Introduction To Heavylift
Introduction To Heavylift
21 November 2011
INTRODUCTION
TO
HEAVY HAUL TRAILERS
Part 1 of 2
(Contains the first basic type of heavy haul trailers)
The hauling of heavy construction equipment is a fascinating thing to behold. It usually takes months of
planning and preparation before the actual move is made. Sometimes, special transportation equipment has to
be fabricated for that move to make it happen or to be street legal. If all of the above is carefully planned and
reviewed, then the move itself usually looks very easy and simple.
There are basically three types of heavy haul trailers:
1.
The lowboy type trailers with many axles, which must be street legal and usually can travel up to
35 mph legally .
2.
The pull type modular trailers that have many axles, are very seldom street legal, travel up to 35
mph and usually used for off highway moves.
3.
The self propelled modular trailers (SPMTs) that have many axles, are very seldom street legal,
travel at a maximum of 5 mph and are most always used for off highway moves.
NOTE: If the numbers are not readable in the photos and drawings in the presentation, then either go to view
and zoom to 200 % or click on the drawing and pull it down from the bottom right corner until things
are legible.
Schnabel fashion, ie, 1-1/8 lashing was connected to the ends of the bridge beams and went over the autoclave
and other 1-1/8 lashing was connected inboard to the bridge beams and went under the autoclave between the
permanent saddles and the tangent lines of the heads. See the bottom photo for a clearer picture of the lashing.
maintained by the use of nitrogen accumulators, one for each cylinder. This way if the ram in one of the
cylinders extended because the four tires fell down into a pothole in the road, the pressure in the cylinder
remained the same at all times and the trailer stayed level or at the same gradient.
As the trailer is only 12 wide with 13 from center of tandem axles, note that Savage had to use six 50 ton
dollies to make this load street legal.
The trailer shown below is a Trail Star 17 axle trailer, another version of Trail Kings 17 axle trailer. Note that
this trailer uses a Schnabel hitch to carry the transformer, where in the photo above, a lowboy and bridge beams
were used. It just goes to show that there is more than one way to skin a cat. Note that the beams pin connect
to the bottom of the transformer to carry the tension and have push pads at the top to carry the compression.
Another way to transport heavy loads is by using a series of 50 ton dollies configured under support beams.
The trailer in the photo below ( I apologize for it blurriness) shows how Bigge/Shaughnessy configured sixteen
50 ton dollies together with support beams to move a large transformer.
22 November 2011
INTRODUCTION
TO
HEAVY HAUL TRAILERS
Part 2 of 2
(Contains the last two types of heavy haul trailers)
available to calculate these values. More on this later. 2) The front pull type trailer will follow the prime
mover in turning as the steering of the trailer comes about when the tongue moves manual linkage connected to
each wheel assembly. The maximum turning angle is approximately 55 degrees. This is the maximum angle
that the tires will turn relative to the centerline of the trailer. The rear trailer is steered by the use of an auxiliary
engine, but can still only turn up to 55 degrees. The trailers are hard to back up so the rigging superintendent
must lay out the route so that the load can be staged under the crane(s) hook the first time.
Note in the photos for this move that staging beams are located under the saddles and they stick about 1 meter
past the side of the trailers. These beams are required to stage the vessel on stanchions at a laydown yard.
More will be said about this topic later. Also note that bolsters are being used under each staging beam. They
can add as much as 0.5 to 1.0 m to the overall height of the load. They are required for turning, unless the
trailers can be driven in a straight line.
supports or saddles to three axles. Otherwise, a buildup frame would have to be fabricated and laid on the trailer
platform and the load positioned on it.
In the drawing below, I have reworked the weight figures given by the contractor based on the latest
information for the move. Note that the total weight of the load, lift attachments, the saddles, weight
contingency and the weight of the trailers = 447 Te. The weight I used for the trailers of 75 Te included the
staging beams. I took the dimensions shown from the contractors dimensional drawing. As you can see, I try
to always be as conservative as possible.
What is not shown on the above drawing is the maximum capacity per axle line for the trailer which is 32 Te.
Or 16 Te per axle.
With any pull type or SPMT haul, the contractor must show on his drawing the way the trailer(s) are plumbed,
ie, are they in a three point hydraulic or a four point hydraulic suspension mode. Bear in mind that there are
several ways to plumb a trailer in a three point hydraulic suspension but the one chosen is because it usually
provides the best tipping stability, ie, the greatest horizontal distanced between the CG and legs of the stability
triangle. Note in the calculations below that this trailer is in a three point hydraulic suspension mode with
twelve axles in the left group at point A and 10 axles in each of the two groups on the right at points B & C. Z
is the horizontal distance from the CG to the edges of the stability triangle. First, the maximum CG shift is
calculated that will overstress the trailer. The limit of overloading is usually in the tires as they are usually the
weakest link. The CG shift usually occurs when the trailer is driven on one side of the road that has a crown or
on a curve with a super elevation.
I need to point out here that whenever possible, the CG of the load should be positioned on the CENTERLINES
of the trailer configuration. This makes it easy to determine how much load is being carried by each hydraulic
group or point. If the CG of the load is not on the centerlines, then a more complicated method has to be
employed to determine the load to each group.
In the calculations below, the vertical distance Y is calculated, which is the maximum the trailer platform can be
out of level before it goes into a tipping mode or becomes overstress structurally. Note that the worst case for Y
is for structural stability and is 102 mm. Using a 5:1 factor of safety, this becomes 20 mm. As it is pretty hard
to keep a trailer platform level within 20 mm, I recommended that this load not be hauled in a three point
suspension.
I want to explain the purpose of the sheet below by pointing out that putting a trailer in a four point suspension
is very similar to placing a load on a table top that has one leg shorter than the other three. As the table is
rocked over the two diagonal legs that are the same length, there are times when the total weight of the load and
table are on these two legs with zero load on the short leg and the other long leg. At other times, a small
percentage of the load is carried by the short leg with most of the load divided between the two diagonal legs
whose lengths are the same. When the table rocks the other way, then a small percentage of the load goes to the
other long leg. But the two diagonal legs are always carrying the biggest percentage of the load and at times
each carrying 50% of the load.
From testing, you can see why I recommended that this load not be hauled on a single wide trailer in a four
point hydraulic suspension system. I recommended using double wide trailers. Another reason was because of
the six axles extending beyond the rear saddle.
The drawing below shows that the vessel was actually transported on a double wide 12 axle line trailer. Note
that having 24 axle lines under the trailer reduced the GBP to 5.17 Te/sq. m.
What this means is that the operator has to take into account this forward/backward shift when setting a load
down into place on the centerlines of the foundation, ie, if he stopped the trailer where the load is directly over
the centerlines of the foundation and lowers the trailer from a normal height to a lower level, the platform will
shift backwards a few millimeters. He would have to move the trailer slightly forward before setting the load.
I felt that the contractors calculations were a little light and did not take into account stopping and starting on
the 6% slope. So, I used another way of calculating the tractive effort required:
3 % Rolling Resistance:
0.03 *1417 Te = 42.51 Te
3 % Internal Resistance:
0.03*1417 Te = 42.51 Te
6 % Grade:
0.06*1417 Te = 85.02 Te
Total
= 170.04 Te
Reserve to accelerate to 3 kph in 60 seconds
Total
Utilization
Some sources recommend using 4 % for rolling resistance, which would increase the tractive effort required to
187.53 Te for a utilization of 95 %.
I made the above calculation to demonstrate that the actual demand for tractive effort could be up to 95 % of
capacity. To be on the safe side, I recommended to the client that the drive capacity be increased from 198 Te
to 220 Te. Swapping out two regular six-axle trailers for two super six trailers could add 4 more drive motors
and 22 Te of tractive effort. This way, even if the trailer was stopped on the 6 % slope, it could start again
without any trouble.
Two power packs were used for this move that had sufficient capacity to make each drive motor put out 5.5 Te.
There should always be a fair amount of over or reserve capacity in the power packs due to the fact that during
driving there is capacity required to operate the steering motors and to activate the pumps for leveling. If the
power packs are just barely large enough for travel and the transporter needs to be leveled, the transporter will
just stop moving. This could be problematic on a hill because all hydraulic motors dont start at the same exact
moment due to internal friction, etc, so the wheels for one motor may start slipping first, which could cause the
compacted soil to be disturbed and the trailer could get stuck.
Staging Vessels:
Quite often, equipment is brought to a construction site before the foundations are ready, so the equipment
needs to be staged until it is ready to be set. In order to eliminate a crane for offloading and reloading, the
equipment is set on stanchions that are high enough for the trailer to be lowered and driven out from under the
load. Most trailers platforms can be adjusted in height from 1.0 m +/- 250 mm. In order to make staging
happen, the saddles of the equipment must be placed on staging beams already on the trailers. The staging
beams need to extend past each side of the trailers by about 1.0 m. If the equipment is heavy, steel load
spreaders that are say 2 m wide x 6 m long should be buried at ground level. Stanchions that are made of 1 m
diameter heavy wall pipe with cover plates x 1 m high or reinforced concrete that is 1 m sq. x 1 m high are
placed on the load spreaders. When the load reaches the staging area the trailer platform is raised higher than
the stanchions, the trailer is driven between the stanchions, lowered down until the staging beams are resting on
the stanchions and then driven out from under the load. The load would be picked up in the reverse order.
The photo below shows the load spreaders and stanchions already attached to the staging beams and are being
used as a work platform for the riggers to ride on. When the load reaches the staging area, the trailer platform is
merely lowered until the load spreaders are resting on the ground and trailer can be driven out from under the
load. The load spreaders do not have to be buried in this case as there is clearance between them for the tires.
Generally, the trailer tires just clear the edge of the stanchions, thus the need to bury the load spreaders.
By looking closely at the drawing below, it can be seen that the CG is not located symmetrically between the
four saddles. If you will go to quiz number 8 on my website, the question will be asked to determine the actual
load to each jack. I will leave it up to each of you to do this for your own edification.
There are several types of climbing jacks available. You have seen one type above. Another type is shown
below on the drawing by Van Seumeren. Note that with these jacks, the steel strips are not required as the jack
base is contoured to allow clearance for the cribbing to be pushed under the ram plate.
The series of photos below show an equipment module being moved onto site and then being jacked down
using climbing jacks. Note the wet conditions, with is usually the case when an operation is being made in the
field. Murphy will make sure of that.
JACKING COMPLETE
SUMMARY:
This presentation has only been an introduction to heavy hauling. If you want more information, just go to my
website and click on my Partner link at the bottom of the home page and it will take you to The Works
International. This is Marco Van Daals website on transportation. You might want to even consider
purchasing his book titled The Art Of Heavy Transport. I know that several of you already have. Marco can
tell you how to calculate the size of the prime mover and the counterweight required for a pull type trailer.
THE END