Drilling Homework

The document contains calculations related to various oil rig operations including: - Calculating engine horsepower, efficiency, and fuel consumption at different speeds - Determining tension in fastlines for different numbers of lines lifting a load - Calculating maximum hook load, speed, and time for a rig hoisting a load - Finding the minimum time to reel cable of a given weight and length - Determining the minimum number of lines needed to support an anticipated hook load - Calculating the maximum force a driller can use trying to free a stuck pipe - Estimating the length of line to the first lap point on a drawworks drum of given dimensions
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
257 views14 pages

Drilling Homework

The document contains calculations related to various oil rig operations including: - Calculating engine horsepower, efficiency, and fuel consumption at different speeds - Determining tension in fastlines for different numbers of lines lifting a load - Calculating maximum hook load, speed, and time for a rig hoisting a load - Finding the minimum time to reel cable of a given weight and length - Determining the minimum number of lines needed to support an anticipated hook load - Calculating the maximum force a driller can use trying to free a stuck pipe - Estimating the length of line to the first lap point on a drawworks drum of given dimensions
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 14

1) The following data are obtained on a gasoline engine:

Fuel Consumption Rate,


Engine speed, rpm Torque, ft-bbr
gal/hr
500
2000
10.1
1000
1850
16.7
1500
1700
22.3
2000
1550
26.8
gasoline
a) Calculate the break HP at each engine speed.
= =2()

P
P
P
P

@
@
@
@

500rpm=
1000rpm=
1500rpm=
2000rpm=

190.39955476 hp
352.23917631 hp
485.51886465 hp
590.23861977 hp

b) Calculate the overall engine efficiency at each engine speed.


_=_/ =_

@500rpm
Consume (lbm/min)
Q
efficiency

1.11
524.53
36.30%

@1000rpm
Consume (lbm/min)
Q
efficiency

1.84
867.29
40.61%

@1500rpm
Consume (lbm/min)
Q
efficiency

2.45
1158.11
41.92%

@2000rpm
Consume (lbm/min)
Q
efficiency

2.95
1391.81
42.41%

6.6 lbm/gal
20000 Btu/lbm

c) Calculate the fuel consumption in gallons per day for an average speed of
1000 rpm and a
12 hour work day.
Comsuption

200.4

2) Compute the tension in the fastline when lifting a


750000 lbf load for
lines strung between the crown block and the traveling block.
_=/()
6 lines
Ff

143021 lbf

8 lines
Ff

111474 lbf

10 lines
Ff

92593 lbf

12 lines
Ff

81169 lbf

14 lines
Ff

72394 lbf

6 8 10

12
Lines (n)
6
8
10
12
14

Efficiency (E)
0.874
0.841
0.810
0.770
0.740

3) A rig must hoist a load of


600000 lb. The drawworks can provide an input power to the bl
tackle system as high as
500 hp.
8 lines are strung between the crown block an
Calculate:
a) The static tension in the fast line when upward motion is impending
_=/()
Ff

89179.54816 lbf

b) The maximum hook HP available


_=EP
Ph
420.5 hp
c) The maximum hoisting speed, and the time to pull
_=_/
vb
t

23.13 ft/min
3.89 min

d) The actual derrick load


_=((1++)/())
fd

764180 lbf

e) The maximum equivalent derrick load


_=((+4)/)
fde

900000 lbf

f) The derrick efficiency factor


_=_/_
Ed

84.91%

90 ft. stand

input power to the block and


en the crown block and traveling block.
Lines (n) Efficiency (E)
6
0.874
8
0.841
10
0.810
12
0.770
14
0.740

4) Calculate the minumum time required to reel a


using a
25 hp engine.
=/(2)
=_/

velocity
time

41.25 min
242.4242 min

20000 ft. cable weighing

1 lbf/ft to the surface

5) A 1.25 in drilling line has a nominal breaking strenght of 150000 lbf. A hook load of
a casing job and safety factor of
2 based on static loading condition is required. Determine
of lines between the crown block and traveling block that can be used. =_/_

Fact

75000 lbf

_=/()

E*n=

8.67

Lines (n) Efficiency (E)


6
0.874
8
0.841
10
0.810
12
0.770
14
0.740

A hook load of
650000 lbf is anticipated on
ion is required. Determine the minimun number
=_/_

E*n
5.24
6.73
8.10
9.24
10.36

6) A driller is pulling on a stuck drillstring. The derrick is capable of supporting a maximum equival
500000 lbf, the drilling line has a strength of
55000 lbf, and the strength of the drillpip
400000 lbf. If
10 lines are strung between the crown block and the traveling block a
2 are required for the derrick, drillpipe, and drilling line, how hard can the driller pull tryin
_=((+4))/
W
178571 lbf
Maximum for Derrick

=_/(((+4)/))

Lines (n)
6
8
10
12
14

=(_)/
W
222750 lbf
Maximum Fast line

=_/
W
200000 lfb
Maximum Drill Pipe

Maximum force that can be used


178571 lbf

a maximum equivalent derrick load of


trength of the drillpipe tension in is
the traveling block and safety factors of
the driller pull trying to free the stuck pipe?
E*n
8.1
Efficiency (E)
0.874
0.841
0.810
0.770
0.740

7) A drawworks drum has a diameter of


45 in, a width of
Calculate the approximate length of line to the first lap point.
turns
50
perimeter of a turn
146.8695 in
length
7343.473 in
length
611.9561 ft

87.5 in., and contains

n., and contains

1.75 in drilling line.