The correct answer for each question is indicated by a This is the correct answer..
1 Which of the following is not one of the commonly heard comments of project managers?
A) Where did this project come from?
B) Why are we doing this project?
C) How can all these projects be first priority?
D) Why is this project so strongly linked to the strategic plan?
E) Where are we going to get the resources to do this project?
Ans : D
2 Strategy considered to be under purview of senior management is
A) Old school thinking
B) A new school of management thought
C) Necessary in a company structure
D) Beneficial to the Project Manager
E) Dependent on company goals
Ans: A
3 The intended outcome of strategy/projects integration is
A) Clear organization focus
B) Best use of scarce organization resources
C) Improved communication across projects and departments
D) Both A and C are correct
E) A, B, and C are all correct
Ans: E
4 Project managers who do not understand the role that their project plays in accomplishing
the organization's strategy tend to make all the following mistakes except:
A) Focusing on low priority problems
B) Overemphasizing technology as an end in and of itself
C) Focusing on the immediate customer
D) Trying to solve every customer issue
E) All the above are likely mistakes
Ans: E
5 The textbook indicated that ________ is the major dimension of strategic management.
A) Responding to changes in the external market
B) Allocating scarce resources of the organization
C) Beating competition to the market
D) Both a and b are correct
E) Both a and c are correct
ANS grin emoticon
6 Which of the following questions does the organization's mission statement answer?
A) What are our long-term strategies?
B) What are our long-term goals and objectives?
C) How do we operate in the existing environment?
B) Bread-and-butter
C) Pearls
D) Oysters
E) White elephants
ANS:A
13 Which of the following is the reason(s) why project managers need to understand their
organization's mission and strategy?
A) To make appropriate decisions and adjustments
B) To be effective project advocates
C) To be able to get their job done
D) Both A and B are correct
E) A, B, and C are all correct
ANS:D
14 Which of the following is not true of multi-weighted scoring models?
A) Will include quantitative criteria
B) Will include qualitative criteria
C) Each criterion is assigned a weight
D) Projects with higher scores are considered more desirable
E) All of the above are true
ANS: E
15 Which of the following is a common multicriteria selection model?
A) Checklist
B) Net Present Value
C) Weighted criteria model
D) Both A and C are correct
E) All of these are common multicriteria selection models
ANS:D