STFFD-P1-006002-D10-1001 Rev B HVAC System - Piping & Instrumentation Diagram

Download as pdf or txt
Download as pdf or txt
You are on page 1of 4
At a glance
Powered by AI
The document discusses an HVAC system for an e-house package, including equipment, piping, instrumentation, and design specifications.

The HVAC system piping and instrumentation diagram shows the layout and connections of the major equipment in the HVAC system to control temperature and humidity in the e-house building.

The HVAC system includes a compressor, evaporating fan motor, condensing fan motor, expansion valve, oil separator, and condenser to circulate and condition refrigerant for cooling.

SU TU TRANG FULL FIELD

DEVELOPMENT PHASE 1 PROJECT


VENDOR FRONT SHEET
DOCUMENT TITLE

HVAC System Piping & Instrumentation Diagram

TOTAL NO. OF PAGES


(INCLUDING FRONTSHEET)

04

VENDOR'S ORDER NO.

TBA

VENDOR'S OWN DOCUMENT NO

REV. NO

DATE

VENDOR'S APPROVAL

STFFD-P1-006002-D10-1001

05.11.2015

PHAN THE VINH

Submitted For :
REVIEW

APPROVAL

INFO

FINAL DOCS

SU TU TRANG FULL FIELD


DEVELOPMENT - PHASE 1
PROJECT

REVIEW DOES NOT CONSTITUTE ACCEPTANCE OF


DESIGN DETAILS, CALCULATIONS, TEST METHODS
OR MATERIALS DEVELOPED OR SELECTED BY
VENDOR NOR DOES IT RELIEVE VENDOR FROM FULL
COMPLIANCE WITH CONTRACTUAL OR OTHER
OBLIGATIONS.

VENDOR NAME:

VIETSOVPETRO JV

PACKAGE
DESCRIPTION:

E-HOUSE PACKAGE

1. ACCEPTED

PO/LOI NO: 030-2015/STTFFD- LOI

2. ACCEPTED, PROCEED WITH WORK AND


INCORPORATE COMMENTS AND RE-SUBMIT

TAG NOS./PO ITEM NOS:

3. NOT ACCEPTED.
REVISE AND RE-SUBMIT.
4. FOR INFORMATION ONLY.

DE

PTSC

CLJOC

PACKAGE NO.

VDRL
CAT.

SEQUENCE
NO.

REV.

STFFD-P1-006002

D10

1001

Name:
Date:
Sign:

VENDOR DATA COMMENTS/RESPONSES


PROJECT TITLE: SU TU TRANG FULL FIELD DEVELOPMENT - PHASE I

PREPARED BY:

RFQ NO.: STFFD-P1-006002-D10-1001

SIGNED BY:

PACKAGE DESCRIPTION: E-HOUSE BUILDING

REV.:

PO/CONTRACT NO.: 030-2015/STTFFD- LOI

DATE:

5-Nov-15

PHAN THE VINH

VENDOR: VIETSOVPETRO JV

ITEM
DATA CODE
NO.

D10-1001

DOCUMENTS TITLE

HVAC System Piping And


Instrumentation Diagram

REV.

PTSC/CLJOC COMMENTS

VENDOR PROPOSALS

Add Start/Stop/Trip for Compressor, Evaporating Fan Motor, Condensing


Noted & Incorporated in next revision
Fan Motor

Add and revise tag number for all equipment

To check with manufacturer that if a shut off valve is used with the
expansion valve, it
Isolate valve after Expansion Valve shall be
affects to performance or not? Normally, elbow or valve is not allowed to removed
mount behind of EXV

Specify insulation material, thickness for refrigerant pipe & drain pipe

Noted & Incorporated in next revision

Check necessary or not. Semi-hermitic compressor has charging port

Yes, charging valve is still necessary

A
A

Isolate Valve shall be provided for Instrument equipment (LPIT, HPIT,


OPIT)
Check valve should be mounted between the oil separator and condenser
to avoid refrigerant migration during off cycle

CLJOC RESPONSES

REMARKS

Noted & Incorporated in next revision

Noted & Incorporated in next revision


Noted & Incorporated in next revision

Show different pipe type between Liquid line, Instrument tubing, hardwire Noted & Incorporated in next revision

Tubing SS316L size???

Tubing shall be SS316, 1/4"OD

HCP (Typical comment)

Noted & Incorporated in next revision

Add Notes:
- Refrigerant shall be R407c
- Compressor shall be load/unload type to control capacity
- Compressor, motor shall send the status to BPCS through HCP via serial Noted & Incorporated in next revision
link
- Common trip shall be sent from GFS/SIS to HCP. Individual trip action
within HVAC shall be done by HCP

STFFD-P1-006002-D10-1001 Rev B HVAC System Piping & Instrumentation Diagram_CRS

PTSC RESPONSES

1 of 1

E-HOUSE PACKAGE
HVAC SYSTEM

E-HOUSE PACKAGE
HVAC SYSTEM