. Stainless steel
or cast iron shall be used for all internal pipework in basements.

13.1.3

Pre-commissioning tests and inspection

All existing underground or above ground drainage pipes that can be used as part of the oil
containment system must have full hydraulic testing undertaken in accordance with the AS 3500.3.
All installed drainage pipes shall have zero leakage.

13.1.4

Design

Generally, a minimum of 0.5% fall is to be maintained for all drainage channels and pipework
draining to an oil containment tank.
Oil containment pipes for gravity drainage shall be 150mm in diameter, except for CBD substations
where larger diameter pipes may be necessary to cater for the high velocity water spray system.
As a guide, the oil containment tank should be sized such that oil globule sizes of 33 microns or
larger are contained within the tank for the following rainfall events:

1 in 1 year ARI storms of 1 hour, 12 hour, 24 hour, 48 hour and 72 hour duration, and
1 in 20 year ARI storm of 5 minute duration.

The various flow rates for firefighting medium are discussed in Section 6.1. For CBD substations
the oil containment pipes shall have sufficient capacity for the transformer high velocity water spray
system flowrates.
At suburban locations the pipework can be designed to allow the transformer bund area to
surcharge during firefighting flows. At these locations a butterfly valve is provided to shut off the oil
containment tank discharge to stormwater before firefighting commences (refer to Section 13.3.2).
For gravity drainage systems that adopt the use of pits at junctions (refer to Section 13.2.1), the
pipework shall be designed to ensure any downstream pits do not surcharge in the event that all
the oil from one transformer is lost instantaneously within one bunded area. During such events it is
assumed there will be no additional flow from a storm event or activation of fire hoses.

13.2

Pits and drainage channels


13.2.1

Encasement and finish

The use of continuous metal pipework laid in open trenches for gravity drainage systems negates
the need for any pits at junctions and also the need for watertightness at those pits. For pipework in
open trench systems, there shall be no pits on the inlet drainage line.
An alternative gravity drainage system that uses buried pipework with pits at junctions may also be
viable, but is generally not preferred . Where adopted (e.g. to retrofit existing sites) the associated
pits shall be cast in-situ and a hydrophilic seal placed around the pipe and cast into the pit.
Hydrophilic seals shall also be used on any concrete joints in the pit construction.
The finish on the inside of pits and drainage channels must be watertight. If a watertight structure
has not been achieved, a suitable concrete sealant shall be applied to achieve a seal. The sealant
used must be resistant to transformer oil and remain effective for the life of the pit or drainage
channel.
NW000-S0034

UNCONTROLLED IF PRINTED

Page 24 of 46

NS189 Oil Containment for Major Substations

Amendment No 0

Pipe trenches that are used to protect oil containment pipelines are not considered to be drainage
channels and the above requirements for watertightness do not apply.

13.2.2

Flame traps

Flame traps consist of a down turned pipe with a 300 mm (minimum) downturn and a 150 mm
clearance from the pit floor. The pits are typically 900 mm x 900 mm. The flame traps remain full of
water or oil forming a seal.
Flame traps are required for gravity drainage systems and should be located as close to the
transformer as possible to:
(a)

facilitate the fast removal of oil/water;

(b)

reduce oil drainage paths across the bunded area; and

(c)

reduce flame front size.

Flame traps must be cast in-situ with a hydrophilic seal around the pipe. Concrete joints should be
avoided in flame traps, but where they are required hydrophilic seals shall be used.

13.3

Valves
13.3.1

Closed drainage PPS systems

PPS systems shall use a ball valve to facilitate maintenance and removal of the pump. The ball
valve material shall be suitable for connection to the adjoining pipework

13.3.2

Gravity drainage systems

A butterfly valve shall be used to shut off an oil containment tank or to direct flow as required. The
valve shall be located in a pit that is readily accessible and identifiable, and shall be operable with a
spindle extension so entry to the valve pit is not required. The pit must have a hinged grate cover.
The butterfly valve shall be located such that it can be safely operated manually during a fire. A
suitable separation distance or a fire resistant barrier should be provided to reduce the radiant heat
exposure to an acceptable level. Refer to NS187 Passive Fire mitigation Design of Substations.
Where adequate fire segregation cannot be provided for the butterfly valve location, a risk
assessment shall be undertaken for the site.
The location of the butterfly valve can allow for a reduced fire front area based on the bunds being
gravity drained. The radiant heat level can be based on a transformer tank fire (sides and top)
together with a small pool fire along the flow path from the transformer to the sump. Modelling of a
full bund oil fire is not required during operation of the butterfly valve.
The position of the valve within a tank outlet area depends on the secondary containment method.
If the tank is to be used as secondary containment, the valve is positioned on the inlet to the valve
pit. If the secondary containment is a separate area, the valve needs to be positioned appropriately
to direct flow.
The equipment shall be capable of withstanding the conditions expected on site including potential
water/oil temperatures in a fire and be corrosion resistant. Valves shall also be low maintenance,
simple to operate, and all automatic shut off valves shall have a manual override.
The use of nonreturn valves should be avoided wherever possible, however they may be required
if the system is likely to be effected by:

a 1:100 year flood; or


surcharge of the pipework.

The Hume-King Flood Gate or approved equivalent is recommended for use as a non-return
valve.

NW000-S0034

UNCONTROLLED IF PRINTED

Page 25 of 46

NS189 Oil Containment for Major Substations

Amendment No 0

A stainless steel non-return valve is the only type acceptable for use in the major substation
environment.

13.4

Pumps
All pumps to be used on low lift oil containment systems shall be diaphragm pumps.
Diaphragm pumps are preferred for low lift applications. The system should be designed to ensure
that dirty water is low lift and this may mean relocating the discharge point closer to the influent
source.
Where high lift is required, a non-emulsifying screw pump may be used. These are prone to seizing
from debris and do not tolerate no flow conditions. Therefore, it is preferred to redesign the system
to facilitate the use of diaphragm pumps wherever possible.

13.4.1

Pumps for Parallel Plate Separators

All pumps used on the PPS system shall be ASM DS32 diaphragm pumps or approved
equivalent.

13.5

Infiltration Trenches
The use of infiltration trenches is generally not preferred and shall be subject to the approval of
Ausgrid.

14.0 FIRE FIGHTING WATER CONTAINMENT CAPACITY


For CBD and other major indoor substations using fixed firefighting systems, provision shall be
made for up to 90 minutes of expelled firefighting water to be stored in accordance with Fire Safety
Study Guideline, Hazardous Industry Planning Advisory Paper No. 2, Department of Planning NSW
Fire Brigades.
At non-rural sites, the minimum containment storage time for non-fixed system firefighting is 20
minutes. The assumed firefighting method shall be one hose with foam at 4 l/s.
For rural sites, the minimum containment storage shall also be 20 minutes. However, the flow rate
shall depend on the use/storage of foam. Where water only is available, a minimum of two fire
hoses at 10 l/s each (20 l/s) shall be assumed.
For both non-rural and rural sites, the required minimum containment storage can be inclusive of
the volume available within the bunded areas, plus any secondary containment or overflow areas
available on site. Refer also to Annexure A.
Where a full bund oil fire may occur, a suitable volume allowance can be made based on a
nominated burn down rate of 100mm per hour applied across the surface area of the bund. Actual
burn down rates may vary based on conditions and the use of higher values shall be subject to
approval by Ausgrid.

15.0 CAPACITORS
High voltage capacitors contain either Jarylec or Faradol fluid for the purpose of insulation. With a
specific gravity of 1.006 and 1.001 respectively, these fluids are slightly heavier than water and
therefore, standard gravity separation is impractical. Stormwater run-off from capacitor bank areas
must not pass into the standard oil containment catchments or oil containment tanks.

15.1

Outdoor capacitor banks


Capacitors are generally sealed units containing minimal oil with low risk of leakage. For this
reason, capacitors in outdoor yards shall not be bunded.

NW000-S0034

UNCONTROLLED IF PRINTED

Page 26 of 46

NS189 Oil Containment for Major Substations

Amendment No 0

If there is a significant risk of leaking capacitors, the use of a concrete perimeter bund may be
required and a risk assessment should be undertaken.
Evidence of leaking oil should be visible on founding concrete slabs or the ground around them and
should be inspected during oil containment maintenance.

15.2

Capacitor banks and fire sprinklers


Where the capacitor banks are located within a building and the room is fire protected with fire
protection sprinklers, the room shall be drained to a dedicated containment tank. The containment
tank must have the capacity to take minimum 90 minutes of the firefighting water. The room must
also be bunded.

16.0 POST EMERGENCY CLEAN UP


After an emergency it will be necessary to empty the oil containment system or storage tank and
undertake remediation of any areas of the major substation as required. Clean up work must be
undertaken in accordance with appropriate environmental guidelines and legislation. Contact
Environmental Services and Aqueous Waste Services for more information regarding emergency
clean up.
Following the emergency use of the system, the system will need to be re-commissioned.

17.0 DECOMMISSIONING OF OIL CONTAINMENT TANKS


An underground oil containment tank that has been taken out of service shall be either;
a)

removed, or

b)

drained, steam cleaned and completely filled with an inert solid material (e.g. sand, backfill
mortar).

All pipework shall be disconnected and removed from the tank, drained and the open ends sealed
off.
Due to the nature of an oil containment tank, there is potential for oil leakage during the service life
and resulting contamination of the surrounding soil and groundwater. When oil containment tanks
are decommissioned and/or removed the potential for contamination must be investigated.
Contact Ausgrid's Environmental Services for more information regarding the management of
contaminated land.

NW000-S0034

UNCONTROLLED IF PRINTED

Page 27 of 46

NS189 Oil Containment for Major Substations

Amendment No 0

18.0 RECORDKEEPING
The table below identifies the types of records relating to the process, their storage location and
retention period.
Table 1 Recordkeeping
Type of Record

Storage Location

Retention Period*

Approved copy of the network


standard

BMS Network sub process Standard


Company

Unlimited

Draft Copies of the network


standard during
amendment/creation

BMS Network sub process Standard


Company working folder

Unlimited

Working documents (emails,


memos, impact assessment
reports, etc.)

BMS Network sub process Standard


Company working folder

Unlimited

* The following retention periods are subject to change eg if the records are required for legal
matters or legislative changes. Before disposal, retention periods should be checked and
authorised by the Records Manager.

19.0 AUTHORITIES AND RESPONSIBILITIES


For this network standard the authorities and responsibilities of Ausgrid employees and managers
in relation to content, management and document control of this network standard can be obtained
from the Company Procedure (Network) Production/Review of Network Standards. The
responsibilities of persons for the design or construction work detailed in this network standard are
identified throughout this standard in the context of the requirements to which they apply.

20.0 DOCUMENT CONTROL


Content Coordinator

Transmission and Distribution Substation Engineering Manager

Distribution Coordinator

Manager Engineering Information & Services

NW000-S0034

UNCONTROLLED IF PRINTED

Page 28 of 46

NS189 Oil Containment for Major Substations

Amendment No 0

Annexure A Secondary Containment Options


A1

Greenfield and brownfield sites with PPS systems


Where the site has no tank and the closed drainage PPS system will be installed, the following
options in order of preference, should be considered.
Options

Containment
method

Detailing
requirements

Additional
containment
available

Disadvantages

Allow for the


burn down rate
due to a full
bund oil fire

Adopt a burn
down rate of
100mm/hr over
the full bund
surface area

Dependant on bund
surface area and
3
time. (e.g. 12m for a
2
60m bund after 2
hours)

Available volume is time


dependant

Raise bund
height

Raise bunds to a
height to meet risk
assessment
containment
volumes.

Minimum 5000 litres maximum depends


on maximum
allowable bund
height.

Higher bunds means


greater heights for persons
to traverse into the bund.
This may create a WHS
risk.

Provide overflow
into
neighbouring
bunds

Needs connection
to neighbouring
bunds via
pipework or
underflow weirs.

Available volume has


to be calculated for
each site, but
generally will be
approximately 40,000
litres.

Foam is corrosive. Some


damage may occur to the
neighbouring assets.
Extensive pipework may be
required where bunds are
not adjacent to one
another.
Preferred only where
FSWs are in place.

Provide an
overflow area

Requires drainage
paths to direct
flow to the
containment area.

Limited only
by site constraints.

Difficult to achieve at
brownfield sites due to
topography and space.

Requires
installation of
appropriate
signage and
warnings.
5

Use the cable


basement

Requires the
basement to be
made watertight.
Requires
appropriate shut
off valves and
additional
drainage lines.

NW000-S0034

Suitable containment area


must be available at the
site.

Requires a clean-up of the


area following an incident.
Depends on the
basement size.
Generally in excess
of 30,000 litres.

UNCONTROLLED IF PRINTED

Corrosive foam could


cause damage to the
assets in the basement.
Requires extensive
pipework.
Many sites do not have
cable basements.
Requires a clean-up of the
area following an incident.

Page 29 of 46

NS189 Oil Containment for Major Substations

A2

Amendment No 0

Greenfield sites with tanks (EGOWS)


Where the site has a tank that the bunded areas can drain to by gravity, the following options in
order of preference should be considered.
Options

Containment
method

Detailing requirements

Utilise the
freeboard in the
tank

Needs the tank outlet shut


off valve to be fitted. The
valve is to be shut prior to
application of fire-fighting
medium.

Additional
containment
available
Approximately
5000 litres.
Actual volume
depends on the
tank size.

Needs the drainage system


from the bunds to the tank
to be watertight system to
prevent loss.

Disadvantages

Needs bolt down


covers which are a
minor inconvenience
for maintenance.
Watertight systems
may exclude FRC pipe
systems.

All pits must have bolt


down gas lids.
2

Provide overflow
into neighbouring
bunds

Needs connection to
neighbouring bunds via
pipework or underflow
weirs.

Available
volume has to
be calculated for
each site, but
generally will be
approximately
40,000 litres.

Foam is corrosive.
Some damage may
occur to the
neighbouring
transformer.
Would require a cleanup after an incident.

Utilise the
freeboard in the
tank and raise
bunds

Same as option 1, except


for the addition of raised
bunds.

Limited by bund
height
restrictions on
site

Same as option 1,
except the increased
WHS risk of raising
bunds must be
considered.

Provide an
overflow area

Requires tank outlet pit


outlet shut-off valve. This
will direct flow to another
area.

Limited only by
site constraints
(topography and
site use).

Suitable containment
area must be available
at the site.

Depends on the
basement size.

Corrosive foam could


cause damage to the
cables.

Alternatively, the tank can


overflow to the secondary
containment area and the
outlet from that area is
provided with a shut off
valve.
5

Direct flow to the


cable basement

Requires the basement to


be made watertight - or
keep a zone 300 mm from
the floor penetration free.
Requires appropriate shut
off valves and additional
drainage.

Generally in
excess of
30,000 litres.

Would require clean-up


after an incident.

Would require a cleanup after an incident.

Requires appropriate
warning alarms to
evacuate the basement.

NW000-S0034

UNCONTROLLED IF PRINTED

Page 30 of 46

NS189 Oil Containment for Major Substations

A3

Amendment No 0

Brownfield sites with tanks (Single stage, three stage or other)


Where the site has an existing tank that will be re-used when upgraded, the following options in
order of preference should be considered.
Options

Containment
method

Detailing requirements

Utilise the
freeboard in
the tank

Needs tank outlet shut off


valve to be fitted. The
valve is to be shut prior to
application of fire-fighting
medium.

Additional
containment
available

Disadvantages

Approximately 5000
litres.

Potentially expensive.

Available volume has


to be calculated for
each site, but
generally will be
approximately 40,000
litres.

Foam is corrosive.
Some damage may
occur to the
neighbouring
transformer. Potentially
expensive.

Existing drainage lines


may not be watertight
in most, if not all,
cases.

Needs watertight system.


2

Provide
overflow into
neighbouring
bunds

Needs connection to
neighbouring bunds via
pipework or underflow
weirs.
Needs shut off to tank
inlet.
Needs a watertight
drainage system between
bunds and the tank, to
prevent oil loss.

Existing drainage lines


may not be watertight
in most, if not all,
cases.

All lids must have bolt


down gas tight lids.

Would require a cleanup after an incident.


Preferred only where
FSWs are in place.

Utilise the
freeboard in
the tank and
raise bunds

Same as option 1, except


for the addition of raised
bunds.

Limited by bund
height restrictions on
site.

Same as option 1,
except the increased
WHS risk of raising
bunds must be
considered.

Provide an
overflow area

Requires tank outlet pit


outlet shut-off valve. This
will direct flow to another
area.

Limited only by the


site constraints.

Suitable containment
area must be available
at the site.
Containment areas will
require maintenance
and monitoring.

Alternatively, the tank


can overflow to the
secondary containment
area and the outlet from
that area is provided with
a shut off valve.
5

Direct flow to
the cable
basement

Would require a cleanup after an incident.

Requires the basement


to be made watertight.

Depends on the
basement size.

Requires appropriate
shut off valves and
additional drainage to
divert flow to the
basement.

Generally in excess
of 30,000 litres.

Requires appropriate
warning alarms to
evacuate the basement.

NW000-S0034

UNCONTROLLED IF PRINTED

Corrosive foam could


enter and cause
damage to the cables.
Requires extensive
pipework.
Many sites do not have
cable basements.
Would require a cleanup after an incident.

Page 31 of 46

NS189 Oil Containment for Major Substations

Amendment No 0

Annexure B Oil Separator Design, Installation and


Commissioning Requirements

B1

Introduction
The design, installation and operation of an oil containment system requires the coordination of a
number of functional groups within Ausgrid. A fully compliant system requires the timely input of
various design, environmental, procurement, construction and operational personnel in order to
achieve a satisfactory outcome.
Figures B1 and B2 provide an outline of the key roles and responsibilities within Ausgrid from initial
design up to the practical completion stage.

B2

Key responsibilities
1. Parallel Plate Separator systems
There are a number of manufacturers and types of PPS oil containment systems. The PPS unit
currently being installed in major substations for Ausgrid is the Ovivo EnviroSEP OS 7500 Oil
Separator.
The design principle is generally consistent across all substations but may require variations to the
final placement of some components due to local equipment and conditions.
The key roles and responsibilities within Ausgrid for the design, installation and commissioning of
PPS oil containment systems are as follows:
1. The installation or upgrade of the PPS system is project managed by the Major Projects or
Capital Programs Group;
2. The design drawings For Construction are provided by the Project Development Group;
3. The installation is mainly carried out by Contractors, with power supply and SCADA connections
by Ausgrid Field Technicians;
4. The inspection and commissioning responsibilities are as identified in Annexure C. The
commissioning checklist and procedure are contained in Sections B5 and B6 of this Annexure;
5. The emergency drainage diagram is prepared by Project Development Group to meet the
requirements of NS 186, and is installed by Aqueous Waste Services Group;
6. The operation and maintenance functions are to be carried out by the Aqueous Waste Services
Group. Refer to Annexure A of NS 190.
The PPS oil containment system shall be correctly installed and fully commissioned on site with a
minimum 12 months defects liability period to ensure effective long term operation of the system.
To facilitate this process, and ensure an effective handover of the equipment, the Project Manager
shall obtain the advice and input of the Aqueous Waste Services Group during the delivery,
installation and final inspection of the PPS system.
Certification that the system has been installed in accordance with the design documentation and
manufacturers requirements shall be provided by all commissioning parties (including the PPS
manufacturer) at the completion of commissioning works.

2. Oil containment tank systems


The key roles and responsibilities within Ausgrid for the design, installation and
commissioning of oil containment tank systems are as follows;
1. The overall system design, internal configuration, internal dimensions and standard details are
the responsibility of the Project Development Group. The Project Development Group may
delegate any aspect of these functions to others as required;
2. Project management, construction and fit-out of the oil containment system is the responsibility
of the Major Projects or Capital Programs Group;

NW000-S0034

UNCONTROLLED IF PRINTED

Page 32 of 46

NS189 Oil Containment for Major Substations

Amendment No 0

3. Final inspection and acceptance of the completed installation is the responsibility of the Project
Development Group (Civil Works), with specialist and technical input for equipment (e.g. oil
sensors) as required by the Aqueous Waste Services Group during installation and
commissioning;
4. The emergency drainage diagram is prepared by Project Development Group to meet the
requirements of NS 186, and is installed by Aqueous Waste Services Group;
5. Operation and maintenance of the complete oil containment system is the responsibility of the
Aqueous Waste Services Group. Refer to Annexure A of NS 190.

NW000-S0034

UNCONTROLLED IF PRINTED

Page 33 of 46

NS189 Oil Containment for Major Substations

Amendment No 0

Figure B1 Oil containment systems design responsibilities

NW000-S0034

UNCONTROLLED IF PRINTED

Page 34 of 46

NS189 Oil Containment for Major Substations

Amendment No 0

Figure B2 Oil containment systems procurement and construction responsibilities

NW000-S0034

UNCONTROLLED IF PRINTED

Page 35 of 46

NS189 Oil Containment for Major Substations

B3

Amendment No 0

Parallel Plate Separator design and installation


The Ovivo EnviroSEP OS 7500 Oil Separator Unit is made of 304 Grade Stainless Steel and
designed to operate at a maximum flowrate of 5000L/hr. Welding uses mild steel rods as standard,
with stainless steel available on request.
The Ovivo EnviroSEP OS 7500 Unit is 2.1m x 1.86m x 1.175 m high and weighs 550kg empty and
2400kg when full.
The PPS oil separator can be used with inlets from up to four bund pumps. Each pump is set at an
equal proportional flowrate so as not to exceed the maximum 5000L/hr at the PPS inlet. Hence, the
Total System Capacity of 5000L/hr = F (proportional single flowrate) x N (Number of sump pumps).
The required flowrate for various combinations of pumps is indicated below. All pumps should have
the required flowrate indicated on the Pump ID label, located near the pump.

Required Flowrate
L/hour

Allowable Range
L/hour

2,500

2,400 2,500

All pumps operating

5,000

4,900 5,000

One of two pumps operating

2,500

2,400 2,500

One of three pumps operating

1,700

1,600 1,700

One of four pumps operating

1,250

1,150 1,250

Description
1. Single Pump Sites
One pump operating
2. Multi-Pump Sites

Wherever possible all pipes carrying water shall be installed inside the bund area to enable leaks to
be contained.
All conduits and termination boxes for electrical cables shall be in accordance with AS 3000.
Each pump is to be supplied by a dust-tight, immersion-proof (rated IP67 or above) 10A 240v
Switched Outlet accessible from outside the bund.
The PPS shall have a dedicated 240vAC 20Amp supply from a 20A Combination Circuit Breaker
and RCD (Safety Switch) on the Substation main AC Board and be labelled at both ends to identify
the circuit. When commissioned a single Alarm shall be operational to the System Control Room,
with the contact phone number marked on the Control Panel. The Alarm shall have the provision
inside the Control Panel of being made Non-Auto during servicing.
The PPS oil separator tank shall be located in a bunded area and mounted on four 50mm x 15mm
threaded mounting studs so as to provide a height adjustment nut below the support bracket and a
locknut above.
The Control Panel shall be mounted to be accessible from outside the bund area. The Control
Panel door shall be lockable with a lock type that enables fitting of a suitable Abloy lock to be
supplied and keyed by the Oil Containment Group.
The PPS shall have all outflow 50mm Kamlock fittings located for the easy connection of tanker
hoses from the front. Where the PPS is located in confined areas, the use of a detachable 900
elbow with Kamlock fittings is acceptable.
Each bund pump shall have a stainless steel flexible hose approximately 500mm long (end fittings
excluded) to suit the site constraints and located on the outlet side only. Each pump outlet shall
have a ball valve between the flexible hose and rigid pipe. Each pump shall have a stainless steel
weatherproof cover that can be easily removed for servicing and is fitted with ventilation louvres on
three sides adjacent to the motor vents. The pump cover is to be hinged on the opposite side to the
pump pulleys.

NW000-S0034

UNCONTROLLED IF PRINTED

Page 36 of 46

NS189 Oil Containment for Major Substations

Amendment No 0

Where cables are installed in metal pipes or covers, the ends shall be bushed to prevent cable
damage.
The discharge of the PPS shall be directed to the transformer roadway or other well drained areas
and shall allow sufficient space for future sampling. The discharge shall not be connected directly
to stormwater pipes or pits. Site drainage shall be arranged so as to avoid long term ponding
directly in front of the Control Panel.
The Control Panel shall have an Auto/Off Selector Switch for the PPS Alarm circuit. A Control
Panel Operations Manual and PLC logic diagrams shall be available to enable the interrogation
and calibration of the Control Panel PLC. An electrical circuit diagram for the Control Panel shall
also be available in order to facilitate connection of sensors etc by qualified persons.

B4

PPS manufacturer installation requirements


B4.1 General
Installation

Electricals must comply with AS 3000. The installing electrical Contractor shall
provide to the Project Manager a Certificate of Completion - Electrical Works
(CCEW) to confirm compliance with AS 3000.

Pump installation

A stainless steel flexible hose of approximately 500mm in length (end fittings


excluded) and correct diameter on the discharge side only of the pump. Refer
to OCD 513.

Level Floats

Pump start and stop settings are to be to Ausgrid standard detail OCD 514.
The high level float should operate at the maximum height in the sump just
below the grate level.

B4.2 Electrical requirements


Rating

Minimum
Requirements

20A RCD Unit on Sub AC


Board to Control Panel

240vAC 20A

1 x 3 core cable

Sub SCADA to Control Panel

110vDC

1 x 2 core cable

Item

Description

Supply
SCADA

Sub SCADA to Control Panel


Floats

Pumps

1 x 4 core fibre cable

Junction Box to each Float

24vAC

1 x 2 core cable per float

Junction Box to Control


Panel

24vAC

1 x 6 core cable

Control Panel to each Pump


Motor Supply Outlet

240vAC 10A

1 x 3 core cable per


pump

B4.3 Pump installation


Generally, ASM DS32 pumps shall be used on all sites to reduce the requirement for spares. Other
pump sizes may be used where specific site conditions dictate
The pump motor must be covered to the details shown on the project drawings.

B4.4 Pipe installation


Pipes shall be as specified on the project drawings. Generally, the use of ASM DS32 pumps will
require 40mm suction pipes and 50mm discharge pipes.

NW000-S0034

UNCONTROLLED IF PRINTED

Page 37 of 46

NS189 Oil Containment for Major Substations

Amendment No 0

B5 OVIVO EnviroSEP OS7500 Oil separator commissioning checklist


Substation No.:
A

Name :

1
2
3
4
5
6
7

OIL SEPARATOR UNIT


Unit installed on four mounting studs c/w nuts for height adjustment
Lids are adequate and can be secured in Open and Closed Positions
Levels are Weir +/- 0mm across the fixed secondary weir and max 5mm along the unit
Hose Kamlock fittings readily accessible with or without the 900 detachable elbow, as applic.
Discharge to well drained area and no long term ponding in front of Control Panel
Flowrate checked OK
High Oil Alarm operation checked

1
2
3
4
5
6
7
8
9

CONTROL PANEL
Control Panel door is lockable and hinged mounting panel is lockable
Installed securely to enable access from outside of bund area
Oil Containment Label and contact phone number on outside
Control Room Operator contact number on inside, near Alarm Switch
20A Supply on a dedicated circuit from Substation AC Board
Alarm Auto/Non-Auto Switch fitted to Control Panel
Alarm and cancel operation checked with Control Room
All conduit and cable entries are waterproof and secure
Pump Isolating Switch is lockable in OFF Position

BUND AREAS, PUMPS and FLOAT SWITCHES

1 Pumps installed above high water level


2 Pumps are fitted with a removable weatherproof cover
Each Pump Motor is supplied via a 240vAC 10A Switched Power
3
Outlet (rated IP67 or above)
4 Pump motor clockwise rotation (from rear) and breather checked
5 Pump primed and flowrate checked
6 Flexible hose length is 500mm on the discharge side only of pump
7 All pipes sizes are as per pipe schedules on project drawings
8 Ball valve fitted only between flex hose and fixed pipes.
9 All electrical conduits are in accordance with AS 3000
10 Float Switch position and operation checked
11 Bunds and Pumps labelled correctly

GENERAL
1
2
3
4
5
6

All conduits with cables are bushed to prevent cable damage


All conduits are mechanically protected over/outside of bunds
Water supply available nearby. (where possible)
Power Supply circuit protected by RCD Unit incorporating a C.B.
Operation/Maintenance settings and functionality checked
Discharge water 500ml sample for Oil%, PCB and pH levels.

1
2
3
4
5

The Substation has an Emergency Drainage Diagram


Oil Separator Unit entered in TIS as Task U116
Electricians Certificate of Completion signed and submitted No.
A copy of this report is given to Major Projects Group
Identified remedial actions completed.

ADMINISTRATION
Dwg :
Dated:
Date:
Date:

Checked by: ................................................................................. Date: ....................................

NW000-S0034

UNCONTROLLED IF PRINTED

Page 38 of 46

NS189 Oil Containment for Major Substations

B6

Amendment No 0

OVIVO EnviroSEP OS7500 Oil separator commissioning procedure


Substation :
Contact:
Equipment
required:

System
Status:

System
Preparation:

Pump
Operation
Checks:

Bund
Float
Alarm
Checks

High Oil
Level
Alarm

NW000-S0034

Major Projects Group :


1. Socket Set
2. Silicon and Application Gun
3. Allen Keys
4. Rags
5. Spirit Level
6. Rule / Tape measure
7. Permanent Marker
1. Installation is complete
2. Power is connected
3. Pump direction has been checked clockwise from rear of pump motor
4. Oil Separator unit is filled with water
5. Water is available on site for this procedure
1. Alarm Non-Auto and advise System Control Room as per label
2. Record details of the Oil Separator Unit and all pumps
3. Ensure all switches in the Control Panel are OFF
4. Check the Pump Isolating Switch on the side of the Control Panel is OFF
5. Check the Main Supply Circuit Breaker inside the Control Panel is OFF
6. Check that all wiring appears complete.
7. Check that the pumps are mounted above the bund spill height.
8. Check that electrical cables do not rub against metal edges
9. Check that the pump has been prepared for operation
10. Pipework between the sumps and pumps are complete and correct size (40mm).
11. Pipework between the pumps and separator are complete and correct size (50mm)
12. Flexible hoses are used between pumps and discharge pipes of at least 500mm in
length (end fittings excluded).
13. The oil separator outlet pipe flows to stormwater.
14. Water in all the bund sumps covers the float switches.
15. Check the Oil Separator Unit levels front to back (+/- 0mm) and side to side (+/- 5mm)
1. Ensure the Main Supply Circuit Breaker inside the Control Panel is ON
2. Ensure the Pump Isolating Switch on the side of the Control Panel is ON
3. Turn Pump Switch No1 to AUTO
4. Raise No.1 float switch to initiate No.1 pump start
5. With each pump operation check pump direction and water flow prime if necessary
6. Repeat pump operation check for each Pump Switch
7. Ensure that all Pump Switches are OFF after each pump operation check
1. Ensure the Main Supply Circuit Breaker inside the Control Panel is ON
2. Ensure the Pump Isolating Switch on the side of the Control Panel is ON
3. Raise High Alarm Float in Bund No.1 and observe alarm operation
4. Bund No.1 Alarm and Common Flashing Alarm should both light up.
5. Lower the High Alarm Float and both the Alarm Indicators should reset
6. Repeat the High Alarm check for each bund.
1.
2.

Ensure the Main Supply Circuit Breaker inside the Control Panel is ON
Ensure the Pump Isolating Switch on the side of the Control Panel is ON

UNCONTROLLED IF PRINTED

Page 39 of 46

NS189 Oil Containment for Major Substations

Amendment No 0

Check

3.
4.
5.

Raise High Oil Alarm Float in the Oil Separator and observe alarm operation
The High Oil Alarm and Common Flashing Alarm should both light up.
Lower the High Oil Alarm Float and both the Alarm Indicators should reset

Pump
Supply
Fail
Alarm
Check

1.
2.
3.
4.
5.
6.

Ensure the Main Supply Circuit Breaker inside the Control Panel is ON
Ensure the Pump Isolating Switch on the side of the Control Panel is ON
Trip the Circuit Breaker for Pump No.1 inside the Control Panel
Observe that the Pump Fault Light and Common Alarm Light operate
Reset the Circuit Breaker and observe that both alarms reset
Repeat this test for each pump

Oil
Weir
Setting

1.
2.
3.
4.
5.

Fill unit with water to almost full


Note the distance from the top of the water to the top of the fixed oil weir
Set the distance from the water to the adjustable oil weir
Set the adjustable oil weir with silicon
Ensure that the silicon is level across its length

Outlet
Weir
Setting

1.
2.
3.
4.
5.
6.
7.
8.

The Outlet Weir setting determines the level of the water in the separator.
Ensure the Main Supply Circuit Breaker inside the Control Panel is ON
Ensure the Pump Isolating Switch on the side of the Control Panel is ON
Turn each Pump Switch on the Control Panel to AUTO
Allow the flow to maximise and settle
Adjust the Outlet Weir to be 3 8 mm below both the oil weirs.
Lock the Outlet Weir using an Allen Key on the grub screw.
Allow the system to drain each bund which automatically switches each pump OFF

Discharge
Testing

1.

Ensure that the oil separator has stabilised and is operating with discharge water
flowing
Fill a 500ml sample bottle from the discharge outlet flow for testing
Arrange for testing of the discharge sample for Oil, PCB and pH.

2.
3.
Checks
completed

1.
2.
3.
4.
5.
6.
7.

NW000-S0034

Contact Supervisor if the supply RCD Safety Switch does not reset after test.
Ensure that all Switches are in AUTO or ON
Secure the inside panel and Control Panel door and retrieve all access keys
Restore Alarm then contact System Control Room Operator to confirm Alarm and
Reset
Ensure all equipment details are recorded
Record any defects, required repairs and items for attention
Contact Supervisor if any unsafe condition is found.

UNCONTROLLED IF PRINTED

Page 40 of 46

NS189 Oil Containment for Major Substations

Amendment No 0

Annexure C Oil separator inspection requirements and hold


points

NW000-S0034

UNCONTROLLED IF PRINTED

Page 41 of 46

NS189 Oil Containment for Major Substations

NW000-S0034

UNCONTROLLED IF PRINTED

Amendment No 0

Page 42 of 46

NS189 Oil Containment for Major Substations

Amendment No 0

Annexure D Sample Compliance Checklist

NW000-S0034

UNCONTROLLED IF PRINTED

Page 43 of 46

NS189 Oil Containment for Major Substations

NW000-S0034

UNCONTROLLED IF PRINTED

Amendment No 0

Page 44 of 46

NS189 Oil Containment for Major Substations

NW000-S0034

UNCONTROLLED IF PRINTED

Amendment No 0

Page 45 of 46

NS189 Oil Containment for Major Substations

NW000-S0034

UNCONTROLLED IF PRINTED

Amendment No 0

Page 46 of 46

You might also like