MERALCO Service Application Process
MERALCO Service Application Process
2
Receipt of
Application
3
Pre-Survey
and Processing
Design
and Prepare
Project Cost
Presentation
and Acceptance
Of Contract
Payment /
compliance to
requirements
Construct
Lines
and Facilities
2
Receipt of
Application
CUSTOMER DELIVERABLE
1.1
Submit initial
requirements
MERALCO DELIVERABLE
3
Pre-Survey
and Processing
Design
and Prepare
Project Cost
Presentation
and Acceptance
Of Contract
Payment /
compliance to
requirements
Construct
Lines
and Facilities
Initial Requirements
Service Application can already proceed even with the initial
submission of the following three important requirements:
2
Receipt of
Application
CUSTOMER DELIVERABLE
1.1
Submit initial
requirements
MERALCO DELIVERABLE
1.2
Receives and
reviews
application
3
Pre-Survey
and Processing
Design
and Prepare
Project Cost
Presentation
and Acceptance
Of Contract
Payment /
compliance to
requirements
Construct
Lines
and Facilities
2
Receipt of
Application
3
Pre-Survey
and Processing
CUSTOMER DELIVERABLE
1.1
Submit initial
requirements
MERALCO DELIVERABLE
1.2
2.1
Receives and
reviews
application
Surveys and
advises customer
on service entrance
requirement
Estimates the
project cost and
determines viability
Design
and Prepare
Project Cost
Presentation
and Acceptance
Of Contract
Payment /
compliance to
requirements
Construct
Lines
and Facilities
Secondary Nominal
Voltages
230 Volts, 400 Volts, 460 Volts
Primary Nominal
Voltages
13.2 kV, 13.8 kV, 34.5 kV, 69 kV, 115 kV
Secondary Nominal
Voltages
230 Volts, 400 Volts, 460 Volts
Nominal Voltage
230 Volts, Single Phase (1), Two (2)Wire
230 Volts, Single Phase (1), Three (3)Wire
230 Volts, Three Phase (3), Four (4)Wire
400/230 Volts, Three Phase (3), Four
(4)-Wire (Grounded Wye)
460/265 Volts, Three Phase (3), Four
(4)-Wire (Grounded Wye)
Primary Nominal
Voltages
13.2 kV, 13.8 kV, 34.5 kV, 69 kV, 115 kV
Limitations
Maximum capacity of MERALCO-supplied
transformer for non-residential
secondary service applications :
230 Volts : 1000 kVA
400 Volts : 1000 kVA
460 Volts : 2000 kVA
Secondary Nominal
Voltages
230 Volts, 400 Volts, 460 Volts
Nominal Voltage
230 Volts, Single Phase (1), Two (2)Wire
230 Volts, Single Phase (1), Three (3)Wire
230 Volts, Three Phase (3), Four (4)Wire
400/230 Volts, Three Phase (3), Four
(4)-Wire (Grounded Wye)
460/265 Volts, Three Phase (3), Four
(4)-Wire (Grounded Wye)
Primary Nominal
Voltages
13.2 kV, 13.8 kV, 34.5 kV, 69 kV, 115 kV
Requirements
service shall be metered at the secondary
voltage side
service entrance shall be located along
the property line not more than 30
meters horizontal distance from nearest
MERALCOs secondary existing facilities
Otherwise, the application shall be
covered by a project study for the
extension of facilities. (Related guidelines
in accordance with ERC rules apply)
Secondary Nominal
Voltages
230 Volts, 400 Volts, 460 Volts
Nominal Voltage
13.2/7.62 kV Three Phase (3), Four (4)Wire (Grounded Wye)
13.8/7.97 kV Three Phase (3), Four (4)Wire (Grounded Wye)
34.5/19.92 kV Three Phase (3), Four (4)Wire (Grounded Wye)
69 kV Three Phase (3), Four (4)-Wire
(Grounded Wye)
115 kV Three Phase (3), Four (4)-Wire
(Grounded Wye)
Primary Nominal
Voltages
13.2 kV, 13.8 kV, 34.5 kV, 69 kV, 115 kV
Requirements
service shall be metered at the primary
voltage side
applicant shall provide space, as determined
by MERALCO, for the installation of the
necessary metering facilities
applicant shall provide, install and maintain
all electrical facilities after the metering point
(i.e., transformers, distribution facilities,
main primary service protection, etc.)
CONNECTION
460 volts
3.6kV 34.5 kV
Sub-transmission Voltage
Service
69kV 115kV
2
Receipt of
Application
3
Pre-Survey
and Processing
CUSTOMER DELIVERABLE
1.1
Submit initial
requirements
2.2
Signifies intention
to proceed with
project (thru MOA,
if applicable)
Sign-off on project
Gantt chart by both
parties
MERALCO DELIVERABLE
1.2
2.1
Receives and
reviews
application
Surveys and
advises customer
on service entrance
requirement
Estimates the
project cost and
determines viability
Design
and Prepare
Project Cost
Presentation
and Acceptance
Of Contract
Payment /
compliance to
requirements
Construct
Lines
and Facilities
ACTIVITY
Submission of Application and Initial Requirements (Letter of Request, EE Plan)
Receipt of Application & Advise of all pertinent requirements
Submission of Initial Vault Drawing
Initial Survey
Submission of all the Required Documents
Submission of CFEI
Service Technical Assessment (STA) preparation & Routing to PMS & Design Office
Review of Initial Vault Drawing
Submission of Revised Transformer / Primary Metering Vault Drawing
Approval of Transformer Vault Drawing
Completion of Service Entrance/ Transformer or Metering Vault
Design Completion
Securing of Right-of-Way/APL/Permits (except DPWH/MMDA - 45 days)
Contract Preparation
Delivery of LA & LFC & Explaining Contract's content to Customer
Submission of Signed Contract and Letter Agreement
Final Inspection & Accomplishment of Checklist for SE/TV/MV
Submission Right of Way and payment of Deposits/Charges
Acceptance of Payment for Bill Deposits/IR/CA or other charge
Work Order Release Authorized / Field Order Release to Meter
Work Order Released by Design Office to Network/Sector
Work Order in Execution
Work Order Completed. Testing of Meralco and/or Cust. Facilities
Energization
PRECEDING
ACTIVITY
N/A
1
2
2
2
4
3
7
8
9
10
10
12
12
14
15
11
17
18
19
20
21
22
23
LEAD TIME
(DAYS)*
2
2
7
5
15
30
2
5
7
7
30
20
30
3
2
3
5
7
5
1
1
30
1
1
Meralco Activity
Customer Activity
Critical activities
Processing &
submission of CFEI
15
Transformer vault
drawing
30
2
5
Design completion
7
7
30
20
30
3
2
Payment of bill
deposit
3
5
7
5
1
1
30
1
1
Meralco Activity
Customer Activity
2
Receipt of
Application
Design
and Prepare
Project Cost
Pre-Survey
and Processing
CUSTOMER DELIVERABLE
1.1
Submit initial
requirements
2.2
3.1
Signifies intention
to proceed with
project (thru MOA,
if applicable)
Sign-off on project
Gantt chart by both
parties
Starts wiring
installation and
construction of
service
entrance
MERALCO DELIVERABLE
1.2
2.1
Receives and
reviews
application
Surveys and
advises customer
on service entrance
requirement
Estimates the
project cost and
determines viability
Presentation
and Acceptance
Of Contract
Payment /
compliance to
requirements
Construct
Lines
and Facilities
MERALCO FACILITIES
CUSTOMER FACILITIES
Facilities
27kV Surge Arrester
Fuse Cut-Out or Power Fuse
34.5kV Current Transformer (CT)
34.5kV Potential Transformer (PT)
Meter and Accessories
Metering Pole
Quantity
6 Units
3 Units
3 Units
3 Units
1 Set
1 Unit
Facilities
27kV Surge Arrester
Load Break Switch
Fuse Cut-Out or Power Fuse
Transformer, 3-333 kVA, 34.5kV/230V
Concrete Flat form
Poles
Meter and accessories
High Voltage Wire, Insulated, 36 kV, 1 50 mm
Breakers, 4 2000A, 2 1600A, 1 1000A
Three phase lines 250 mm2
Quantity
3 Units
1 Unit
3 Units
3 Banks
3 Units
9 Units
3 Units
175 m/phase
7 Units
7 wires/phase
2
Receipt of
Application
Design
and Prepare
Project Cost
Pre-Survey
and Processing
CUSTOMER DELIVERABLE
1.1
2.2
3.1
Signifies intention
to proceed with
project (thru MOA,
if applicable)
Sign-off on project
Gantt chart by both
parties
Starts wiring
installation and
construction of
service
entrance
1.2
2.1
3.2
Receives and
reviews
application
Surveys and
advises customer
on service entrance
requirement
Submit initial
requirements
MERALCO DELIVERABLE
Estimates the
project cost and
determines viability
Prepares
design and
actual project
cost
Presentation
and Acceptance
Of Contract
Payment /
compliance to
requirements
Construct
Lines
and Facilities
2
Receipt of
Application
Design
and Prepare
Project Cost
Pre-Survey
and Processing
Presentation
and Acceptance
Of Contract
CUSTOMER DELIVERABLE
1.1
2.2
3.1
Signifies intention
to proceed with
project (thru MOA,
if applicable)
Sign-off on project
Gantt chart by both
parties
Starts wiring
installation and
construction of
service
entrance
1.2
2.1
3.2
Receives and
reviews
application
Surveys and
advises customer
on service entrance
requirement
Submit initial
requirements
4.2
Accepts and
signs contract
MERALCO DELIVERABLE
Estimates the
project cost and
determines viability
Prepares
design and
actual project
cost
4.1
Presents service
contract
indicating the bill
deposit and
project cost, if
applicable
Payment /
compliance to
requirements
Construct
Lines
and Facilities
Annex 6. Contracts
Customer
Captive
Required Contracts
Contestable
Connection agreement
(FABD Fixed Asset Boundary Document)
DWSA (Distribution Wheeling Service Agreement)
Line extension agreement (if applicable)
* either cash advance or CIAC
2
Receipt of
Application
Design
and Prepare
Project Cost
Pre-Survey
and Processing
Presentation
and Acceptance
Of Contract
Payment /
compliance to
requirements
CUSTOMER DELIVERABLE
1.1
2.2
3.1
Signifies intention
to proceed with
project (thru MOA,
if applicable)
Sign-off on project
Gantt chart by both
parties
Starts wiring
installation and
construction of
service
entrance
1.2
2.1
3.2
Receives and
reviews
application
Surveys and
advises customer
on service entrance
requirement
Submit initial
requirements
4.2
Accepts and
signs contract
MERALCO DELIVERABLE
Estimates the
project cost and
determines viability
Prepares
design and
actual project
cost
4.1
5.1
Presents service
contract
indicating the bill
deposit and
project cost, if
applicable
Inspects
customer
compliance to
all requirements
Construct
Lines
and Facilities
2
Receipt of
Application
Design
and Prepare
Project Cost
Pre-Survey
and Processing
4.2
5.2
Accepts and
signs contract
4.1
5.1
Presents service
contract
indicating the bill
deposit and
project cost, if
applicable
Inspects
customer
compliance to
all requirements
Presentation
and Acceptance
Of Contract
Payment /
compliance to
requirements
CUSTOMER DELIVERABLE
1.1
2.2
3.1
Signifies intention
to proceed with
project (thru MOA,
if applicable)
Sign-off on project
Gantt chart by both
parties
Starts wiring
installation and
construction of
service
entrance
1.2
2.1
3.2
Receives and
reviews
application
Surveys and
advises customer
on service entrance
requirement
Submit initial
requirements
MERALCO DELIVERABLE
Estimates the
project cost and
determines viability
Prepares
design and
actual project
cost
Construct
Lines
and Facilities
2
Receipt of
Application
Design
and Prepare
Project Cost
Pre-Survey
and Processing
4.2
5.2
Accepts and
signs contract
4.1
5.1
Presents service
contract
indicating the bill
deposit and
project cost, if
applicable
Inspects
customer
compliance to
all requirements
Presentation
and Acceptance
Of Contract
Payment /
compliance to
requirements
Construct
Lines
and Facilities
CUSTOMER DELIVERABLE
1.1
2.2
3.1
Signifies intention
to proceed with
project (thru MOA,
if applicable)
Sign-off on project
Gantt chart by both
parties
Starts wiring
installation and
construction of
service
entrance
1.2
2.1
3.2
Receives and
reviews
application
Surveys and
advises customer
on service entrance
requirement
Submit initial
requirements
MERALCO DELIVERABLE
Estimates the
project cost and
determines viability
Prepares
design and
actual project
cost
Constructs
lines and
facilities
2
Receipt of
Application
Design
and Prepare
Project Cost
Pre-Survey
and Processing
Presentation
and Acceptance
Of Contract
Payment /
compliance to
requirements
CUSTOMER DELIVERABLE
1.1
Construct
Lines
and Facilities
PROJECT COMPLETED
2.2
3.1
Signifies intention
to proceed with
project (thru MOA,
if applicable)
Sign-off on project
Gantt chart by both
parties
Starts wiring
installation and
construction of
service
entrance
1.2
2.1
3.2
Receives and
reviews
application
Surveys and
advises customer
on service entrance
requirement
Submit initial
requirements
4.2
5.2
Accepts and
signs contract
4.1
5.1
Presents service
contract
indicating the bill
deposit and
project cost, if
applicable
Inspects
customer
compliance to
all requirements
CUSTOMER
FACILITY IS
ENERGIZED
MERALCO DELIVERABLE
Estimates the
project cost and
determines viability
Prepares
design and
actual project
cost
Constructs
lines and
facilities
Thank You!