Estimating Activity Durations
Estimating Activity Durations
Estimate Activity
Durations
30 September 2013
Padding
I have no idea how long it will
take. I dont even know what I
am asked to do. So what do I
say?
The customer
If a customer want the shortest possible
schedule, they should not pressure you to
lower your estimates or to provide them with
misleadingly precise estimates.
One-Point Estimating
II.
Three-Point Estimates
One-point Estimating
The estimator submits one estimate per activity (
that activity will take 5 days)
Maybe based on expert judgment, historical info or it
could be just a guess
Expert judgment
Expert judgment guided by historical information, can
provide estimates from prior similar projects and
experience
Vendors may be a good source
Parametric Estimating
Uses statistical relationship between historical data
and other variables
For example, the estimator may use measures like time
per line of code
Three-point Estimates
The accuracy of activity duration estimates can be
improved by considering uncertainty and risk
This concept originated with the Program Evaluation
and Review Technique (PERT), which uses three
estimates to define an approximate range for an
activitys duration.
PERT calculates a risk based Expected activity
duration using a weighted average of these three
estimates)
E = (o + 4m + p) / 6
where E is Estimate; o = optimistic estimate; p = pessimistic
estimate; m = most likely estimate
Reserve Analysis
Duration estimates may include contingency reserves
(time reserves or buffers) into the overall project
schedule to account for schedule uncertainty
May be a percentage of the estimated activity duration,
or a fixed number of work periods.
We should establish a reserve risk remaining after the
risk management process. THIS IS DIFFERENT THAN
PADDING
Estimating Tips
Rushed
estimates are
inaccurate
estimates
Sources:
A Guide to the Project management Body of Knowledge, 4th edition
(Project Management Institute)
Effective Software Project Management (2006, Robert Wysocki)
Rapid Development (1996, Steve McConnell)
PMP exam prep, 7th edition (Rita Mulcahy)
Stavros Labrou
Senior Project Manager