veloci-Q 101

Section A: Multiple Choices 1) _______ is a monthly mechanism to track metric trends,


exceptions of metrics and ensure Process Improvements in the Business Unit
QICs
Look Ahead Meetings
PIP Board meetings
Quality meet
2) The set of actions to be taken when the perceived risk becomes a reality is
documented as part of
Contingency plan
Mitigation Plan
Defect Prevention Report
Risk Tracker
3) Project Performance Analysis (PPA) is an exercise which examines :
Lessons learnt and best practices
Individual performance
Process Improvement Proposals
Conformance of requirements
4) Schedule deviation, effort deviation, field error rate are some of the metrics captured
for
Service projects
Development projects
Maintenance projects
Any of the above
5) Which of the below situations recommends an RCA?
Metrics computed as part of the project is better than norm
Metrics computed as part of the project is below norm
Metrics is equal to the norm
All of the above
6) Bureau of India Standards emphasizes on
Project Quality
Process Quality
Quality Models
Product Quality
7) The ratio of defected reported during UAT to the size of project is
Overall Productivity
Phantom Error Rate
Post Delivery defect rate

Any of the above


8) What is the monthly mechanism to record and track metrics of the project?
PDMR
Work Plans
PMR
ASR
9) The prevention activities coming out of a LAM is documented in
Project Plan
PDMR
Defect Prevention Report
Risk Plan
10) Wipros quality policy is
Meet the needs and expectations of customers
Achieve customer satisfaction by providing defect free products and services on time.
Attain CMMi Level 5 compliance
None of the above
11) ___________ methodology involves breaking of the requirements into modules with
information on Interface Requirements between the modules.
High Level design
Top Down design
Coupling
Cohesion
12) We take customer complaint seriously
TRUE
FALSE
None of the above
All of the above
13) Pair Programming, Small & Frequent releases are practices recommended by
XP model
V-Process model
2I process model
All of the above
14) Which of these set of parameters are used for Risk Quantification in Risk Plan?
Probability and Impact
Mitigation and Contingency
Probability and Mitigation
Contingency and Impact
15) Taxonomy based checklist is used for

Risk identification
Team members
Project name
None of the above
16) _________ is a technique used for arriving and prioritizing requirements.
Pugh matrix
Quality Function Deployment (QFD)
Voice Of Customer (VOC)
All of the above
17) Quality is defined as
Ability of the product to meet stated or implicit needs of customers
Set of process and procedures
Use of checklists and templates
All of the above
18) Risk quantification is done based on
Risk probability and impact of risk
Risk mitigation
Risk schedule
None of the above
19) Release note is prepared :
Prior to the release , contains the list of software items
To explain the project closure norms
After the final test case is executed
On acceptance of the release
20) This is the testing procedure according to which modules, sub modules are tested and
test case verification is done
Functional testing
Module testing
Unit testing
System testing
21) Quality Policy
Should not be shown to the customer as it is very confidential
is prepared for the Mission Quality Group
is used to rate the Mission Quality Group performance every year
states a clear commitment to quality and consistent with organization goals
22) Which of this is a planned mechanism for Defect Prevention?
Look Ahead Meetings
PDMR and PMR reviews
Customer feedback

All of the above


23) Which phases of SDLC can be sources for errors?
RS, Design, CUT, IT, ST & AT
RS, Design, CUT, IT & ST
RS, Design, CUT & IT
RS, Design & CUT
24) Modification of the approved process to suit the requirements of a project are
documented in
Project Plan
Veloci-Q
Master List of Process
None of the above
25) The role of a person who facilitates the six sigma team project to align with the
methodology is:
Green Belt
Champion
Black Belt
Yellow Belt