Aux. Plant Control and Instrumentation System 1.00.00 General
Aux. Plant Control and Instrumentation System 1.00.00 General
Aux. Plant Control and Instrumentation System 1.00.00 General
GENERAL
The Contractor shall provide Independent Control &
Instrumentation system for control, monitoring and operation of Water
Demineralising Plant including associated drives and auxiliaries in all
regimes of operation in safe and most efficient manner. The Contractor
shall provide all systems, equipment, accessories and associated
equipment, which are included in Contractors scope, in a fully operational
condition acceptable to the Employer. The Contractor shall also provide all
material, equipment and services which may not be specifically stated in
the specifications but are required for completeness of the
equipment/systems furnished by the Contractor and for meeting the intent
and requirements of this specifications. The work shall be consistent with
modern power plant practices and shall be in compliance with all
applicable codes, standards, guidelines and safety requirements in force
on the date of award of the contract.
The following clauses describe the brief scope of supplies only.
The detailed technical specifications are stipulated under Part - B,
Section-VI of the specification as well as in various other Parts of the
Technical Specifications.
2.00.00
2.1.00
(b)
All Instruments which are Integral to equipment like pumps, motors etc.,
which are not indicated in enclosed P & IDs but required for control,
monitoring and operation of the equipment/plant/ Systems are to be
provided. All the instruments shall be provided by the Contractor to meet
actual system requirements subject to Employers approval.
(c)
PAGE 1 OF 4
3.00.00
(d)
For Binary and analog inputs required in major equipment protection triplesensing devices as indicated in P&Ids shall be provided. For other critical
binary and analog inputs required for protection and interlock purpose of
other equipment (e.g. those interlocks which may result in loss of
generation, non-availability of a major equipment etc.), dual sensors shall be
provided.
(d)
All the instruments which are required to implement the control philosophy
as specified in corresponding mechanical sections shall be provided by the
contractor.
4.00.00
5.00.00
PAGE 2 OF 4
6.00.00
ELECTRICAL ACTUATORS
Electrical Actuators with integral starter shall be provided for all
on/off and inching type valves along with necessary interface units for
linking to corresponding Control System as applicable as detailed out in
Sub-section-Electric Actuator, Part-B, Section-VI of Technical
Specification.
7.00.00
ON/OFF control, Indication, annunciation of Incomers and BusCouplers are also to be performed from Contractors Control System.
I. Water De-mineralising Dual processor PLC based System with two nos.
System
Operator Workstations (OWS).Both the OWS shall
be placed in Water De-mineralising plant Control
Room.
PAGE 3 OF 4
8.00.00
9.00.00
PAGE 4 OF 4