Managing Resources Maximo
Managing Resources Maximo
Managing Resources Maximo
Acciona Energy
Implementing Maximo in the Wind Industry
Wind: 3,876 MW installed -6% of the world total- (2,636 MW part., 2,008 attr.)
Biofuels: 35,000 tonnes per year biodiesel plant (1.2 Mtonnes in project)
Vertical integration
Implementing Maximo in the Wind Industry
Technical
• Technically complex machines, requiring ongoing preventative,
predictive and corrective maintenance
Commercial
• Significant investment, where return is based on the production of
the turbines
Stakeholder
• Numerous stakeholders with diverse expectations from the turbines
Implementing Maximo in the Wind Industry
• Variable speed
• Rated voltage: 12 kV
• Horizontal shaft
Essential components
Generator
Independent
pitch control
High speed for each
shaft blade
2 Bearings
Double Support
frame
Gearbox
Hub
Main shaft
Technical – Wind Turbine
Asset Management on the Turbines has several key points
• Facility buildings
• Alternate items
Installed equipment
• Optimisation of purchasing
Waubra Wind Farm
Site consists primarily of cleared agricultural land used for sheep and
cattle grazing and potato growing
• 24/7 operation
Work Orders
Availability
Utilisation
Scheduled stops
Commercial partners
Joint venture partners
Electricity industry
Grid connection utilities
NEMCO
Energy Retailers
Community
Landowners
Local community
Public
Stakeholders - Commercial Partners
AWP Contractors
AWP Contractors
AEO
Contractors
Stakeholders – Electricity Industry
Lease payments
Lease payments
Summary
Thank you
www.waubrawindfarm.com.au
www.acciona-energia.com