1 Pre-Construction Requirements: 2.1.8 Finish Building Foundation

This document outlines a project schedule spanning from March 2015 to February 2016. It includes 4 main stages: pre-construction requirements, building construction, mechanical and electrical systems, and miscellaneous facilities. Key milestones include completing the building foundation by September 2015, installing the PU panel insulation by January 2016, and having the project ready for final commissioning by February 2016. The critical path runs through the refrigeration, electrical, and pre-startup systems work.

Uploaded by

Jom Bonhayag
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
172 views2 pages

1 Pre-Construction Requirements: 2.1.8 Finish Building Foundation

This document outlines a project schedule spanning from March 2015 to February 2016. It includes 4 main stages: pre-construction requirements, building construction, mechanical and electrical systems, and miscellaneous facilities. Key milestones include completing the building foundation by September 2015, installing the PU panel insulation by January 2016, and having the project ready for final commissioning by February 2016. The critical path runs through the refrigeration, electrical, and pre-startup systems work.

Uploaded by

Jom Bonhayag
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

ID

Task
Mode
1

Task Name

Duration

Start

Finish

1 PRE-CONSTRUCTION REQUIREMENTS

53 days

Wed 3/25/15

Fri 6/5/15

1.1 Civil design & permit

16 days

Wed 3/25/15

Wed 4/15/15

1.2 Electrical design & permit

11 days

Wed 4/1/15

Wed 4/15/15

1.3 Structural design & approval

14 days

Fri 4/3/15

Wed 4/22/15

1.4 Insulation design & final approval

15 days

Mon 5/18/15

Fri 6/5/15

1.5 Refrigeration design approval & downpayment

1 day

Wed 3/25/15

Wed 3/25/15

2 BUILDING CONSTRUCTION

206 days?

Wed 4/8/15

Wed 1/20/16

2.1 BUILDING CIVIL WORKS

206 days?

Wed 4/8/15

Wed 1/20/16

2.1.1 Site preparation

11 days?

Wed 4/8/15

Wed 4/22/15

10

2.1.2 Fabrication of rebars

120 days

Wed 4/8/15

Tue 9/22/15

11

2.1.3 Footing & Column @ GL A,B,D,H & J/1-15

71 days

Tue 4/21/15

Tue 7/28/15

12

2.1.4 Installation of anchor bolts

1 day

Tue 8/4/15

Tue 8/4/15

13

2.1.5 Tie Beam, Ret. Wall & Slab-on-Grade@ GL A-C/1-15

43 days

Tue 6/30/15

Thu 8/27/15

14

2.1.6 Tie Beam, Ret. Wall & Slab-on-Grade @ GL D-H/1-15

65 days

Tue 6/30/15

Mon 9/28/15

15

2.1.7 Tie Beam, Ret. Wall & Slab-on-Grade @ GL I-J/1-15

43 days

Tue 6/30/15

Thu 8/27/15

16

2.1.8 Finish building foundation

0 days

Mon 9/28/15

Mon 9/28/15

17

2.1.9 Machine Room & EE Room

38 days

Tue 6/30/15

Thu 8/20/15

18

2.1.10 Finish machine room foundation

0 days

Thu 8/20/15

Thu 8/20/15

19

2.1.11 Slab-on-Grade @ C-D & G-I/1-15

34 days

Tue 9/29/15

Fri 11/13/15

20

2.1.12 Top Slab

14 days

Sat 1/2/16

Wed 1/20/16

114 days

Thu 4/23/15

Tue 9/29/15

21

2.2 BUILDING STEEL STRUCTURE

22

2.2.1 Fabrication up to shipment

10 wks

Thu 4/23/15

Wed 7/1/15

23

2.2.2 Erection & installation

8 wks

Wed 8/5/15

Tue 9/29/15

24

2.2.3 Roofing

7 wks

Wed 8/12/15

Tue 9/29/15

25

163 days?

Mon 6/8/15

Wed 1/20/16

26

2.3.1 Fabrication

56 days

Mon 6/8/15

Mon 8/24/15

27

2.3.2 Shipment

78 days?

Mon 7/6/15

Wed 10/21/15

28

2.3.3 Installation of PU panels

100 days

Thu 9/3/15

Wed 1/20/16

237 days?

Thu 3/26/15

Fri 2/19/16

155 days

Thu 3/26/15

Wed 10/28/15

29
30

2.3 PU PANEL INSULATION

3 MECHANICAL & ELECTRICAL SYSTEM


3.1 REFRIGERATION SYSTEM

31

3.1.1 Fabrication of equipment

14 wks

Thu 3/26/15

Wed 7/1/15

32

3.1.2 Packing & shipment

7 wks

Mon 6/22/15

Fri 8/7/15

33

3.1.3 Equipment installation

5 wks

Thu 8/20/15

Wed 9/23/15

34

3.1.4 Piping works

10 wks

Thu 8/20/15

Wed 10/28/15

35

3.2 ELECTRICAL SYSTEM

168 days?

Wed 7/1/15

Fri 2/19/16

36

3.2.1 Electrical substation

86 days?

Wed 7/1/15

Wed 10/28/15

37

3.2.2 MTS/power panel/MDP/LP

14 wks

Wed 7/1/15

Tue 10/6/15

38

3.2.3 Cable trays

10 wks

Thu 8/20/15

Wed 10/28/15

39

3.2.4 Wiring (power, lighting, refrigeration intruments & controls)

12 wks

Thu 9/3/15

Wed 11/25/15

40

3.2.5 Miscellaneous (Genset & reefer outlet)

22 wks

Wed 7/1/15

Fri 2/19/16

90 days

Wed 7/22/15

Tue 11/24/15

41

3.3 WATER & WATER TREATMENT SYSTEM

42

3.3.1 Water divining & deepwell construction

6 wks

Wed 7/22/15

Tue 9/1/15

43

3.3.2 Pumping & piping works

10 wks

Wed 9/2/15

Tue 11/10/15

44

3.3.3 Water treatment (water softener for condenser water)

11 wks

Wed 8/5/15

Tue 10/20/15

45

3.3.4 Testing of water softener

2 wks

Wed 11/11/15

Tue 11/24/15

46

50 days

Mon 11/30/15

Fri 2/5/16

47

3.4.1 Testing & Commissioning

5 wks

Mon 11/30/15

Fri 1/1/16

48

3.4.2 Temperature pull-down

4 wks

Mon 1/11/16

Fri 2/5/16

49

3.4.3 Ready for final commissioning

0 days

Fri 2/5/16

Fri 2/5/16

185 days

Wed 6/17/15

Tue 3/1/16

35 days

Wed 11/4/15

Tue 12/22/15

7 wks

Wed 11/4/15

Tue 12/22/15

160 days

Wed 7/22/15

Tue 3/1/16

50
51
52
53

3.4 PRE-STARTUP

4 MISCELLANEOUS FACILITIES
4.1 FIRE FIGHTING
4.1.1 Sprinklers, hydrants & fire hose cabinets (incl. piping)

4.2 WASTE WATER TREATMENT FACILITY

54

4.2.1 Design & awarding to contractor

8 wks

Wed 7/22/15

Tue 9/15/15

55

4.2.2 Delivery & construction

16 wks

Wed 9/16/15

Tue 1/5/16

56

4.2.3 Testing & commissioning

8 wks

Wed 1/6/16

Tue 3/1/16

57

155 days

Wed 6/17/15

Tue 1/19/16

58

4.3.1 Design & awarding to contractor

8 wks

Wed 6/17/15

Tue 8/11/15

59

4.3.2 Fabrication of shoots & conveyors

23 wks

Wed 8/12/15

Tue 1/19/16

60

4.3.3 Bidding & purchase of weighing scales

3 wks

Wed 6/17/15

Tue 7/7/15

Project: Project1
Date: Mon 10/26/15

4.3 FISH RECEIVING AREA

Task

Inactive Summary

External Tasks

Split

Manual Task

External Milestone

Milestone

Duration-only

Deadline

Summary

Manual Summary Rollup

Progress

Project Summary

Manual Summary

Manual Progress

Inactive Task

Start-only

Inactive Milestone

Finish-only

Page 1

Predecessors

9SS
2FS+3 days
11FS+4 days
11SS+45 days
11SS+45 days
11SS+45 days
11SS+45 days

4
12,22,16FF
16FF
5
26FS-38 days
16FS-25 days

6
31FS-20 days
18,32
33SS

38SS+2 wks

42
43,44

47FS+5 days

54
55

58
58SS

Resource1st
Names
Quarter
Feb

2nd Quarter
Apr

Mar

May

Jun

3rd Quarter
Jul

Aug

Sep

4th Quarter
Oct

Nov

Dec

1st Quarter
Jan

Feb

9/28
8/20

2/5

Project: Project1
Date: Mon 10/26/15

Task

Inactive Summary

External Tasks

Split

Manual Task

External Milestone

Milestone

Duration-only

Deadline

Summary

Manual Summary Rollup

Progress

Project Summary

Manual Summary

Manual Progress

Inactive Task

Start-only

Inactive Milestone

Finish-only

Page 2

Mar

2nd Quarter
Apr