Inventory Problems at Nike
Inventory Problems at Nike
Inventory Problems at Nike
NIKE
CASE STUDY SOLUTION
VANDANA SINGH
R110307045
R110307049
VANDANA SINGH
5)
6)
7)
8)
Communication gap between i2 technology which was contracted to implement the supply chain
software.
Both companies didnt bother to test the software rigorously eventually the problem were solved
till 2003. They were moving too fats without taking any cautionary measures.
Next problem they were facing was the supply chain software that they had implemented was a
failure hence resulted in less profit.
They also faced the certain technical glitches.
Nike started blaming i2 for this. And i2 claimed due to the mismatch in using incomplete
system and its unwillingness to use i2 standard system and procedure. This resulted in
loosing the market share to their rivals (Reebok and New Balance)
Neither Nike nor i2 brought into 3-party integration to adapt the system to the organizational
processes as the 3rd party integrator was of importance in large scale project like the one at Nike.
Implementation of two major projects simultaneously i.e. supply chain and customer relation
management as they had to cover large no of suppler and customer of Nike, and it was creating
unnecessary complications for itself in the bargain.
I2 was also relatively inexperience in providing supply chain software for the apparel industry as
it had earlier worked with Dell corp., 3M etc. and Nike was the first apparel company that it
worked with.
Moreover i2 did not provide the quality service, and sometimes it also led to under manufacturing
and over manufacturing of the product.
VANDANA SINGH
Question 2: The failure of the new supply chain system affected Nike adversely. What were the
reasons for the failure and how did the breakdown harm Nike?
Answer2:
Reasons for the failure:
1) Communication gap between i2 technology which was contracted to implement the supply chain
software.
2) Both companies didnt bother to test the software rigorously eventually the problem were solved
till 2003. They were moving too fats without taking any cautionary measures.
3) Next problem they were facing was the supply chain software that they had implemented was a
failure hence resulted in less profit.
4) Neither Nike nor i2 brought into 3-party integration to adapt the system to the organizational
processes as the 3rd party integrator was of importance in large scale project like the one at Nike.
5) Implementation of two major projects simultaneously i.e. supply chain and customer relation
management as they had to cover large no of suppler and customer of Nike, and it was creating
unnecessary complications for itself in the bargain.
6) I2 was also relatively inexperience in providing supply chain software for the apparel industry as
it had earlier worked with Dell corp., 3M etc. and Nike was the first apparel company that it
worked with.